HomeMy WebLinkAboutOCSD 02-23RESOLUTION NO. OCSD 02-23
MAKING CERTAIN FINDINGS RELATING TO SIGNIFICANT
ENVIRONMENTAL EFFECTS IDENTIFIED IN THE FINAL
SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT FOR
IMPLEMENTATION OF THE EFFLUENT PUMP STATION ANNEX,
JOB NO. J-77 AND COLLECTION SYSTEM ODOR AND
CORROSION CONTROL PROGRAM; ADOPTING A MITIGATION
MONITORING AND REPORTING PROGRAM SUPPLEMENTING
THE 1999 STRATEGIC PLAN EIR; CERTIFYING THE FINAL
SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT FOR THE
EFFLUENT PUMP STATION ANNEX. JOB NO. J-77 AND
COLLECTION SYSTEM ODOR AND CORROSION CONTROL
PROGRAM ("PROJECT"); AND AUTHORIZING THE FILING OF A
NOTICE OF DETERMINATION RE SAID PROJECT
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE
ORANGE COUNTY SANITATION DISTRICT MAKING CERTAIN
FINDINGS RELATING TO SIGNIFICANT ENVIRONMENTAL
EFFECTS IDENTIFIED IN THE FINAL SUPPLEMENTAL
ENVIRONMENTAL IMPACT REPORT FOR IMPLEMENTATION OF
THE EFFLUENT PUMP STATION ANNEX, JOB NO. J-77 AND
COLLECTION SYSTEM ODOR AND CORROSION CONTROL
PROGRAM; ADOPTING A MITIGATION MONITORING AND
REPORTING PROGRAM SUPPLEMENTING THE 1999 STRATEGIC
PLAN EIR; CERTIFYING THE FINAL SUPPLEMENT AL
ENVIRONMENTAL IMPACT REPORT FOR THE EFFLUENT PUMP
STATION ANNEX, JOB NO. J-77 AND COLLECTION SYSTEM
ODOR AND CORROSION CONTROL PROGRAM ("PROJECT");
AND AUTHORIZING THE FILING OF A NOTICE OF
DETERMINATION RE SAID PROJECT
WHEREAS, the Board of Directors of the Orange County Sanitation District
("District"), hereinafter referred to as "Board", is presently considering the
approval of the Effluent Pump Station Annex ("EPSA") and Collection System
Odor and Corrosion Control Program ("OCP"); and,
WHEREAS, on October 27, 1999, the Board adopted a Final Program EIR
for the Strategic Plan ("PEIR"), which identified projects and programs needed to
accommodate the projected population growth in its service area through 2020;
and,
WHEREAS, the PEIR identified (1) the need to upgrade the Foster Pump
Station ("FPS"), which acts as a back-up pump to the ocean discharge outfall,
and (2) the existing odor system control program, which consists of intermittent
application of caustic soda at various locations in the collection system; and,
WHEREAS, the District proposes to modify the program evaluated in the
PEIR by (1) constructing a new back-up pump station, the EPSA, to replace the
FPS, and (2) the continued operation and future installation of continuous
chemical feed systems at various locations along the collection system; and,
WHEREAS, the District is the lead agency for the preparation and
consideration of environmental documents for the Effluent Pump Station Annex
and Collection System Odor and Corrosion Control Program , pursuant to the
California Environmental Quality Act of 1970, as amended, ("CEQA"), the State
of California CEQA Guidelines and District CEQA procedures; and,
WHEREAS, in accordance with CEQA Guidelines § 15163, District staff
determined that a supplement to the PEIR (SEIR) was required because only
minor additions or changes were necessary to make the PEIR adequately apply
to the EPSA and OCP; and,
WHEREAS, District staff consulted with other public agencies and the
general public, and gave them several opportunities to comment on the Draft
SEIR as required by CEQA; and,
WHEREAS, on September 4, 2002, the District staff held a duly-noticed
public workshop to provide a further opportunity for the general public to
comment on and respond to the Draft SEIR; and,
WHEREAS, the Board has objectively evaluated the comments from public
agencies and persons who reviewed the Draft SEIR; and,
WHEREAS, the comments and recommendations received on the Draft
SEIR, either in full or in summary, together with the District staff's responses to
significant environmental concerns raised in the review and consultation process,
have been included in the Final SEIR; and,
. WHEREAS, District staff presented to the Board the PEIR and the Final
SEIR consisting of the Draft SEIR, list of comments on the Draft SEIR, and
responses to the comments received on the Draft SEIR for review and
consideration prior to the final approval of, and commitment to, the two projects.
NOW, THEREFORE, the Board of Directors of Orange County Sanitation
District,
DOES HEREBY RESOLVE, DETERMINE AND ORDER:
1. That the Board of Directors hereby certifies that the Final
Supplemental Environmental Impact Report (FSEIR) has been completed in
compliance with CEQA and the State CEQA Guidelines and that the Board of
Directors has reviewed and considered the information contained in the PEIR as
revised by the FSEIR prior to approval of, or commitment to, the two projects,
..
)
and that the FSEIR, consisting of the Draft SEIR and the Response to
Comments, reflects the District's independent judgment and analysis; and,
2. The Board finds that changes or alterations have been required in,
or incorporated into, the proposed project, which avoid or substantially lessen the
significant environmental effects of the project and adopts the Findings of Fact as
described in Attachment A; and,
3. The District will implement the mitigation measures recommended
in the PEIR and the mitigation measures recommended in the FSEIR to reduce
the significant impacts of the project to a less than significant level.
4. The Board adopts the Mitigation Monitoring and Reporting Program
as described in Attachment B to ensure that all mitigation measures are
implemented; and,
4. The Board authorizes and directs the Board Secretary to file the
Notice of Determination and any other documents in accordance with the
requirements of CEQA and the District's CEQA procedures.
PASSED AND ADOPTED at a regular meeting held December 18, 2002.
,\ ) .1 -; '
. '' ' . ' .. " . 1'
'-. '
ATIEST: . \ ) ~ ' ' .~ '
·~
\ r · .. , J. ' ' . . -( -
Board
•
ATTACHMENT A -FINDINGS OF FACT
ESA / 960436
ATTACHMENT A -FINDINGS OF FACT
I. FINAL SEIR FOR THE PROJECT
The Final Supplemental Environmental Impact Report (SEIR) consists of one volume including
the revised Draft SEIR, comments letters received on the Draft SEIR, and responses to those
comments.
