HomeMy WebLinkAbout2007-03 Ops CORRECTED
MINUTES OF THE
OPERATIONS COMMITTEE
Engineering, Operations & Maintenance, and Technical Services
Orange County Sanitation District
Wednesday, March 7, 2007—5:00 P.M.
A meeting of the Operations Committee of the Orange County Sanitation District was held on
March 7, 2007, at 5:00 p.m. in the Sanitation District's Administrative Office.
(1) ROLL CALL
A quorum declared present, as follows:
Operations Directors Present: Staff Present:
Larry Crandall, Chair Jim Ruth, General Manager
Cathy Green, Vice Chair Bob Ghirelli, Assistant General Manager
Don Bankhead Nick Arhontes, Dir. of Operations & Maintenance
Patsy Marshall Jim Herberg, Director of Engineering
Roy Moore Ed Torres, Director of Technical Services
David Shawver Lorenzo Tyner, Director of Finance and
Harry Sidhu Administrative Services
Constance Underhill Lilia Kovac, Committee Secretary
Don Webb Jim Burror, Engineering Supervisor
James M. Ferryman, Board Chair Mark Esquer, Engineering Manager
Tod Haynes, Engineering Manager
Operations Directors Absent: Matt Smith, Engineering Manager
Steve Anderson John Linder, Engineering Manager
Charles Antos
Doug Davert, Board Vice Chair Others:
Olga Cervantes
Norbert Gala
Juanita Skillman ILE
(2) APPOINTMENT OF CHAIR PRO TEM THE CFERKHpF TTHE EISAHD
ORANGE COUNTY SANITATION DISTRICT
No appointment was necessary.
MAR
2 8 2007
(3) PUBLIC COMMENTS BY: /
There were no public comments.
(4) REPORT OF THE COMMITTEE CHAIR
Chair Crandall noted that the July meeting falls on the 41°of July, It was suggested the meeting
be rescheduled to Monday, July 9".
Minutes of the Operations Committee
March 7, 2007
Page 2
(5) REPORT OF THE GENERAL MANAGER
No report was given.
(6) CONSENT CALENDAR ITEMS
a. Approve minutes of the February 7,2007 Engineering and Operations Committee
meeting.
b. OP07-11 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No. 23 to Bushard Trunk Sewer
Rehabilitation, Job No. 1-2-4, with Steve P. Rados, Inc., authorizing an
addition of$48,198, increasing the total contract amount to$31,164,224.
C. OP07-12 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No.4 to Ellis and Bushard
Intersection, Contract No. 1-24A,with Mike Bubalo Construction, Inc.,
authorizing an addition of$194,229.34, increasing the total contract
amount to$11,123,055.70.
d. OP07-13 MOVED, SECONDED,AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No. 8 to Trickling Filter Rehabilitation
and New Clarifiers,Job No. 131-76, with J.R. Filanc Construction
Company Inc., authorizing an addition of$232,036, increasing the total
contract amount to$35.223,546.
e. OP07-14 MOVED, SECONDED,AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No. 2 for Activated Sludge Plant
Rehabilitation at Plant No. 1, Job No. P1.82,with J.R. Filanc Construction
Company Inc., authorizing an addition of$36.543, increasing the total
contract amount to$32,378,621.
f. OP07-15 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to Ratify Change Order No.4 to Headworks Replacements at
Plant No. 2, Job No. 172-66, with J.F. Shea Construction, Inc., authorizing
an addition of$332,489, increasing the total contract amount to
$193,474,189.
g. OP07-16 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to: (1) Approve Amendment No. 5 to the Professional
Services Agreement with RBF Consulting, Inc. providing for additional
design engineering services for Carbon Canyon Sewer and Pump Station
Abandonment, Contract No. 2-24-1,for an additional amount of$40,771,
increasing the total amount not to exceed $622,557;
(2) Approve a 4% Contingency($25,000); and,
Minutes of the Operations Committee
March 7, 2007
Page 3
(3) Authorize staff to commence negotiations with RBF Consulting for
support services during the construction, commissioning, and close out
phase of Contract No. 2-24-1.
In. OP07-17 MOVED, SECONDED,AND DULY CARRIED: Recommend to the Board
of Directors to: (1)Approve Amendment No. 7 to Professional Services
Agreement with Lee& Ro, Inc., providing for additional design
engineering services for Replacement of the Bitter Point Pump Station,
Contract No. 5-49; Replacement of the Rocky Point Pump Station,
Contract No. 5-50; Rehabilitation of the 14" Street Pump Station,
Contract No. 5-51; and Rehabilitation of the"A"Street Pump Station,
Contract No. 5-52,for an additional amount of$69,000, increasing the
total amount not to exceed $4,878,382; and,
(2) Approve a 1% contingency($48,784).
I. OP07-18 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to a authorize staff to commence negotiations with Earth
Tech for support services during the construction, commissioning, and
closeout phases of Truck Wash and Dewatering Beds at Plant No. 1, Job
No. P1-106.
J. OP07-19 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to authorize staff to commence negotiations with Malcolm
Pimie for support services during the construction, commissioning, and
closeout phases of Primary Treatment Rehabilitation Refurbishment, Job
No. P2-80.
k. OP07-20 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to authorize staff to commence negotiations with Brown and
Caldwell for support services during the construction, commissioning, and
closeout phases of Plant No. 2 Primary Sludge Feed System, Job No. P2-
91.
I. OP07-21 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to authorize staff to commence negotiations with Dudek and
Associates, Inc.for support services during the construction,
commissioning,and closeout phases of Rehabilitation of District Siphons,
Contract No. 2-68.
M. OP07-22 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to authorize staff to commence negotiations with PBS&J Inc.
for support services during the construction, commissioning, and closeout
phases of Rehabilitation of Westside Pump Station, Contract No. 3-52.
n. OP07-23 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to authorize staff to commence negotiations with Spec
Services, Inc. for support services during the construction,
commissioning, and closeout phases of Gisler-Redhill Trunk Sewer
Relocation, Phase 1 Construction, Contract No. 7-32-1.
Minutes of the Operations Committee
March 7, 2007
Page 4
o. OP07-24 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to authorize staff to commence negotiations with RBF
Consulting for support services during the construction,
commissioning, and closeout phases of Rehabilitation of College
Avenue Pump Station, Contract No. 7-47.
(7) ACTION ITEMS
a. OP07-25 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to: (1) Approve a budget increase for Rehabilitation of the
10 Street Pump Station, Contract No. 5-51, in the amount of$86,836 for
a total project budget of$9,759,836; and,
(2) Ratify Change Order No. 3 to Rehabilitation of the14'Street Pump
Station, Contract No. 5-51, and Rehabilitation of the"A" Street Pump
Station, Contract No. 5-52,with Kiewit Pacific Company authorizing an
addition of$178,181 and 0 calendar days, increasing the total contract
amount to$12,273,404.
(8) INFORMATIONAL ITEMS
There were none.
(9) REPORT OF DIRECTOR OF ENGINEERING (Jim Herberal
Mr. Jim Herberg reported that the District is the recipient of a prestigious award from the
Construction Management Association of America (CMAA)with a Project Achievement Award
for the Trickling Filter Facility, Mr. Herberg also reviewed the CIP budget, consent decree
requirements timeline, and implications of budget increases.
(10) REPORT OF DIRECTOR OF OPERATIONS AND MAINTENANCE (Nick Arhontes)
Mr. Nick Arhontes briefly reported that an investigation of odor control techniques at the Asoon
landfill in Huntington Beach was done by staff. A sprayed on foam material was used as a
surface barter to minimize odors. This method would not be of use in OCSD's process. He also
reported attending a SCAP Wastewater Issues Conference and its various papers offered for
review,which offer perspectives on processes that should or should not be used by the District.
O&M staff had also met with Technical Services staff regarding our current disinfection
strategies for ocean discharge. Staff will continue to work on optimization and may perform
added testing as well as utilize a panel of independent experts to assist in evaluating strategies
prior to recommending any major changes. The budget for disinfection chemicals is over$9 MM
per year.
Minutes of the Operations Committee
March 7, 2007
Page 5
(11) REPORT OF DIRECTOR OF TECHNICAL SERVICES (Ed Torres)
Mr. Ed Torres briefly reported on quarterly testing for toxicity; a consortium with U.C. Irvine
Technology demo project for hydrogen gas; he also informed the committee members of the
South Kern County Biosolids Composting facility grand opening ceremony scheduled for May 8,
2007. Directors interested in attending the event may advise Penny Kyle, Clerk of the Board at
(714) 593-7130, in order to coordinate a vanpool for everyone attending.
(12) OTHER BUSINESS, COMMUNICATIONS OR SUPPLEMENTAL AGENDA ITEMS, IF ANY
There were none.
(13) MATTERS WHICH A DIRECTOR MAY WISH TO PLACE ON A FUTURE AGENDA
FOR ACTION AND STAFF REPORT
There were none.
(14) CLOSED SESSION
There was no closed session.
(15) FUTURE MEETING DATES
The next Operations Committee meeting is scheduled for April 4, 2007, at 5:00 p.m.
(16) ADJOURNMENT
The Chair declared the meeting adjourned at 5:55 p.m.
Submitted by:
Lille (ovac
Committee Secretary
HidepNmM15011510SWhutes1030707 Draft OpemOons Mhutes.00c
t) ORANGE COUNTY SANITATION DISTRICT
pl,ona:
V 14)952 24
fv:
NOTICE OF MEETING
wwv.orx.emn
awlllap Md.:
en S. 5121 OPERATIONS COMMITTEE
limntan Valley 19
927P 8122 Engineering, Operations & Maintenance, and Technical Services
w.bt,marase:
16W4Bh'h '.
fi'W"sp> 7 ac ORANGE COUNTY SANITATION DISTRICT
wAr.
WEDNESDAY, MARCH 7, 2007 - 5:00 P.M.
C1tin DISTRICT'S ADMINISTRATIVE OFFICES
nn•mea» 10844 ELLIS AVENUE
6 ea
9nW,a v,,,1; FOUNTAIN VALLEY, CALIFORNIA 92708
t.)'— wvvw.ocsd.com
Fnw In initial,
NH n
Gi M: G fiaaJ ih
Hunnrxpw,
Irnne
la "p"a FiNnre The regular meeting of the Operations Committee of the Board of Directors of
1 a
i:>s aa,nn,a Orange County Sanitation District will be held at the above location and time.
Ne1YIMAR 6b9:'JI
6XIyf.'
P13L3.'
