HomeMy WebLinkAbout95.102517 Late Communication - Distributed 2016-17 CIP Annual Report.pdf d� , r�t AWN gap t � Orange County Sanitation District B I in u ■ ■ for the ld 9 Fulupe CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2016/ 17 directorfrom the . engineering Every day, the Orange County Sanitation District's (OCSD) Engineering Department is focused on the future of the agency. Our goal is to make sure OCSD is prepared and equipped for future operations while maintaining our expected levels of service. This past year, we completed a Facilities Master Plan to assure OCSD's capability to meet regulatory requirements, future capacity demands, level of service goals, and to meet our Board of Director's policies for enhanced resource recovery and energy independence. With the use of clever engineering, we were able to lay out a 20-year Capital Improvement Program (CIP)that coordinates and optimizes the refurbishment and replacement of our collection system and treatment assets. The master plan balances the on-going treatment capacity needs, available staffing to deliver projects, and our inflation adjusted current cash flow to provide world class asset management. The recent completion of several studies on odor, biosolids, and water reuse provided a strong foundation for our master planning efforts. Our facilities are being designed to not only treat the water coming in, but to recover the valuable resources in that water. We are building resiliency by focusing on resource recovery, creating energy independence, and being fiscally responsible, which in turn helps us build a sustainable model for the future. With this clear plan in place, I am confident OCSD will be able to deliver its vital services to the public we serve at the lowest possible cost. On behalf of the Engineering Department, I would like to extend our gratitude to the Board of Directors and our rate payers for their continued support. A Rob Thompson, P.E. Director of Engineering {caplW improvement project}page 3 ., �. J . �. �_ - �- Y,� � c +��' n _ }.. _ � r J� y J� y'J P r. II ! � l � TY ✓ "�l '� r�y+9i�� s yn. ' ...Sii___ �� .Y ..C� .rt w � _� i A's -1' r>-�� a �n ,i ..A.r • � xf}� •b.e�:: f - p q� +1� �a�µa a iq- r/' table of contents Agency Information p7 Capital Improvement Program Overview p7 Community Outreach Program p9 Awards pll Planning and Research p13 Treatment Plant No. 1 p14 Treatment Plant No. 2 p15 Collection System Projects p 15b Financial Data and Contract Activity p17 Program Cash Flow p16 Contract Activity p20 Engineering CIP Projects p22 Board of Directors p26 .w tai....p,- ,,,e,,t p,o,Iem'1 [age 5 . fir • : :-_• � .a .�� - `. JJI y � .� �rJ ! •Fir. t, _ � • � a J - � r i t r '• Cured-in-p a installation for the Red Hill - Sewer Im ant Project Over 1,000 feet of pipe wa 0aMlitated using this method. The existing ✓lines were originally constructed -" - in the 1960's and 1970's. mapual mipm ii e.eleoe�e.a.a 75t introduction Agency Information The Orange County Sanitation District is a public agency that • provides wastewater collection, treatment, and recycling for 2.6 million people in central and northern Orange County. We have background two operating facilities that treat wastewater from residential, commercial, and industrial sources. The wastewater from these communities is conveyed through 396 miles of regional sewer and 15 pump stations to either the reclamation plant in Fountain Valley or the treatment plant in Huntington Beach where it is treated and sent for water recycling or released into the Pacific Ocean. Over the years, we have evolved from a wastewater treatment facility to a resource recovery facility that treats wastewater as the resource that it is, not a waste. We convert wastewater into clean water, energy, and soil amendments. Capital Improvement Program Overview The Capital Improvement Program (CIP) is our blueprint for addressing the future demands and needs of the agency. Our newly updated CIP details the planned projects that will maintain, enhance, and adapt our facilities into the future. The program was put together by first identifying the issues that need to be addressed. The issues range from condition assessments of our current assets, current and anticipated regulations, capacity, resiliency, health and safety, and overall OCSD resource recovery initiatives. A project list was developed for each collection system drainage basin and pump station, as well as for each in-plant process area that included project descriptions, project elements, and cost. Once the complete list was created, the projects were prioritized to develop a timeline and budget for execution. The comprehensive