HomeMy WebLinkAboutResolution 1954 - 0352RESOLUTION NO.352—1 A RESOLUTION ACCEPTING THE CONSTRUCTION OF THE BIJSHARD STREET AND TREAT1~ENT PLANT TRUNK SE1N~RS AND AUTHORIZING THE EXECUTION AND RECORDING OF THE NOTICE OF COMPLETION. The Board of Directors of County Sanitation District No.l of Orange County,California,resolves as follows: WHEREAS,the contractor has completed the construction in accordance with the terms of the contract for the construction of the Bushard Street and Treatment Plant Trunk Sewers;and WHEREAS,the Engineers recommend and th~General Manager concurs in the said recommendation that said work be accepted as completed in accordance with the ter~:is of the contract for the construction thereof; NO~J,THREFORE,BE IT RESOLVED: That the work of the contractor,Jerry Artukovich and N.A. Artukovich Construction Company,a joint venture,for the construction of the Bushard Street and Treatment Plant Trunk Sewers be accepted as completed in accordance with the terms of the contract for the construction thereof; BE IT FURTHER RESOLVED: That the Chairman and Secretary of the Board of Directors of County Sanitation District No.1 of Orange County,California be authorized and directed to execute a Notice of Completion of said work and have same recorded. The foregoing resolution was approved and adopted at a regular meeting of the Board of Directors of County Sanitation District No.1.of Orange County,California,on the 24t~~ day of February ,1954. ~ Secretary,Board of Directors County Sanitation District No. Orange County,California —l — STATE OF CALIFORNIA) ss COUNTY OF ORANGE ) I,ORA MAE MERRITT,Secretary o~the Board of Directors of County Sanitation District No.~~.of Orange County,california, do hereby certify that the foregoing Resolution was passed and adopted at a regular meeting of the Board of Directors of County Sanitation District No.X of Orange C~tinty,California held on the 24th day of FO~Ua?Y ,1954 by the following roll call vote: AYES:Directors Willie U.Warner,J.L.MØx’ide and courtney R.Ch*r~er ~NOES:Directors None ABSENT:.Dtr•ctors Now. IN WITNESS WHEREOF,I have hereunto set my hand and affixed the seal of County Sanitation District ~o.3~of Orange County, ~California,t~iis 24th dayS of ?ObrU~Z’y ,~954 ~37~~ Secretary,Board of Directors County Sanitation District No11 Orange County,California 2 RESOLUTIOW NO.352~2 A RESOLUTION ACCEPTING THE CONSTRUCTION OF THE BUSHARD STREET AND TREATI:ENT PLANT TRUNK SEWERS AND AUTHORIZING THE EXECUTION AND RECORDING OF THE NOTICE OF COMPLETION. The Board of Directors of County Sanitation District No.2 of Orange County,California,resolves as follows: WHEREAS,the contractor has completed the construction in accordance with the terms of the contract for the construction of the Bushard Street and Treatment Plant Trunk Sewers;and WHEREAS,the Engineers recommend and th~General Manager concurs in the said recommendation that said work be accepted as completed in accordance with the ter~as of the contract for the construction thereof; NOU,THEREFOi~E,BE IT RESOLVED: That the work of the contractor,Jerry Artukovich and N.A. Artukovich Construction Comnany,a joint venture,for the construction of the Bushard Street and Treatment Plant Trunk Sewers be accepted as completed in accordance with the terms of tho contract for the construction thereof; BE IT FURTHER RESOLVED: That the Chairman and Secretary of the Board of Directors of County Sanitation District No.1 of Orange County,California be authorized and directed to execute a Notice of Completion of said work and have same recorded. The foregoing resolution was approved and adopted at a regular meeting of the Board of Directors of County Sanitation District No.2 of Orange County,California,on the 24th day of ,1954. ~~~ Secretary,Board of Directors 2 County Sanitation District No. Orange County,California —1— STATE OF CALIFORNIA~ ss COUNTY OF ORANGE ) I,ORA MAE MERRITT,Secretary of~the ~oard of Directors of County Sanitation District NOST 2 of Orange County,California, do hereby certify that the foregoing Resolution was passed and adopted at a regular meeting of the Board of Directors of County Sanitation Distrjc~No.,*of Orange County,California held on the 24th day qt V.b*U*I~ ,1954 by the following roll call vote~ AYES:Directors ~J.$chw.it*.r’,fr.,Hugh W,Ward~rt~ WtUia 0,Wa*’n~r~Char’l.*L.8t*vne,Ch*rl.s Moirgan, L.$~Wissir and cour~tns~’*.