SaIrW Q,IS
Snell fiaa J,
$LIDOi
Tustin
vme
x,rta 1 in,inda
w
County a Cranpe
Wit., vm"Iata
u hf�!
U.:eyy iiq
Weten Uibtrlets
n•ana itanrn
To maintain world-cless leadership in wastewater and water resource management.
OPERATIONS COMMITTEE MEETING DATES
OPERATIONS COMMITTEE BOARD
MEETING DATE MEETING DATE
03/07/07 03/28/07
04/04/07 04/25/07
05/02/07 05/23/07
06/06/07 06/27/07
07/05/07 07118107"
AUGUST DARK O8/22/07
09/05/07 09/26/07
10/03/07 10/24/07
11/07/07 11/28/07
12/05/07 12/19/07"
JANUARY DARK 01/23/08
02/06/08 02/27/08
'Meetings are being held on the third Wednesday of the month.
ROLL CALL
OPERATIONS COMMITTEE
Engineering, Operations & Maintenance, and Technical Services
Meeting Date: March 7. 2007 Time: 5:00 p.m.
Adjourn:
COMMITTEE MEMBERS
Larry Crandall Chair
Cathy Green ice Chair
Steve Anderson
Charles Antos
Don Bankhead
Patsy Marshall
Roy Moore
David Shawver
Harry Sidhu
Constance Underhill
Don Webb
James M. Ferryman Board Chair
Doug Davert Board Vice Chair
OTHERS
Brad H in, General Counsel
STAFF
Jim Ruth, General Manager
Nick Arhontes, Director of Operations
Bob Ghirelli, Assistant General Manager
Jim Herber , Director of Engineering
Ed Torres, Director of Technical Services
Lorenzo Tyner, Director of Finance and
Administrative Services
Lille Kovac, Committee Secretary
Matt Smith
John Linder
H:1dept\agendalCommiRee Opemlions Committeel0pemUons 200M30A02.Roll Call.dm
AGENDA
REGULAR MEETING OF THE
OPERATIONS COMMITTEE
Engineering, Operations & Maintenance, and Technical Services
ORANGE COUNTY SANITATION DISTRICT
March 7, 2007 - 5:00 P.M.
ADMINISTRATIVE OFFICE
10844 Ellis Avenue
Fountain Valley, California 92708
www.ocsd.com
(1) DECLARATION OF QUORUM (13)
(2) APPOINTMENT OF CHAIR PRO TEM, IF NECESSARY
(3) PUBLIC COMMENTS
(4) REPORT OF COMMITTEE CHAIR
a. Consider July meeting schedule.
(5) REPORT OF GENERAL MANAGER
(6) CONSENT CALENDAR ITEMS
Consideration of motion to approve all agenda items appearing on the Consent Calendar not
specifically removed from same, as follows:
a. Approve minutes of the February 7, 2007 Engineering and Operations Committee meeting.
b. OP07-11 Recommend to the Board of Directors to ratify Change Order No. 23 to Bushard
Trunk Sewer Rehabilitation, Job No. 1-2-4, with Steve P. Rados, Inc.,
authorizing an addition of$48,198, increasing the total contract amount to
$31,164,224. (Book Page 11)
C. OP07-12 Recommend to the Board of Directors to ratify Change Order No. 4 to Ellis and
Bushard Intersection, Contract No. I-2-4A, with Mike Bubalo Construction, Inc.,
authorizing an addition of$194,229.34, increasing the total contract amount to
$11,123,055.70. (Book Page 14)
Book Page I
Operations Committee
03/07/07
Page 2
d. OP07-13 Recommend to the Board of Directors to ratify Change Order No. 8 to Trickling
Filter Rehabilitation and New Clarifiers, Job No. P1-76, with J.R. Filanc
Construction Company Inc., authorizing an addition of$232,036, increasing the
total contract amount to$35,223,546. (Book Page 17)
e. OP07-14 Recommend to the Board of Directors to ratify Change Order No. 2 for
Activated Sludge Plant Rehabilitation at Plant No. 1, Job No. 131-82, with J.R.
Filanc Construction Company Inc., authorizing an addition of$36,543,
increasing the total contract amount to$32,378,621. (Book Page 20)
f. OP07-15 Recommend to the Board of Directors to Ratify Change Order No. 4 to
Headworks Replacements at Plant No. 2, Job No. P2-66, with J.F. Shea
Construction, Inc., authorizing an addition of$332,489, increasing the total
contract amount to $193,474,189. (Book Page 23)
g. OP07-16 Recommend to the Board of Directors to: (1) Approve Amendment No. 5 to the
Professional Services Agreement with RBF Consulting, Inc. providing for
additional design engineering services for Carbon Canyon Sewer and Pump
Station Abandonment, Contract No. 2-24-1, for an additional amount of
$40,771, increasing the total amount not to exceed $622,557;
(2) Approve a 4% Contingency ($25,000); and,
(3) Authorize staff to commence negotiations with RBF Consulting for support
services during the construction, commissioning, and close out phase of
Contract No. 2-24-1. (Book Page 26)
h. OP07-17 Recommend to the Board of Directors to: (1)Approve Amendment No. 7 to
Professional Services Agreement with Lee & Ro, Inc., providing for additional
design engineering services for Replacement of the Bitter Point Pump Station,
Contract No. 5 49; Replacement of the Rocky Point Pump Station, Contract
No. 5-50; Rehabilitation of the 10 Street Pump Station, Contract No. 5-51; and
Rehabilitation of the"A" Street Pump Station, Contract No. 5-52, for an
additional amount of$69,000, increasing the total amount not to exceed
$4,878,382; and,
(2) Approve a 1%contingency ($48,784). (Book Page 28)
i. OP07-18 Recommend to the Board of Directors to a authorize staff to commence
negotiations with Earth Tech for support services during the construction,
commissioning, and closeout phases of Truck Wash and Dewatering Beds at
Plant No. 1, Job No. P1-106. (Book Page 31)
j. OP07-19 Recommend to the Board of Directors to authorize staff to commence
negotiations with Malcolm Pirnie for support services during the construction,
commissioning, and closeout phases of Primary Treatment Rehabilitation
Refurbishment, Job No. P2-80. (Book Page 33)
Book Page 2
Operations Committee
03/07/07
Page 3
k. OP07-20 Recommend to the Board of Directors to authorize staff to commence
negotiations with Brown and Caldwell for support services during the
construction, commissioning, and closeout phases of Plant No. 2 Primary
Sludge Feed System, Job No. P2-91. (Book Page 35)
I. OP07-21 Recommend to the Board of Directors to authorize staff to commence
negotiations with Dudek and Associates, Inc. for support services during the
construction, commissioning, and closeout phases of Rehabilitation of District
Siphons, Contract No. 2-68. (Book Page 37)
M. OP07-22 Recommend to the Board of Directors to authorize staff to commence
negotiations with PBSBJ Inc. for support services during the construction,
commissioning, and closeout phases of Rehabilitation of Westside Pump
Station, Contract No. 3-52. (Book Page 39)
n. OP07-23 Recommend to the Board of Directors to authorize staff to commence
negotiations with Spec Services, Inc. for support services during the
construction, commissioning, and closeout phases of Gisler-Redhill Trunk
Sewer Relocation, Phase 1 Construction, Contract No. 7-32-1. (Book Page 40)
0. OP07-24 Recommend to the Board of Directors to authorize staff to commence
negotiations with RBF Consulting for support services during the
construction, commissioning, and closeout phases of Rehabilitation of
College Avenue Pump Station, Contract No. 7-47. (Book Page 41)
END OF CONSENT CALENDAR
P. Consideration of items deleted from Consent Calendar, if any.
(7) ACTION ITEMS
a. OP07-25 Recommend to the Board of Directors to: (1) Approve a budget increase for
Rehabilitation of the 10 Street Pump Station, Contract No. 5-51, in the amount
of$86,836 for a total project budget of$9,759,836; and,
(2) Ratify Change Order No. 3 to Rehabilitation of the14' Street Pump Station,
Contract No. 5-51, and Rehabilitation of the "A" Street Pump Station, Contract
No. 5-52, with Kiewit Pacific Company authorizing an addition of$178,181 and
0 calendar days, increasing the total contract amount to $12,273,404.(Book Page 42)
(8) INFORMATIONAL ITEMS
Book Page 3
Operations Committee
03/07/07
Page 4
(9) REPORT OF DIRECTOR OF ENGINEERING
a. 2007/08 CIP Budget Update
(10) REPORT OF DIRECTOR OF OPERATIONS AND MAINTENANCE
(11) REPORT OF DIRECTOR OF TECHNICAL SERVICES
(12) OTHER BUSINESS, COMMUNICATIONS OR SUPPLEMENTAL AGENDA ITEMS, IF ANY
(13) MATTERS WHICH A DIRECTOR MAY WISH TO PLACE ON A FUTURE AGENDA FOR ACTION
AND STAFF REPORT
(14) CLOSED SESSION
----------'-'--"-------------'- reg lar-------
;During the course of conducting Me business set forth on this agenda as a regular meeting of the Committee,the
.Chair may convene the Committee in dosed session to consider matters of pending real estate negotiations,
;pending or potential ftigation, or personnel matters, pursuant to Government Code Sections 54956.8, 54956.9,
54957 or 54957.6.as noted.
:Reports relating to (a) purchase and sale of real property; (b) matters of pending or potential litigation; (c)
€employee actions or negotiations with employee representatives; or which are exempt from public disclosure
.under the California Public Records Act, may be reviewed by the Committee dudng a permitted dosed session
_and are not available for public inspection. At such lime as the Committee takes final actions on any of these
su iects_theminuteswill_reflectallrequired.disci s resofinformation.
a. Convene in closed session.
b. Reconvene in regular session.
c. Consideration of action, if any, on matters considered in closed session.
(15) FUTURE MEETING DATES
The next Engineering and Operations Committee meeting is scheduled for April 4, 2007, at
5:00 P.M.
(16) ADJOURNMENT
Book Page 4
Operations Committee
03/07/07
Page 5
Agenda Posting: In Accordance with the requirements of California Government Code Section 54954.2,this
agenda has been posted in the main lobby of the District's Administrative offices not less than 72 hours prior to the
meeting date and time above. All written materials relating to each agenda item are available for public inspection
in the office of the Clerk of the Board.
Items Not Posted: In the event any matter not listed on this agenda is proposed to be submitted to the Committee
for discussion and/or action, it will be done in compliance with Section 54954.2(b)as an emergency item or
because there is a need to take immediate action,which need came to the attention of the Committee subsequent
to the posting of agenda, or as set forth on a supplemental agenda posted in the manner as above, not less than 72
hours prior to the meeting date.
