HomeMy WebLinkAboutGM Purchasing Policy v5 Ref. in Ordinance OC SAN-61 Orange County Sanitation District General Manager Purchasing Policy Version Number: 5.0 Approved By: General Manager Approved Date: Subject: Purchasing Policies and Procedures Effective Date: 8/25/2023 Contents Article 1. General Provisions .............................................................................. 5 Section 1.1 Purpose and Scope ............................................................................. 5 Section 1.2 Definitions ............................................................................................ 5 Section 1.3 The Purchasing Manager .................................................................... 5 Section 1.3.1. Duties..................................................................................................... 5 Section 1.3.2. Authority to Reject Requisition Requests ............................................... 6 Section 1.3.3. Authority to Revise Contracts Based on Sales, Transfers, Reorganization and Name Changes ...................................................... 7 Section 1.3.4. Delegation of the Purchasing Manager’s Authority ................................ 7 Section 1.4 Written Determinations ....................................................................... 7 Section 1.5 Bonds and Contract Security ............................................................. 8 Section 1.6 Public Access to Procurement Documents ...................................... 8 Section 1.7 Disposition of Bids or Proposals ....................................................... 8 Section 1.8 Sole Source Procurement ................................................................... 9 Section 1.8.1. Conditions for Use of Sole Source Procurement ................................... 9 Section 1.8.2. Negotiation in Sole Source Procurement ............................................... 9 Section 1.8.3. Record of Sole Source Procurement ..................................................... 9 07/31/2023 Subject: Purchasing Policies and Procedures Page 2 of 30 Effective Date: 08-25-2023 Section 1.9 Emergency Procurements .................................................................. 9 Section 1.9.1. Scope of Emergency Procurements ...................................................... 9 Section 1.10 Employment of Former Employees.................................................. 10 Article 2. Goods and Services .......................................................................... 10 Section 2.1 General ............................................................................................... 10 Section 2.1.1. Selection of Contract Types ................................................................. 10 Section 2.2 Convenience Blanket Purchase Orders........................................... 10 Section 2.3 Multi-Year Contracts.......................................................................... 11 Section 2.3.1. Solicitation ........................................................................................... 11 Section 2.3.2. Cancellation ......................................................................................... 12 Section 2.3.3. Incremental Award ............................................................................... 12 Section 2.4 Competitive Bids ............................................................................... 12 Section 2.4.1. Specifications ....................................................................................... 12 Section 2.4.2. Mistakes............................................................................................... 14 Section 2.4.2.1. Mistakes Discovered After Opening but Before Award ................ 14 Section 2.4.2.2. Mistakes Discovered After Award ................................................ 15 Section 2.4.2.3. Determinations Required ............................................................. 15 Section 2.4.3. Responsibility ....................................................................................... 15 Section 2.4.4. Determination of Lowest Bidder ........................................................... 15 Section 2.4.5. Notice of Award ................................................................................... 16 Section 2.5 Multi-Step Sealed Bidding for Goods and Services ....................... 16 Section 2.5.1. Definition .............................................................................................. 16 Section 2.5.2. Conditions for Use ............................................................................... 17 Section 2.5.3. Pre-Bid Conferences in Multi-Step Sealed Bidding .............................. 17 Section 2.5.4. Step One.............................................................................................. 17 Subject: Purchasing Policies and Procedures Page 3 of 30 Effective Date: 08-25-2023 Section 2.5.5. Mistakes During Multi-Step Sealed Bidding ......................................... 19 Section 2.5.6. Step Two .............................................................................................. 19 Section 2.6 Competitive Proposals ...................................................................... 20 Section 2.6.1. Content of Requests for Proposals ...................................................... 20 Section 2.6.2. Notice................................................................................................... 20 Section 2.6.3. Late Proposals ..................................................................................... 20 Section 2.6.4. Receipt of Proposals ............................................................................ 20 Section 2.6.5. Evaluation of Proposals ....................................................................... 21 Section 2.6.6. Discussions with Individual Proposers ................................................. 21 Section 2.6.7. Mistakes............................................................................................... 21 Section 2.7 Master Contracts for Maintenance and Repair Services ................ 22 Article 3. Professional Services ....................................................................... 23 Section 3.1 General Requirements ...................................................................... 23 Section 3.1.1. Solicitation of Proposals....................................................................... 23 Section 3.1.2. Contents of Request for Proposals and Request for Qualifications ....................................................................................... 23 Section 3.1.3. Evaluation Committee .......................................................................... 23 Section 3.1.4. Negotiations ......................................................................................... 24 Section 3.1.5. Documentation ..................................................................................... 24 Section 3.1.6. Master Contracts for Professional Services ......................................... 24 Section 3.1.7. Master Contracts: Professional Services Qualified Lists ...................... 24 Article 4. Professional Design and Related Services ..................................... 24 Section 4.1.1. Master Contracts for Professional Design and Related Services ......... 24 Article 5. Public Works, Sewerage Maintenance, and Repair Work .............. 24 Article 6. Protests .............................................................................................. 25 Subject: Purchasing Policies and Procedures Page 4 of 30 Effective Date: 08-25-2023 Section 6.1 Solicitation Phase Protests .............................................................. 25 Section 6.1.1. General Provisions .............................................................................. 25 Section 6.1.2. Evaluation and Determination .............................................................. 25 Section 6.2 Award Protest .................................................................................... 