HomeMy WebLinkAbout95.Item 13 PPP Board 03-22-2017_FE16-08 Authorize GM to Award ConstructionCarbon Canyon Clay Pipe Repairs Project No. FE16-08 Authorization for General Manager to Award Construction Contract March 22, 2017 Carbon Canyon Repairs •Clay pipe installed in 2009 •Some segments have a severe material defect Sancon $ Repairs and Concerns •Cured-in-place structural lining designed in-house •Two bids received March 16th •Sancon Engineering, Inc. $303,563 •Insituform Technologies $431,646 •2-foot hole found on March 13th. •More failures may occur before lining starts •$150,000 contingency to cover repairs that might be needed. Recommended Action •Authorize the General Manager to receive and review bids, and award a construction contract to the lowest responsive, responsible bidder for an amount not to exceed $432,000 for the Carbon Canyon Clay Pipe Repairs, Project No. FE16-08. •Authorize a construction contingency of $150,000 for the Carbon Canyon Clay Pipe Repairs, Project No. FE16-08