Public Comments: Any member of the public may address the Operations Committee on specific agenda items or
matters of general interest. As determined by the Chair, speakers may be deferred until the specific item is taken
for discussion and remarks may be limited to three minutes.
Matters of interest addressed by a member of the public and not listed on this agenda cannot have action taken by
the Committee except as authorized by Section 54954.2(b).
Consent Calendar: All matters placed on the consent calendar are considered as not requiring discussion or further
explanation, and unless a particular item is requested to be removed from the consent calendar by a Director of
staff member, there will be no separate discussion of these items. All items on the consent calendar will be
enacted by one action approving all motions, and casting a unanimous ballot for resolutions included on the
consent calendar. All items removed from the consent calendar shall be considered in the regular order of
business.
The Committee Chair will determine if any items are to be deleted from the consent calendar.
Items Continued: Items may be continued from this meeting without further notice to a Committee meeting held
within five(5)days of this meeting per Government Code Section 54954.2(b)(3).
Meeting Adjournment: This meeting may be adjourned to a later time and items of business from this agenda may
be considered at the later meeting by Order of Adjournment and Notice in accordance with Government Code
Section 54955(posted within 24 hours).
Accommodations for the Disabled: The Board of Directors Meeting Room is wheelchair accessible. If you require
any special disability related accommodations, please contact the Orange County Sanitation District Clerk of the
Board's office at(714)593-7130 at least 72 hours prior to the scheduled meeting. Requests must specify the
nature of the disability and the type of accommodation requested.
........................................................................................................................................................................................................................................................................................................
!Notice to Committee Members:
For any questions on the agenda or to place any items on the agenda,Committee members should contact the Committee
Chair or Secretary ten days in advance of the Committee meeting.
.Committee Chair Larry Crandall (714)593-4400 slcrandallCaraol.com
.Committee Secretary: Lilia Kovac (714)593-7124 Ikovac@ocsd.wm
?General Manager Jim Ruth (714)593-7110 iwth9Docsd.wm
Assistant General Manager Bob Ghirelli (714)593-7400 bghirelliCalocsd.com
Dir. of Technical Services Ed Tones (714)593-7080 etorres0omd.wm
Director of Engineering Jim Herberg (714)593-7020 iherbermMocsdoom
;Dir.of Operations and Maintenance Nick Amontes (714)593-7210 narhontesMocsd.wm
i........................................................................................................................................................................................................................................................................................................
.
Book Page 5
Operations Committee
Rolling Agenda Report Calendar
Date Dept. Action or
Description of Report Information
April O&M Award Sole Source of Parts and Services for Existing
Equipment Action
April O&M Adopt Fleet Rules for Public—Agencies—CA Title 13 Action
April TS Waste Water Discharge Regulations (Ordinance)
Revision Action
April ENG Approve Amendment No. 6 to PSA re 1-10, Rehabilitation
of Ellis Avenue Pump Station Action
April ENG Approve Amendment No. 1 to PSA re 5-58, Newport
Trunk Sewer and Force Mains Action
April ENG Approve Amendment No. 2 to PSA re 1-2-4, Bushard
Trunk Sewer Rehabilitation Action
April ENG Establish CIP Projects Change Order Contingencies per Action
Delegation of Authority
April ENG FY 2007-08 CIP Budget Information
Ratify Change Order Nos. 4&5 to 5-51, Rehabilitation of
May ENG 14P Street Pump Station - Action
May ENG Approve Amendment No. 3 to PSA re P2-80, Primary
Treatment Rehabilitation/Refurbishment Action
May ENG FY 2007-08 CIP Budget information
May 0&M Award Potable Water System Hydraulic Analysis Action
H9deptUgenda\Commgtees\0perations Committee\Operations 2007MOM4.030707 Rolling Agenda.doc
Book Page 6
MINUTES OF THE ENGINEERING AND
OPERATIONS COMMITTEE
Orange County Sanitation District
Wednesday, February 7, 2007—5:00 P.M.
A meeting of the Engineering and Operations Committee of the Orange County Sanitation
District was held on February 7, 2007, at 5:00 p.m. in the Sanitation District's Administrative
Office.
(1) ROLL CALL
The roll was called and a quorum declared present, as follows:
E&O Directors Present: Staff Present:
Larry Crandall, Chair Jim Ruth, General Manager
Cathy Green, Vice Chair Bob Ghirelli, Assistant General Manager
Steve Anderson Nick Arhontes, Dir. of Operations & Maintenance
Charles Antos Jim Herberg, Director of Engineering
Don Bankhead Ed Torres, Director of Technical Services
Roy Moore Lorenzo Tyner, Director of Finance and
David Shawver Administrative Services
Harry Sidhu Life Kovac, Committee Secretary
Constance Underhill Tod Haynes, Engineering Manager
Don Webb Matt Smith, Engineering Manager
Doug Davert, Board Vice Chair Chuck Windsor, Engineering Manager
John Linder, Engineering Manager
E & O Directors Absent:
Patsy Marshall Others:
James M. Ferryman, Board Chair Norbert Gaia
Jim Clark
Juanita Skillman
Joe Fortieth, General Counsel
(2) APPOINTMENT OF CHAIR PRO TEM
No appointment was necessary.
(3) PUBLIC COMMENTS
There were no public comments.
(4) REPORT OF THE COMMITTEE CHAIR
Chair Crandall did not give a report.
Book Page 7
Minutes of the E & O Committee
February 7, 2007
Page 2
(5) REPORT OF THE GENERAL MANAGER
No report was given.
(6) CONSENT CALENDAR ITEMS
a. Approve minutes of the December 6, 2006 Operations, Maintenance and Technical LI
Services (OMTS) Committee meeting and minutes of the December 7, 2006 Planning,
Design and Construction (PDC) Committee meeting. Directors Underhill and Green
abstained.
b. E&O07-01 MOVED, SECONDED, AND DULY CARRIED: Approve Amendment No.
1 to the Professional Services Agreement with KOMEX for Underground
Storage Tank Evaluation and Remediation at Plant No. 1, Job No. 121-98,
for an additional amount of$39,487, increasing the total amount not to it
exceed $135,718.
C. E&007-02 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No. 31 to Primary Clarifiers Nos. 16-
31 and Related Facilities, Job No. P1-37, with Margate Construction,
authorizing an addition of$16,964, increasing the total contract amount to
$72,897,044.
d. E&O07-03 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to approve Amendment No. 3 to the Professional Services
Agreement with MDS Consulting to provide for additional services for
Surveying Services, Specification No. PSA-2003-176, for an additional
amount of$50,000, increasing the total contract amount not to exceed
$550.000.
e. E&O07-04 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to approve a budget increase of$440,000 to the budget for
Rehabilitation of Westside Pump Station, Contract No. 3-52, for a total
budget amount of$8,731,000.
f. E&007-05 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to approve Amendment No. 4 to Cooperative Projects
Program Contract No. 0130 with the City of Orange providing for a time
extension with no additional funding.
(7) ACTION ITEMS
a. ESO07-06 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No. 22 to Bushard Trunk Sewer
Rehabilitation, Job No. 1-2.4,with Steve P. Rados, Inc., authorizing an
addition of$251,350, increasing the total contract amount to$31,116,026.
i
Book Page 8
I '
Minutes of the E& O Committee
February 7, 2007
Page 3
Directors required clarification on legality of traffic impact fees. General
Counsel Brad Hogin will investigate and report back to the committee at
the next committee meeting.
b. E&O07-07 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to: (1)Approve a Professional Services Agreement with Black
and Veatch for engineering services for Power Monitoring and Control at
Plants No. 1 and No. 2, Job No. J-33-3,for an amount not to exceed
$1,184,736; and,
(2)Approve a 20% contingency ($236,947).
Directors requested that a summary of bids with scores received to be
included in future agenda reports.
c. E&O07-08 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to approve Amendment No. 1 to the Professional Services
Agreement with Dudek &Associates, Inc., providing for additional
engineering services for Rehabilitation of District Siphons, Contract
No. 2-68,for an additional amount of$164,000, increasing the total
contract amount not to exceed $1.151.156.
d. E&O07-09 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to: (1)Approve Amendment No. 3 to the Professional
Services Agreement with Brown and Caldwell to provide construction
support services for Trickling Filters at Plant No. 2, Job No. P2-90, for an
additional amount of$7,480,600, increasing the total contract amount not
to exceed$17,563,820; and,
(2)Approve a 60% contingency($448,836).
e. E&007-10 MOVED, SECONDED, AND DULY CARRIED: Recommend to the Board
of Directors to approve a budget increase of$2.844,000 to the budget for
Rehabilitation of College Avenue Pump Station, Contract No. 7-47, for a
total budget amount of$10,820,000.
(8) INFORMATIONAL ITEMS
There were none.
(9) REPORT OF DIRECTOR OF ENGINEERING
No report was given.
Book Page 9
Minutes of the E &O Committee Y
February 7, 2007
Page 4
(10) REPORT OF DIRECTOR OF OPERATIONS AND MAINTENANCE
Nick Arhontes, Director of Operations and Maintenance, reported that compliments had been
given by an out-of-state visitor to the Sanitation District plant for its lack of foul odor; also, a
letter of complaint was received from a Huntington Beach resident citing foul odors.
(11) REPORT OF DIRECTOR OF TECHNICAL SERVICES
No report was given.
(12) OTHER BUSINESS COMMUNICATIONS OR SUPPLEMENTAL AGENDA ITEMS, IF ANY
(13) MATTERS WHICH A DIRECTOR MAY WISH TO PLACE ON A FUTURE AGENDA
FOR ACTION AND STAFF REPORT
(14) CLOSED SESSION
The Committee convened in closed session at 5:40 p.m., pursuant to Government Code
Section 54956.9(b)to discuss Agenda Item No. 14(a). Confidential Minutes of the
Closed Session held by the Clerk of the Board have been prepared in accordance with
California Government Code Section 54957.2 and are maintained by the Clerk of the
Board in the Official Book of Confidential Minutes of Board and Committee Meetings.
(15) FUTURE MEETING DATES
The next Engineering and Operations Committee meeting is scheduled for March 7,
2007, at 5:00 p.m.
(16) ADJOURNMENT
The Chair declared the meeting adjourned at 6:04 p.m.
