HomeMy WebLinkAboutLate Communication PPP 10-17-18 Ad Hoc Committee.pdfHeadquarters Building, Project P1-128A
Rob Thompson
Assistant General Manager
October 17, 2018
Ad Hoc Committee
Agenda
•Project Scope
•Proposed Programming
•Project Description
•Site Layout / Parking
•Public Areas / Tours / Signage
•Pedestrian Bridge
•Office Areas
•Building Amenities
•Schedule
•Laboratory Rehabilitation
Scope: Consolidate Office Staff FromPlant-side Buildings
Building
Relocating
Staff
Administration Building 119
Engineering Trailers A&B 62
Trailers E & F 28
Human Resources 16
PCI/EIM 28
Laboratory Offices 16
Purchasing 9
Risk Management 11
Control Center (partial)12
Total 301
Existing Building Areas
Building
Relocating
Staff
Actual Area,
sq. ft
Equivalent
Building Area,
sq. ft
Administration Building 119 41,600 41,600
Engineering Trailers A&B 62 17,500 23,600
Trailers E & F 28 10,100 13,600
Human Resources 16 4,200 5,700
PCI/EIM 28 6,100 8,200
Laboratory Offices 16 3,600 3,600
Purchasing 9 2,800 3,800
Risk Management 11 2,300 3,100
Control Center (partial)12 2,300 2,300
Total 301 90,500 105,500
Programming Approach
•Determine project goals and objectives with EMT
•Data Collection:
Site tours of existing work spaces.
Series of meetings held with EMT and key staff to determine space requirements,
adjacencies and building criteria.
•Determine projected staff growth.
•Develop space program detailing all spaces.
Staff Count Basis
Division Current Planned
110 General Manager's Office 6 6
120 Board Services 5 5
140 Public Affairs 7 7
160 Human Resources 16 16
161 Risk Management 11 11
210 Administrative Services 3 3
220 Financial Management 19 19
230 Contracts and Purchasing 22 22
250 Information Technology 50 50
610 Environmental Services Admin 2 2
620 Resource Protecion 38 38
710 Engineering Admim 2 2
740 Planning 14 14
750 Project Management Office 16 16
760 Civil & Mechanical Engineering 40 40
770 Electrical and Control Systems 33 33
875 Maintenance Reliability & Planning 17 17
Growth and Peaking 38
Hot-Desk / Field Work Stations 20
Total 301 359
Space Standards
EMT Managers Supervisors Other Staff Field Staff
Public Space Requirements
Feature Function
Public Plaza at entrance •Public face
•Benefit to area
•Assembly area
Lobby •Reception
•Pre-meeting congregating
•Informational displays
•Security features
Contract/Purchasing Counter •Receiving bid packages
•Public counter
Interview Rooms •Seating area for applicants
•Accessible outside security
Tour Accommodations •Assembly Areas
•Access to bridge
Proposed Board Functions
•Multifunction -no raised dias or permanent seating
•Separate access to secure area for Board, staff
•Separate conference room in public area for committee meetings immediately prior to Board Mtg
•Controlled visibility to lobby (normally open, blocked
for closed sessions)
•Outside visibility?
Proposed Square Footage
Public Spaces 11,800
Board Room 2,800
Lobby / Display 4,700
Meeting Rooms 1,700
Other 2,600
Support Spaces 16,600
Employee Amenities 1,800
Collaboration Spaces 6,200
Building Support 8,600
Offices 65,100
Circulation / Exterior Wall 15,500
Total 109,000
LEED Certification
Direct Benefits of Certification
•Requires accountability for the entire project team to implement and follow through with sustainable goals and/or requirements
•Public recognition of OCSD’s commitment to sustainable practices
Outcomes for Certified Projects
•Reduced operating costs and improved operations and maintenance (O&M) from commissioning, staff training, additional metering and increased building performance.
•Enhanced occupant well-being from the use of healthier materials
•Environmental benefits that can be quantified due to increased tracking and data collection
LEED Certification
Certified = 40-49 pts, Silver = 50-59 pts, Gold = 60-79 pts, Platinum = 80+ pts
Category B.O.D.Maybe + Cost No
Integrative Process 1 0 0 0
Location and Transportation 2 3 0 11
Sustainable Sites 1 2 7 0
Water Efficiency 8 2 1 0
Energy & Atmosphere 26 1 6 0
Materials & Resources 5 3 0 5
Indoor Environmental Quality 8 3 5 0
Innovation & Design 6 0 0 0
Regional Priority 3 0 1 0
Total 60 14 20 16
LEED Gold
LEED PLATINUM –0% -7% COST PREMIUM
Design Objectives
•Code Compliance
•Efficiency
•Space
•Energy
•Cost
•Meetings Spaces / Collaboration
•Light
•Circulation
Site Layout
Visitor Circulation
Employee Circulation
Board Member Circulation
Bridge
Building Amenities
Included in New Building
•Break Rooms on each
floor
•Catering kitchen for
events
•Staff showers and lockers
•Site provisions for food
trucks
Provided Plant Side
•Existing Fitness Center
•Bike Storage
•Some on plant-side
employee parking.
Most parking on
building side
View From Ellis Avenue
View From Bandelier Circle
Lobby Area
P1-128 Program Budget
Project Budget 179,067,000
Headquarters Building
Construction Costs
Demolition 3,900,000
Site Work / Parking 10,000,000
Building 60,200,000
Bridge 9,300,000
Escalation to Mid Point 9,600,000
Subtotal - Construction $93,000,000
Non-Construction Costs 28,850,000
Project Contingency 19,667,000
Bandilier Property Purchase 18,550,000
Subtotal - Headquarters $160,067,000
Plant 1 South Security $9,000,000
Laboratory Allowance $10,000,000
Schedule
Demolition
Design
Permit
Construction
Procurement
Construction
Ellis Property
2018 2019 2020 2021 2022 2023
PreliminaryDesign
2024
Bandilier Property
FinalDesign
Laboratory Rehabilitation
•During pursuit of Sukut Parcels, alternatives to
replacing the Laboratory were investigated
•Staff now believes rehabilitation a viable option that would extend the life of the existing building
•Purchase of Mt. Langley has freed office space in the lab to allow staging of work
•Further review has concluded we could outsource enough analytical work to avoid temporary relocation
•20-years after rehab, Lab would be replaced off site.
•Intent is to retain a disinterested consultant to verify
the feasibility of Rehab
Ad Hoc Committee
•Role?
•Next Meeting?