II. THE ADMINISTRATIVE RECORD
CONTENTS OF THE RECORD
The following information is incorporated by reference and made part of the record supporting
these findings and the actions taken by the District in certifying the Final SEIR and approving the
project:
1. The Final Supplemental EIR and all documents relied upon or incorporated by reference in
the Final Supplemental EIR.
2. The Final Program EIR for the 1999 Strategic Plan and all documents relied upon or
incorporated by reference in the Final Program EIR, including the Mitigation Monitoring
and Reporting Plan.
3. All testimony, documentary evidence and all correspondence submitted to or delivered to
the District in connection with the meetings and public hearings at which the Draft SEIR or
Final SEIR was considered by the District.
4. All testimony, documentary evidence and all correspondence submitted to or delivered to
any of the District's member districts in connection with the meetings, workshops and
public hearings at which the Draft SEIR or Final SEIR was considered by the District's
member districts.
5. All staff reports, memoranda, maps, slides, letters, minutes of meetings and other
documents relied upon or prepared by District staff and consultants relating to the project.
6. Any other documents specified by Public Resources Code section 21167.6(e).
LOCATION OF ADMINISTRATIVE RECORD
The District is the custodian of the administrative record, including all CEQA documents and the
other background documents and materials, which constitute the record of the proceedings upon
which the District's Board decisions to certify the Final SEIR and approve the projects are based.
The administrative record is located at the District's administrative offices at 10844 Ellis Avenue,
Fountain Valley, California, 92708.
III. PURPOSE OF FINDINGS
In accordance with CEQA, the Board is required to make a finding under 14 Cal.Code Regs
§ 15091 for each significant effect shown in the previous EIR as revised by the Final SEIR. 14
ESA /960436
•
'"" "I-' ;~1·"' ~ •. ' ' ..
ATIACHMENT A-FINDINGS OF FACT
Cal. Code Regs § 15163. The purpose of these findings is to supplement the previous Board's
findings when they adopted the Strategic Plan PEIR. The previous Board findings, which are
provided in Resolution No. OCSD 99-19, are incorporated by reference herein.
The Final SEIR, prepared in accordance with the California Environmental Quality Act (CEQA),
evaluates the significant adverse environmental impacts that could result from the project.
Section 15091 of the CEQA Guidelines requires that the public agency approving or carrying out
the project shall make written findings for each significant impact identified in the SEIR. These
findings include one of the following:
1. Changes or alterations have been required in, or incorporated into, the project which avoid
or substantially lessen the significant environmental effect as defined in the EIR.
2. Such changes or alterations are within the responsibility and jurisdiction of another public
agency and not the agency making the finding. Such changes have been adopted by such
other agency or can and should be adopted by such other agency.
3. Specific economic, legal, social, technological, or other considerations, including provision
of employment opportunities for highly trained workers, make infeasible the mitigation
measures or project alternatives identified in the final EIR.
These findings accomplish the following:
I. They address the significant environmental effects identified in the SEIR for the approved
project.
2. They incorporate all mitigation measures associated with these significant impacts
identified in either the Draft SEIR or Final SEIR -Response to Comments.
3. They indicate whether a significant effect is avoided or reduced by the adopted mitigation
measures to a less than significant level, or remain significant and unavoidable, either
because there are no feasible mitigation measures or because, even with implementation of
mitigation measures, a significant impact will occur.
The conclusions presented in these findings are based on the PEIR, the Final SEIR and other
evidence in the record of proceedings. The Final SEIR identifies no impacts that remain
significant and unavoidable consequences of the project.
IV. EFFECT OF FINDINGS
To the extent that these findings conclude that various proposed mitigation measures outlined in
the Program EIR as modified by the Final SEIR are feasible and have not been modified,
superseded, or withdrawn, the District hereby binds itself to implement these measures. These
findings, in other words, are not merely information. The mitigation measures identified as
feasible and within the District's authority to implement for the approved project are express
conditions of approval which the District binds itself to upon adoption of this resolution and
project approval. Other requirements are referenced in the Mitigation Monitoring/Reporting
Program ("MMRP") adopted concurrently with these findings, becoming effective through
ESA / 960436 '
2
AITACHMENT A-FINDINGS OF FACT
project implementation. The MMRP developed for the SEIR does not supersede the MMRP
developed for the Program EIR, but rather provides additional measures applicable to the newly
proposed projects. In other words, the projects assessed in the SEIR must be consistent with the
MMRP for the Program EIR in addition to the newly developed MMRP.
V. FINDINGS CONCERNING THE PROJECTS
EFFLUENT PUMP STATION ANNEX
The District proposes construction of a new backup pump station, the Effluent Pump Station
Annex EPSA, to replace the Foster Pump Station (FPS). The proposed EPSA will consist of
three different buildings (a pump station, distribution building, and standby power facility),
associated piping and replacement of the existing Santa Ana River emergency overflow weirs.
Two existing buildings will be demolished to make room for the new buildings and several
conduits and junction boxes will also be demolished or modified. Approximately 40,000 to
50,000 cubic yards ( cy) of soil will be excavated during construction and approximately I 0,000 to
20,000 cy of soil will be needed for fill. Therefore, the net volume of soil to be removed will be
about 30,000 cy, which will require approximately 1,500 round-trip truck trips to remove from
the site. In addition, approximately I .5 acres of existing property will be graded and designed to
generally match existing grades.
Construction activity will take up to 33 months from early 2003 through 2005, with
approximately 750 days (2 years) of actual construction work. The FPS will remain in-service
until the middle of construction of the EPSA, at which time the FPS will be demolished and
removed from the Plant No. 2 site. The on-site construction workforce will likely average about
35 to 45 workers per day over the course of the project. During peak construction activity, this
number will range from approximately I 00 to 150 workers.