Subu�b�miiitt�teedd��b'�y`::
Lilia K' ovac i ��
Committee Secretary
Engineering and Operations Committee
H:WepragendM0=mittees\Operations G=1rdee\0pe1dw1 2 0 0710 3 0T05.020707 E80 MlnulesAm
Book Page 10
OPERATIONS COMMITTEE Meeting Date Toltd.uf Dlr.
03/07/07 03/28/07
AGENDA REPORT llem Number Item Number
Orange county Sanitatlon Dlstrict - -- — -- DF07.11
j collections
Facilities
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: BUSHARD TRUNK SEWER REHABILITATION, JOB NO. 1-2-4
GENERAL MANAGER'S RECOMMENDATION
Ratify Change Order No. 23 to Bushard Trunk Sewer Rehabilitation, Job No. 1-2-4, with
Steve P. Rados, Inc., authorizing an addition of$48,198, increasing the total contract
amount to $31,164,224.
SUMMARY
• Job No. 1-24, Bushard Trunk Sewer Rehabilitation, includes the installation of
21,600 linear feet oust over four miles) of 108-inch reinforced concrete pipe,
manholes, junction structures, and miscellaneous utility relocations.
• Boyle Engineering Corporation prepared the plans and specifications and the
contract was awarded to Steve P. Rados, Inc. (SPR) on June 26, 2002.
• Scope changes and timing constraints required modification of Job No. 1-2-4 to
include new Job No. 1-24A, the work in the Ellis-Bushard Intersection.
• The Mediation Settlement Agreement required further modification of Job No. 1-2-4
to include new Job No. I-24P, the fabrication and delivery of 108-inch and
96-inch pipe.
• This change order includes seven items of added work. There are no reimbursable
or non-reimbursable design errors associated with this change order. Liquidated
damages on this contract are $2,000 per calendar day and the bonus provisions are
$750 per calendar day. The contract is now 85% complete.
PRIOR COMMITTEE/BOARD ACTIONS
The contract was awarded by the Board of Directors on June 26, 2002.
ADDITIONAL INFORMATION
Form No.ow.toaz nwima cvcmci
Book Page I I
i
This change order complies with authority levels of the Sanitation District's Delegation
of Authority. This item has been budgeted. (Line item: Section 8, Page 48).
The project manager on this project is David May.
Contract Schedule
Contract Start Date September 16, 2002
Original Contract Completion Date March 18, 2004
Total Number of Change Orders to Date 22
Current Contract Completion Date June 20, 2007
Actual Completion Date TBD
Days Subject to Liquidated Damages N/A
Change Order No. 23 Content
Item No. Description Amount Days Type
1 Additional public outreach $658 0 Other
si na e
2 Additional manholes in the north $16,903 0 Staff Requested
Indianapolis structure Design Change
3 Addition of flow meters to de- $2,195 0 Staff Requested
silting tank outlets Design Change
4 108-inch pipe modification at $2,218 0 Staff Requested
STA 93+56 Design Change
5 Removal of unsuitable material $6,354 0 Unknown
Condition j
6 Additional handling of 108-inch $13,504 0 Other
RCP
7 Undisclosed utilities at STA $6,366 0 Unknown
118+25 and STA154+27 Condition
Total Change Order No. 20 $48,198 0
ATTACHMENTS
Change Order Status Report
DM:cj:sp:eh
H:Wepltagenda\Committees\Operations Commlltee\Operations 20071030T07-11-1-24 CO23.doc
Fom,No.o 102-2 as y 011 7
Book Page 12
CHANGE ORDER STATUS REPORT
BUSHARD TRUNK SEWER REHABILITATION
JOB NO. 1-2-4 CO #20
CONTRACT CONTRACT COST PERCENTAGE AUTHORIZED AUTHORIZED TIME
ITEM APPROVAL DATE COST TO DATE INCREASE TIME TO DATE
(DAYS) (DAYS)
CONTRACT June 26,2002 $30,003,210 $30,003,210 550 550
CO NO, 1• April23, 2003 $150,000 $30,153,210 0.50% 0 550
CO NO.2 June 25,2003 $107,7241 $30,260,934 0.86% 2'-• 552
CO NO. 3 October 22,2003 $44,2931 $30,305,227 1.01% 1— 553
CO NO.4 February 25.2004 $380,251 $30,685,478 2.27% 0 553
CO NO. 5 March 24,2004 $409,301 $31,094,779 3.64% 0 553
gCO NO. 6 May 26,2004 $27,612 $31,122,391 3.73% 5"' 558
>r CO NO. 7 June 23, 2004 $163,618 $31,286,009 4.28% 0 558
CO NO. 8 July 21, 2004 $230,317 $31,516,326 5,04% 0 558
CO NO, 9 September 22, 2004 $153,119 $31,669,445 5.55% 0 558
`-' CO NO. 10 November 17,2004 $242,360 $31,911,805 6.36% 0 558
CO NO. 11 December 15,2004 $0 $31,911,805 6.36% 49— 607
CO NO. 12 December 15,2004 $0 $31,911.805 6.36% 27"• 634
CO NO. 13 February 23, 2004 $225,331 $32,137,136 7.11% 7... 841
CO NO. 14 March 23,2005 $98,750 $32,235,886 7.44% 0 641
CO NO. 15 June 22,2005 $28,253 $32,264,139 7.54% 0 641
CO NO. 16.1 August 22, 2005 $3 422,266.80 $35,686,405.80 18.94% 0 841
CO NO, 17 October 26 2005 $23,707.00 $35,710,112.80 19.02% 0 641
CO NO. 18 February22,2006 -$823,407.00 $34,886,705.80 16.28% 0 641
CO NO. 19 July19,2006 -$4,358,204.00 $30,528,501.80 1 1.75% 0 641
CO',N0:20- Pendln c$151375.00 r %; $30678876,80 1 2.25% 0 1 WA--
*Approved by PDC Committee per delegated authority by Board Resolution 99-23
—Approved by General Manager pursuant to Settlement Agreement and Release effective 811/05
—Authorized Time to Date was replaced with a new contract end date of June 20, 2007, per terms of the Settlement Agreement and Release.
Accordingly,all time extensions granted in prior change orders are null and void.
EDMS 003B142/3
OPERATIONS COMMITTEE memos Dare ro ad.orf)
03/07/07 O31 17
AGENDA REPORT Rem Number Item Number
OP07-12
Orange County Sanitation District
CollFacilities
ns
FROM: James Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: ELLIS AND BUSHARD INTERSECTION, CONTRACT NO. 1-2-4A
GENERAL MANAGER'S RECOMMENDATION
Ratify Change Order No. 4 to Ellis and Bushard Intersection, Contract No. 1-2-4A, with Mike
Bubalo Construction, Inc., authorizing an addition of$194,229.34, increasing the total
contract amount to $11,123,055.70.
SUMMARY
• Contract No. I-2-4A is related to Contract No. 1-2-4, Bushard Trunk Sewer Rehabilitation.
Contract No. 1-2-4 replaces approximately five miles of existing 54-inch diameter pipe
with new 108-inch diameter pipe.
• The purpose of Contract No. 1-24A is to consolidate work in the Ellis Avenue Bushard
Street intersection and allow work to be performed in less time and in a safer work area.
Work is also performed in parallel with new piping being installed on Bushard Street
south of the intersection ensuring the entire effort is completed in a shorter duration.
• Malcolm Pirnie, Inc. prepared the plans and specifications and the contract was
awarded to Mike Bubalo Construction Company, Inc. on February 22, 2006.
• This change order included four items of added work and five modifications to the
contract specifies requirements. There is one non-reimbursable design errors and no
reimbursable design errors associated with this change order. Liquidated damages on
this contract are $5,400 per day. The contract is now 95% complete.
• Orange County Water District will reimburse the Sanitation District $111,443 for work
described in item 7 per a cooperative agreement between the Sanitation District and
Orange County Water District.
PRIOR COMMITTEE/BOARD ACTIONS
The contract was awarded by the Board of Directors on May 8, 2006. Please refer to the
attached Change Order Status Report for information on all previous change orders.
ADDITIONAL INFORMATION
This change order complies with authority levels of the Sanitation District's Delegation of
Authority. This item has been budgeted. (Line item: Section 8, Page 48).
The project manager on this project is David May.
Page 1
Book Page 14
Contract Schedule
Contract Start Date May 8, 2006
Original Contract Completion Date January 2, 2007
Total Number of Change Orders to Date 4
Current Contract Completion Date January 22, 2007
Actual Completion Date TBD
Days Subject to Liquidated Damages N/A
Change Order No.4 Content
Item No. Description Amount Days Type
1 Minor changes to the VECP section $0 0 Staff
F.3.D Requested
2 Modification of the contract end date $0 190 Design
for convenience Change
3 Release of retainage from 10%to 5% $0 0 Design
—Change
4 Additional umbrella insurance $24,890.00 0 Other
coverage within City of Fountain
Valle
5 Installation of T-Lock protective Lining $4,226.00 0 Non
Reimbursable
Design error
6 Unknown obstruction encountered $68,975.00 0 Unknown
during i installation condition
7 Installation of a 480 VAC line for $111,443.00 0 Other
OCWD
8 Bid Item 9 reduction $15,168.00 0 Other
9 Adjustment to bid addition $136.66 0 Other
Total Change Order No. 4 $194,229.34 0
ATTACHMENTS
Change Order Status Report
DM:cj:eh
K: pp genda%Commifi a U)pemtions Cammdt"W)pemtww 200710307n7-12-1-24A CO 4AW
Page 2
Book Page 15
CHANGE ORDER STATUS REPORT
BUSHARD TRUNK SEWER REHABILITATION
CONTRACT NO. 1-2-4A CO#4
APPROVAL CONTRACT CONTRACT COST PERCENTAGE AUTHORIZED AUTHORIZEDTIME
ITEM DATE COST TO DATE INCREASE TIME TO DATE
(DAYS) (DAYS)
CONTRACT February 22,2006 $11,191,500.00 $11,191,500.00 240 240
CO NO. 1 May 24, 2006 $0 $11,191,500.00 0.00% 0 240
CO NO.2 August 23, W06 ($815,658) $10,375.842.36 -7.29% 0 240
CO NO.3 November 15,2006 $552,984 $10,928,826.36 -2.35°k 20 260
CO N0.4 Pending $194,229 $11,123,055.70 -0.61% 190 450
r.