effort resulted in the Capital Improvement Program Master Plan which will be carried out over the next 20 years. We program to invest over$2 billion in capital in the next 10 years.This includes 80 projects that stretch from research and planning all the way through construction and commissioning. These projects will allow OCSD to continue providing a reliable and necessary service to our rate payers at the lowest life cycle cost. The CIP is a large endeavor that requires the participation and support from staff throughout the agency. There are over 100 members of the Engineering Department whose job, day in and day out, is to support the CIP. However, additional resources are needed to carry out the complex projects that are planned, designed, and constructed. We utilize on-call staff from local firms to supplement our Engineering staff on an as-needed basis. This allows us the flexibility of soliciting a specific skill set for a predetermined amount of time, and the ability to swiftly adjust staffing to meet shifting needs. We currently have approximately 20 supplemental staff members working at our facilities. The culture of ownership and dedication carried out by our talented team is passed on to our supplemental staff, allowing us to manage and implement the projects effectively and efficiently. For additional information regarding the Capital Improvement Program, please visit our website at www.ocsd.com/construction or by contacting our Construction Hotline at 714-378-2965 or via email at constructionhotline@ocsd.com (caplW improvement project}page 7 r � rJ z k i M1 '' % m ni wl •�i . R Y I . 2 � • _ lip 1 I T• r. �s t 1 1 Install tion f 30-inch diameter pipe for the Red Hill Se er I proyement Project in the Cities of Tustin; Irvine,and Santa Ana.Over one mile of pipe was replaced with a larger diameter pipe at a depth of approximately 20 feet. EMM e P Jea B.H.8 programcommunity outreach The Capital Improvement Program (CIP) has projects sprinkled throughout central and northern Orange County, as well as at our two plants in Fountain Valley and Huntington Beach. It is no surprise that these projects have the potential to impact our neighbors. This means that we must keep our rate payers informed of the activities and solicit their input in planning and design to mitigate the potential impact to their daily activities. The Community Outreach Program was developed to establish a relationship with the community to ensure they are well informed of the CIP projects prior to construction. The purpose is to build a strong rapport that allows the outreach team to be the liaisons and advocates for the community, and to make sure the concerns, issues, and questions of the public are addressed prior to and during construction. We strive to educate the public on the importance of maintaining and upgrading the infrastructure to preserve their quality of life. TF The outreach program is comprised of: • Community Liaison • Neighborhood Bulletins • Community Meetings • Presentations • Community Database and Research • Social Media • Construction Hotline • Website • E-mail Notifications • Plant Tours • Letters, Notifications, and Flyers • On-site Visits hL • Media Relations To learn more about the Capital Improvement Program and the Community Outreach Program, please visit our website at www.ocsd.com/construction. You can reach our Community Liaisons by contacting our Construction Hotline at 714-378-2965 or via email at constructionhotline@ocsd.com. (caplW improvement projectj page 9 i h� i i i Awards American Academy of Environmental Engineers & Scientists Honor Award in Planning for Biosolids Master Plan Honor Award in Environmental Sustainability for Effluent Reuse Study Santa Ana River Basin Section of the California Water Environment(SARBS) Supervisor of the Year-William Cassidy Communicator Awards Silver Award of Distinction - CIP Annual Report 2015-2016 I I ' (capital improvement projects page It 1 - r _ - I • 11�,I�II 1. •.•I II •�•.�•�Y ILI ------------------- I • r _ • Ilbr•I •�.