HomeMy WebLinkAbout1959 Resolution Index 0595-0625Number Title District Date
583-11 Approving and adopting plans and specs for Golden
West Trunk,Unit4,and ordering publication of notice
calling for bids
11 12/03/58
584-2 Authorizing condemnation of property 2 12/10/58
585-3 Authorizing condemnation of property 3 12/10/58
586-11 Authorizing condemnation of property 11 12/10/58
587-5 Employing J.R.Lester Boyle as Engineer;and ordering
Engineering Report
5 11/13/58
588-11 Awarding contract for construction of Golden West
Trunk Sewer,Unit 4,to Doriman Construction Co.,Inc.
11 12/19/58
589-11 Awarding contract for construction of Atlanta Interceptor
Trunk Sewer-Unit 7 to J.S.Barrett,Contractor
11 12/19/58
590 Approving and authorizing execution of contract dated
Dec.10,1958 with John A.Carollo for a 5 year Master
Plan
ALL 12/10/58
591-2 Authorizing Modification No.2 of the 1958 Engineers’
Report
2 12/10/58
592-3 Authorizing Modification No.2 of the 1958 Engineers’
Report
3 12/10/58
593-7 Determining necessity for issuance of additional bonds 7 12/17/58
594-7 Employing J.R.Lester Boyle and Sidney L.Lowry as
Engineers
7 12/17/58
595-3 Awarding contract for Miller-Holder Trunk to J.5.
Barrett
3 01/07/59
596-2 Awarding contract for construction of the Newhope-
Placentia Trunk Sewer to Vido Artukovich &Son
2 01/14/59
597-11 Award to Bejac Construction Co.for construction of
Golden West Street Pumping Station and Force Main
Sewer Unit No.3,Contract 11-5
11 01/14/59
598-11 Awarding contract to Weardco Construction Co.for
construction of Hamilton Ave.Force Main Unit 1-b,
Contract 11-4
11 01/14/59
599 Allowing monthly progress payments to contractors to
exceed not more than 10%of Engineer’s estimate
ALL 01/14/59
600-1 Approving grant deed to Flood Control and authorizing
execution of quit claim deed
1 01/14/59
Number Title District Date
601-5 Authorizing Modification of Engineering Report dated
January,1958
5 01/21/59
602-7 Calling bond election for March 10,1959 to incur a
bonded indebtedness of $2,230,000 for the purpose of
acquiring and constructing sewerage facilities
7
•
03/10/59
603-3 Authorizing condemnation proceedings 3 01/28/59
604-11 Approving and adopting Modification No.2 to the
Engineer’s 1958 Report
11 01/28/59
605-11 Authorizing purchase of Slater property for pumping
plant site;and authorizing recordation of grant deed
11 01/28/59
606-3 Approving and adopting plans and specs for contract 3-
2,Miller-Holder trunk;ordering publication of notice
calling for bids
3 01/28/59
607-11 Approving and adopting plans and specs for contract
11-6,Slater Springdale;and ordering publication of
notice calling for bids
11 01/28159
608-11 Approving and adopting plans and specs for Smeltzer
Bolsa Chica Trunk and Smeltzer Ave.Sewerage Lift
Station;and ordering publication of notice calling for
bids
11 01 /28/59
609-3 Modification No.3 of March,1958 Engineer’s Report 3 02/25/58
610-3 Approving and adopting plans and specs for Miller-
Holder Trunk Sewer,Contract 3-3;and ordering
publication of notice calling for bids
3 02/25/59
611-3 Approving and adopting plans and specs for Hover-
Western Subtrunk Sewer,Sugar Branch,Trask Branch
and Lampson Branch Contract 3-5;and ordering
publication of notice calling for bids
3 02/25/59
612 Approving and authorizing execution of contract with
John A.Carollo,Engineer,for Districts 1,2,3,5,6,7 and
11
ALL 02/11/59
613 Ratifying action of General Manager in ordering plans
and specs and approving and adopting plans and specs
for construction of the Ocean Outfall Booster Station;
and ordering publication of notice calling for bids
ALL 02/11/59
614-5 Approving and authorizing execution of contract for
purchase of Jamboree Road Sewerage facilities
5 02/11/59
615-3 Condemnation for Contract 3-3 3 03/11/59
Number Title District Date
616-2 Approving and adopting Modification No.3 to 1958
Engineers’Report
2 03/11/59
617-3 Receive and order filed tabulation of bids and
recommendation of Engineers and General Manager
that award of contract be made to Steve P.Rados,Inc.
for construction of Miller-Holder Trunk Sewer,Contract
3-2;and authorizing execution of contract
3 03/11/59
618-11
~
Receive and order filed tabulation of bids and
recommendation of Engineers and General Manager
that award of contract be made to L.L.Dobkins
Construction Co.,Inc.for construction of Smeltzer Bolsa
Chica Sewer and Smeltzer Ave.Sewerage Lift Station,
Contract No.11-7;and authorizing execution of contract
11 03/11/59
619 Amending Resolution No.533 as amended authorizing
employment of clerk-typist
ALL 03/11/59
620-11 Receive and order filed tabulation and recommendation
of Engineers and General Manager that award of
contract be made to Dorfman Construction Co.,Inc.for
construction of Slater-Springdale Trunk Sewer,Unit No.
5,Contract 11-6
11 03/11/59
621-1 Award of contract for Ocean Outfall Booster Station at
Plant No.2 to Hoagland-Findlay Engineering Co.And
Kemper Construction Co.,a joint venture and
authorizing execution of contract for said work
1 03/20/59
622-7 Declaring result of canvass of election returns of special
bond election held on March 10,1959
7 03/20/59
623-3 Approving and adopting Modification to the 1958
Engineers Report
3 03/25/59
624-3 Approving and adopting plans and specs for Miller-
Holder Trunk Sewer,Contract 3-4A;and ordering
publication of notice calling for bids
3 03/25/59
625 Opposing Assembly Bill No.1974 in its present form ALL 04/08/59