Capital p rove m e nt P rog ra m
Contract Performance Report
February 6, 2019
Contents
• Construction Contracts
• Design Consultant Agreements
• Master Budget Projects
• Staff Augmentation Contract
Active Contracts
by Contractor / Consultant
Table 1.3
Active Construction Contracts by Contractor
Contractor/Project Number Project Name Current Contract Construction Contracts
Value
Abhe&SVOboda,Inc. By Contractor
P2-118 Activated Sludge Aeration Basin Deck Repair at Plant No.2 $ 906,975
Access
J 126E Pacific Roof Fall Protection and Skylights $ 418,0D0 See Ta b I e 1.3
AMPCO Contracting
FE16-05 Buried Water Valve Support Upgrades at Plant 2 $ 139,000
Amtek Construction
J-126AH Hot Surfaces Insulation PS/P2/Bay Bridge PS/Slater PS $ 452,757
1-126BFG Lights,Ladder and Walkway Hazards $ 557,759
Charles King Company,Inc.
6-17 District 6 Trunk Sewer Relief $ 3,699,301
FE15-10 East Lido Force Main Rehabilitation $ 1,389,0D0
Filanc
FEIS-09 CenGen Hot Water Pipe Bracing at Plant 1 $ 94,784
Table 2.1
Active Design Consultant Contracts by Consultant
Project Project Name Agreement Original Number of Amendments
Number Type Value Amendments To Date
AECOM Technical Services,Inc. $ 20,923,626 7 $ 721,2SB
344 Rehabilitation of Western Regional Sewers PDSA $ 12,761,337 7 $ 721,25- Design Consultant Contracts
P3-100 Digester Rehabilitation at Plant 1 PCSA $ 2,761,337 0 $ -
PI-129 Return Activated Sludge Piping Replacement at Activated Sludge Plant No.1 PDSA $ 523,039 0 $ -
Arndls $ 7, 7,000 2 $ 1,39,027 By Consultant
5-67 Bay Bridge Pump Station Replacement PDSA $ ,13137,000 1 $ 139,027
J-126 Safety Improvements Program PDSA $ 1,540,000 1 $ I,So0,000
Black&Veatch $ 18,141,423 4 $ %M,396
P2-98 Primary Treatment Rehabilitation at Plant 2 PDSA $ 19,141,423 4 $ 908,396 See Ta b I e 2.1
Brown and Caldwell $ 38,082,044 26 $ 5,776,476
5-60 Newport Force Main Rehabilitation PCSA $ 2,231,925 4 $ 839,714
J-117 Ocean Outfall System Rehabilitation PDSA $ 6,778,015 16 $ 4,405,708
J-117A Interplant Effluent Pipeline Rehabilitation PCSA $ 1,121,666 0 $ -
J.124 Digester Gas Facilities Rehabilitation PDSA $ 11,770,000 0 $ -
P2-107 SCADA System and Network Upgrades PDSA $ 2,818,197 6 $ 531,054
P2-92 Sludge Dewatering and Odor Control at Plant 2 PCSA $ 4,798,328 0 $ -
J-1176 Outfall Low Flow Pump Station PCSA $ 8,563,913 0 $ -
Contract Performance
Active Construction Contracts
Table 1.2
Contract Performance -Active Construction Contracts
OriginalProject No Construction
Orders%Complete Amount
cwkcd ns
2-72B 9% $ 58,242,000 $ - $ 58,242,000
6-17 92% $ 3,699,301 $ 344,931 $ 4,044,232
FE15-10 94% $ 1,389,000 $ - $ 1,389,000
Plant Projects
FE14-03 100% $ 594,000 $ 19,739 $ 613,739
FE15-06 100% $ 909,700 $ - $ 909,700
FE15-07 37% $ 1,790,000 $ - $ 1,790,000
FE16-10 93% $ 529,350 $ - $ 529,350
FE16-14 16% $ 459,674 $ - $ 459,674
1-117A 97% $ 12,609,012 $ 606,339 $ 13,215,351
J-117B 0% $ 90,200,000 $ - $ 90,200,000
J-126AH 70% $ 452,757 $ - $ 452,757
1-126BFG 33% $ 557,759 $ - $ 557,759
1-126E 87% $ 418,000 $ - $ 418,000
1-126JK 0% $ 3,637,601 $ - $ 3,637,601
J-126L 0% $ 212,700 $ - $ 212,700
J-126PQ 0% $ 786,000 $ - $ 786,000
P1-101 97% $ 126,908,300 $ 10,091,285 $ 136,999,585
PI-115B 59% $ 2,235,563 $ 39,129 $ 2,274,692
P2-110 72% $ 16,730,000 $ 993,300 $ 17,723,300
P2-92 95% $ 49,850,000 $ 1,328,604 $ 51,178,604
P2-92A 86% $ 3,304,000 $ 224,179 $ 3,528,179
See Table 1.2
Change Order Rates Over Time
Chart 1.2
Change Order Rates Over Time
All Closed Projects
53%
5.2%
/ s.o%
5.00% %' 4.7% 4.7% 4.7;o4.7Yo4.7% U% 454:
4.6Y.