��I I• :I - ,I•h�rr •rrri• i r11 rr planning The Capital Improvement Program has various components and that take meticulous planning, coordination, and management. Every project goes through a rigorous evaluation that often research begins or derives from a study. Below are some of the largest studies conducted during the past year that are setting the tone for the CIP's future. Biosolids Master Plan One of the strategic goals in the agency's 2013 Five-Year Strategic Plan was to study biosolids management options. The study for the Biosolids Master Plan was recently completed. The Biosolids Master Plan evaluated the biosolids market and investigated technology options for future Plant No. 2 digestion facility replacement, keeping in mind OCSD's plan to accommodate Orange County's food waste diversion needs. The result was a comprehensive plan for Plant No. 2 digestion facilities to be implemented over the next twenty years. The new digestion facilities will generate Class A biosolids, which will provide a sustainable, cost-effective, and diverse biosolids management strategy for OCSD as specified in the strategic goal. Currently, the project team is developing a programmatic Environmental Impact Report (EIR) for the projects recommended by the Biosolids Master Plan, with certification planned for summer 2018. Collections Capacity Evaluation Evaluating and monitoring the flow entering our facilities is crucial to ensuring our plants are properly built and operated. Last year, approximately 85 flow monitors were installed throughout the service area to gather data that will be analyzed as part of the Collections Capacity Evaluation Study. The main objective of the study is to update the existing collections hydraulic model to identify and prioritize capacity-related projects in our collections system. The flow data collected will be used to calibrate the model, and to analyze the amount of inflow and infiltration that enters the system during wet weather events. Data used to estimate flows such as population projections will also be updated to make the hydraulic model more accurate. This study will be completed in 2018. 2017 Facilities Master Plan A Facilities Master Plan is used to guide the CIP based on the identified needs. Last year the development of the 2017 Facilities Master Plan began to validate and prioritize OCSD's 20-year capital improvement program plan, which will be the basis for a sewer rate study scheduled for later this year. The Facilities Master Plan focused on assessing OCSD's capability to meet regulatory requirements, future capacity demands, level of service goals and initiatives set by the Strategic Plan, to determine the scope, schedule and budget of projects that are needed. The plan also incorporated projects identified by other recent more focused master plans and planning studies, such as the Biosolids Master Plan, Odor Control Master Plan, and the Effluent Reuse Study. The result is CIP outlays of$2.5 billion and $5 billion, for the next 10 and 20 years, respectively. The next step is to take this information and conduct a rate study to recommend a rate structure for the next 5 years. The rate study is slated to be completed by October 2017. Odor Control Master Plan As part of our good neighbor policy, an Odor Control Master Plan was conducted to further improve our odor control systems. The plan identified nuisance-level odors for each process area utilizing the Odor Profile Method, which is the first application of this method for wastewater processes. The Odor Profile Method is a tool to identify odors that are below the detection limit of standard analytical methods, yet odorous and detectable by the human nose. Pilot testing of odor control technologies was also conducted to determine particular odorant removal rates for each filter technology. The results help determine the best treatment to address odorants present at process areas. The combined testing methods formed the basis for the Odor Control Master Plan which provides a guide for the necessary future investment to ensure odor control is effective for each plant process area. (Capital improvement pm t)page 13 reclamation plant Plant No. 1 is a 100-acre facility located in Fountain Valley adjacent to the Santa Ana River, 1-405, and the Orange County Water District. The aging facility is undergoing some major upgrades to continue providing quality service. These are some of the projects we are working on. Sludge Dewatering and Odor Control Where: East side of Plant No.1 What: Enhancement of solids processing and odor control systems. New facilities will reduce the water content of our trucked biosolids reducing the hauling costs, resulting in cost savings of $3.6 million annually. Why: Higher treatment level has created more solids to be handled and processed. When: Construction began in 2013, completion scheduled for 2019. Headworks Complex, Site and Security, and Entrance Realignment Program Where: North end of Plant No. 1 and property across Ellis Avenue. What: Relocation of the administration offices from the north end of Plant No. 1 to a new property across Ellis Avenue from the existing location. Upon construction of the new building, the old office buildings will be demolished. Why: The current offices can't accommodate administrative