�a
ry
P
OPERATIONS COMMITTEE Meebng Date To Bd.ofN
03/07/07 03/28/07
AGENDA REPORT Item NumberItem Number
OPo]-13
Orange County Sanitation District
Secondary Treatment
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: TRICKLING FILTER REHABILITATION AND NEW CLARIFIERS,
JOB NO. P1-76
GENERAL MANAGER'S RECOMMENDATION
Ratify Change Order No. 8 to Trickling Filter Rehabilitation and New Clarifiers, Job
No. P1-76, with J.R. Filanc Construction Company Inc., authorizing an addition of
$232,036, increasing the total contract amount to $35,223,546.
SUMMARY
• Job No. P1-76, Trickling Filter Rehabilitation and New Clarifiers, includes the
construction of two new trickling filters and clarifiers, a pump station, a meter vault,
and all support equipment and piping.
• Black & Veatch prepared the plans and specifications and the contract was
awarded to J.R. Filanc Construction Company, Inc. on March 26, 2003.
• This change order includes thirteen items of additional work. There are four
nonreimbursable design errors and no reimbursable design errors associated with
this change order. Liquidated damages on this project are $3,000 per day and
there are no bonus provisions. The project is 99% complete.
PRIOR COMMITTEE/BOARD ACTIONS
The contract was awarded to J.R. Filanc Construction Company, Inc. by the Board of
Directors on March 26, 2003. Please refer to the attached Change Order Status Report
for information on previous change orders.
ADDITIONAL INFORMATION
Contract Schedule
Contract Start Date June 2, 2003
Original Contract Completion Date February 26, 2006
Total Number of Change Orders to Date 8
Current Contract Completion Date February 26, 2006
Actual Completion Date Pending
Days Subject to Liquidated Damages Pending
Page 1
Book Paee 17
Change Order No. 8 Content
Item Description Amount Days Type
No.
Change to stucco exterior from
1 Exterior Insulation Finish System ($15,258) 0 Other
for Power Building 8
2 Ductbank North of PEDB $16,100 0 Unknown Condition
3 Modify 60-inch Pipe Connection at $30,574 0 Nonreimbursable
Prima Basins Design Error
4 Work activities to Support Future $12,856 0 Other
Projects
5 Unknown Field Conditions Found $9,768 0 Unknown Condition
During the Course of Construction
6 Final Program Modifications $10,094 0 Staff Requested
Design Changes
Fiber Termination Panels, Tube Staff Requested
7 Cable, Control Panel, Turbidity $25,566 0
Meter, and Induced Voltage Work Design Changes
8 120 Volt Power for Alarm Beacons $2,290 0 Unknown Condition
9 Control Conduit Grounding $34,677 0 Nonreimbursable
Design Error
10 Sludge Line Support Members $13,562 0 1 Unknown Condition
11 Paving Modifications $116,628 0 Nonreimbursable
Design Error
12 Trickling Filter Vent Fan Damper $11 479 0 Nonreimbursable
Wiring Modifications Design Error
13 Underground Storage Tank ($36301) 0 Staff Requested
,
Deletion Design Change
14 Retention Reduction to 2% $0 0
Total Change Order No. 8 $232,036 0
This change order complies with authority levels of the Sanitation District's Delegation
of Authority. This item has been budgeted. (Line item: Section 8, CIP, P1-76).
ATTACHMENT
Change Order Status Report
JH:BEB:kf:gc
H:WepM9enda\Commisees\0pemlions Committee\Operations 20071030]107.13.Pt-76 CO a.dw
Page 2
Book Page 18
CHANGE ORDER STATUS REPORT
TRICKLING FILTER REHABILITATION AND NEW CLARIFIERS
JOB NO. P1.76
d234
L CONTRACT CONTRACT COST PERCENTAGE AUTHORIZED AUTHORIZED TIME
ITEMCOST TO DATE INCREASE TIME T( DATE
(DAYS) (DAYS)
CONTRACT $ 33,037,000 $ 33,037,000 0.00 1000 1000
m
c CO NO. 1 $ 0.00 $ 33,037,000 0.00 0 1000
9 CO NO.2 $ (84,405) $ 32,952,595 (0.26) 0 1000
CO NO. 3 $ 123,258 $ 33,075,853 0.12 0 1000
CO NO.4 $ 356.962 $ 33,432,815 1.20 0 1000
CO NO, 5 7/20/2005 $ 787,043 $ 34,219,858 3.58 0 1000
CO NO.6 12/21/2005 $ 489,920 $ 34,709,778 5.06 0 1000
CO NO.7 1 628/2006 1 $ 281,732 $ 34,991,5101 5.92 0 1000
=CO NO.8 1 Pending $ 232,0361 $ •:35,223,8{I6 - 6.62 0 -- 1000
EOMS:003027324
OPERATIONS COMMITTEE Meedng Date To ad.of on.
03/07/07 03/28/07
AGENDA REPORT Item Iem Numbe
OP07-1407-14
Orange County Sanitation District
HISecondary Treatment
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: ACTIVATED SLUDGE PLANT REHABILITATION AT PLANT NO. 1,
JOB NO. P1-82
GENERAL MANAGER'S RECOMMENDATION
Ratify Change Order No. 2 for Activated Sludge Plant Rehabilitation at Plant No. 1, Job
No. P1-82, with J.R. Filanc Construction Company Inc., authorizing an addition of
$36,543, increasing the total contract amount to $32,378,621.
SUMMARY
• Job No. P1-82, Activated Sludge Plant Rehabilitation, consists of modifications and
additions to the Blower Building, Aeration Basin, and Secondary Clarifier Complex.
• The plans and specifications were prepared by HDR Engineering, Inc., and the
contract was awarded to J.R. Filanc Construction Company, Inc. on June 22, 2005.
• Change Order No. 2 includes four items of added work. There are no reimbursable
design errors and two nonreimbursable design errors associated with this change
order. Liquidated damages on this project are $4,000 per day and there are no
bonus provisions (the contract is now 75% complete).
PRIOR COMMITTEE/BOARD ACTIONS
The contract was awarded to J.R. Filanc Construction Company, Inc. by the Board of
Directors on June 22, 2005. Please refer to the attached Change Order Status Report
for information on previous change orders.
ADDITIONAL INFORMATION
Contract Schedule
Contract Start Date August 25, 2005
Original Contract Completion Date June 16, 2007
Total Number of Change Orders to Date 2
Current Contract Completion Date September 25, 2007
Actual Completion Date N/A
Days Subject to Liquidated Damages 0
Book Page 20
Change Order No. 2 Content
Item Description Amount Days Type
No.
Nonreimbursable
1 Lower Tunnel 25 Cable Tray $7,425 0 Design Error
2 Repair Secondary Clarifier Conduit $3,150 0
Nos. 1, 3, and 11 Unknown Condition
3 Modify Secondary Clarifier Motor $4,794 0
Conduits Unknown Condition
4 Cable Tray Changes $21,174 0 Nonreimbursable
Design Error
Total Change Order No. 2 $36,5431 0
This change order complies with authority levels of the Orange County Sanitation
District's Delegation of Authority. This item has been budgeted. (Line item: Section 8,
Page 54).
ATTACHMENT
Change Order Status Report
DED:kf
H9deptlagenda\Commitleee\Operations Committee\Operations 200T OM7-14-Pl-82 CO 2.dw
Book Page 21
CHANGE ORDER STATUS REPORT
ACTIVATED SLUDGE PLANT REHABILITATION AT PLANT NO. 7
JOB NO. P1-82
APPROVAL CONTRACT CONTRACT COST PERCENTAGE AUTHORIZED AUTHORIZED TIME
ITEM DATE COST TO DATE INCREASE TIME TO DATE
)DAYS) (DAYS)
CONTRACT 6/22/2005 $ 32,193,000 $ 32,193,000 0.00 660 660
CO NO. 1 7/19/2006 $ 149,078 $ 32,342,078 0.46 101 761
CO NO.2 Pending $ 36,543 $ 32 378,621 0.58 10 761
w
0
0
x
v
m
eo
m
N
N
EDMS 083827583
OPERATIONS COMMITTEE Meeting Date Toso.orDir.
03/07/07 03/28/07
AGENDA REPORT HemNumW Item Number
OP07-15
Orange County Sanitation District
QHeadworks
FROM: James D. Ruth, General Manager
Originator: James D. Herberg, Director of Engineering
SUBJECT: HEADWORKS REPLACEMENTS AT PLANT NO. 2, JOB NO. P2-66
GENERAL MANAGER'S RECOMMENDATION
Ratify Change Order No. 4 to Headworks Replacements at Plant No. 2, Job No. P2-66,
with J.F. Shea Construction, Inc., authorizing an addition of$332,489, increasing the
total contract amount to $193,474,189.
SUMMARY
• Job No. P2-66 provides for the construction of new a 340 mgd Headworks which
includes new odor control facilities and a new power facility (Power Building E).
• Carollo Engineers prepared the plans and specifications and the contract was
awarded to J.F. Shea Construction, Inc. on May 25, 2005.
• Change Order No. 4 includes six items of added work, and no time extension. There
are five nonreimbursable design errors, and no reimbursable design errors
associated with this change order. Liquidated damages for this contract are $6,000
per day and there are no bonus provisions. The project is now 36.0% complete.
PRIOR COMMITTEE/BOARD ACTIONS
The contract was awarded by the Board of Directors on May 25, 2005. Please refer to
the attached Change Order Status Report for information on all previous change orders.
Contract Schedule
Contract Start Date September 15, 2005
Original Contract Completion Date February 8, 2011
Total Number of Change Orders to Date 4
Current Contract Completion Date March 12, 2011
Actual Contract Completion Date TBD
Days subjected to Liquidated Damages N/A
A��wn: aroaioa Page 1
Book Page 23
Change Order No. 4 Content
Item
No. Description Amount Da s Type
Added Reber at the Influent
1 Pump Station $6,224 0 Nonreimbursable Design Error
Fire Alarm Circuit Changes
2 at Building No. 10 $0 0 Nonreimbursable Design Error
Modifications to Pneumatic
3 Valve Actuators $15,635 0 Nonreimbursable Design Error
Added Wire and Conduits
4 for Scrubber Pumps $20,240 0 Nonreimbursable Design Error
Electrical Dud Bank
Changes and Added Staff Requested Design
5 Breakers $76,928 0 Change
Cable Connection Between
Electrical Service Center
6 and Central Generation $213,462 0 Nonreimbursable Design Error
Total Change Order No. 4 1 $332,489 0
ADDITIONAL INFORMATION
This change order complies with authority levels of the Orange County Sanitation
District's Delegation of Authority. This item has been budgeted. (Line item: Section 8,
Page 50). Project contingency funds will be used for this amendment.