ODOR AND CORROSION CONTROL PROGRAM
In an effort to provide a more effective odor control program for the collection system and reduce
corrosion from caustic soda, the District is proposing to implement a new Odor and Corrosion
Control Program (OCP) involving chemicals and application methods recommended in the pilot
study. The chemicals would be stored in above-ground storage tanks installed in local utility
yards. Eight continuous feed systems were recommended in various locations throughout the
collection system, with more possible locations to be identified in the future depending on the
need for odor control. Locations of the future storage tanks have not been determined, but could
be located near sensitive land uses such as residential areas, schools, and care facilities. The
tanks would not be located in areas where zoning restrictions forbid chemical storage.
Installation of the continuous feed systems is a relatively minor operation involving the
installation of temporary polyethylene tanks with PVC pipes running from the tank to the pumps
and injection points. These aboveground tanks have a storage capacity of roughly 4,000 gallons
and range in size from 8 to I 2 feet in diameter and 8 to I 6 feet in height. The tanks would be
ESA / 960436
3
•
•
AITACHMENT A -FINDINGS OF FACT
refilled approximately 1 to 3 times per week. Installation of the feed system and storage tanks
takes one to two weeks and may involve minor excavation, trenching, and potentially temporary
lane closures. The OCP system's overall annual chemical usage would be approximately
1,500,000 gallons of ferric chloride, 500,000 gallons of hydrogen peroxide, 440,000 gallons of
magnesium hydroxide, and 550,000 gallons of nitrates. None of these chemicals are toxic or pose
an air quality hazard to public health if accidentally spilled.
VI. FINDINGS CONCERNING SIGNIFICANT UNA VOIDABLE
ADVERSE IMPACTS
The Final SEIR indicates that the project would not result in any significant unavoidable impact
to the environment.
VII. FINDINGS CONCERNING SIGNIFICANT IMPACTS REDUCED
TO LESS THAN SIGNIFICANT LEVELS BY MITIGATION
MEASURES IN CORPORA TED INTO THE PROJECT
The Final SEIR identifies significant impacts that are reduced to a "less than significant" level by
the inclusion in the project approval of the mitigation measures identified in the Final SEIR.
Changes or alternations have been required in, or incorporated into, the project which avoid or
substantially lessen the significant environmental effects identified in the Final SEIR to a less
than significant level. These changes and alterations are presented in the Mitigation Monitoring
and Reporting program, which the Board is adopting concurrently with these findings.
AESTHETICS
As described in Section 3.2 of the Final SEIR, the new EPSA pump station building would be
visible from adjacent residential neighborhoods and PCH. In addition, the tanks for the odor
control program could be visible from adjacent land uses. These impacts, however, will be
avoided or reduced to a less than significant level based on the following:
a. The Final SEIR identifies mitigation measure M-3.2-1 which requires the
contractor to replace damaged landscaping and restore the construction area near the
property boundary to a condition similar to existing conditions. This will insure that
there will be an equally effective landscape buffer between the new EPSA building and
nearby residential neighborhoods and Pacific Coast Highway. This mitigation measure
will further insure that the existing aesthetic quality and degree of visibility of the EPSA
site is maintained post-construction.
b. The Final SEIR identifies mitigation measure M-3.2-2 which provides that when
siting future chemical feed systems, the District will prioritize industrial sites, such as
storage yards, which are generally not adjacent to sensitive land uses. If an industrial site
is not available, the District will attempt to place the chemical storage tanks out of public
ESA / 960436
4
ATIACHMENT A-FINDINGS OF FACT
view. The District will shield the tanks from public view using fencing or by other
means as appropriate to match the existing character of the surrounding area. This
measure will insure that future tank locations are visually compatible with surrounding
neighborhoods.
c. Although mitigation measure M-3.2-1 and M-3.2-2 reduce any significant
aesthetic impacts to a level of insignificance, the Final SEIR also recommended
mitigation measure M-3.2-3, which requires the District to coordinate with the various
affected cities prior to installing new chemical storage tanks in the service area. This
measure will provide an additional safeguard and allow each affected city input on the
location of the continuous feed systems within their communities. This will further
insure that aesthetic impacts would be further reduced to a level of insignificance.
GEOLOGY AND SOILS
As described in Section 3.3 of the Final SEIR, the proposed EPSA and OCP project could expose
people or structures to potential adverse effects due to rupture of a known earthquake fault, strong
ground shaking, ground failure, including liquefaction and landslides due to seismic activity.
The Final SEIR also concluded that the proposed EPSA project could be located on expansive
soil, creating risks to proposed structures. These impacts, however, will be avoided or reduced to
a less than significant level based on the following:
a. To mitigate potential seismic impacts, the SEIR provides stringent requirements
that apply to the construction of new facilities. The Final SEIR states that "any new
structures under the proposed project would be required to meet updated California
Building Codes standard specific for the underlying geologic materials in order to insure
the safety of the stmctures and its occupant. (See page 3 .3-8). The SEIR also identifies
specific mitigation measures from the 1999 PEIR to mitigate impacts, specifically
mitigation measure 6.6-IA and 6.6-lB. These mitigation measures provide that the
District will design and construct new facilities in accordance with District seismic
standards and/or meet or exceed seismic design standards in the most recent edition of the
California Building code. Mitigation measure 6.6-1 A identifies the "performance
standard" as "minimization of the hazards" and lists the following measures to achieve
minimization of liquefaction hazards:
• De-densification or de-watering of surface or sub-surface soils
• Construction of pile or pier foundations to support pipelines and/or
buildings
ESA / 960436
5
..
•
AITACHMENT A -FINDINGS OF FACT
• Removal of material that could undergo liquefaction in the event of an
earthquake and replacement with stable material
b. To reduce potential geologic hazards relating to the OCP, the Final SEIR
identifies M-3.3-1, which provides that chemical storage tanks and appurtenant piping
and connections will be designed to withstand ground shaking to avoid potential spills
during a seismic event. This measure insures that structural seismic standards will be
incorporated into the design of future tank facilities.
c. To reduce the potential hazards from expansive soils, the Final SEIR identifies
mitigation measure 6.6-IB from the program EIR. As discussed in subsection (a), this
mitigation measure identifies a specific performance standard and provides various
measures to minimize risks associated with expansive soils and liquefaction.
