Project Drivers
• Agreements with City of Fountain Valley: follow building code,
ADA compliance, permit occupied buildings
• Aging buildings, multiple trailers, extensive rehabilitation
• Consolidation of employees and business functions
• New buildings provided the lowest cost alternative
• OCTA asked us to move our front entry to support 1-405
widening and Ellis freeway on-ramp ( No longer a driver)
• Preservation of Plant 1 land for future process needs, as
identified by Master planning efforts
Plant 1 Administrative Buildings Under
Agreements with City of Fountain Valley
2013 agreement
Ago As
War c,-
\ _ JJ
ld rr'
1 1 Ser, Administration
3 � Building
Rif
Y T \
\
2008 agreement
=' Aging Buildings
e c Risk Mgt Trailer - 2000
r� � .Y
`:S r li; � .1.■ U■■.rYn .i �� .fir � �_
f ` 1 :a!3 r.�r ti... �•.
Administration — 19641 1971, 1976, 1990
Human Resources — 1971 (Lab), 1996
PCl/EIM Trailers 1996
�
A
!'
kl Z�4` f
i►, i o
Purchasing - 1980
. . . . . . . . . �i
j Laboratory - 1990
�j. . . . . . . .
r . . . . . . . . . c, s
.. � y -
i
` III f��1•II�
Trailers E, F — 2001 — GWRS, Contracts,
Maintenance, Electrical Engineering
M . . . a �.
Trailers A, B — 2003 - Engineering
.._ .-._. -..__._.. ._... .... _ Y j' ��� __ �-.-ram' ►il.-.�.. _�.
.. i�_�R1r r• .� ..-i�isr.wn7�_ .t..._ .- `" _ _sec.._ �'r
Distributed Staff
-+ Widely distributed staff -+ Over 100 staff in 40,000 sq. ft. of trailers
SAN
Purchasing- 9 I � ;1- � ' � Administration - 125
iINLh
Fleet Services - 8 —' ;1 � . . y 1
-+ ^ Risk Mgt Trailer- 10
Reuse of
Vacated space II ++� _ r1✓
Control Center- 13
Building 6 - 13
I Trailers E, F - 19
Trailers A, B -74 v
::III Ills, i
�...rr.. �• y __ -,,, 'o'er. 'Ipi(r► w
•• ate':-��■.1+• _ ' � `��, �`n ��
J 1_ /
� �■�• � IIIIItI�
■ �1
Currently Planned Location : North of Ellis Avenue
� �• 1 "� ! 1.
Property Acquisition Status
.Purchase Price
Bender $10,619,180 Closed Feb 2017
Mt. Langley $9,750,000 Closed Mar 2018 r R
M Langley 1+
Xm
Sukut Parcels TBD In Progress �; �,.
• . Sukut
'o n ri ParcelsIs
.
!�' Bender '. _,
■
Pl -128 Headquarters Complex, Site and Security
and Entrance Realignment Program
r.,
Headquarters Complex
Administration
---_..; Laboratory
Parking
'' �� r
P1 North
A
• P1 Entrance Realignment
Building Demolition
P1 South
0► �� Perimeter Security
• Trailer Demolition
" ► # Storm Drain Improvements
• 4
Garfield Avenue
Consultant Status
HDR — Design Consultant
• Contract Awarded June 2016 ($11,785,709)
• Original Schedule: June 2016 — May 2018
• Amendment #1: Sep 2016 for Property Evaluation ($97,240)
• Amendment #2: Pending for New Site and Revised Scope
LSA — CEQA Consultant
• Contract Awarded June 2016 ($420,927)
• Original Schedule: June 2016 — June 2017 (12 months)
• Amendment #1: Pending for New Site and Revised Scope
Currently no plans to request additional contingency on either contract.
Changes Since June 2016
• Location — North of Ellis Avenue instead of P1 Southwest
• New Elements
• Pedestrian/Utility Bridge
• Multi-Level Parking Structure
• Maintenance Engineers now in Building (formerly Plant 1)
• Security Wall on Ward Street
• Time
• Escalation — Construction Costs
• Staff and Consultant Costs for Evaluation of Alternatives
• OCTA/Caltrans Front Entrance Realignment
Then and Now
2016 SP-194 Alternate Site Evaluation 2018 P1-128 Concept Site Plan
-F=
NEWLABBUILDING
U
7 �
s
NEW ADMINISTRATION
3 BUILDING
Z O L�
Cost Reduction Options
1. Budget Entrance Realignment and Building Demo separately
2. Rehabilitate Mt. Langley and Reduce Size of New Building
3. Delay, Eliminate, or Reduce Parking Structure
4. Eliminate Pedestrian/Utility Bridge
5. Eliminate Upgrade of Perimeter Fence Along Ward Street to
Block Wall
Project Options Without Sukut Properties
Mt.Langley Mt.Langley
' Mt.Langley
Sukut � ���
Sukut
Bender -
i \ Sukut
Bender
Plant 1
Bender �v �` Plant 1
�— Plant t
Option #1 Option #2 Option #3
• Demolish Existing Mt. Langley 0 Renovate Existing Mt. Langley 0 No Use of Mt. Langley Property
Building Building for Offices 0 Build New Lab on Plant 1
• Build New Lab Building at Mt. 0 Build New 3-Story Lab/Admin 0 Build New 4-Story Admin Building
Langley Building at Ellis at Ellis
• Build New 4-Story Administration 0 Nominal Public Parking at 0 Nominal Public Parking at
Building at Ellis Administration Building in Small Administration Building
• Nominal Public Parking at Parking Structure 0 All Administration Staff Parking on
Administration Building 0 All Administration Staff Parking Plant 1
• All Administration Staff Parking on on Plant 1
Plant 1