The Project Manager on this project is Pam Koester.
ATTACHMENT
Change Order Status Report
AA:TH:MB:lg:gc
H:Weptlagende\CommittemlOpemlions Committee\Operation 20D7XG3OM7-15-P2.65 CO 4.dm
oar Page 2
Book Page 24
CHANGE ORDER STATUS REPORT
Headworks Replacement at Plant No. 2
Job No. P2-66, Change Order No. 4
CUMULATIVE AUTHORIZED AUTHORIZED TIME
APPROVAL CONTRACT CONTRACT COST PERCENTAGE
ITEM DATE COST TO DATE INCREASE/ TIME T DATE
(DAYS)
DECREASE (DAYS) (DAYS)
to CONTRACT $192,296,073 $192,298,073 0.00 1973 1,973
0
CO NO. 1 4/21/2006 $72,192 $192,368,265 0.04% 0 1,973
v
CO No.2 524/2006 $356,647 $192,724,912 0.22% 0 1,973
10
CO No 10/25/2006 $416,788 $193,141.700 0.44% 32 2,005
CO No. 4 Pending $332,489 $193,474,189 0,61% 0 2.005
EDMS, 003829691
OPERATIONS COMMITTEE MeeangDate ToW.oFDir.
03/07/07 03/29/07
AGENDA REPORT Item Number Item Number
OPo7dfi
Orange County Sanitation District
Collections
RW Facilities
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: CARBON CANYON SEWER AND PUMP STATION ABANDONMENT,
CONTRACT NO. 2-24-1
GENERAL MANAGER'S RECOMMENDATION
1. Approve Amendment No. 5 to the Professional Services Agreement with RBF
Consulting, Inc. providing for additional design engineering services for Carbon
Canyon Sewer and Pump Station Abandonment, Contract No. 2-24-1, for an
additional amount of$40,771, increasing the total amount not to exceed
$622,557.
2. Approve a 4% Contingency ($25,000).
3. Authorize staff to commence negotiations with RBF Consulting for support
services during the construction, commissioning, and close out phase of Contract
No. 2-24-1.
SUMMARY
• This contract is for abandonment of the existing pump station and the force
mains and for the construction of a new gravity feed line across the Carbon
Canyon Dam.
• The proposed amendment provides for the additional design, engineering, and
pre-construction support services necessary to complete the final design that
satisfies the CEQA and Army Corps of Engineers (ACOE) requirements.
• It will be necessary to conduct several meetings with key stakeholders; AERA
Energy, Army Corps of Engineers (ACOE), Department of Fish and Game,
Regional Water Quality Control Board, and County of Orange, in order to seek
their input and approval on the proposed alignment and design. An additional
4% contingency to the original Professional Services Agreement (PSA)
(equivalent to $25,000) will allow RBF to make changes to the design documents
requested by these stake holders.
Page 1
Book Page 26
• RBF Consulting has satisfactory executed the design and possesses an in-depth
and unique knowledge of the nuances of the design. This places RBF
Consulting in the best position to provide support services during the
construction, commissioning, and closeout phases of this project.
• The Plans and Specifications are expected to be completed July 2007. The
engineer's estimated construction cost is $6,000,000.
PRIOR COMMITTEE/BOARD ACTIONS
• June 1998 -Approval of Contract No. 2-24-1 Professional Services Agreement
with William Frost and Associates for engineering design and construction
support services for Construction of Carbon Canyon Dam Sewer and Pump
Station Abandonment for an amount not to exceed $74,000; and approval of an
additional budget increase of$419,000 for a total project budget of$2,194,000.
• August 2001 —Approval of Amendment No. 1 to the Professional Services
Agreement with RBF Consulting for $136,000, increasing the total amount not to
exceed $210,000.
• February 2003 —Approval of Amendment No. 2 to the Professional Services
Agreement with RBF Consulting for$75,656, increasing the total amount not to
exceed $285,656.
• June 2004—Approval of Amendment No. 3 to the Professional Services
Agreement with RBF Consulting for$276,130, increasing the total amount not to
exceed $561,786.
• October 2005—Approval of Amendment No. 4 to the Professional Services
Agreement with RBF Consulting for$20,000, increasing the total amount not to
exceed $581,786.
ADDITIONAL INFORMATION
It is anticipated that construction would start early 2008 and would likely extend to 2009.
This amendment complies with authority levels of the Sanitation District's Delegation of
Authority. This item has been budgeted. (Line item: Section 8, Page 16). Project
contingency funds will be used for this amendment.
Award Date: 02128107 Contract Amount: $622,557 Contingency: 4%
The Project Manager on this project is Umesh Murthy.
JH:UM:ha:eh:bm:kf
H:\dept\agerida\Committees\Operations Committee\Operations 2007\0307\07-16-2-24-1 PSA 5.doc
Page 2
Book Page 27
OPERATIONS COMMITTEE Meeling Date Toad.or Dir.
03/07/07 03/28/07
AGENDA REPORT Item Number Item Number
OP07-17
Orange County Sanitation District
®Collections Facilities
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: REPLACEMENT OF THE BITTER POINT PUMP STATION,
CONTRACT NO. 549; REPLACEMENT OF THE ROCKY POINT PUMP
STATION, CONTRACT NO. 5-50; REHABILITATION OF THE 14TN
STREET PUMP STATION, CONTRACT NO. 5-51; REHABILITATION OF
THE "A" STREET PUMP STATION, CONTRACT NO. 5-52
GENERAL MANAGER'S RECOMMENDATION
1. Approve Amendment No. 7 to Professional Services Agreement with Lee & Ro,
Inc., providing for additional design engineering services for Replacement of the
Bitter Point Pump Station, Contract No. 549; Replacement of the Rocky Point
Pump Station, Contract No. 5-50; Rehabilitation of the 141h Street Pump Station,
Contract No. 5-51; and Rehabilitation of the "A" Street Pump Station, Contract
No. 5-52, for an additional amount of$69,000, increasing the total amount not to
exceed $4,878,382.
2. Approve a 1% contingency ($48,784).
SUMMARY
• This project will replace the existing 70 year old Bitter Point Pump Station. The
project includes the design and construction of mechanical, electrical,
instrumentation and controls, structural, landscape, and architectural improvements
to create a new facility in compliance with the Orange County Sanitation District
(Sanitation District) Standards.
• The new pump station will be built next to the exiting station on land purchased in
2006 from Aare Energy. The land has historically supported oil drilling operations by
both the City of Newport Beach and West Newport Oil Company. Because of the
potential for soil contamination associated with oil drilling operations, staff believes
the previous geotechnical testing performed in 2004 did not adequately characterize
the site for soil and ground water contamination.
• This amendment is for supplemental geotechnical and environmental services. The
purpose is to provide additional ground water, soil, and vapor extraction testing to
characterize the site for potential contamination. The additional services will also
include the installation of monitoring wells to record analytical information necessary
to estimate construction dewatering rates.
Page 1
Book Page 28
• An Agreement with the City of Newport Beach to release their lease rights to the
Bitter Point Pump Station property is currently being negotiated. OCSD purchased
the property in 2006 with the City's lease rights in tact. Per the pending Agreement,
OCSD is required to relocate the City's interfering gas, water, storm, and electrical
utilities. The Scope of Work for the final design of utility relocation is complete and
planned to be performed under a Facilities Engineering (FE) Task. Additional
coordination with Lee and Ro is required to insure that the plans prepared under FE
Task Order 06-05 are coordinated with the Bitter Point Pump Station contract
documents.
PRIOR COMMITTEEIBOARD ACTIONS
• March 2000—Approval of Professional Services Agreement with Lee & Ro, Inc. for
an amount not to exceed $1,149,801.
• March 2002—Approval of Amendment No. 1 to the Professional Services
Agreement with Lee & Ro, Inc. for $495,247, increasing the total contract amount
not to exceed $1,645,048.
• September 2003 —Approval of Amendment No. 2 to the Professional Services
Agreement with Lee & Ro, Inc. for $447,047, increasing the total contract amount
not to exceed $2,092,095.
• September 2004—Approval of Amendment No. 3 to the Professional Services
Agreement with Lee & Ro, Inc. for$818,093, increasing the total contract amount
not to exceed $2,910,188.
• May 2005 —Approval of Amendment No. 4 to the Professional Services Agreement
with Lee & Ro, Inc. for$553,312, increasing the total contract amount not to exceed
$3,463,500.
• February 2006—Approval of Amendment No. 5 to the Professional Services
Agreement with Lee & Ro, Inc. for $1,017,247, increasing the total contract amount
not to exceed $4,480,816.
• March 2006—Approval of Amendment No. 6 to the Professional Services
Agreement with Lee & Ro, Inc. for $328,566, increasing the total contract amount
not to exceed $4,809,382.
ADDITIONAL INFORMATION
In March 2000, the Sanitation District entered into a PSA with Lee & Ro, Inc. for design
and construction support services for the replacement of four pump stations: Bitter Point
(5-49), Rocky Point (5-50), 14n Street (5-51) and A Street (5-52). This amendment is
for Project 5-49 only. This Amendment No. 7 complies with authority levels of the
Page 2
Book Page 29
Sanitation District's Delegation of Authority. This item has been budgeted. (Line item:
Section 8, Page 25).
Award Date: 03100 Contract Amount: $1,149,801 Contingency%: 1%
JH:MD:kf:gc
H:WepflagendMCommigees\Opemtions Commigee\Operations 20071MA07-17.S 9 PSA 7Aw
Page 3
Book Page 30
OPERATIONS COMMITTEE Meeting Date To Bd.of Dlr.
03/07/07 03/28/07
AGENDA REPORT [tem Number Item Number
oy07aa
Orange County Sanitation District
Solids Handling
91 8 Digestion
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: TRUCK WASH AND DEWATERING BEDS AT PLANT NO. 1,
JOB NO. P1-106
GENERAL MANAGER'S RECOMMENDATION
Authorize staff to commence negotiations with Earth Tech for support services during the
construction, commissioning, and closeout phases of Truck Wash and Dewatering Beds
at Plant No. 1, Job No. P1-106.
SUMMARY
• In December 2005, the Orange County Sanitation District (Sanitation District)
issued a Professional Services Agreement (PSA) to Earth Tech to provide
engineering services for Truck Wash and Dewatering Beds at Plant No. 1, Job
No. P1-106.
• Earth Tech satisfactorily executed the design and possesses an in-depth and
unique knowledge of the details of the design. This history makes Earth Tech the
best firm to provide support services during the construction, commissioning, and
closeout phases of this project.