HAZARDS AND HAZARDOUS MATERIALS
The Final SEIR analyzes impacts relating to hazards and hazardous materials in Section 3.4. As
discussed in this section, the proposed EPSA and OCP project would include the transport,
storage, and use of diesel fuel and odor reduction chemicals that could pose a spill or leak hazard.
The Final SEIR further provides that OCP chemical storage site construction could impair or
interfere with emergency response routes due to the temporary lane closures. These impacts,
however, will be avoided or reduced to a less than significant level based on the following:
a. To reduce potential impacts resulting from a potential spill or leak, the Final
SEIR identifies 2 mitigation measures. Mitigation measure M-3.4-1 provides that storage
and use of hazardous materials at the Treatment Plant and OCP sites throughout the
service area will comply with state and federal regulations and storage and dispensing
permits will be obtained as necessary. In addition, the District will follow procedures
relating to the proper handling and storage of hazardous materials at the OCP sites as
required by mitigation measure M-3.4-2. These procedures require the District to (1)
obtain a permit to store hazardous materials from the local fire department; (2) provide
notification to the Orange County health care agency of each storage site location and
caustic soda application site; (3) equip chemical delivery trucks with spill equipment
adequate to contain and clean up any solid or liquid spill; (4) provide chemical storage
tanks with adequate secondary containment; and (5) modify the District's Spill
Prevention Containment and Counter Measure Plan to include the OCP chemical storage
sites. As provided for in mitigation measure M-3.4-3, the District shall require that all
personnel working with such chemicals have health and safety training per OSHA
requirements. Mitigation measure M-3.4-4 requires controlled access at the OCP
chemical storage sites to prevent trespassing and unauthorized encounters with chemical
ESA I 960436
6
ATTACHMENT A -FINDINGS OF FACT
substances. Combined, these measures insure that any risks associated with the use of
hazardous materials are reduced to a level of insignificance.
b. To reduce the risk of exposure to hazards and hazardous materials during
construction, the Final SEIR identifies two mitigation measures. Mitigation measure M-
3.4-5 provides that any contaminated soils encountered on the project site during
demolition, site clearance, or construction activities shall be removed from the project
site and disposed of off-site in accordance with applicable hazardous waste regulations.
Mitigation measure M-3.4-6 requires that all structures to be demolished must be
investigated for the presence of lead paint and/or asbestos containing material and
precautions must be taken to insure the safe removal and disposal of these materials.
These measures will reduce the risk of exposure to construction personnel in areas
immediately adjacent to the construction site.
c. To reduce potential interference with emergency response routes to a level of
insignificance, the Final SEIR identifies mitigation measure M-3 .4-7 which requires the
District to provide notice of construction and lane closures lasting more than one day to
local emergency service providers within 72 hours prior to construction activities.
District coordination with these emergency service provides would insure that alternative
routes are available for emergency vehicles.
HYDROLOGY
The Final SEIR analyzes hydrology and water quality impacts in section 3.5. The Final SEIR
concludes that the EPSA and OCP projects could violate water quality standards or waste
discharge requirements due to ground disturbance activity during construction. These impacts,
however, will be avoided or reduced to a less than significant level based on the following:
a. To reduce potential water quality impacts, the Final SEIR identifies mitigation
measure M-3 .5-1 which requires the District to prepare a storm water pollution
prevention plan to identify best management practices to minimize water quality impacts
resulting from EPSA construction activities. The District will also file a Notice oflntent
for de-watering activities during construction to the Santa Ana Regional Water Quality
Control Board and all de-watering activity would comply with the general NPDES permit
(CAG998001) for de minimus discharges including construction de-watering. Mitigation
measures for de-watering activities are also discussed in the PEIR in measure 6.7-2A and
6. 7-2B which will further reduce water quality and hydrology impacts.
b. To mitigate potential flooding impacts at EPSA and OCP, the District shall
obtain an encroachment permit from the Orange County Flood Control District prior to
ESA I 960436
7
•
•
ATIACHMENT A-FINDINGS OF FACT
working within the Santa Ana River levee, as required by mitigation measure M-3.5-2.
In addition, mitigation measure M-3.5-3 prohibits construction activity in the Santa Ana
River channel. With respect to the OCP, mitigation measure M-3.5-4 provides that no
chemical storage tanks shall be installed within the FEMA-designated l 00-year
floodplain. Therefore, the potential that these facilities will be impacted by future flood,
is less than significant.
NOISE
The Final SEIR identified potential noise impacts during construction of the EPSA and during
operation of both the EPSA and OCP. Construction activities that may generate noise include
demolition, grading and earth moving activities, hauling materials, pile driving, and ultimate
construction of the building structures. Construction noise levels would generally fluctuate
depending on the type, number, and duration of construction equipment.
Potential operational noise sources include testing of emergency generators and back-up pumps,
and additional traffic_ trips at the EPSA. Regarding the OCP, operational noise sources include
potential truck trips to fill the chemical storage tanks. These impacts, however, will be avoided
or reduced to a less than significant level based on the following:
a. To reduce potential operational noise impacts of the EPSA, the new facilities will
be designed to insulate noise of the machinery, such that the fence line noise standards
would not be exceeded. This will insure that any surrounding sensitive land uses would
not be adversely impacted by the testing of emergency generators and back-up pumps.
b. To reduce potential construction noise impacts at the EPSA, the Final SEIR
identifies mitigation measure M-3.6-2 which requires the construction contractor to
comply with the city of Huntington Beach and Orange County noise standards. In
addition, mitigation measure M-3.6-3 provides that all equipment used during
construction should be muffled and maintained in good operating condition. Moreover,
all internal combustion engine driven equipment should be fitted with intake and exhaust
mufflers that are in good condition. These measures will reduce the noise levels during
construction activity to prevent disturbance of surrounding sensitive land uses.
TRAFFIC
The Final SEIR discusses potential traffic impacts in section 3.7. The Final SEIR concludes that
during periods of peak construction, the EPSA and OCP project would add to traffic to local
access streets during peak commute hours. During peak commute hours, EPSA construction
traffic will temporarily impact the Orange County freeway system and local roadways, primarily
ESA / 960436
8
A IT ACHMENT A -FINDINGS OF FACT
Brookhurst. However, as documented in the Final SEIR, Brookhurst St. operates at LOS A under
existing conditions and would not be adversely impacted. In addition, project construction traffic
would not substantially reduce the level of service on I-405, which conveys over 240,000 daily
trips (over 14,000 of which are trucks) with a peak hour average over 19,000 trips1 at Brookhurst
Street.