26 Section 6.2.1. General Provisions .............................................................................. 26 Section 6.3 Appeal Process .................................................................................. 26 Section 6.4 Protest Requirements and Timelines............................................... 26 Article 7. Delegation of Authority to Make Purchases ................................... 26 Section 7.1 Original Contracts, Contingencies, and Renewals ......................... 26 Section 7.1.1. Delegation to Purchasing Manager ...................................................... 26 Section 7.1.2. Co-Signatures ...................................................................................... 27 In addition to the signature of the Delegated Authority: ........................................ 27 Section 7.1.3. Delegation of Authority ........................................................................ 27 Section 7.1.4. Contingency Release ........................................................................... 28 Section 7.2 Not Used ............................................................................................. 28 Section 7.3 Amendments, Change Orders, Renewals, Time Extensions and Assignments ...................................................................................... 28 Section 7.4 Change Orders to Public Works Contracts ..................................... 29 Section 7.5 Procard ............................................................................................... 29 Article 8. Revision History ................................................................................ 29 Subject: Purchasing Policies and Procedures Page 5 of 30 Effective Date: 08-25-2023 Article 1. General Provisions Section 1.1 Purpose and Scope Section 1.04 of OC San’s Purchasing Ordinance (OC SAN-61) requires the General Manager to adopt policies, rules, and guidelines governing the purchase of Goods and Services, and the award of Contracts for Public Works Projects. The General Manager hereby adopts these Policies and Procedures pursuant to Section 1.04 of the Purchasing Ordinance. These Policies and Procedures apply to all OC San Staff. Section 1.2 Definitions Words and terms defined herein and in Article 9 of the Purchasing Ordinance have the same meanings in these Purchasing Policies and Procedures, unless the use of a word or term clearly requires a different meaning, or a different definition is prescribed for a particular section or portion thereof. Section 1.3 The Purchasing Manager Section 1.3.1. Duties Under Section 1.06(A) of the Purchasing Ordinance, the Purchasing Manager is required to procure, or supervise the procurement of, all Goods, Services, and Public Works Projects purchased by OC San, and supervise and control inventories of supplies and materials. In addition, the Purchasing Manager will: (a) Prepare administrative regulations for the internal management and operation of the Purchasing Division, the warehousing of inventories, and the disposition of surplus property; (b) Negotiate Contracts for the purchase of supplies, services, materials, and equipment, and recommend their approval; (c) Submit to General Counsel for review or approval, as necessary, Contracts, purchase orders, and other related documents; (d) Prepare and adopt forms that are reasonably necessary for the implementation of OC San’s Purchasing Ordinance and these Policies and Procedures; (e) Keep informed of current developments in the field of purchasing and Contracts, including but not limited to prices, market conditions, and new products; (f) Review and recommend changes to specifications to establish minimum standards for all purchases; Subject: Purchasing Policies and Procedures Page 6 of 30 Effective Date: 08-25-2023 (g) Supervise the inspection of all supplies, services, materials, and equipment purchases to ensure conformance with specifications; (h) Exercise custody and control of all inventories and surplus property; (i) Maintain records needed for the efficient operation of the Purchasing Division as required by law and OC San policy; (j) Retain custody of all executed Contracts other than those approved by the Board of Directors. The Purchasing Manager will retain all original purchase orders in accordance with OC San’s record retention policy; (k) Discourage uniform bidding and endeavor to obtain full and open competition to the extent possible on all purchases and sales; and (l) Receive Requisition(s). Requisitions up to $25,000 may be accompanied by a single quote obtained by OC San staff, which may be used for order placement, as approved by the Purchasing Manager. Requisitions greater than $25,000 may be accompanied by a single quote obtained by OC San staff for estimating purposes, as approved by the Purchasing Manager. (m) Ensure Clearinghouse approvals have been obtained in accordance with the Clearinghouse Guidelines. Section 1.3.2. Authority to Reject Requisition Requests The Purchasing Manager may return a request for procurement filed by a Department Director if the Purchasing Manager determines that he or she requires additional information to process the request. The Purchasing Manager may reject a request for procurement if the Purchasing Manager determines that the proposed procurement is clearly not in the best interest of OC San. A proposed procurement may not be in the best interest of OC San, for example, if: (a) the request can be satisfied from existing OC San inventory, OC San Contracts or other procurement options; (b) the request exceeds OC San’s needs; (c) the supplies, services, or construction requested could be procured more economically at a different time without detriment to OC San; or (d) the quality requested is inconsistent with OC San standards and usage. The Purchasing Manager will consult with the Department Director before rejecting any request for procurement. The Purchasing Manager will provide the reasons in support of any rejection. Subject: Purchasing Policies and Procedures Page 7 of 30 Effective Date: 08-25-2023 Section 1.3.3. Authority to Revise Contracts Based on Sales, Transfers, Reorganization and Name Changes The Purchasing Manager may revise Contracts and related records to reflect the sale, transfer, or reorganization of a Contractor’s business, or a change in the Contractor’s name for doing business, as long as all other terms, conditions and scope elements of the original Contract remain the same. In the event that there are inconsequential changes proposed in the terms, conditions or scope elements of the Contract, the Purchasing Manager may elect to approve the proposed changes. For material changes, the new form of Contract will require the approval of the appropriate awarding authority. The Purchasing Manager may approve an assignment of a purchase order or Contract by one Contractor to another if: (1) the Contract does not prohibit assignment; (2) the Contract assignment does not require approval of the Board of Directors; and (3) the assignment, in the reasonable determination of the Purchasing Manager, does not conflict with the best interest of OC San. Any such approval must be in writing. If a purchase order is being assigned the assignment must be made through a change to the purchase order. If a Contract is being assigned, the assignment must be made through a Contract Amendment/Change Order and a change to the purchase order. The form of assignment must be consistent with OC San recognized purchasing and accounting principles and practices. Section 1.3.4. Delegation of the Purchasing Manager’s Authority The Purchasing Manager may delegate his or her authority to employees within the Purchasing Division, and/or to employees in other Departments, as he or she deems appropriate in the interest of efficient administration. Any such delegation will be in writing, and must describe, at a minimum: (a) the activity or function authorized; (b) any limits or restrictions on the exercise of the delegated authority; (c) whether the authority may be further delegated; and (d) the duration of the delegation. Section 1.4 Written Determinations Each written determination required by the Purchasing Ordinance and/or