3.8%
4.00% 3.8%3.BY. 3.85e
35%
3AY.
3.5%
3.00%
2.00% Note: Contracts closed this quarter are listed on this graph
Change
Contracts Closed in Last Quarter Original Value Orders
1.00% FE16-05 Buried Water Valve Support $139,000 12.01%
Upgrades at Plant
o.00%
N T Q N N M Q 0 N 0 O N f+l O N T O 0 N 0 0 0 N 0 O N T Q N 0 C 0 C 0 N 0 V 0 N
pOp pOp pOp pO� pO� pO� pO� O O O O O O O O O O O ryO O O O O O O O O O O O O O O O O O O O O O O O O O O
O O O O O O O .N-� N .�-1 .M-1 .�-� N .a-. N N .N-1 .�-1 eN-1 ems-. .ni .�i Or10
d Cl d CI U U U U U U U U U U U U d U U C C U U U U U U U U U U U U Cr U U U 8 U U U 0 U U U
See Chart 1.2
Master Consultant Agreements
• Master Design Agreements
• 2009 (expired) Table2.7
Activity Report for 2017 Master Agreements for Wastewater Treatment Studies
Firm
• 2012 (expired) Brown and Caldwell Task Order Status Project t cription FY18-19 FY19-20 FY20-21
No Task Orders Issuedd Date
to Date
PLAN2017-01(Wastewater)
• 2 015 (expired) FISCAL YEAR TOT 0.00
Spill Prevention,Control,and Countermeasure Plan $2821800
AECOM 2017-02-01 W W Open for Sludge Dewatering and Odor Control at Plant 1
PLAN2017-02(Wastewater) Amendment No.1 $10935.00
• 2018 (active) FISCAL YEAR TOTAL $39 151.00 $0.00 $0.00
No Task Orders Issued to Date
HDR Engineering
PLAN2017-03(Wastewater)
FISCAL YEAR TOTAL $0.00 $0.00 $0.00
Studies
l
• V t u d i e s No Task Orders Issued to Date
• 2017 CEQA Studies
• 2018 Planning Studies — Collections
• 2017 Planning Studies — Wastewater Treatment
List of Projects
Under Master Budgets
W� BudgetPage
Program Budgetgl&, (Sect 8)
Planning Studies $55,000,000 51 Table 3.1
Research $8,500,000 49 Table 3.2
Small Construction Projects $55,000,000 47 Table 3.3
Information Technology $10,000,000 48 Table 3.4
Operations and Maintenance Capital $15,622,000 50 Table 3.5
Table 3.3
Small Construction Projects Program - Status Report
Project Number Project Name Status Allocated Budget
FEIO-21 FE10-21 Area 02 Craig Regional Park Manhole Improvements Design S 1,359,000
FE12-10 FE12-10 IT Server Room Cooling Improvements Closed S 956,086
FEH-04 FE13-04 Plant No.2 Trickling Filter Chemical Odor Control Close-Out S 4,730,000
FE14-03 FE14-03 Rehabilitation of Digester Mixing Pumps at P2 Digesters E, H,R,S,�Close-Out S 1,360,000
FE14-OS FE14-05 Plant No. 1 Fleet Services UST Leak Remediation Design S 1,487,311
FEL"l FE15-01 Fullerton Creek Channel Crossing Close-Out S 90,000
Staff Contract
• Jacobs Project Management
• May 2016 to June 2020
• To June 2023 with three 1-year renewals)
Table 4.1 Staff Augmentation Contract Status
Total Fees Time
Contract $41,000,000 86 months (1)
Actuals to Date $13,741,711 34% 32 months 37%
Remaining $27,258,289 66% 54 months 63%
(1)Assuming three 1-year extensions
Table 4.2 Staff Augmentation Labor Summary
This Quarter Inception to Date
Labor Hours 12,434 102,358
Full Time Equivalents 27.6 21.3
Labor Costs (no expenses) $1,412,025 $13,419,057
Average Hourly Rate $114 $131
Questions ?.