Installation of the continuous feed systems and storage tanks takes one to three weeks and may
involve excavation, trenching, and potentially lane closures. Chemical deliveries to storage tanks
could require temporary lane closures one to three times per week. The construction activities
would be short and chemical deliveries would be brief and are not expected to pose significant
traffic impacts.
These impacts, will be further avoided or reduced to a less than significant level based on the
following:
a. Despite the project's nominal or less than significant traffic contribution during
the peak hours, the Final SEIR identified Mitigation Measure M-3.7-1 which limits truck
traffic to non-peak hours to the extent feasible. The project must also comply with
mitigation measure 6.2-1 of the PEIR which requires the District to minimize peak hour
construction traffic. The measure will reduce the volume of construction traffic accessing
the freeway and local streets during the peak commute hours and would ensure that
construction traffic impacts remain less than significant.
b. Mitigation measure M-3.7-2 requires the District to provide construction worker
parking on site for each phase of construction. This will prevent any spill-over parking
effects on surrounding neighborhoods and local streets. Mitigation measure M-3.7-3 also
requires that for any lane closure excavation within the CalTrans right of way, including
Pacific Coast Highway, the District must comply with CalTrans encroachment permit
application project. This last measure will insure that the project would not disrupt traffic
flows on CalTrans rights of way.
1 Caltrans Website accessed October 4, 2002,
http://www.dot.ca.gov/hq/traffops/saferesr/trafdata/200 I all/r280405i .htm
9
ESA /960436
•
ATIACHMENT A-FINDINGS OF FACT
VIII. FINDINGS CONCERNING IDENTIFIED IMP ACTS THAT
WERE DETERMINED TO BE LESS THAN SIGNIFICANT
WITHOUT NEEDING TO IDENTIFY MITIGATION MEASURES
The Final SEIR identifies impacts that are considered to be "less than significant" not requiring
mitigation measures. It is hereby determined that these environmental impacts of the project will
be less than significant.
AIR QUALITY
The Final SEIR analyzes potential air quality impacts in section 3.1. According to the Final
SEIR, construction of the EPSA would emit criteria pollutants. However, the estimated daily
average construction emissions would not exceed the significance thresholds set by the South
Coast Air Quality Management District ("SCAQMD"). Construction related emissions would
primarily be: (l) dust generated from excavation grading, grading and soil removal; (2) exhaust
emissions from powered construction equipment; and (3) motor vehicle emissions associated with
construction activities. As shown on Table 3 .1-4 of the Final SEIR, each distinct phase of
construction activity would not exceed the SCAQMD significance criteria. Nonetheless, as an
added precaution, the Final SEIR identifies mitigation measure M-3.1-1 which requires soil
removal contractors to cover all trucks hauling soil, sand, and other loose materials, or maintain at
least two feet of free board.
The Final SEIR also concluded that the operation of the proposed EPSA and OCP project would
emit criteria pollutants. However, similar to construction emissions, the estimated daily average
emissions would not exceed the SCAQMD significance thresholds or otherwise violate air quality
standards. Although stationary emissions would be generated by the occasional use of back-up
diesel generators, no SCAQMD permits are required because the back-up generators would be
used less than 200 hours per year. Therefore, these emissions are not considered significant. In
addition, the two to three delivery truck trips per week that the OCP facilities would generate a
negligible amount air emissions and would not be significant. Moreover, no additional mobile
source emissions are anticipated because the project entails the replacement of the existing Foster
Pump Station with the EPSA.
The proposed OCP project is anticipated to reduce objectionable odors generated by the
collection system. The OCP would reduce the odorous gases currently generated by the waste
water collection system and is considered a beneficial impact of the project.
HYDROLOGY
The EPSA and OCP project could alter existing drainage patterns and result in erosion and
flooding, especially during construction activities. The existing site, however, is fairly flat and
little erosion or flooding is anticipated to occur. The EPSA, in fact, is located in an area where
ESA /960436
10
ATTACHMENT A-FINDINGS OF FACT
storm water is collected and sent back through the treatment system. Implementation of BMPs
during construction would minimize erosion and siltation impacts. Due to the minimal amount of
excavation, the OCP would not require or result in any change in drainage patterns that could
result in substantial erosion or flooding. Therefore, no mitigation is required for potential
drainage and flooding impacts.
NOISE
Because the OCP requires only 3 trucks per week, additional trips would not raise the ambient
noise in the area significantly and no mitigation is required. Although the proposed EPSA project
could expose persons to, or generate, excessive groundborne vibration or groundborne noise
levels. However, the groundborne noise and vibration levels would be temporary in nature and
would only occur during specified construction phases. In addition, the distances to sensitive
receptors would greatly lessen groundborne noise and vibration perceived at local sensitive
receptors. Therefore, this impact is considered less than significant and no mitigation is required.
TRAFFIC
Operations of the EPSA and OCP project would modify impacts to traffic locally. Regarding the
EPSA, projected numbers of District personnel listed on page 3-32 of the PEIR would not
change substantially as a result of the EPSA project. Operation of the OCP would not increase
truck traffic since the chemical delivery trucks servicing these new locations would replace the
trucks that previously delivered caustic soda for the slug dosing application method. In addition,
the slug application method of discharging caustic soda to the sewer through manholes requires
temporary lane closures lasting less than a whole day. In areas where permanent continuous feed
systems are installed, slug application would be eliminated, reducing the need for lane closures.
This would reduce the existing level of impact.
IX. FINDINGS CONCERNING ALTERNATIVES
The 1999 PEIR, as supplemented by the SEIR addressed alternatives to the program. For
purposes of the Final SEIR, the alternatives to the proposed EPSA and OCP, include proceeding
in accordance with the program analyzed in the PEIR, which included upgrading the existing
Foster Pump Station and continuing caustic soda application for odor control. The following
specific economic, legal, social, technological or other considerations make these alternatives,
which entail proceeding under the original program infeasible or outweighed by the benefits of
this project:
As stated on page 2-1 of the Final SEIR, the District conducted a study assessing the Foster Pump
Station upgrade project identified in the 1999 Strategic Plan and evaluated in the Program EIR.