• The Plans and Specifications were issued for bid on January 8, 2007. The
engineer's estimated construction cost is $2,350,000.
PRIOR COMMITTEEIBOARD ACTIONS
• Approval of PSA with Earth Tech for an amount not to exceed $237,676
(Board — December 2005).
• Approval of Amendment No. 1 to the PSA with Earth Tech for$15,200, increasing
the contract total amount not to exceed $252,876 (General Manager— November
2006).
ADDITIONAL INFORMATION
This authorization complies with authority levels of the Sanitation District's Delegation of
Authority. This item has been budgeted. (Line item: Section 8, Page 60). Amendment
No. 2 to the original PSA with Earth Tech will be presented at the time that the
construction contract is presented for award. At that time, a contingency amount will be
assigned to the PSA amendment following the guidelines in the Sanitation District's
Delegation of Authority.
Page 1
Book Page 31
The Project Manager on this project is Pam Koester.
Award Date: 12/21/05 Contract Amount: $237,676 "Contingency%: 0
"No contingency has been established.
JH:PK:kf:bm:gc
H:Wephagenda\Committees%Opemtions Committee\Operations 206T WA07-i6-Pt-106 P&A Ph 4 Neg.doc
Page 2
Book Page 32
OPERATIONS COMMITTEE Meetlng Date To'11.of Dr.
03/07/07 03/2a/07
AGENDA REPORT rte P07_19 r Item rvumber
OP07-19
Orange County Sanitation District
Primary Treatment
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: PRIMARY TREATMENT REHABILITATION/REFURBISHMENT,
JOB NO. P2-80
GENERAL MANAGER'S RECOMMENDATION
Authorize staff to commence negotiations with Malcolm Pirnie for support services during
the construction, commissioning, and closeout phases of Primary Treatment
Rehabilitation Refurbishment, Job No. P2-80.
SUMMARY
• In March 2004, the Orange County Sanitation District (Sanitation District) issued a
Professional Services Agreement (PSA) to Malcolm Pirnie, Inc. to provide
engineering services for Primary Treatment Rehabilitation and Refurbishment,
Job No. P2-80.
• Malcolm Pirnie satisfactorily executed the design and possesses an in depth and
unique knowledge of the all of the details of the design. This history makes
Malcolm Pirnie the best firm to provide support services during the construction,
commissioning, and closeout phases of this project.
• The Plans and Specifications were issued for bid on February 13, 2007. The
engineer's estimated construction cost is $23,000,000.
PRIOR COMMITTEE ACTION
• March 2004—Approval of Job No. P2-80 Professional Services Agreement with
Malcolm Pirnie, Inc. to provide engineering design services for upgrades to the
odor control facilities for the primary clarifiers in the North and South Scrubber
Complexes as well as the rehabilitation and refurbishment of the concrete and
steel structures in the primary clarifiers in Plant No. 2 in an amount not to exceed
$5,778,518.
• September 2005—Approval of Amendment No. 1 to the Professional Services
Agreement with Malcolm Pirnie for $829,984, increasing the total amount not to
exceed $6,608,502.
• August 2006—Approval of Amendment No. 2 to the Professional Services
Agreement with Malcolm Pirnie for $793,641, increasing the total amount not to
exceed $7,402,143.
Page 1
Book Page 33
ADDITIONAL INFORMATION
This authorization complies with authority levels of the Sanitation District's Delegation of
Authority. This item has been budgeted. (Line item: Section 8, Page 53). An
amendment to the original PSA with Malcolm Pirnie will be presented at the time that the
construction contract is presented for award. At that time, a contingency amount will be
assigned to PSA amendment following the guidelines in the Sanitation District's
Delegation of Authority.
The Project Manager on this project is Bob Schirripa.
Award Date: 03124/04 Contract Amount: 5,778,518 'Contingency%: NA
'No contingency has been established.
JH:RS:kf
H:bepltageMa\Commidees\Operations Commidee\Operations 200MMM7-19-P2.80 PSA Ph 4 Neg.dm
Page 2
Book Page 34
OPERATIONS COMMITTEE Meeting Date To Bd.of Dir.
03/07/07 03/28/07
AGENDA REPORT Den Number Item Number
OP07-20
Orange County Sanitation District
Dig scion& Handling
8 lids
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: PLANT NO. 2 PRIMARY SLUDGE FEED SYSTEM, JOB NO. P2-91
GENERAL MANAGER'S RECOMMENDATION
Authorize staff to commence negotiations with Brown and Caldwell for support services
during the construction, commissioning, and closeout phases of Plant No. 2 Primary
Sludge Feed System, Job No. P2-91.
SUMMARY
• In September 2004, the Orange County Sanitation District (Sanitation District)
issued a Professional Services Agreement (PSA) to Brown and Caldwell to
provide engineering services for Plant No. 2 Primary Sludge Feed System, Job
No. P2-91.
• Brown and Caldwell satisfactorily executed the design and possesses an in-depth
and unique knowledge of the nuances of the design. This history makes Brown
and Caldwell the best firm to provide support services during the construction,
commissioning, and closeout phases of this project.
• The Plans and Specifications were issued for bid on February 13, 2007. The
engineer's estimated construction cost is $15,000,000.
PRIOR COMMITTEEIBOARD ACTIONS
• Approval of PSA with Brown and Caldwell for an amount not to exceed
$2,677,550 (Board — September 2004).
• Approval of Amendment No. 1 to the PSA with Brown and Caldwell for $312,816,
increasing the contract total amount not to exceed $2,990,366 (Board — March
zoos).
• Approval of Amendment No. 2 to the PSA with Brown and Caldwell for $28,644,
increasing the contract total amount not to exceed $3,019,010 (Board —
December 2006).
Page 1
Book Page 35
ADDITIONAL INFORMATION
This authorization complies with authority levels of the Sanitation District's Delegation of
Authority. This item has been budgeted. (Line item: Section 8, Page 63). Amendment
No. 3 to the original PSA with Brown and Caldwell will be presented at the time that the
construction contract is presented for award. At that time, a contingency amount will be
assigned to the PSA amendment following the guidelines in the Sanitation District's
Delegation of Authority.
The Project Manager on this project is Pam Koester.
Award Date: 9122104 Contract Amount: $2,677,560 'Contingency%: 0
No contingency has been established.
JH:PK:kf:gc
H:WepllagendalCommitleeeQmmlions Committee\Operations 200710307W7-20-P2-91 PSA Ph 4 Neg.dm
Page 2
Book Page 36
OPERATIONS COMMITTEE PeebngDate roed.orar.
03/07/07 03/2a/07
AGENDA REPORT Item Number Item Numbe
rn UMt
Orange County Sanitation Dlstrlct
Colle Ions
Facilities
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: REHABILITATION OF DISTRICT SIPHONS, CONTRACT NO. 2-68
GENERAL MANAGER'S RECOMMENDATION
Authorize staff to commence negotiations with Dudek and Associates, Inc. for support
services during the construction, commissioning, and closeout phases of Rehabilitation
of District Siphons, Contract No. 2-68.
SUMMARY
• In October 2004, the Orange County Sanitation District (Sanitation District) issued
a Professional Services Agreement (PSA) to Dudek and Associates, Inc. to
provide engineering services for Rehabilitation of District Siphons, Contract
No. 2-68.
• Dudek and Associates, Inc. satisfactorily executed the design and possesses an
in-depth and unique knowledge of the all of the details of the design. This history
makes Dudek and Associates, Inc. the best firm to provide support services
during the construction, commissioning, and closeout phases of this project.
• The Plans and Specifications will be issued for bid on March 30, 2007. The
engineer's estimated construction cost is $4,700,000.
PRIOR COMMITTEE ACTION
• October 2004 -Approval of Professional Services Agreement with Dudek and
Associates, Inc. for an amount not to exceed $987,156.
• February 2004 -Approval of Amendment No. 1 to Professional Services
Agreement with Dudek and Associates, Inc. for an additional amount of$164,000,
increasing the total contract amount not to exceed $1,151,156.
ADDITIONAL INFORMATION
This authorization complies with authority levels of the Sanitation District's Delegation of
Authority. This item has been budgeted. (Line item: Section 8, Page 21). An
amendment to the original PSA with Dudek and Associates, Inc. will be presented at the
time that the construction contract is presented for award. At that time, a contingency
amount will be assigned to PSA amendment following the guidelines in the Sanitation
District's Delegation of Authority.
Page 1
Book Page 37
The Project Manager for this project is Alberto Acevedo.
Award Date: 10/04 Contact Amount: $987,156 'Contingency%:
'No contingency has been established.
JH:AC:kf:gc
H-.bephagen0a\Committees%Ommbons Cwrh;Hee\Operalions 2007MOM7-21 -2- PSA Ph C Neg.dm
Page 2
Book Page 38
OPERATIONS COMMITTEE Meelmg Date To9d.ol Dir.
03/07/07 03/ze/07
AGENDA REPORT Item Number Item Number
OP07-22
Orange County Sanitation District
Collections
Faclities
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: REHABILITATION OF WESTSIDE PUMP STATION,
CONTRACT NO. 3-52
GENERAL MANAGER'S RECOMMENDATION
Authorize staff to commence negotiations with PBS&J Inc. for support services during the
construction, commissioning, and closeout phases of Rehabilitation of Westside Pump
Station, Contract No. 3-52.
SUMMARY
• In July 2004, the Orange County Sanitation District (Sanitation District) issued a
Professional Services Agreement (PSA) to Malcolm Pirnie, Inc. to provide
engineering services for Rehabilitation of Westside Pump Station, Contract No. 3-52.
• PBS&J Inc. satisfactorily executed the design and possesses an in-depth and unique
knowledge of all of the details of the design. This history makes PBS&J Inc. the best
firm to provide support services during the construction, commissioning, and closeout
phases of this project.
• The Plans and Specifications will be issued for bid on March 26, 2007. The
engineer's estimated construction cost is $5,200,000.
PRIOR COMMITTEE ACTION
• July 2004—Approval of Professional Services Agreement with PBS&J for an amount
not to exceed $1,164,721.
ADDITIONAL INFORMATION
This authorization complies with authority levels of the Sanitation District's Delegation of
Authority. This item has been budgeted. (Line item: Section 8, Page 22). An amendment to
the original PSA with PBS&J Inc. will be presented at the time that the construction contract
is presented for award. At that time, a contingency amount will be assigned to PSA
amendment following the guidelines in the Sanitation District's Delegation of Authority.