staff resulting in personnel being spread out through the plant in temporary trailers. The new building will be large enough to house all of the Plant No. 1 administrative staff in a joint location. Construction will include administration offices, laboratory, and a parking structure. When: Project currently in preliminary design. Construction anticipated for 2020 with a three-year project duration. Headworks Rehabilitation and Expansion Where: North-east side of Plant No. 1 What: Rehabilitation and expansion of the Headworks Facility. Includes replacing peak wet weather pumping capacity, replacing and upgrading grit removal systems, upgrading odor control system, and installing a more reliable power supply to the facilities. Why: To increase the life of critical assets, Headworks is the heart of the process. Improve service to other areas in the plant, and meet the level of service. When: Project is currently in design, construction anticipated for 2020. (capital improvement project)pW 14 treatment plant Plant No. 2 is a 100-acre facility located in Huntington Beach adjacent to the Santa Ana River, Huntington State Beach, and Brookhurst Street. The plant is in the midst of major upgrades and improvements that are preparing us for current and future needs. These are some of the projects we are working on. Ocean Outfall System Rehabilitation - Phase A Where: Adjacent to Santa Ana River trail between Plant No. 1 and No. 2, and east side of Plant No. 2 What: Rehabilitation of the 84-inch and 120-inch interplant lines that run between the two plants. Repair the wetwell and junction boxes of the Ocean Ouffall Booster Station. Why: To extend service life of facilities by approximately 20 years. When: Construction began in summer 2017, estimated completion for mid-2019. Ocean Outfall System Rehabilitation - Phase B Where: East side of Plant No. 2 What: Construction of new joint Ouffall Low Flow Pump Station and Plant Water Pump Station facility, and rehabilitation of the existing Ocean Ouffall Booster Station, Central Power Generation Building, Effluent Pump Station Annex, and Standby Power Facility. Why: To repair and improve the reliability and efficiency of the Ocean Ouffall System at Plant No. 2, and accommodate lower flows to ocean due to expansion of Groundwater Replenishment System (GWRS). When: Project is currently in design, construction anticipated for fall 2018 with completion in 2022. Sludge Dewatering and Odor Control Where: West side of Plant No. 2 What: Construction of facilities to reduce biosolids handling and disposal costs and add odor control components. Old structures no longer needed will be demolished. Why: To replace aged sludge dewatering facilities and add odor control. When: Project is currently in construction with completion estimated for 2020. [capital improvement project}page 15 collection There are 396 miles of regional sewer and 15 pump stations in the OCSD collection system. A system that collects flow from 2.6 million people who reside and frequent our service area. Projects within the collection system require a different approach than those within our plants because of the elaborative coordination required with the cities, the public, and other system agencies. Showcased in the map are projects that are currently in construction or will be in the next couple of years. projects Newhope Sewer Replacement Project - Phase A (State College Sewer Project) Where: State College Blvd. from Yorba Linda Blvd. to south of SR-91, Yorba Linda Blvd. from State College to Associated Road—Cities of - Fullerton and Anaheim. What: Installed new, larger sewer line. Newhope Sewer Replacement Project — Why: To allow flow to be rerouted so more water is available for Phase B (State College Sewer Project) recycling, to abandon the Yorba Linda Pump Station and eliminate maintenance and operating cost, to provide greater capacity. Where: State College Blvd. from south of SR-91 to Orangewood When: Construction began in May 2016, completed summer 2017. Avenue—City of Anaheim. What: Installing new, larger sewer pipeline ranging from 48 inches to 54 inches. Why: Project is continuation of Phase A. Once entire segment is completed, an additional 8 million gallons of water will be available for recycling. When: Project currently in final design, construction anticipated from Western Regional Sewers Rehabilitation LA Summer 2018-Fall 2020. Where: Seal Beach Blvd., Los Alamitos Blvd., Cerritos Avenue, HABRA BREA Bloomfield Avenue, Denni Avenue, Moody Street, Katella Avenue, Orange Avenue, Western Avenue—Cities of Anaheim Buena Park, Cypress, La Palma, Los Alamitos, Seal Beach, ORBA and unincorporated areas