The study concluded that the Foster Pump Station was ineffective and located on an active fault.
ESA / 960436
11
AITACHMENT A-FINDINGS OF FACT
As such, the study recommended construction of a new pumping facility. The study also
concluded that upgrading the Foster Pump Station would be costly for the minimal benefit
provided. Based on this recommendation, the District developed the EPSA project to avoid these
impacts in a cost effective manner. The EPSA project would avoid impacts that the original
project as conceived in the 1999 Strategic Plan would not.
The OCP was developed to provide greater odor reduction benefit in the collection system than
the original program described in the 1999 Strategic Plan. The OCP would reduce odor and
corrosion impacts more effectively than the original program with minimal cost differences.
X. FINDINGS CONCERNING MITIGATION MEASURES
IDENTIFIED IN THE FINAL SEIR THAT WILL BE
ELIMINATED AND WILL NOT BE ADOPTED AS PART OF THE
PROJECT OR IN THE MITIGATION MONITORING AND
REPORTING PLAN
The Final SEIR identifies Mitigation Measure 3.7-4 that would require all soil haul trucks leaving
the treatment plant to allow 3 minute intervals at a minimum between departures to avoid
bunching at local intersections and surface streets. The District has determined that this
mitigation measure is infeasible because it would impose undue burdens on haul truck operations,
substantially increasing construction periods, substantially reducing efficiency and increasing
costs to such a degree. Furthermore, Mitigation Measure 3.7-1 was identified in the Final SEIR
on page 3. 7-4 as being sufficient in and of itself to reduce the identified impacts to peak hour
traffic to a less than significant level. Therefore, Mitigation Measure 3.7-4 will not be adopted as
part of the project and will not be included in the MMRP.
ESA / 960436
12
ATTACHMENT B -MITIGATION
MONITORING/REPORTING PROGRAM
ESA /960436
AITACHMENT B -MITIGATION AND MONITORING PRO RAM
SEIR FOR EPSA AND OCP
ORANGE COUNTY SANITATION DISTRICT
MITIGATION MONITORING AND REPORTING PROGRAM
FOR THE
EFFLUENT PUMP STATION ANNEX AND
COLLECTION SYSTEM ODOR AND CORROSION CONTROL PRORAM
EFFLUENT PUMP STATION ANNEX (EPSA)
AIR QUALITY
Impact 3.1-1: Construction of the EPSA would emit criteria pollutants. Estimated daily average construction emissions would not exceed significance thresholds
set by the SCAQMD.
Measure (M-3.1-1) Soil removal contractors shall cover all trucks hauling soil, sand, and other loose materials, or maintain at least two feet offreeboard.
IMPLEMENTATION PROCEDURE
I. Include in construction contract
specifications
AESTHETICS
MONITORING AND REPORTING
ACTIONS
Maintain record of site inspection (i.e. truck
trips, coverage for administrative record)
MONITORING
RESPONSIBILITY
OCSD
Impact 3.2-1: The new EPSA pump station building would be visible from adjacent residential neighborhoods and PCH.
MONITORING SCHEDULE
Prior to and during construction
Measure (M-3.2-1) The contractor shall replace damaged landscaping and restore the construction area near the property boundary to a condition similar
to existing conditions.
B-1 Environmental Science Associates
IMPLEMENTATION PROCEDURE
I. Include in construction contract
specifications
GEOLOGY AND SOILS
MONITORING AND REPORTING
ACTIONS
Monitor compliance with construction
contract specifications. Maintain record of
communication and pre and post-construction
site conditions for administrative record
AITACHMENT B -MITIGATION AND MONITORING PROGRAM
SEIR FOR EPSA AND OCP
MONITORING
RESPONSIBILITY
OCSD
MONITORING SCHEDULE
Prior to and during construction
activities
Impact 3.3-1: The proposed EPSA and OCP project could expose people or structures to potential adverse effects due to rupture of a known earthquake fault,
strong ground shaking, ground failure, including liquefaction and landslides due to seismic activity.
Measure (M-6.6-la in the PEIR) During the project design phase for all facilities, the District will perform design-level geotechnical evaluations. The
geotehcnical evaluations will include subsurface exploration and review of seismic design criteria to ensure that design of the facilities meet seismic
safety requirements of the Uniform Building Code.
Site-specific testing for soils susceptible to liquefaction would be conducted. If testing results indicates that conditions are present that could result in
significant liquefaction and damage to project facilities, appropriate feasible measures will be developed and incorporated into the project design. The
performance standard to be used in the geotechnical evaluation for mitigation liquefaction hazards will be minimization of the hazards. Measures to
minimize significant liquefaction hazards could include the following:
• Densification or dewatering of surface or subsurface soils
• Construction of pile or pier foundations to support pipelines and/or buildings
• Removal of material that could undergo liquefaction in the event of an earthquake and replacement with stable material.
Recommendations of the geotechnical report will be incorporated into the design and construction of proposed facilities.
Measure (M-6.6-1 bin the PEIR) Seismic Safety. The District will design and construct new facilities in accordance with District seismic standards
and/or meet or exceed seismic, design standards in the most recent edition of the California Building Code.
Environmental Scien tes
ATIACHMENT 8 -MITIGATION AND MONITORING PR RAM
SEIR FOR EPSA AND OCP
Impact 3.3-2: The proposed EPSA project could be located on expansive soil, creating risks to proposed structures.
Refer to Measure 6.6-lb of the PEIR and implementation procedure described above.
IMPLEMENTATION PROCEDURE
1. Include in construction contract
specifications
MONITORING AND REPORTING
ACTIONS
Monitor compliance with construction
contract specification
Maintain record of construction
specifications, geotechnical evaluation, soil
surveys and construction oversight for
administrative record
HAZARDS AND HAZARDOUS MATERIALS
MONITORING
RESPONSIBILITY
OCSD
MONITORING SCHEDULE
Prior to approving final design and
construction
Prior to and during construction
Impact 3.4-1: The proposed EPSA and OCP project would include the transport, storage, and use of diesel fuel and odor reduction chemicals that could pose a
spill or leak hazard.
