HomeMy WebLinkAboutResolution 1983 - 0132RESOLUTION NO. 83-132
AWARDING JOB NO. PW-085-1
A JOINT RESOLUTION OF THE BOARDS OF DIRECTORS
OF COUNTY SANITATION DISTRICTS NOS. 1, 2, 3,
S, 6, 7 AND 11 OF ORANGE COUNTY, CALIFORNIA,
RESCINDING JULY 13, 1983 BOARD ACTION AND
AWARDING CONTRACT FOR BULK CHLORINE SAFETY
PIPING AND PLATFORMS AT PLANTS NOS. 1 AND 2,
JOB NO. PW-085-1
* * * * * * * * * * * * * * *
WHEREAS, the Board of Directors at its regular meeting on July 13, 1983,
authorized the General Manager to receive bids and award a contract for Bulk Chlorine
Safety Piping and Platforms at Plants Nos. 1 and 2, Job No. PW-085-1, in an amount
not to exceed $60,000.00: and,
WHEREAS, bids were received and publicly opened on July 26, 1983: and,
WHEREAS, the low bid of $86,344.00 exceeds the engineer's estimate and
·-'"maximum authorized award amount: and,
WHEREAS, the Districts' engineer has evaluated th~ bids and the engineer's
original estimate and found that an error was made resulting in an estimate that did
not reflect current market prices: and,
WHEREAS, said evaluation has determined that the low bid received is
representative of the cost of constructing said project.
NOW, THEREFORE, the Boards of Directors of County Sanitation Districts Nos. 1,
2, 3, 5, 6, 7 and 11 of Orange County, California,
DO HEREBY RESOLVE, DETERMINE AND ORDER:
Section 1. That the Board's action of July 13, 1983, authorizing the General
Manager to receive bids and award a contract for Bulk Chlorine Safety Piping and
Platforms at Plants Nos. 1 and 2, Job No. PW-085-1, in an aIOC>unt not to exceed
$60,000.00, be, and is hereby, rescinded: and,
Section 2. That the written recommendation this day submitted to the.Boards of
"N-1" AGENDA ITEM #9(N) -· ALL DISTRICTS "N-1"
.. l ......... ...: .. • · •• • ...... -~~' · .... , ..... t-' •••
Directors by the Districts' Deputy Chief Engineer that award of contract be made to
Dorado Enterprises, Inc~·.for Bulk Chlorine Safety Piping and Platforms at Plants
Nos. l and 2, Job No. PW-085-1, and bid tabulation and proposal submitted for said
work are hereby received and ordered filed; and,
Section 3. That the contract for Bulk Chlorine Safety Piping and Platforms at
Plants Nos. 1 and 2~ Job No. PW-085-1, be awarded to Dorado Enterprises, Inc. in the
total amount of $86,344.00 in accordance with the terms of their bid and the prices
contained therein; and,
Section 4. That the Chairman and Secretary of District No. 1, acting for
itself and as agent for Districts Nos. 2, 3, S, 6, 7 and 11, are hereby authorized
and directed to enter into and sign a contract with said contractor for said work,
pursuant to the specifications and contract documents therefor, in form approved by
·the General Counsel; and,
"N-2"
Section S. That all other bids for said work are hereby rejected.
PASSED AND ADOPTED at a regular meeting held August 10, 1983.