The Project Manager on this project is Alberto Acevedo.
Award Date: 7104 Contract Amount: $1,164,721 'Contingency %: NIA
'No contingency has been established.
JH:AC:kf:gc
H:ldepllagendalCommid•es\Operations CommideelOpemtions 20071030T,07-22-352 PSA Ph 4 Neg.doc
Page 1
Book Page 39
OPERATIONS COMMITTEE rneeanyoate Toed.wur.
0310,107 031jit 7
AGENDA REPORT Iem Item Number
Po7-23
_ O7-23
Orange County Sanitation District
I Collections
= �Facilities
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: GISLER-REDHILL TRUNK SEWER RELOCATION, PHASE 1
CONSTRUCTION, CONTRACT NO. 7-32-1
GENERAL MANAGER'S RECOMMENDATION
Authorize staff to commence negotiations with Spec Services, Inc. for support services
during the construction, commissioning, and closeout phases of Gisler-Redhill Trunk Sewer
Relocation, Phase 1 Construction, Contract No. 7-32-1.
SUMMARY
• In March 2004, the Orange County Sanitation District (Sanitation District) issued a
Professional Services Agreement(PSA) to Spec Services, Inc. to provide engineering
services for Gisler-Redhill Trunk Sewer Relocation, Phase 1 Construction, Contract
No. 7-32-1.
• Spec Services, Inc. satisfactorily executed the design and possesses an in depth and
unique knowledge of all the details of the design. This history makes Spec Services,
Inc. the best firm to provide support services during the construction, commissioning,
and closeout phases of this project.
• The Plans and Specifications were issued for bid on December 18, 2006. The
engineers estimated construction cost is $1,270,000.
PRIOR COMMITTEE ACTION
• March 2004—Approval of a Professional Services Agreement (PSA) with Spec
Services, Inc. for an amount not to exceed $102,591.
ADDITIONAL INFORMATION
This authorization complies with authority levels of the Sanitation District's Delegation of
Authority. This item has been budgeted. (Line item: Section 8, Page 37). The Project
Manager on this project is Hardat Khublall.
Award Date: 03/24/04 Contract Amount: $102,591 'Contingency %:
'No contingency has been established.
JH:AC:kf:gc
H:WenhagendMCommittees\Opemlions Carnmtltea\Operations 20CrA0307t07-23-7-32-1 PSA Ph 1 Neg.doc
Page 1
Book Page 40
OPERATIONS COMMITTEE Mcetln9D. TofiA.ofl) -
03/07107 03/2a/W
AGENDA REPORT Item Number teem Number
OP07-24
Orange County Sanitation District
®Collections
Facilities
FROM: James D. Ruth, General Manager
Originator: Jim Herberg, Director of Engineering
SUBJECT: REHABILITATION OF COLLEGE AVENUE PUMP STATION,
CONTRACT NO. 7-47
GENERAL MANAGER'S RECOMMENDATION
Authorize staff to commence negotiations with RBF Consulting for support services during
the construction, commissioning, and closeout phases of Rehabilitation of College Avenue
Pump Station, Contract No. 7-47.
SUMMARY
• In August 2004, the Orange County Sanitation District(Sanitation District) issued a
Professional Services Agreement (PSA)to RBF Consulting to provide engineering
services for Rehabilitation of College Avenue Pump Station, Contract No. 7-47.
• RBF Consulting satisfactorily executed the design and possesses an in-depth and
unique knowledge of all the details of the design. This history makes RBF Consulting
the best fine to provide support services during the construction, commissioning, and
closeout phases of this project.
• The Plans and Specifications will be issued for bid on March 28, 2007. The
engineer's estimated construction cost is $7,600,000.
PRIOR COMMITTEE ACTION
• August 2004—Approval of Professional Services Agreement with RBI Consulting for
an amount not to exceed $941,576.
ADDITIONAL INFORMATION
This authorization complies with authority levels of the Sanitation District's Delegation of
Authority. This item has been budgeted. (Line item: Section 8, Page 39). An amendment to
the original PSA with RBF Consulting will be presented at the time that the construction
contract is presented for award. At that time, a contingency amount will be assigned to PSA
amendment following the guidelines in the Sanitation District's Delegation of Authority.
The Project Manager on this project is Alberto Acevedo.
Award Date: 08104 Contract Amount: $941,576 `Contingency%:
'No contingency has been established.
JH:AC:kf:gc
H:WepNgendMCanmittees\0Pe2ticn5 Ccinmmee\Operations 2007W30T07-24-747 PSA Ph 4 Neg.doc
Page 1
Book Page 41
OPERATIONS COMMITTEE Meeting Data To Btl.or Db.
03/07/07 03/29/07
umb
AGENDA REPORT Item Ner Item Numbe
OP07-25
umt
Orange County Sanitation District
1W Collectionsies
FROM: James D. Ruth, General Manager
Originator: Jim Hallberg, Director of Engineering
SUBJECT: REHABILITATION OF THE 14" STREET PUMP STATION, CONTRACT
NO. 5-51, AND REHABILITATION OF THE "A" STREET PUMP STATION,
CONTRACT NO. 5-52
GENERAL MANAGER'S RECOMMENDATION
1. Approve a budget increase for Rehabilitation of the 14" Street Pump Station,
Contract No. 5-51, in the amount of$86,836 for a total project budget of$9,759,836;
and,
2. Ratify Change Order No. 3 to Rehabilitation of the14tb Street Pump Station, Contract
No. 5-51, and Rehabilitation of the "A" Street Pump Station, Contract No. 5-52, with
Kiewit Pacific Company authorizing an addition of$178,181 and 0 calendar days,
increasing the total contract amount to$12,273,404.
SUMMARY
• This contract is for construction of a new 14" Street Pump Station at 1510 W.
Balboa Boulevard and construction of a new"A" Street Pump Station at 810 W.
Balboa Boulevard in the City of Newport Beach. The existing pump stations are
about 50 years old and do not meet current standards of performance and safety.
• Lee & Ro, Inc. prepared the plans and specifications, and the construction contract
was awarded to Kiewit Pacific Company on September 22, 2004.
• Change Order No. 3 includes eighteen items of added work. There are no
reimbursable design errors and nine nonreimbursable design errors associated with
this change order. The contract includes liquidated damages of$1000 per day and
no bonus provisions. The contract is 100% complete.
PRIOR COMMITTEE/BOARD ACTIONS
The contract was awarded to Kiewit Pacific Company by the Board of Directors on
September 22, 2004. Please refer to the attached Change Order Status Report.
Page 1
Book Page 42
ADDITIONAL INFORMATION
Contract Schedule
Contract Start Date: November 10, 2004
Original Contract Completion Date: June 7, 2006
Total Number of Change Orders to Date: 3
Current Contract Completion Date: October 12, 2006
Days Subject to Liquidated Damages: N/A
Liquidated Damages Assessment: 0 Calendar Days
Change Order No. 3 Content
Item No. Description Amount Days Type
Contract
No. 551
Slurry Blanket Under Masonry
1 Wall $3,742 0 Other
Place and Remove Temporary
2 Paving $16,748 0 Other
3 Dewatering System Shutdown $7,620 0 Other
14 Street Pump Station Nonreimbursable Design
4 Force Main Modifications $1,924 0 1 Error
Move Junction Boxes for Staff Requested Design
5 Pump Motors $2,594 0 Change
Security Fence and Curb
Detail at 10 Street Pump Nomeimbursable Design
6 Station $20,110 0 Error
Upgrade of UPS Capacity Nonreimbursable Design
7 $8,129 0 Error
Contract
No. 552
8 1 Hot Tap Into City Water Main $6,283 0 Other
"A" Street Alley Sewer
9 Modifications $66,639 0 Unknown Conditions
Additional Site Work at"A" Nonreimbursable Design
10 Street Pump Station $7,688 0 Error
Temporary Paving in "A"
11 Street Pump Station Alley $2,464 0 Other
Page 2
Book Page 43
Contract
No.551
and
No. 552
Architectural Modifications at
"A"Street and 10 Street
12 Pump Stations $17,267 0 Other
13 Added Dewatering Flow $3.645 0 Staff Requested Design
Meters Change
14 Added UPS Power Source $4,314 0 Nonreimbursable Design
Error
Remove and Reinstall
15 Receptacles for Sump Pumps $2,133 0 Nonreimbursable Design
Error
Install Fiber Optic Media Nonreimbursable Design
16 Converters $1,633 0 Error
Pump Moisture Detector Nonreimbursable Design
17 Control Circuit $1,141 0 Error
Nonreimbursable Design
18 PLC Enclosure Change $4,107 0 Error
Total—Change Order No. 3 $178,181 1 0
A budget amendment of$86,836 is being requested. Additional funds are being
requested to cover costs for change orders and staff labor to support added
construction activities beyond the original contract completion date. The proposed
source of funding is from the Orange County Sanitation District's (Sanitation District)
Capital Improvements Reserves.
This change order complies with authority levels of the Sanitation District's Delegation
of Authority. This item has been budgeted, but there are insufficient funds (Line Rem:
Section 8, Pages 27 and 28)
The Project Manager on this project is Umesh Murthy.
ATTACHMENTS
Change Order Status Report
UM:BP:bm:gc
H:\ PPa9e \Committees\Opealions CommMtt Qpemtans 200n030M]-25-5-51 S52 CO 3.doc
Page 3
Book Page 44
CHANGE ORDER STATUS REPORT
REHABILITATION OF THE 14TH STREET PUMP STATION
REHABILITATION OF THE "A" STREET PUMP STATION
CONTRACT NOS. 5-51 AND 5-52
APPROVAL CONTRACT CONTRACT COST PERCENTAGE AUTHORIZED AUTHORIZEDTIME
ITEM DATE COST TO DATE INCREASE TIME TO DATE
(DAYS) (DAYS)
CONTRACT 1 1/1 012 0 04 $11,697,780 $11,697,780 0.00 575 575
8
F CO NO. 1 6/28/2006 $141,364 $11,839,144 1.21% 113 688
v
m
Rio CO NO. 2 12/20/2006 $256,079 $12,095,223 3.40% 14 702
A
CO NO. 3 1 Pending $178,181 $12,273,404 4.92% 0 702
EDMS'.003825705
DRANGE COUNTY SANITATION DISTRICT
(714) 962-2411
NvAv.ocsd.com
Mailing Address:
M. Box 8127
ountain Valley, California
)2728-8127
Itreet Address:
_0844 Ellis Avenue
ountain Valley, California
12708-7018