these Purchasing Policies and Procedures must set forth the relevant facts and the reasoning supporting the determination. Each such written determination will be kept in the appropriate solicitation or Contract file, in accordance with OC San’s records retention policy. Subject: Purchasing Policies and Procedures Page 8 of 30 Effective Date: 08-25-2023 Section 1.5 Bonds and Contract Security Bid bonds, performance bonds, payment bonds (labor and material) and/or other forms of security may be required for Contracts for Goods and Services as the Purchasing Manager deems advisable to protect the interest of OC San. Any such requirement must be set forth in the Notice Inviting Bids or the Request for Proposals. Bid bonds and performance bonds should be used in addition to, not in lieu of, a determination that a bidder or proposer is responsible. Per California Civil Code OC San is required to secure a payment bond (labor and material) from direct Contractors performing Public Works Projects and Services involving construction or repair work where the expenditure exceeds $25,000. Bid bonds, performance bonds and payment bonds are required for all Public Works Contracts. Section 1.6 Public Access to Procurement Documents Documents generated in connection with the procurement process will be made available to the public to the extent required by the California Public Records Act. In accordance with applicable law, OC San may keep confidential proposals received in response to a Request for Proposals until the proposer executes a Contract with OC San or a Contract is presented to the Board or Standing Committees for approval, in order to: (a) protect OC San’s bargaining position in relation to the Contractor(s) ultimately selected; (b) insulate the evaluation committee from outside political pressure; and/or (c) ensure that proposers do not appropriate innovative solutions presented in one or more competing proposals. Competitive Sealed Bids let to lowest responsive and responsible bidders are public once sealed bids are opened. Section 1.7 Disposition of Bids or Proposals When OC San rejects bids or proposals or cancels a solicitation after bids or pro- posals are received, all the bids or proposals which have been opened will be retained in OC San’s web-based system. Subject: Purchasing Policies and Procedures Page 9 of 30 Effective Date: 08-25-2023 Section 1.8 Sole Source Procurement Section 1.8.1. Conditions for Use of Sole Source Procurement If a Department Director desires to pursue a Sole Source Procurement, the Requisition must explain how the Goods and/or Services to be acquired are (1) unique based on their quality, durability, availability, fitness, or qualification for a particular use, or (2) only available from one source. This section does not apply to Public Works Projects, which must comply with the limitations of the Public Contracts Code. A Sole Source Procurement may be appropriate in certain circumstances such as but not limited to the following: (a) OC San requires equipment, accessories, or replacement parts that are compatible with existing equipment; (b) OC San desires to purchase a proprietary Good or Service; (c) OC San requires services from a public utility; (d) emergencies or time sensitive procurements. Section 1.8.2. Negotiation in Sole Source Procurement In connection with any Sole Source Procurement, the Purchasing Manager will negotiate with the Contractor, as appropriate, as to price, delivery, and other Contract terms. Section 1.8.3. Record of Sole Source Procurement The Purchasing Manager will maintain a record of each Sole Source Procurement setting forth the following information: (a) the Contractor's name; (b) the amount and type of each Contract; (c) a listing of the supplies, services, or construction procured under each Contract; (d) the identification number of each Contract file; and (e) the justification memo submitted by the requesting Department. Section 1.9 Emergency Procurements Section 1.9.1. Scope of Emergency Procurements In the event that OC San pursues an emergency procurement, the procurement will Subject: Purchasing Policies and Procedures Page 10 of 30 Effective Date: 08-25-2023 be limited to those Goods, Services, or Public Works items necessary to respond to the emergency. Section 1.10 Employment of Former Employees Guidance on the employment of former employees can be found in the OC San Personnel Policies and Procedures Manual, Policy 1.4 Recruitment and Selection, Section 7.0. Article 2. Goods and Services Section 2.1 General Section 2.1.1. Selection of Contract Types The selection of an appropriate Contract type depends on factors such as the nature of the Goods or Services to be procured, the uncertainties which may be involved in Contract performance, and the extent to which OC San or the Contractor is to assume the risk of the cost of performance of the Contract. Contract types differ in the degree of responsibility assumed by the Contractor. OC San may consider the following factors in selecting the type of Contract: (a) the type and complexity of the Good or Service being procured: (b) the difficulty of estimating performance costs such as the inability of OC San to develop definitive specifications, to identify the risks to the Contractor inherent in the nature of the work to be performed, or otherwise to establish clearly the requirements of the Contract; (c) the administrative costs to both parties; (d) the degree to which OC San must provide technical coordination during the performance of the Contract; (e) the effect of the choice of the type of Contract on the amount of competition to be expected; (f) the stability of material or commodity market prices or wage levels; (g) the urgency of the requirement; and (h) the length of Contract performance. Section 2.2 Convenience Blanket Purchase Orders Purchasing Manager may issue blanket purchase orders for recurring purchases of Subject: Purchasing Policies and Procedures Page 11 of 30 Effective Date: 08-25-2023 miscellaneous supplies and services that: (a) have been competitively bid because the Purchasing Manager determines it is in the best interests of OC San to issue a blanket order; (b) are for miscellaneous supplies, services, materials and equipment where such purchase may be procured from a single vendor during the period as specified by the Purchasing Manager, without observing the procedures prescribed in Article 2. A blanket order may be utilized if, in the Purchasing Manager’s discretion, it is determined that such blanket purchase orders are either cost favorable to OC San or will result in a more expeditious or efficient procurement of such items; or (1) Are non-recurring low value items and services where the exact nature of the requirement cannot be determined at the time of issuing the blanket order; (2) Piecemealing is prohibited. Purchases shall not be artificially divided so as to keep each purchase amount approximately $25,000 or less (c) Purchasing Manager has determined the vendor is uniquely qualified to provide specialized goods or perform specialized services. Convenience blanket purchase orders shall be in conformity with the spirit and intent of this policy. Section 2.3 Multi-Year Contracts Section 2.3.1. Solicitation Each solicitation for a multi-year Contract must state: (a) the amount of Goods or Services required for the proposed contract period; (b) that a unit price will be given for each Good or Service, and that such unit price will be the same throughout the contract term (except to the extent price adjustments may be provided for in the solicitation and resulting Contract); (c) that the multi-term Contract will be cancelled if funds are not appropriated or otherwise made available to support continuation of performance in any contract period succeeding the first; however, this does not affect either OC San’s or the Contractor's rights under any termination clause in the Contract; (d) whether bidders or proposers may submit prices for: (1) the first contract period only; Subject: Purchasing Policies and Procedures Page 12 of 30 Effective Date: 08-25-2023 (2) the entire time of performance only; or (3) both