~*n4I.r NOES:Directors ABSENT :Dir*stsz’i Dean W.Heasen IN WITNESS WHEREOF,I have hereunto set my hand and affixed the seal of County Sanitation District No.of Orange County, California,this 2~th day of ,1954 ~ecrétáry~oarc Ô~f Directors 2 County Sanitation District No. Orange County,California RESOLUTIOW NO.352~3 A RESOLUTION ACCEPTING THE CONSTRUCTION OF THE BUSHARD STREET AND TREATI:ENT PLANT TRUNK SEWERS AND AUTHORIZING THE EXECUTION AND RECORDING OF THE NOTICE OF COMPLETION. The Board of Directors of County Sanitation District No. of Orange County,California,resolves as follows: WHEREAS,the contractor has completed the construction in accordance with the terms of the contract for the construction of the Bushard Street and Treatment Plant Trunk Sewers;and WHEREAS,the Engineers recommend and the General Manager concurs in the said recommendation that said work be accepted as completed in accordance with the ter~~s of the contract for the construction thereof; NOW,TH2REFO~E,BE IT RESOLVED: That the work of the contractor,Jerry Artukovich and N.A. Artukovich Construction Company,a joint venture,for the construction of the Bushard Street and Treatment Plant Trunk Sewers be accepted as completed in accordance with the terms of the contract for the construction thereof; BE IT FURTHER RESOLVED: That the Chairman and Secretary of the Board of Directors of County Sanitation District No.1 of Orange County,California be authorized and directed to execute a Notice of Completion of said work and have same recorded. The foregoing resolution was approved and adopted at a regular meeting of the Board of Directors of County Sanitation District No.3 of Orange County,California,on the 24th day of F*b~La~ ,1954. ~~~ Secretary,Board of Directors County Sanitation District No. Orange County,California —1— STATE OF CALIFORNIA) COUNTY OF ORANGE ) I,ORA MAE MERR±TT~Secretary of the Board of Directors of County Sanitation District No~3 of Orange County,California, do hereby certify that the foregoing Resolution was passed and adopted.at a regular meeting of the Board of Directors of County Sanitation District No.3 of Orange County,California held on the 24th day of ~‘ebrUa*~,1954 by the following roll call vote: AYES:.Directors ~*O~Z4Ufle~,~U1I ~X.~*rzor’1 ~.~• ~ss.r~chsr~Xos 8tøyans,~1o*eph t~*bb.r and Kugh~~. NOES:Directors ~i*fl~ ABSENT ~~1ICtO~*~O.R.~L.r IN WITNESS WHEREOF,I have hereunto set my hand and affixed the seal of County Sanitation District No.3 of Orange County, California,this 24th day of ,1954 ~5ecretary,Board of Directors County Sanitation District No.3 Orange County,California RESOLUTION NO.352~6 A RESOLUTION ACCEPTING THE CONSTRUCTION OF THE BUSHARD STREET AND TREATi:ENT PLANT TRUNK SEWERS AND AUTHORIZING THE EXECUTION AND RECORDING OF THE NOTICE OF COMPLETION. The Board of Directors of County Sanitation District No.6 of Orange County,California,resolves as follows: WHEREAS,the contractor has completed the construction in accordance with the terms of the contract for the construction of the Bushard Street and Treatment Plant Trunk Sewers;and WHEREAS,the Engineers recommend and th~General Manager concurs in the said recommendation that said work be accepted as completed in accordance with the ter::Ls of the contract for the construction thereof; NOW,THIREFORE,ED IT RESOLVED: That the work of the contractor,Jerry Artukovich and N.A. Artukovich Construction Company,a joint venture,for the construction of the Bushard Street and Treatment Plant Trunk Sewers be accepted as completed in accordance with the terms of the contract for the construction thereof; BE IT FURTHER RESOLVED: That the Chairman and Secretary of the Board of Directors of County Sanitation District No.1 of Orange County,California be. authorized and directed to execute a Notice of Completion of said work and have same recorded. The foregoing resolution was approved and adopted at a regular meeting of the Boerd of Directors of County Sanitation District No. 6 of Orange County,California,on the 24th day of ,1954. ~~ Secretary,&ard of Directors 6 County Sanitation District No. Orange County,California —1— // STATE OF CALIFORNTA) 85 COUNTY OF ORANGE ) I,ORA MAE MERRITT,secretary of’the Board of ~~rectors of County Sanitation DIstrict No.6 of Orange :County,California, do hereby certify that the foregoing Resolution was passed and adopted at a regular meeting of the Board of Directors of County Sanitation District No.4 of Orange County,California held on the 24tb da~r ot ~øbvua~,1954 by the following roll call vote: AYES:Directors £.