of the County of Orange. FULLS TON 0 LINDA What: Rehabilitating or replacing 17 miles of pipe along PLACENTIA four distinct sewer lines, and replacing the wet well and installing odor control measures at B ENA Westside Pump Station. LA RK Why: Aging infrastructure, need to upgrade to ALMA continue providing safe and reliable service. ANAHEI When: Project currently in preliminary design, CYPRESS VILLA construction anticipated for 2019. PARK r1 LOS STANTON ALAMITOS ORANGE GARDEN GROVE SEAL EACH WESTMINSTER rf SANTA / FOUNTAIN ANA TUSTI VALLEY HUNTINGTON BEACH IRVINE Red Hill Sewer Improvements �, COSTA Where: Red Hill Avenue from McGaw ■ MESA Avenue to Mitchell Avenue, and intersection of Newport Avenue and Mitchell Avenue—Cities of Tustin, Irvine, and Santa Ana. ` What: Rehabilitated and/or replaced '�,° 1It't.�:d% - •'- NEWPORT segments of an existing trunk line BEACH LEGEND Sewer pipelines and an interceptor line. — Why: To extend the life of the sewer - - Plane No.1 (P11 line and eliminate risk of spill Plant No.2(P21 during wet weather flows. Pump stations When: Construction began in May 2016, unincorporated completed summer 2017. orange County Seal Beach Pump Station (white areas) Rehabilitation Where: Corner of Seal Beach Blvd. and Westminster Avenue, District 6 Trunk Sewer Project and Westminster Avenue between Seal Beach Blvd. and Springdale Street—Cities of Seal Beach and Where: Newport Blvd. between Pacific Coast Highway and Industrial Way; Westminster. and Pomona Avenue and 17th Street—Cities of Newport Beach and Costa Mesa. What: Rehabilitation of existing Seal Beach Pump Station and dual force main system. What: Installation of new sewer pipe to increase the size of the existing pipeline, rehabilitation of some segments of pipe, as well as Why: Aging infrastructure. Project will increase system manholes. reliability, modernize and standardize equipment, and address odor and corrosion concerns to extend service Why: Pipe is severely corroded and needs to be replaced with larger life by 30-40 years. pipe to allow additional capacity. When: Project currently in preliminary design, construction When: Construction from September 2017—Spring 2018. anticipated for 2019—2021. {eapitar impsemen pmjeet}page 15b Y+ �. / I 4A. l LI I .�.�,0 - Cd� t; I 1 Ss ads •ti � I The p0 feet of pipe that was installed under the 91 s Freeway in Anaheim was encased in steel. Pic*(r d here + is the launch pit for the jack and bore operation o5-Sta College Boulevard. Page L8 The Capital Improvement Program budget represents the dollar financial data amount allocated to projects from project development to closeout. The individual projects are closely evaluated to confirm that the • contract appropriate funds are budgeted. While this annual report focuses on the efforts made by the activity Engineering Department, the numbers noted in the following tables and charts represent the agency's overall Capital Improvement Program which includes projects by Information Technology and Operations and Maintenance. The chart below shows the 10-year budget for all the proposed CIP projects, including projects that are not fully scoped or identified which are designated as Replacement, Rehabilitation, and Refurbishment. Fiscal Year 2017-18 through Fiscal Year 2026-27 Net CIP Outley $2,458,634,000 RR&R $132,418,000 S% Non-Engineering 2% $38,977,856 Collections 21% $508,916,556 14% Joint $353,923'854 2 on Plant No. 2 $665,761,267 Plant No. 1 $758,636,467 310/0 (oapital improvement project)page 17 At the end of the year the net outlay is compared against the program actual expenditures to evaluate what occurred during that time and determine if any adjustments need to be made. cash The graph below shows the actual expenditures for the past few years and the proposed net outlays for the years to come. The flow charts showcase the actual expenditures for the reporting period (FY16/17) and the net outlay for the current year (FY17/18). SSW M $300 M =50 M $200 M $150 M $loo M ESOM 2AM4FY So Y1293 FY 1344 FY 1A95 FY 1596 FY 16-1] Y 1]-18 0. FY ButlgaVAduels "M $$JM $1RM $1EBM $13BM $1g0M $18BM $1e3M $23CM $WBM $332M $289M $2]SM $28BM E250M I F.FIJII ■/Wtllde ■Protected e inch manhole at Red Hill and Mitchell Avenue in Over I manholes were also rehabilitatedandlor replaced as part of the project. �s Fiscal Year 2016-17 Actual CIP Expenditures $137,706,036 Non-Engineering 1% $1,3Zs, Collections 32% $43,792,261 24% Plant No. 2 $33,821,018 Plant No.1 21% � $29,066,708 Joint 22% $29,723,914 Fiscal Year 2017-18 Net CIP Outlay $148,060,657 Non-Engineering 5% $7,773,778 Collections 26% $37,761,923 17% Joint $24,785""' 30% Plant No. 2 Plant No. 1 ° $45,078,845 $32,882,22- 22 /o (oppite Improvement p:oja t)page 1B The Engineering Department and Contracts Administration Division stay busy all year long going through an extensive procurement process to award multiple contracts. Over contractthe course of the year four planning studies, seven design contracts, and five construction contracts were awarded, activity totaling almost$60 million. We also completed a total of ten construction projects. The tables below showcase the specific contract activity that occurred during the fiscal year. STUDIESPLANNING 1 AWARDED THIS FISCAL YEAR City/Plant Project No. Project Name Consultant Amount of Award Date of Award Plant No.1,Plant No.2 PS15-06 Seismic Hazard Evaluation at Plant No. Geosyntec $2,578,028 June 2017 1 and Plant No.2 Consultants OCSD Service Area Psi 5-08 Collections Capacity Evaluation Study RMC Water& $2,802,675 August 2016 Environment Plant No.1,Plant No.2, PS15-10 2017 Facilities Master Plan Carollo Engineers $3,132,052 July 2016 &OCSD Service Area Newport Beach PS15-07 Pressurization and Odor Control Study Dudek&Associates, $256478 Sept.2016 at Newport Beach Inc. DESIGN CONTRACTSAWARDED THIS FISCAL YEAR City/Plant Project No. Project Name Consultant Amount of Award Date of Award yorba Linda 2-41-8 SARI Rock Stabilizers Removal Michael Baker $399,008 Sept.2016 International,Inc. Irvine FE16-11 Lane Channel Crossing HDR Engineering, $131,939 June 2017 Inc. Plant No.1,Plant No.2, J-126 Safety Improvements Program Arcadis $1,540,000 Jury 2016 &OCSD Service Area Plant No.1,Plant No.2 J-128 Project Management Information PM Web Inc. $1,022,500 May 2017 System Plant No.1 P1-129 AS1 RAS Header Piping Replacement AECOM Technical $523,039 May 2017 at Plant No.1 Services,Inc. Plant No.2 P2-122 Headworks Modificationsat Plant No. CDM Smith $5,319,930 May 2017 2 for GWRS Final Expansion Plant No.2 P2-98 Primary Treatment Rehabilitation at Black&Veatch $18,141,423 Jury 2016 Plant No.2 CONSTRUCTION 1 AWARDED THIS FISCAL YEAR City/Plant Project No. Project Name Contractor Amount of Award Date of Award Newport Beach, 6-17 District 6 Trunk Sewer Relief Charles King Company, Inc. $3,699,301 Sept.2016 Costa Mesa Brea FE16-08 Carbon Canyon Clay Pipe Repairs SANCON Engineering $303,563 March 2017 Plant No.2 P2-110 Consolidated Demolition and Utility Flatiron West Inc. $16,730,000 January 2017 Improvements at Plant No.2 Plant No.2 P2-92A Truck Loading Bay Odor Control at Kiewit Infrastructure West $3,304,000 Nov.2016 Plant No.2 Plant No.1 FE15-04 Plant No.1 Primary Clarifier Back- United Riggers&Erectors $21,591 July 2016 wash System Demo Inc. (capital improvement project!page 20 CONSTRUCTION I COMPLETED THIS FISCAL YEAR City Project No. Project Name Contractor Newport Beach 5-60 Newport Force Main Rehabilitation Kiewit Infrastructure West Plant No-1 P1-115 Title 24 Access Compliance and Building Rehabilitation Project, Stronghold Engineering, Inc. Package A Plant No.2 J-110 Final Effluent Sampler and Building Area Upgrades Shimmick Construction Plant No.1 J-111 Cengen Emissions Control Project Shimmick Construction Plant No.2 P2-89 Solids Thickening and Processing Upgrades W.M.Lyles Company Plant No.1, FE10-20 2011 Miscellaneous Fall Protection Improvements OConnell Engineering& Plant No.2 Construction, Inc. Plant No.2 FE12-10 IT Server Room Cooling Improvements CDC Engineering and Technology Plant No.2 FE14-06 Plant No.2 Repairs to Air Dampers at OOBS OConnell Engineering& Construction, Inc. Plant No.1 FE15-04 Plant No.1 Primary Clarifier Backwash System Demo United Riggers&Erectors Inc. Plant No.1 FE14-04 Primary Influent Channels Repair at Plant 1 Jamison Engineering it Fjpd�ork for the sheer wall and to, roof level of the Centrifuge Bull Dewatering and Odor Control Prej building design combines cast in place sheer engineering The projects listed below are those that were active during the CIP reporting period. projects COLLECTION t Cities Project Num- Project Description Phase Project Budget ber Costa Mesa,Fountain Valley, 1-17 Santa Ana Trunk Sewer Rehab Completed $6,974,000 Santa Ana Yorba Linda 2-41 SARI Re-Alignment Construction S11,404,000 Yorba Linda 2-41-8 SARI Rock Stabilizers Removal Construction $6,860,000 Fullerton 2-65 Newhope-Placentia Trunk Grade Separation Construction $4,300000 Replacement Fullerton,Anaheim 2-72 Newhope-Placentia Trunk Replacement Construction $112,000,000 Anaheim,Placentia 2-75 Lakeview Grade Separation Project Close-out $330,000 Anaheim,Placentia 2-76 Tustin Rose DICTA Grade Separation Close-out $586,000 Anaheim,Placentia 2-77 Orangethome DICTA Grade Separation Close-out $1,505,000 Seal Beach 3-62 Seal Beach Pump Station Rehabilitation