Measure (M-3.4-1) Storage and use of hazardous materials at the Treatment Plant and OCP sites throughout the service area will comply with state and
federal regulations and storage and dispensing permits will be obtained as necessary.
Measure (M-3.4-5) Any contaminated soils encountered on the project site during demolition, site clearance, or construction activities shall be removed
from the project site and disposed of off-site in accordance with applicable hazardous waste regulations.
Measure (M-3.4-6) Structures to be demolished will be investigated for the presence of lead paint or asbestos containing material and proper precautions
will be taken for safe removal and disposal of these materials prior to demolition activities.
B-3 Environmental Science Associates
.. .;....
_,.
IMPLEMENTATION PROCEDURE
I. Include in construction contract
specifications
MONITORING AND REPORTING
ACTIONS
Contractor's SPCC Plan to be approved by
the District's Safety Division
2. Modify OCSD SPCC Monitor compliance with the approved
construction contract specifications, OCSD's
3. Notify Orange County Health Care Agency SPCC and approved contractor SPCC
HYDROLOGY
Compliance with approved asbestos and lead
paint removal plans. Monitor removals and
maintain adminstrative record
ATIACHMENT B -MITIGATION AND MONITORING PROGRAM
SEIR FOR EPSA AND OCP
MONITORING
RESPONSIBILITY
OCSD
MONITORING SCHEDULE
Prior to installation
Prior to and during installation
Impact 3.5-1: The proposed EPSA and OCP project could violate water quality standards or waste discharge requirements.
Measure (M-3.5-1) The District will prepare a SWPPP that will identify BMPs to minimize water quality impacts resulting from EPSA construction
activities.
IMPLEMENTATION PROCEDURE MONITORING AND REPORTING
ACTIONS
MONITORING
RESPONSIBILITY
MONITORING SCHEDULE
t
Environmental Science Associates
ATIACHMENT 8-MITIGATION AND MONITORING PR RAM
I. Include in construction contract
specifications
2. Contractor to comply with BMPs outlined in
the OCSD's Storm Water Management Plan
SWPPP to be reviewed and approved by
OCSD's Environmental Compliance &
Monitoring Division
Maintain record of site inspections and
construction oversight.
OCSD
Impact 3.5-3: The proposed EPSA and OCP project would be susceptible to potential flooding impacts.
SEIR FOR EPSA AND OCP
Prior to construction
Ongoing
Measure (M-3.5-2) The District shall obtain an encroachment permit from the Orange County Flood Control District prior to work within the Santa Ana
River levee.
Measure (M-3.5-3) No construction activities would be conducted within the Santa Ana River channel.
IMPLEMENTATION PROCEDURE
I. Coordinate with OCFCD
2. Include in construction contract
specifications
3. Obtain OCFCD permit
NOISE
MONITORING AND REPORTING
ACTIONS
Maintain record of communication with
affected agency, encroachment permits and
construction oversight for administrative
record
Impact 3.6-1: Operations of the proposed EPSA and OCP project would generate noise.
B-5
MONITORING
RESPONSIBILITY
OCSD
MONITORING SCHEDULE
Prior to and during construction
Envirorunental Science Associates
ATIACHMENT B -MITIGATION AND MONITORING PROGRAM
SEIR FOR EPSA AND OCP
Measure (M-3.6-1) The EPSA and emergency generator buildings will be designed to insulate noise of the machinery such that fence-
line noise standards would not be exceeded.
IMPLEMENTATION PROCEDURE
I. Include in construction contract
specifications.
MONITORING AND REPORTING
ACTIONS
MONITORING
RESPONSIBILITY
Maintain record of construction oversight for OCSD
administrative record
Impact 3.6-2: The proposed EPSA project would generate noise during construction.
MONITORING SCHEDULE
Prior to and during construction
Measure (M-3.6-2) During construction phases, the contractor shall ensure that all construction is performed in accordance with the City of Huntington
Beach and Orange County noise standards.
Measure (M-3.6-3) All equipment used during construction should be muffled and maintained in good operating condition. All internal combustion
engine driven equipment should be fitted with intake and exhaust mufflers that are in good condition.
IMPLEMENTATION PROCEDURE
I. lnch.ide in construction contract
specifications
MONITORING AND REPORTING
ACTIONS
MONITORING
RESPONSIBILITY
Maintain record of construction oversight and OCSD
project communication (i.e. public notices,
construction schedule) for administrative
record
MONITORING SCHEDULE
Prior to and during construction
Environmental Scie ciates •
ATIACHMENT B-MITIGATION AND MONITORING PR
SEIR FOR EPSA AND OCP
TRAFFIC
Impact 3.7-1: Periods of peak construction of the proposed EPSA and OCP project would add to traffic along local access streets.
Measure (M-3.7-1) Dirt haul trucks and construction deliveries shall avoid peak traffic periods (7:00-9:00 AM and 4:00 -6:00 PM) to the extent
feasible.
Measure (M-3. 7-2) Parking for construction workers shall be provided on District property for each phase of construction.
Measure (M-3.7-3) Projects that would require lane closure or excavation within a Caltrans right-of-way including the PCH must comply with
Caltrans' Encroachment Permit application process.
IMPLEMENTATION PROCEDURE
I. Include in construction contract
specifications
2. Obtain permit from Caltrans
MONITORING AND REPORTING
ACTIONS
Monitor compliance with construction
contract specifications.
Maintain record of traffic control plan,
permits, and inspection of pre and post-
construction site
B-7
MONITORING
RESPONSIBILITY
OCSD
MONITORING SCHEDULE
Prior to and during construction
Environmental Science Associates
AITACHMENT B-MITIGATION AND MONITORING PROGRAM
SEIR FOR EPSA AND OCP
COLLECTION SYSTEM ODOR AND CORROSION CONTROL PROGRAM (OCP)
AESTHETICS
Impact 3.2-2: The tanks for the OCP could be visible from adjacent land uses.
Measure (M-3.2-2) When siting future chemical feed systems, the District will prioritize industrial sites, such as storage yards, which are generally
not adjacent to sensitive land uses. If an industrial site is not available, the District will attempt to place the chemical storage tanks out of public view.
The District will shield the tanks from public view using fencing or by other means as appropriate to match the existing character of the surrounding
area.