the first contract period and the entire time of performance; (e) that a multi-term Contract may be awarded and how award will be determined including, if prices for the first contract period and entire time of performance are submitted, how such prices will be compared; and (f) the Contractor will be compensated for the Goods delivered/accepted and/or the amount of work performed to the effective date of cancellation. Section 2.3.2. Cancellation "Cancellation," as used in multi-term contracting, means the cancellation for some or all of the requirements for the remaining portion of the Contract due to factors as identified by the Purchasing Manager. Section 2.3.3. Incremental Award An incremental award is an award of portions of a definite quantity requirement to more than one Contractor. Each portion is for a definite quantity and the sum of the portions is the total definite quantity required unless specified. An incremental award may be used only when awards to more than one bidder or proposer for different amounts of the same item are necessary to obtain the total quantity or the required delivery. If an incremental award is anticipated, OC San will reserve the right to make such an award and the criteria for award will be stated in the solicitation. The Purchasing Manager will make a written determination setting forth the reasons for the incremental award, which will be made a part of the procurement file. Section 2.4 Competitive Bids Section 2.4.1. Specifications Specifications must, to the extent practicable, emphasize functional or performance criteria while limiting specific manufacturers’ design or other detailed physical descriptions to those necessary to meet the needs of OC San. To facilitate the use of such criteria, Departments will endeavor to include as a part of each Requisition the principal functional or performance needs to be met. It is the general policy of OC San to procure standard commercial products whenever practicable. In developing specifications, accepted commercial standards will be used and unique requirements will be avoided, to the extent practicable. Purchasing Manager may issue Notices Inviting Bids for purchases of goods or services in accordance with the requirements stated below: Subject: Purchasing Policies and Procedures Page 13 of 30 Effective Date: 08-25-2023 (a) Notice Inviting Bids. A Notice Inviting Bids shall be published and include a general description of the articles or services to be purchased or sold, shall state where bid forms and specifications may be secured, and the time and place for opening bids. (b) Published Notice. The Notice Inviting Bids shall set a date for the opening of bids. The publication or posting of the Notice shall be at least ten (10) days before the date of opening the bids. Notice may be published in a newspaper of general circulation, printed and published within the Sanitation District’s jurisdiction; or by electronic bulletin board procedures designed to reach the industry or market of supply; OC San’s on-line vendor database; or through OC San’s internet site. (c) Contractor’s List. Purchasing Manager may also solicit sealed bids, or receive bids electronically, from all responsible prospective Contractors whose names are on the Bidder’s List maintained by OC San, or who have requested their names to be added thereto. (d) Bulletin Boards. Purchasing Manager may also advertise pending purchases or sales by a notice posted on a public bulletin board in the Purchasing Office, and by electronic bulletin board, as deemed appropriate by the Purchasing Manager. (e) Bidder’s Security. When deemed necessary by the Purchasing Manager, a bidder’s security may be prescribed in the Contract specifications or in the Notice Inviting Bids. The Purchasing Manager shall maintain said bidders’ security. Bidders shall be entitled to the return of a bid security upon the full execution of an awarded Contract or issuance of a purchase order by the successful bidder. A successful bidder shall forfeit its bid security upon refusal or failure to execute the Contract within the prescribed time after the Notice of Award of Contract has been delivered to the bidder, unless OC San is responsible for a delay in the prescribed time. The Purchasing Manager may, on refusal or failure of the successful bidder to execute the Contract, award it to the next lowest responsive, responsible bidder. If the Purchasing Manager awards the Contract to the next lowest bidder, an amount of the lowest bidder’s security equal to the difference between the low bid and the awarded bid shall be forfeited to OC San and the surplus, if any, shall be returned to the lowest bidder. (f) Bid Opening Procedure. Sealed or electronically received bids shall be submitted to the Purchasing Manager and shall be identified as a bid on the envelope or the electronic bulletin board. Bids shall be opened, concurrently, in public by the Purchasing Manager at the time and place stated in the public notices. A tabulation of all bids received shall be available for public inspection during regular business hours for a period of not less than thirty (30) calendar days after the bid opening. Subject: Purchasing Policies and Procedures Page 14 of 30 Effective Date: 08-25-2023 (g) Rejection of Bids. Refer to the Purchasing Ordinance (h) Equal Bids. Refer to the Purchasing Ordinance (i) Performance Bonds. Refer to Section 1.6 The above procedures do not apply to procurements covered by Section 2.03 Exceptions, of the Purchasing Ordinance. Section 2.4.2. Mistakes Section 2.4.2.1. Mistakes Discovered After Opening but Before Award (a) Minor Irregularities. Minor irregularities are matters of form rather than substance evident from the bid document, or insignificant mistakes that can be waived or corrected without prejudice to other bidders; that is, the effect on price, quantity, quality, delivery, or contractual conditions is negligible. The Purchasing Manager will waive such irregularities or allow the bidder to correct them depending on which is in the best interest of OC San. Examples include the failure of a bidder to: (1) return the number of signed bids required by the Notice Inviting Bids; (2) sign the bid, but only if the unsigned bid is accompanied by other material indicating the bidder's intent to be bound; or (3) acknowledge receipt of an addendum to the Notice Inviting Bids, but only if: i. it is clear from the bid that the bidder received the addendum and intended to be bound by its terms; or ii. the addendum involved had a negligible effect on price, quantity, quality, or delivery (b) Mistakes Where Intended Correct Bid is Evident. If the mistake and the intended correct bid are clearly evident on the face of the bid document, the bid will be corrected to the intended correct bid and may not be withdrawn. Examples of mistakes that may be clearly evident on the face of the bid document are typographical errors, errors in extending unit prices, transposition errors, and arithmetical errors. (c) Mistakes Where Intended Correct Bid is Not Evident. A bidder may be permitted to withdraw a low bid if: (1) a mistake is clearly evident on the face of the bid document, but the Subject: Purchasing Policies and Procedures Page 15 of 30 Effective Date: 08-25-2023 intended correct information is not similarly evident; or (2) the bidder submits proof of evidentiary value which clearly and convincingly demonstrates that a mistake was made. Section 2.4.2.2. Mistakes Discovered After Award Mistakes will not be corrected after award of the Contract except where the Purchasing Manager makes a written determination that it would be unconscionable not to allow the mistake to be corrected. Section 2.4.2.3. Determinations Required When a bid is corrected or withdrawn, or correction or withdrawal is denied, the Purchasing Manager will prepare a written determination showing that the relief was granted or denied in accordance with these Policies and Procedures. Section 2.4.3. Responsibility In a Competitive Sealed Bid procurement, OC San will award the Contract to a responsive and responsible bidder that submits the lowest bid. OC San will not consider the relative