Preliminary Design $54,000,000 Anaheim,Buena Park,Cypress, 3-64 Rehabilitation of Western Regional Sewers Preliminary Design $217,069,000 La Palma,Los Alamitos,Seal Beach,County of Orange Fountain Valley 3-66 405 Widening Project Impacts on OCSD Project Development $528,000 Sewers Newport Beach 5-60 Newport Force Main Rehabilitation Close-out $59,668,000 Newport Beach 5-67 Bay Bridge Pump Station Replacement Project Development $64,000,000 Costa Mesa,Newport Beach 6-17 District Trunk Sewer Relief Construction $7,965,000 Tustin, Irvine,Santa Ana 7-37 Red Hill Sewer Improvements-Reach B Construction $25,213,000 Fullerton FE10-21 Area 02 Craig Regional Park Manhole Im- Design $1,359,000 provements Fullerton FE15-01 Fullerton Creek Channel Crossing Design $260,000 Newport Beach FE15-10 East Lido Force Main Rehabilitation Project Development $2,628,000 Newport Beach FE16-01 Big Canyon Nature Park Improvements Project Development $533,000 Newport Beach FE16-02 Jamboree Sewer Realignment at Big Canyon Project Development $930,000 Brea FE16-08 Carbon Canyon Clay Pipe Repairs Design $1,131,000 Irvine FE16-11 Lane Channel Crossing Project Development $1,251,000 Plant No.2 FE16-13 Collections Infrastructure Relocation at Plant Project Development $216,000 2,Phase I Huntington Beach FE16-14 Slater Pump Station Valve Replacements Project Development $906,000 (cepiEal improvement pryeat)page 22 RECLAMATION PLANT NO. 1 Cities/Plants Project Number Project Description Phase Project Budget Plant No.1 Pl Digester Rehabilitation at Plant No.1 Construction $67,150,000 Plant No. 1 P1-101 Sludge Dewatering and Odor Control at Plant No.1 Construction $188,328,000 Plant No.1 P1-105 Headworks Rehabilitation and Expansion at Plant No.1 Preliminary Design S436.000,000 Plant No. 1 P1-112 Plant Water System Rehabilitation at Plant No.1 Completed $6,157,000 Plant No.t P1-115 Title 24 Access Compliance and Building Rehabilitation Construction $21,717,000 Project Plant No. 1 Pt-123 Trunk Line Odor Control Improvements Construction $9,299,000 Plant No.1 P1-124 Plant No.1 Primary Treatment Upgrades Completed $9,146,000 Plant No. 1 P1-128 Headquarters Complex,Site and Security,and Entrance Preliminary Design $179,067,000 Realignment Program Plant No.1 P1-129 AS1 RAS Header Piping Replacement at Plant No.1 Project Development $3,979,000 Plant No. 1 P1-132 Uninterrupted Power Supply Improvements at Plant No.1 Project Development $4,800,000 Plant No.1 FE12-10 IT Server Room Cooling Improvements Completed $960,000 Plant No. 1 FE14-05 Plant No.1 Fleet Services UST Leak Rome Nation Design $7,032,000 Plant No.1 FE15-09 CenGen Hot Water Pipe Bracing at Plant No.1 Design $425,000 Plant No. 1 FE16-06 Fuel Cell Facilities Demolition Project Development $166,000 Plant No.1 FE16-10 East Basin Distribution Box Repair Design $854,000 Plant No. 1 FE16-12 Garfield Road Perimeter Security Fence Project Development $121,000 TREATMENT PLANT r Cities/Plants Project Number Project Description Phase Project Budget Plant No.2 P2-89 Solids Thickening and Processing Upgrades Commissioning $48,150,000 Plant No.2 P2-91-1 Plant No.2 Digester Facilities Rehabilitation Project Development $49,220,000 Plant No.2 P2-92 Sludge Dewatering and Odor Control at Plant No.2 Construction $90,477,000 Plant No.2 P2-96 Site and Security Improvements at Plant No.2 Construction $252,000 Plant No.2 P2-98 Primary Treatment Rehabilitation at Plant No.2 Preliminary Design $490,880,000 Plant No.2 P2-101 Plant Water System Rehabilitation at Plant No.2 Completed $3,854,000 Plant No.2 P2-196 Boiler System Rehabilitation and Scrubbers H&I Demolition at Completed $3,095,000 Plant No.2 Plant No.2 P2-107 SCADA System and Network Upgrades Design $24,100,000 Plant No.2 P2-110 Consolidated Demolition and Utility Improvements at Plant No.2 Construction $30,300,000 Plant No.2 P2-118 Activated Sludge Aeration Basin Deck Repair at Plant No.2 Design $2,800,000 Plant No.2 P2-122 Headworks Modifications at Plant No.2 for Ell Final Project Development $54,000,000 Expansion Plant No.2 P2-123 Return Activated Sludge Piping Replacement at Plant No.2 Project Development $15,000,000 Plant No.2 P2-124 Interim Food Waste Receiving Facility Project Development $5,400,000 Plant No.2 P2-125 Plant No.2 Southwest Perimeter Screening Project Development $2,800,000 Plant No.2 FE13-04 Plant No.2 Trickling Filter Chemical Odor Control Construction $4,290,000 Plant No.2 FE14-03 Rehabilitation of Digester Mixing Pumps at Plant No.2 Digesters Construction $1,360,000 E, H,R,S,and T Plant No.2 FE15-02 Plant No.2 Control Center Server Room HVAC Upgrade Design $773,000 Plant No.2 FE15-06 Gas Compressor Building Piping Replacement