HomeMy WebLinkAboutItem 05 Late Communication1
ORANGE COUNTY SANITATION DISTRICT
Memorandum
December 2, 2020
TO: Operations Committee
Orange County Sanitation District
FROM: Kelly A. Lore
Clerk of the Board
RE: LATE COMMUNICATION – Item No. 5
The Clerk of the Board received communication from Assistant General Manager Lorenzo Tyner
after the publication of the agenda was presented to the OCSD Operations Committee requesting
removal of Item No. 5 from consideration due to a recently filed protest.
5. PLANT WATER PIPELINE REPLACEMENT IN KINNISON, 2020-1272
LINDSTROM, AND SCOTT TUNNELS AT PLANT NO. 2, PROJECT NO.
FE18-14
RECOMMENDATION: Recommend to the Board of Directors to:
A. Receive and file Bid Tabulation and Recommendation for Plant Water Pipeline
Replacement in Kinnison, Lindstrom, and Scott Tunnels at Plant No. 2, Project
No. FE18-14;
B. Award a Construction Contract to MMC Inc. for Plant Water Pipeline
Replacement in Kinnison, Lindstrom, and Scott Tunnels at Plant No. 2, Project
No. FE18-14, for a total amount not to exceed $1,134,000; and
C. Approve a contingency of $170,100 (15%).
Originator: Kathy Millea