superiority of the bidders, but only whether the low bidder is responsive and responsible. In evaluating a prospective Contractor's responsibility, the Purchasing Manager will consider the Contractor's past performance, expertise, integrity, and available resources such as finances, equipment, facilities, and personnel. The prospective Contractor will supply all information needed for the evaluation. If the Contractor fails to supply requested information, the Purchasing Manager will either (1) base the determination of responsibility upon the available information, or (2) find the prospective Contractor to be non-responsible if the Purchasing Manager determines that the failure to provide information is unreasonable. A prospective Contractor may demonstrate the availability of financing, equipment, facilities, expertise, and personnel by, among other things, submitting acceptable plans to subcontract for the required resources, or providing a documented commitment form, or explicit arrangement with, a satisfactory source to provide the necessary items. If the Purchasing Manager determines that a prospective Contractor is not responsible, the Purchasing Manager will prepare a written determination setting forth the basis of the finding. The Purchasing Manager will promptly send a copy of the determination to the prospective Contractor. The final determination will be included in the procurement file. Section 2.4.4. Determination of Lowest Bidder OC San will determine the lowest bid based on objective criteria set forth in the Subject: Purchasing Policies and Procedures Page 16 of 30 Effective Date: 08-25-2023 Notice Inviting Bids, such as unit cost, transportation cost, and life cycle costs. Section 2.4.5. Notice of Award At the conclusion of each Competitive Sealed Bid process, the Purchasing Manager will send written notice of award to the successful bidder. Following award, OC San will retain the relevant documents showing the basis for the award. Section 2.5 Multi-Step Sealed Bidding for Goods and Services Section 2.5.1. Definition Multi-step sealed bidding is a combination of competitive procedures designed to obtain the benefits of sealed bidding when adequate specifications are not available, or when the Purchasing Manager determines that a pre-qualification process is necessary and desirable for a particular procurement. This will result in a two-step process consisting of a technical/pre-qualification first step composed of one or more steps in which bidders submit unpriced technical qualifications to be evaluated by OC San or submit their qualifications for evaluation against the stated criteria. The second step occurs when those bidders whose technical qualifications are determined to be acceptable, or who are pre-qualified during the first step have their price bids considered. The process permits OC San to develop a sufficiently descriptive statement of OC San’s requirements, including an adequate technical data package, so that subsequent acquisitions may be made by conventional sealed bidding. This method is especially useful in acquisitions requiring technical proposals, particularly those for complex items. Multi-step sealed bidding is conducted in two steps: (a) Step one consists of the request for, submission, evaluation, and (if necessary) discussion of a technical qualifications, or request for qualifications. No pricing is involved. The objective is to determine the acceptability of the supplies or services offered. As used in this context, the word “technical” has a broad connotation and includes, among other things, the engineering approach, special manufacturing processes, special testing techniques, financial and other professional services. It is the proper step for clarification of questions relating to technical requirements. Conformity to the technical requirements /responsibility is resolved in this step. (b) Step two involves the submission of sealed priced bids by those who submitted acceptable technical qualifications. Bids submitted in step two are evaluated and the awards made to the lowest responsive and responsible bidder. Subject: Purchasing Policies and Procedures Page 17 of 30 Effective Date: 08-25-2023 Section 2.5.2. Conditions for Use Multi-step sealed bidding may be used when it is considered desirable: (a) To invite and evaluate technical qualifications to determine their acceptability to fulfill the purchase description requirements; (b) To conduct discussions for the purposes of facilitating understanding of the technical qualifications and purchase description requirements and, where appropriate, obtain supplemental information, permit clarifications of technical qualifications, or addend the purchase description; (c) To establish the list of pre-qualified bidders for this procurement; (d) To accomplish (a) and (b) above prior to soliciting priced bids; and (e) To award the Contract to the lowest responsive and responsible bidder in accordance with the competitive sealed bidding procedures. Section 2.5.3. Pre-Bid Conferences in Multi-Step Sealed Bidding Prior to the submission of unpriced technical qualifications, a pre-bid conference may be conducted. The Purchasing Manager may also hold a conference with all or any prospective bidders at any time during the evaluation of the unpriced technical qualifications. Section 2.5.4. Step One (a) Form. Multi-step sealed bidding will be initiated by the issuance of a notice inviting bids. In addition to the normal bid requirements, the multi-step notice inviting bids will state: (1) That unpriced technical qualifications are requested; (2) Whether priced bids are to be submitted at the same time as unpriced technical qualifications; if they are, the priced bids must be submitted in a separate sealed file; (3) That it is a multi-step sealed bid procurement, and priced bids will be considered only in the second step and only from those bidders whose unpriced technical qualifications are found acceptable, or are qualified in the first step; (4) The criteria to be used in the evaluation of the unpriced technical qualifications; (5) That OC San, to the extent it finds necessary, may conduct oral or Subject: Purchasing Policies and Procedures Page 18 of 30 Effective Date: 08-25-2023 written discussions of the unpriced technical qualifications; (6) That prospective bidders may designate those portions of the unpriced technical qualifications that contain trade secrets or other proprietary data which are to remain confidential; and (b) Addendum to the Notice Inviting Bids. After receipt of unpriced technical qualifications, addenda to the notice inviting bids will be distributed only to bidders who submitted unpriced technical qualifications, and they will be permitted to submit new unpriced technical qualifications or to amend those submitted. If, in the opinion of the Purchasing Manager, a contemplated Amendment will significantly change the nature of the procurement, the notice inviting bids will be canceled, and a new notice inviting bids issued. (c) Receipt and Handling of Unpriced Technical Qualifications. Unpriced technical qualifications will not be opened publicly but will be received in accordance with the requirements of the NIB/RFQ. Technical qualifications will not be disclosed to unauthorized persons. Bidders may request nondisclosure of trade secrets and other proprietary data identified in writing. (d) Evaluation of Unpriced Technical Qualifications. The unpriced technical qualifications submitted by bidders will be evaluated solely in accordance with the criteria set forth in the notice inviting bids. The unpriced technical qualifications will be categorized as: (1) Acceptable/Qualified; (2) Unpriced Technical Qualifications - Potentially acceptable, that is, reasonably susceptible of being made acceptable; or (3) Unacceptable/Not Qualified. The Purchasing Manager will record in writing the basis for finding a qualification unacceptable and make it part of the procurement file. The Purchasing Manager may initiate step two of the procedure if, in his or her opinion, there are sufficient acceptable unpriced technical qualifications to assure effective price