HomeMy WebLinkAboutResolution 1994 - 0033ALL DISTRICTS
Actions re Electrification of Pump Drives
at Treatment Plant No. 2. Job
No. P2-42-1
Approving Change Order No. 7
to the plans and specifications
for Job No. P2-42-1
Moved, seconded and duly carried:
03/09/94
That Change Order No. 7 to the plans and specifications for Electrification of Pump
Drives at Treatment Plant No. 2, Job No. P2-42-1, authorizing a net addition of
$1,032.00 to the contract with Ziebarth & Alper and C.S. Alper Construction Co.,
Inc. for three items of additional work, granting a time extension of 503 calendar
days for completion of said additional work, and assessment of liquidated damages
at $2,000 per day for 26 days, be, and is hereby, approved.
Accepting Job No. P2-42-1 as
complete
Moved, seconded and duly carried:
That the Boards of Directors hereby adopt Resolution No. 94-33, accepting
Electrification of Pump Drives at Treatment Plant No. 2, Job No. P2-42-1, as
complete, authorizing execution of the Notice of Completion and approving the Final
Closeout Agreement. Said resolution, by reference hereto, is hereby made a part of
these minutes.
ALL DISTRICTS
Receive and file Summons and
Complaint. Roadway Construction Co ..
Inc. vs. Javaid Contractors. Inc. and
County Sanitation Districts of Orange
County. Harbor Judicial District Case
No. 94C0873
Moved, seconded and duly carried:
That the Summons and Complaint, Roadway
Construction Co., Inc. vs. Javaid Contractors,
Inc. and County Sanitation Districts of Orange
County, Harbor Judicial District Case
No. 94C0873, relative to a stop notice filed by a
subcontractor against Districts' contractor, be,
and is hereby, received and ordered filed; and,
FURTHER MOVED: That the Districts' General Counsel be, and is hereby, authorized to
appear and defend the interests of the Districts.
-8-