~~NQ~an ~~i~rnd ~iULs H,~srner NOES:Directors ABSENT : RO*Ø IN WITNESS WHEREOF,I have hereunto set my hand and affixed the sea],of County Sanitation District No. 6 of Orange County, California,this 24th day of F’eb*’UnZI ,1954 ~~ Secretary,‘Board of Directors County Sanitation District No.6 Orange County,California RESOLUTION NO.352~7 A RESOLUTION ACCEPTING THE CONSTRUCTION OF THE BUSHARD STREET AND TREAThENT PLANT TRUNK SEWERS AND AUTHORIZING THE EXECUTION AND RECORDING OF THE NOTICE OF COMPLETION. The Board of Directors of County Sanitation District No.7 of Orange County,California,resolves as follows: WHEREAS,the contractor has completed the construction iii accordance with the terms of the contract for the construction of the Bushard Street and Treatment Plant Trunk Sewers;and WHEREAS,the Engineers recommend and th~General ilanager concurs in the said recommendation that said work be accepted as completed in accordance with the terms of the contract for the construction thereof; NOW,THREFOE,51 IT RESOLVED: That the work of the contractor,Jerry Artukovich and N.A. Artukovich Construction Company,a joint venture,for the construction of the Bushard Street and Treatment Plant Trunk Sewers be accepted as completed in accordance with the terms of the contract for the construction thereof; BE IT FURTHER RESOLVED: That the Chairrian and Secretary of the Board of Directors of County Sanitation District No.1 of Orange County,California be authorized and directed to execute a Notice of Completion of said work and have same recorded. The foregoing resolution was approved and adopted at a regular m~eting of the Board of Directors of County Sanitation District No.7 of Orange County,California,on the ~th day of February ,1954.. ~ Secretary,Board of Directors County Sanitation District No. Orange County,California —1— .:STATE OF CALIFORNIA) s8 COUNTY OF ORANGE ) I,ORA MAE MERRITT,Secretary of the Board of Directors of County Sanitation District No.~7 of Orange County,California, do hereby certify that the foregoing Resolution was passed and adppted at a regular meeting of the Board of Directors of County Sanitation District No.7 of Orange County,California held on the 24th day of P.brusr~,1954 by the following roll call vote: AYES:Director8 Wi~Ui*Mi Wi *2’.~COUTtfl*y ft.Gh*fl4~4r *~d Wintt~rd L,Tadto*k NOES:Directors ABSENT ~D~ra.*t.rs No*e IN WITNESS WHEREOF,I have hereunto set my hand and affixed the seal of County Sax~itat1on District ~o.7 of Orange County, California,this 24th day of ,1954 ~Secretary,Board of Directors -. County Sanitation District No.7 Orange County,California RESOLUTION NO.352—U A RESOLUTIdN ACCEPTING THE CONSTRUCTION OF THE BUSHARD STREET AND TREATIIENT PLANT TRUNK SEWERS AND AUTHORIZING THE EXECUTION AND RECORDING OF THE NOTICE OF COI~LETION. The Board of Directors of County Sanitation District No. of Orange County,California,resolves as follows: WHEREAS,the contractor has completed the construction in accordance with the ter:ns of the contract for the construction of the Bushard Street and Treatment Plant Trunk Sewers;and WHEREAS,the Engineers recommend and th~General Marager concurs in the said recommendation that said work be accepted as co~npleted in accordance with the ter~:s of the contract for the construction thereof; NOW,THEREFOI~E,BE IT RESOLVED: That the work of the contractor,Jerry Artukovich and N.A. Artukovich Construction Company,a joint venture,for the construction of the Bushard Street and Treatment Plant Trunk Sewers be accepted as completed in accordance with the terms of the contract for the construction thereof; BE IT FURTHER RESOLVED: That the Chairman and Secretary of the Board of Directors of County Sanitation District No.1 of Orange County,Califernia be authorized and directed to execute a Notice of Completion of said work and have same recorded. The foregoing resolution was approved and adopted at a regular rn~eting of the Board of Directors of County Sanitation District No.U of Orange County,California,on the 24th day of February ,1954. -~7 ~__ C— Secretary,Board of Directors County Sanitation Jistrict No. Orange County,California —1-- STATE OF CALIFORNIA) 55. COUNTY OF ORANGE ) I,ORA MAE MERRITT,Secretary of the Board of Directors of County Sanitation District No.Ii of Orange County,California, do hereby certify that the foregoing Resolution was passed and adopted at a regular meeting of the Board of Directors of County Sanitation District No.11 of Orange County,California held on the 24th day of February ,1954 by the following roll call vote: AYES:Directors Roy Seabridge,Herbert A Wood an4 Willie H.Warner NOES:Directors None ABSENT:Diieotore None IN WITNESS WHEREOF,I ~have hereunto set my hand and affixed the seal of County Sanitation ‘Dis’triàt No.U of Orange County, California,this ~4th day of ~ebz’ua*7 ,1954 ~-•~-~- Secretary,Board o~f Directors County Sanitation District No.U Orange County,California