competition in the second step without technical discussions. If the Purchasing Manager finds that such is not the case, the Purchasing Manager will issue an addendum to the notice inviting bids/request for qualifications or engage in technical discussions. (e) Discussion of Unpriced Technical Qualifications. The Purchasing Manager may conduct discussions with any bidder who submits an acceptable or potentially acceptable technical qualification. During the course of those discussions the Purchasing Manager will not disclose any information derived from one unpriced technical qualification to any other bidder. Once discussions are begun, any bidder who has not been notified that its Subject: Purchasing Policies and Procedures Page 19 of 30 Effective Date: 08-25-2023 qualifications have been finally found unacceptable may submit supplemental information amending its technical qualification at any time until the closing date established by the Purchasing Manager. Submissions of supplemental information may be made at the request of the Purchasing Manager. (f) Notice of Unacceptable Unpriced Technical Qualifications. When the Purchasing Manager determines a prospective bidder’s unpriced technical qualifications to be unacceptable, no additional opportunity to supplement its technical qualifications will be afforded. Section 2.5.5. Mistakes During Multi-Step Sealed Bidding Mistakes may be corrected or participation may be withdrawn at any time during step one. During step two, mistakes may be corrected or withdrawal permitted only pursuant to Section 2.4.2 above. Section 2.5.6. Step Two (a) Initiation. Upon the Completion of step one, the Purchasing Manager must either: (1) Open priced bids submitted in step one (if priced bids were required to be submitted) from bidders whose unpriced technical qualifications were found to be acceptable; or (2) If priced bids have not been submitted, technical discussions have been held, and addenda to the notice inviting bids have been issued, if necessary, invite each acceptable bidder to submit a priced bid. (b) Procedure and Confidentiality. Step two will be conducted as any other Competitive Sealed Bid procurement except: (1) As specifically set forth in the Multi-Step Sealed Bidding Process above; (2) No public notice need be given of this invitation to submit priced bids because notice was previously given; (3) After issuance of Notice of Intent to Award the unpriced technical qualifications of the successful bidder will be disclosed as follows. The Purchasing Manager will examine written requests of confidentiality for trade secrets and proprietary data in the bidder’s technical qualifications to determine the validity of any requests. If the parties do not agree as to the disclosure of data, the Purchasing Manager will inform the bidder in writing what portion of the unpriced technical qualifications will be disclosed and that, Subject: Purchasing Policies and Procedures Page 20 of 30 Effective Date: 08-25-2023 unless the bidder timely protests, the qualifications will be so disclosed. The Purchasing Manager will hear any protests in accordance with the protest provisions in the procurement. The technical qualifications will be open to public inspection subject to any continuing prohibition on the disclosure of confidential data; and (4) Unpriced technical qualifications of bidders who are not awarded the Contract will not be open to public inspection unless the Purchasing Manager determines in writing that public inspection of such offers is essential to assure confidence in the integrity of the procurement process; provided, however, that the provisions of Subsection (b)(3) above will apply with respect to the possible disclosure of trade secrets and proprietary data. Section 2.6 Competitive Proposals Section 2.6.1. Content of Requests for Proposals Each Request for Proposals must contain the following information: (a) a description of the Goods and/or Services required; (b) a description of the selection process, including the evaluation criteria; (c) a statement that OC San may discuss offers with select proposers at OC San’s discretion, but OC San may accept proposals without further discussions; (d) a statement of when and how price should be submitted; and (e) such other provisions, terms, and conditions, consistent with the Purchasing Ordinance, that the Purchasing Manager determines are necessary, desirable, and/or advantageous to OC San. Section 2.6.2. Notice The Purchasing Manager will give public notice of each Request for Proposals. The Purchasing Manager will set a response date that allows sufficient time for proposers to prepare their proposals. Section 2.6.3. Late Proposals Any proposal received after the established due date will not be considered. Section 2.6.4. Receipt of Proposals The Purchasing Manager will open and secure proposals in the manner identified in Subject: Purchasing Policies and Procedures Page 21 of 30 Effective Date: 08-25-2023 the Request for Proposal. Section 2.6.5. Evaluation of Proposals The evaluation will be based on the evaluation factors set forth in the Request for Proposals consistent with the Purchasing Ordinance. Numerical rating systems may be used but are not required. Proposals will be initially classified as: (a) acceptable; or (b) unacceptable. Proposers whose proposals are unacceptable will be so notified promptly. Section 2.6.6. Discussions with Individual Proposers The Purchasing Manager may arrange discussions with proposers that have been deemed acceptable in order to (a) clarify OC San’s requirements and/or the proposals, and (b) negotiate terms and conditions of a Contract. If the Purchasing Manager determines during discussions that the Request for Proposals must be substantially revised, the Request for Proposals will be amended and re-advertised. Auction techniques (revealing one proposer's price to another) and disclosure of any information derived from competing proposals are prohibited. Any substantial oral clarification of a proposal will be reduced to writing by the proposer. The Purchasing Manager will establish a common date and time for the submission of best and final offers. Best and final offers will be submitted only once, unless the Purchasing Manager determines in writing that it is in OC San’s best interest to conduct additional discussions and require another round of best and final offers. Otherwise, no discussion of, or changes in, the best and final offers will be allowed prior to award. Proposers will also be informed that if they do not submit a notice of withdrawal or another best and final offer, their immediate previous offer will be construed as their best and final offer. Section 2.6.7. Mistakes When the Purchasing Manager knows or has reason to conclude before award that a mistake has been made by a proposer, he or she should request the proposer to confirm the proposal. If the proposer alleges mistake, the proposal may be corrected or withdrawn during any discussions that are held. The following procedures will be applied when mistakes in proposals are discovered after receipt of proposals but before award. (a) During Discussions; Prior to Best and Final Offers. Once OC San commences discussions with any proposer, or after OC San requests best and final offers, any proposer may freely correct any mistake by modifying or withdrawing the Subject: Purchasing Policies and Procedures Page 22 of 30 Effective Date: 08-25-2023 proposal until the time and date set for receipt of best and final offers. (b) Minor Irregularities. Minor irregularities, unless otherwise corrected by a proposer as provided in this section, will be treated as they are under Competitive Sealed Bid procurement. (c) Correction of Mistakes. If discussions are not held or if the best and final offers upon which award will be made have been received, mistakes may be corrected and the intended correct offer considered only if: (1) the mistake and the intended correct offer are clearly evident on the face of the proposal, in which event the proposal may not be withdrawn; or (2) the mistake is not clearly evident on the face of the proposal, but the proposer submits proof