at Plant No.2 Design $3,924,000 Plant No.2 FE16-05 Buried Water Valve Support Upgrades at Plant No.2 Project Development $500,000 Plant No.2 SP-129 Oxygen Plant Demolition at Plant No.2 Completed $3,440,000 {capital improvement project)page 23 PROJECTSJOINT FACILITIES Cities/Plants Project Project Description Phase Project Number Budget Plant No.1,Plant No.2 J-109 CenGen Cooling Water System Replacement Project Completed $11,477,000 Plant No.2 J-110 Final Effluent Sampler and Building Area Upgrades Construction $16,411,000 Plant No.1,Plant No.2 J-111 CenGen Emissions Control Project Close-Out $23,820,000 Plant No.2 J-117 Ocean Outfall System Rehabilitation Preliminary Design $147,000,000 Plant No.1,Plant No.2 J-124 Digester Gas Facilities Rehabilitation Project Development $96,500,000 Plant No. 1,Plant No.2 J-125 Programmable Control Panel Upgrades Completed $2,283,000 Plant No.1,Plant No.2 J-126 Safety Improvements Program Design $19,000,000 Plant No. 1,Plant No.2 J-127 Natural Gas Pipelines Replacement at Plant No.1 and Project Development $1,310,000 Plant No. 2 Plant No.1,Plant No.2 J-128 Project Management Information System Project Development $4,000,000 Plant No. 1 J-36-2 GWRS Final Expansion Coordination Project Development $1,132,000 Plant No.1,Plant No.2 J-98 J-98 Electrical Power Distribution System Project Development $34,608,000 Improvements Plant No. 1 FE16-12 Garfield Road Perimeter Security Fence Project Development $121,000 STUDIESPLANNING I RESEARCH PROJECTS Cities/Plants Project Number Project Description Status Project Budget Plant No.1,Plant No.2 PS15-01 Biosolids Master Plan Active $4,150,000 Huntington Beach PS15-02 Edinger Pump Station Rehabilitation Study Active $1,300,000 Huntington Beach PS15-03 Slater Pump Station Rehabilitation Study Active $1,000,000 Plant No. 1,Plant No,2 Psi 5-06 Seismic Hazard Evaluation at Plant No.1 and Plant No.2 Active $3,860,000 Newport Beach PS15-07 Pressurization and Odor Control Study at Newport Beach Active $535,200 OCSD Service Area Psi 5-08 Collections Capacity Evaluation Study Active $4,529.678 Plant No.1 PS15-09 Wastehauler and Fueling Stations Relocation Study Completed $165,000 Plant No. 1,Plant No.2 PS15-10 2017 Facilities Master Plan Active $4,150,000 &OCSD Service Area Plant No.1,Plant No,2 PS16-01 Stormwater Master Plan Active $1,415,700 &OCSD Service Area Plant No.2 PS16-02 SCE Feed Reliability Improvements Study Active $293.000 Plant No.1 SP-125-15 SCCWRP Nutrient Cycling Sampling Active $95,000 Plant No. 1,Plant No.2 SP-125-17 AquaCritox Evaluation/Design Completed $588,000 Plant No.1,Plant No.2 SP-148 Plant Air System Master Plan Completed $225,000 Plant No. 1,Plant No.2 SP-152 Climate Change Impact Study Active $590,000 &OCSD Service Area Plant No.1,Plant No.2 SP-166 Odor Control Master Plan Completed $1,950,000 Plant No. 1,Plant No.2 SP-173 Effluent Reuse Study Completed $3,250,000 Newport Beach SP-178 Bay Bridge Pump Station and Force Mains Rehabilitation Active $725,000 Study Plant No.1,Plant No.2 SP-195 Capital Improvement Program Management Services Active $300,000 Plant No.1,Plant No.2 SP-196 Process Control Systems Upgrades Study Active $3,554,000 Plant No,1 PS16-04 Rectangular Primary Clarifier Reliability Study Active $420,000 (enpita improvement project)pegs 24 K r t F Aerial view of the Centrifuge Building at Plant No 2 after alb cast in place sheer walls and columns have been placed centrifuges will be located on the second floor of the building;: / r and the rest of the equipment will be on the ground floor. page 25 - 3 board of directors Cities Anaheim La Palma Denise Barnes Peter Kim Brea Los Alamitos Glenn Parker Richard Murphy Buena Park Newport Beach Fred Smith Scott Peotter Cypress Orange Mariellen Yarc Teresa Smith Fountain Valley Placentia Steve Nagel Chad Wanks Fullerton Santa Ana Gregory C. Sebourn Sal Tinajero Garden Grove Seal Beach Steve Jones Ellery Deaton Huntington Beach Stanton Barbara Delgleize David Shawver Irvine Tustin Donald P. Wagner Allan Bernstein La Habra Villa Park Tim Shaw Robert Collacott Sanitary Districts Water Districts Costa Mesa Sanitary District Irvine Ranch Water District James M. Ferryman John Withers Midway City Sanitary District Yorba Linda Water District Al Krippner Phil Hawkins County Areas Member of the Board of Supervisors Michelle Steel (onpiW improvement pryeat)pegs 26 Reclamation Plant No. 1 (Administration Offices) 10844 Ellis Avenue • Fountain Valley, California 92708 • 714.962.2411 Treatment Plant No. 2 22212 Brookhurst Street • Huntington Beach, California 92646 For more information Email:constructionhotline@ocsd.com • Phone:714.378.2965 www.ocsewers.com foe O CC6P1M09