Measure (M-3.2-3) The District will coordinate with the cities prior to installing new chemical storage tanks in the service area.
IMPLEMENTATION PROCEDURE
I. Evaluate prospective storage sites
2. Coordinate with cities to detennine
compatibility of use
GEOLOGY AND SOILS
MONITORING AND REPORTING
ACTIONS
Maintain record of communications with
affected agencies, pre and post-construction
conditions, and construction oversight for
administrative record.
MONITORING
RESPONSIBILITY
OCSD
MONITORING SCHEDULE
Prior to and after tank installation
Impact 3.3-1: The proposed EPSA and OCP project could expose people or structures to potential adverse effects due to rupture of a known earthquake fault,
strong ground shaking, ground failure, including liquefaction and landslides due to seismic activity.
Measure (M-3.3-1) Chemical storage tanks and appurtenant piping and connections will be designed to withstand ground shaking to avoid potential
spills during a seismic event.
Environmental Science es
IMPLEMENTATION PROCEDURE
I. Include in construction contract
specifications
MONITORING AND REPORTING
ACTIONS
Monitor compliance with approved
construction contract specifications.
HAZARDS AND HAZARDOUS MATERIALS
AITACHMENT 8 -MITIGATION AND MONITORING PR
MONITORING
RESPONSIBILITY
OCSD
SEIR FOR EPSA AND OCP
MONITORING SCHEDULE
Prior to and during installation of
tanks
Impact 3.4-1: The proposed EPSA and OCP project would include the transport, storage, and use of diesel fuel and odor reduction chemicals that could pose a
spill or leak hazard.
Measure (M-3.4-1) Storage and use of hazardous materials at the Treatment Plant and OCP sites throughout the service area will comply with state and
federal regulations and storage and dispensing permits will be obtained as necessary.
Measure (M-3.4-2) The District will follow procedures to ensure proper handling and storage of hazardous materials and reduce the potential for spills
at the OCP chemical storage sites. At a minimum, the procedures will include:
• obtain a permit to store hazardous materials from the local fire department;
• provide notification to the Orange County Health Care Agency of the site location and caustic soda application site;
• equip chemical delivery trucks with spill cleanup equipment adequate to contain and clean up any solid or liquid spill;
• equip chemical storage tanks with adequate secondary containment;
• modify the District's SPCC Plan to include the OCP chemical storage sites or ensure that chemical transport contractors have adequate SPCC
plans in place covering the chemical storage sites. The SPCC Plan will cover chemical transfer activities (including DOT requirements}, public
notification and placarding requirements, secondary containment, emergency spill response actions, routine site access control, and site
management and maintenance procedures. The contractor's SPCC Plan would require approval by the District's Safety Division.
Measure (M-3.4-3) The District shall require that all personnel working with hazardous chemicals have health and safety training. This is a legal OSHA
requirement under the Worker Right to Know regulations in the Federal Code of Regulations, Title 29. The training shall include, at minimum, the proper
use of safety equipment, hazard identifications, and proper handling and disposal of spilled hazardous materials.
B-9 Envirorunental Science Associates
ATIACHMENT B-MITIGATION AND MONITORING PROGRAM
SEIR FOR EPSA AND OCP
Measure (M-3.4-4) Access to OCP chemical storage sites will be controlled to allow access only to authorized personnel.
IMPLEMENTATION PROCEDURE
I. Include in construction contract
specifications
2. Modify OCSD SPCC
3. Notify Orange County Health Care Agency
4. Obtain permit from fire departments
MONITORING AND REPORTING
ACTIONS
Contractor's SPCC Plan to be approved by
the District's Safety Division
Monitor compliance with the approved
construction contract specifications, OCSD's
SPCC and approved contractor SPCC
MONITORING
RESPONSIBILITY
OCSD
Impact 3.4-2: OCP chemical storage site construction could impair or interfere with emergency response routes.
MONITORING SCHEDULE
Prior to installation
Prior to and during installation
Measure (M-3.4-7) The District will provide notice of construction and lane closures lasting more than one day to local emergency service providers
within 72 hours prior to construction activities.
IMPLEMENTATION PROCEDURE
1. Include in construction contract
specifications
2. Include 24-hour emergency access in
construction contract specifications
MONITORING AND REPORTING
ACTIONS
Maintain record of signage, public (i.e.
business and fire department) notifications,
inspections, and construction schedule for
administrative record
MONITORING
RESPONSIBILITY
OCSD
MONITORING SCHEDULE
Prior to and during construction
Environmental Scien ces ..
HYDROLOGY
ATIACHMENT B -MITIGATION AND MONITORING PROGRAM
SEIR FOR EPSA AND OCP
Impact 3.5-3: The proposed EPSA and OCP project would be susceptible to potential flooding impacts.
Measure (M-3.5-4) No chemical storage tanks shall be installed within the FEMA-designated I 00-year floodplain.
IMPLEMENTATION PROCEDURE
I. Include in construction contract
specifications
2. Inspection of storage tank site locations
TRAFFIC
MONITORING AND REPORTING
ACTIONS
Compliance with approved construction
contract specifications
Maintain record of construction oversight for
administrative record
MONITORING
RESPONSIBILITY
OCSD
MONITORING SCHEDULE
Prior to installation
Prior to and during installation
Impact 3.7-1: Periods of peak construction of the proposed EPSA and OCP project would add to traffic along local access streets.
Measure (M-3.7-3) Projects that would require lane closure or excavation within a Caltrans right-of-way including the PCH must comply with
Caltrans' Encroachment Permit application process.
IMPLEMENTATION PROCEDURE MONITORING AND REPORTING
ACTIONS
B-11
MONITORING
RESPONSIBILITY
MONITORING SCHEDULE
Envirorunental Science Associates
I. Include in construction contract
specifications
2. Obtain permit from Caltrans
Monitor compliance with construction
contract specifications.
Maintain record of traffic control plan,
permits, and inspection of pre and post-
construction site
ATIACHMENT B -MITIGATION AND MONITORING PROGRAM
SEIR FOR EPSA AND OCP
OCSD
Prior to and during construction
Envirorunental Scien tes
•
ATTACHMENT A -FINDINGS OF FACT
ESA/960436