of evidentiary value which clearly and convincingly demonstrates both the existence of a mistake and the intended correct offer, and such correction would not be contrary to the fair and equal treatment of other proposers. (d) Withdrawal of Proposals. If discussions are not held, or if the best and final offers upon which award will be made have been received, the proposer may be permitted to withdraw the proposal if: (1) the mistake is clearly evident on the face of the proposal and the intended correct offer is not; (2) the proposer submits proof of evidentiary value which clearly and convincingly demonstrates that a mistake was made but does not demonstrate the intended correct offer; or (3) the proposer submits proof of evidentiary value which clearly and convincingly demonstrates the intended correct offer, but to allow correction would be contrary to the fair and equal treatment of the other proposers. Mistakes Discovered After Award. Mistakes will not be corrected after award of the Contract except where the Purchasing Manager finds it would be unconscionable not to allow the mistake to be corrected. Section 2.7 Master Contracts for Maintenance and Repair Services Master Contracts for Maintenance and Repair Services will be procured pursuant to Article 2 of the Purchasing Ordinance. Subject: Purchasing Policies and Procedures Page 23 of 30 Effective Date: 08-25-2023 Article 3. Professional Services Section 3.1 General Requirements The Purchasing Manager will oversee the procurement of Professional Services. During the procurement process, the Purchasing Manager will be sole point of contact for all proposers. The Purchasing Manager will comply with the requirements of the Purchasing Ordinance, the applicable provisions of these Policies and Procedures, and applicable California law. Section 3.1.1. Solicitation of Proposals The Purchasing Manager will solicit Professional Services primarily through OC San’s electronic system, through either a Request for Qualifications or Request for Proposals process. Proposals may be submitted in hard copy (sealed proposals) or securely via OC San’s electronic system. Proposers may be asked to submit rate and/or price information via separate sealed files as part of their proposal. Section 3.1.2. Contents of Request for Proposals and Request for Qualifications Each Request for Qualifications and Request for Proposals must contain the following information: (a) a description of the selection process; (b) the criteria to be applied by OC San in evaluating the qualifications or proposals, including whether, and to what extent, OC San will consider price as a factor; (c) a summary of OC San’s protest procedures; (d) all other information required by the Purchasing Ordinance; and (e) any other information that the Purchasing Manager deems appropriate for the solicitation. Section 3.1.3. Evaluation Committee For each Request for Qualifications/Request for Proposals, the Purchasing Manager may establish a committee to evaluate the qualifications or proposals. The Purchasing Manager will serve as chair of each committee. Each committee may request clarifications and conduct interviews with proposers. At the conclusion of the evaluation process, each committee will rank the qualifications or proposals from most qualified to least qualified. Subject: Purchasing Policies and Procedures Page 24 of 30 Effective Date: 08-25-2023 Section 3.1.4. Negotiations If negotiations are in the best interest of OC San, the Purchasing Manager will commence negotiations with the top ranked firm and proceed in accordance with Article 3 of the Ordinance. Section 3.1.5. Documentation The Purchasing Manager will document the solicitation and receipt of proposals, the evaluation of proposals, and the negotiation process. Section 3.1.6. Master Contracts for Professional Services Master Contracts for Professional Services will be procured pursuant to Article 3 of the Purchasing Ordinance. Section 3.1.7. Master Contracts: Professional Services Qualified Lists Master Contracts for Professional Services Qualified Lists will be procured pursuant to Article 3 of the Purchasing Ordinance. Article 4. Professional Design and Related Services Professional Design and Related Services will be procured pursuant to Article 4 of the Purchasing Ordinance. Section 4.1.1. Master Contracts for Professional Design and Related Services Master Contracts for Professional Design and Related Services will be procured pursuant to Article 4 of the Purchasing Ordinance. Article 5. Public Works, Sewerage Maintenance, and Repair Work Refer to Article 5 of the Purchasing Ordinance concerning OC San’s award of Contracts for the construction of Public Works Projects exceeding $35,000 other than sewerage maintenance or repair projects pursuant to Public Contract Code Section 20783 (Projects estimated at $35,000 or less, and sewerage maintenance or repair projects, may be processed pursuant to Article 2 or Article 5 of the Purchasing Ordinance.) "Maintenance" means routine, recurring, and usual work for the preservation, protection and keeping of any plant, building, structure, component of a sewer system or appurtenance for its intended purposes in a safe and continually usable condition for which it was designed, improved, constructed, altered or repaired. Subject: Purchasing Policies and Procedures Page 25 of 30 Effective Date: 08-25-2023 "Repair" means replacement or restoration of a plant, building, structure, or component of a sewer system or appurtenance by replacing a part or putting together what is broken. A repair does not become an improvement or alteration constituting construction of a Public Work unless the replacement or restoration increases the capacity, or adds new uses or functions to the plant, building, structure, or component of a sewer system or appurtenance. Before finding a low bidder on a Public Works Contract to be not responsible, the Purchasing Manager will (1) notify that bidder of any evidence reflecting upon the bidder's responsibility, (2) afford the bidder an opportunity to rebut such adverse evidence, and (3) permit the bidder to present evidence of qualification. Article 6. Protests All procurements will contain protest procedures. Durations contained in Purchasing Policies and Procedures are a guideline. Deviations from these durations are at the discretion of the Purchasing Manager. Section 6.1 Solicitation Phase Protests Section 6.1.1. General Provisions (a) Any Interested Party may file a Solicitation Protest Statement with the Purchasing Manager on the grounds that a free and open competition has not taken place, or cannot take place, and/or that a particular specification or requirement is impractical, unduly restrictive, or ambiguous. (b) Solicitation Protest Statements must be received as prescribed in the solicitation. (c) Solicitation Protest Statements are public documents. OC San will provide copies of the Solicitation Protest Statements to any person upon written request. Section 6.1.2. Evaluation and Determination No hearing will be held on any Solicitation Protest Statement. The Purchasing Manager will review all material submitted, conduct an investigation of the facts, and may, but need not, request other bidders or proposers to submit statements or arguments regarding the protest. The Purchasing Manager may in his or her sole discretion, discuss the protest with the Protestor. The Purchasing Manager will issue a final written decision regarding any solicitation protest to each bidder or proposer before the bids or proposals are opened. The written decision will describe any actions taken, or to be taken in response to the Solicitation Protest Statement. The decision of the Purchasing Manager concerning the Solicitation Protest Statement shall be final. Subject: Purchasing Policies and Procedures Page 26 of 30 Effective Date: 08-25-2023 Section 6.2 Award Protest Section 6.2.1. General Provisions (a) Any Interested Party may file an Award Protest Statement with the Purchasing Manager on the grounds that a free and open competition has not taken place in connection with the award recommendation or to appeal a determination in connection to the Procurement. The Purchasing Manager will not consider any protest alleging that a bid or proposal is not responsive, which will be considered by the body that has final authority to let the Contract. (b) Any Award Protest Statement must be received by the Purchasing Manager as prescribed in the solicitation. (c) Award Protest Statements are public documents. OC San will notify the affected parties when a protest has been submitted and will provide copies of the Protest Statements to the affected parties upon written request. Section 6.3 Appeal Process If the Protestor intends to appeal the decision by the Purchasing Manager, the Protestor shall submit a written appeal in accordance with the procedures identified in the solicitation documents. Section 6.4 Protest Requirements and Timelines The Purchasing Manager reserves the right to customize protest requirements and timelines as deemed necessary. Article 7. Delegation of Authority to Make Purchases Article 7 of the Ordinance sets forth the delegated authority of the General Manager, and Standing Committees to award Contracts. The General Manager is authorized to approve Requisitions for budgeted purchases up to $150,000. General Manager shall approve Requisitions greater than $150,000 in order to advance the procurement process. This does not constitute award of the resulting Contract. Section 7.1 Original Contracts, Contingencies, and Renewals Section 7.1.1. Delegation to Purchasing Manager (a) The General Manager hereby delegates authority to execute purchase orders for all Goods and Services to the Purchasing Manager. Subject: Purchasing Policies and Procedures Page 27 of 30 Effective Date: 08-25-2023 (b) The General Manager hereby delegates authority to award and execute Contracts for all Goods and Services, excluding Public Works and Professional Design and Related Services, up to $150,000 to the Purchasing Manager. (c) The General Manager hereby delegates authority to execute Contracts for all Goods and Services, excluding Public Works and Professional Design and Related Services, to the Purchasing Manager. (d) The General Manager hereby delegates authority to execute Amendments, Change Orders, Renewals, Time Extensions, and Assignments for Goods and Services, excluding Public Works and Professional Design and Related Services to the Purchasing Manager. Section 7.1.2. Co-Signatures In addition to the signature of the Delegated Authority: (a) To ensure that all policies and procedures governing purchase orders, Contracts, Amendments, and change orders, including Public Works, are followed, all such documents will be signed by the Purchasing Manager, or designee upon approval of the delegated authority specified in the Purchasing Ordinance and this General Manager’s Purchasing Policy. (b) All purchases for computer hardware, software, copiers, faxes, and communication equipment will be pre-approved by the Director responsible for Information Technology, or his/her designee. Section 7.1.3. Delegation of Authority The General Manager may delegate to employees the authority to approve Requisitions for budgeted purchases within the following limits or as prescribed by the General Manager: Employee Delegated Authority Assistant General Manager Authorization to approve Requisitions for budgeted purchases up to $100,000. Department Director Authorization to approve Requisitions for budgeted purchases up to $50,000. Division Manager Authorization to approve Requisitions for budgeted purchases up to $25,000. Subject: Purchasing Policies and Procedures Page 28 of 30 Effective Date: 08-25-2023 Employee Delegated Authority Superintendent/Chief Authorization to approve Requisitions for budgeted purchases up to $10,000. Supervisor/Clerk of the Board Authorization to approve Requisitions for budgeted purchases up to $5,000. Maintenance Specialist Authorization to approve Requisitions for budgeted purchases up to $4,000. Maintenance Lead Authorization to approve Requisitions for budgeted purchases up to $2,000. Section 7.1.4. Contingency Release The General Manager shall manage the expenditure of all approved contingency funds in connection with all Amendments and change orders approved by the Board, the standing committees, and the General Manager. Section 7.2 Not Used Section 7.3 Amendments, Change Orders, Renewals, Time Extensions and Assignments The General Manager hereby delegates to each Department Director, not designee, the authority to approve the Requisitions for specified Amendments, Change Orders, and Renewals to budgeted purchases provided that the cumulative amount of the original purchase plus all Amendments or change orders does not exceed $50,000. For Public Works Change Orders, refer to Section 7.4 of this Policy. Each Department Director may review and recommend that the General Manager approve Requisitions for Amendments, Change Orders, Renewals, and Time Extensions that when combined with the original Contract amount and all prior Amendments, exceeds $50,000, or are nonetheless within the approved Contract contingency. For Public Works Change Orders, refer to Section 7.4 of this Policy. Time Extensions beyond the original, specified and approved period with or without an increase in contract price may be approved by the General Manager, as long as the revised contract price is within the approved contingency. Time Extensions beyond the original, specified and approved period that exceed the approved contingency must go back to the awarding authority for approval. The General Manager may approve and execute Change Orders for Public Works Subject: Purchasing Policies and Procedures Page 29 of 30 Effective Date: 08-25-2023 Project Contract Time Extensions that do not involve any increase in contract price over the approved Contingency. Approval of Time Extensions is specifically not delegated below the General Manager/Assistant General Manager, except as identified in Section 7.1.1. (d). For delegation of authority for assignments, refer to Section 1.3.3. of this Policy. Section 7.4 Change Orders to Public Works Contracts The General Manager hereby delegates the authority to review and recommend Requisitions and Change Orders for Public Works Contracts to the Director of Engineering in accordance with the Department Director delegated authority as presented above in Section 7.1.3. This delegated authority includes authority for award and authorization of payment of Change Orders including unilateral credit change orders. The functional authority level listed above describes the highest level of signature approval needed. Intermediate levels of approvals as they relate to the review of the Change Orders, shall be further described in the Public Works Change Management procedures as approved by the pertinent Department Directors. Extra work, deletions or other revisions will not be fragmented into multiple changes in order to circumvent established authority thresholds. Contracts Administration shall review all Change Orders over $35,000. Section 7.5 Procard The Director of Finance may delegate or assign any or all of the following duties to the Purchasing Manager: Procurement Card (Procard) Program – The Procard Program allows specifically authorized employees to purchase goods and services without competitive sealed bids thereby eliminating the purchase Requisition, purchase order, invoice, and check requirements for these purchases. Approval for use of a Procard must first be obtained from the OC San’s Procard Administrator, with the concurrence of the Purchasing Manager and appropriate Manager and Department Director. Any request for an increase (transactional/monthly) over the amounts specified in the Procard Policy SOP 401-1-06, must first be obtained from the Purchasing Manager. Article 8. Revision History Version Date By Reason 1.0 4/1/16 2.0 7/11/16 3.0 11/29/18 Purchasing Mgmt Updates to reflect new Purchasing Ordinance No. OCSD-52. 4.0 9/14/21 Purchasing Mgmt Updates to reflect new Purchasing Ordinance No. OC SAN-56. Subject: Purchasing Policies and Procedures Page 30 of 30 Effective Date: 08-25-2023 5.0 8/25/23 Purchasing Mgmt Updates to reflect new Purchasing Ordinance No. OC SAN-61.