HomeMy WebLinkAbout2006-06-28 June 21, 2006 ORANGE COUNTY SANITATION DISTRICT
prone:
o141 s6z-2411 tie: NOTICE OF MEETING
0141962d356
wgneAlOtl.tam
PRnji°tlimi
PO,Bozfi1ZJ BOARD OF DIRECTORS
F"" ""y8- 27
92R&B12 ORANGE COUNTY SANITATION DISTRICT
"an".add..:
10BC4 Ellis Avenue
92)097016 WEDNESDAY, June 28, 2006 = 7:00 P.M.
Msslror
Agenda
• DISTRICT'S ADMINISTRATIVE OFFICES
Cities 10844 Ellis Avenue
Ammaim Fountain Valley, California 92708
fire.
Buena Park
Lypress
Po nt.m ✓alley
�a"tee The Regular Meeting of the Board of Directors of the Orange County Sanitation
Huntington Beach District will be held at the above location, time and date.
Irvine
Le Habra
e Be
lms
Los Alamiros
Newpon Beach
O ange
PlIff
acentia
sent.and BdArd Secrolry
Send Beach
Z.,
Tustin
Wild Park
Yorbe Linda
OMTS COMMITTEE -Wednesday,July 5,2006 at 5:00 p.m.
County or orange
PDC COMMITTEE -Thursday,July 6,2006 at 5:00 p.m.
Sallhary Districts
Costs Mesa GWR SYSTEM STEERING COMMITTEE -Monday,July 10, 2006 at 5:30 p.m. @OCWD
Midway Ory
LEGISLATIVE AFFAIRS -Tuesday, July 11,2006 at 8:00 a.m.
YWtae ebcdtts
Arvin. Pali COOPERATIVE PROJECTS GRANT COMMITTEE -Wednesday,July 12,2006 at 4:00 p.m.
FAHR COMMITTEE -Wednesday,July 12,2006 at 5:00 p.m.
STEERING COMMITTEE -Wednesday,July 19,2006 at 5:00 p.m.
To man:ain world class leadersh,p in wnsa,vater and water resource management.
nm
BOARD MEETING DATES
'July 19, 2006
August 23, 2006
September 27, 2006
October 25, 2006
"November 15, 2006
'December 20, 2006
January 24, 2007
February 28, 2007
March 28, 2007
April 25, 2007
May 23, 2007
June 27, 2007
*Meetings are being held on the third Wednesday of the month
H.Wep1U,lPublic AffaimW01BS AgendaX2008 Meeting NDUwsXMN06.2.dm
MEMORANDUM
TO: Orange County Sanitation District Board of Directors
FROM: Jame` t , Interim General Manager
SUBJECT: OCSD Cost Saving Efforts
At this evening's Board meeting, I will present the OCSO 2006-07 and 2007-08 Proposed Budget.
During the budget development process, we have presented information regarding many of the
District's large projects and initiatives. These projects often require substantial resources and
labor allocations. As a result, we often focus on the large funding solutions and cost reduction
strategies required to address these needs.
However, much of our mitigation efforts rely upon the day-to-day activities that allow us to realize
various operating efficiencies. Although these items are often small or appear routine and do not
generally appear in the budget or Board presentations, these measures help us to remain cost
effective. I have provided a small sample of these efforts below:
Operations and Maintenance
1. Through the Department's Plant Optimization process, we were able to decrease chemical
usage, thereby reducing costs by approximately$1.4 million.
• 13.5% decrease in ferric chloride usage
This lower level optimum dosage not only saved chemical costs ($444,500), but also
resulted in a 3.2%decrease in wet tons of biosolids ($331,285).
• 7.5% decreased in outfall disinfection bleach usage
Changing the dosage point pH to make bleach more effective resulted in an approximate
savings of$455,800
• 30.3% decrease in sodium bisulfite usage
Decrease in bleach usage and optimization of dechlorinalion decreased usage, resulting
in an estimated $130,000 savings.
Distributed at
dm�Board Meeting
OCSD PO,W.8127 Fwnt.n V**,.CA 927284127 (714)882@411
2. Other Operations and Maintenance Cost Saving Measures
• Renegotiated cryogenic plant maintenance contract by 10.2%($33,000)
• Optimized the CenGen to during the summer peak power rate periods
• Optimized the CenGen fuel mix between natural and digester gases to minimize costs
• Facilitated participation in the Edison Savings By Design program for several capital
projects that will result in substantial rebates for installing energy efficient components in
new designs.
• Performed national survey on Ferric and Ferrous Chloride to ensure accurate pricing
• Used predictive and reliability centered maintenance to provide the for most efficient and
cost effective asset management program
• Reorganized the Maintenance Divisions for improved support of all our the facilities
• Hired a corrosion expert to support better and more cost effective asset management
• Regularly interacted with other agencies for information regarding vendors,agreements,
operational practices
• Developed a committee to promote safety and process improvements
• Scheduled an interagency meeting in the fall for best practices and strategies to deal with
escalating chemical and bio-solids cost and other common concerns
• Investigated on-site chemical generation
Engineering
1. The Project Management Office(PMO)completed a detailed risk analysis of on-going
projects and was able to reduce the budgets by$66 million.
2. The PMO reduced project support costs(staff, consultants and legal)from an average of 46%
to 32% of the construction costs for a$49 million savings over the past 3 years.
3. The PMO Implemented rigorous Project Management practices to help reduce cost and
schedule impacts. Keeping projects on schedule eliminates escalation costs. (s%-to%per year)
4. The PMO developed a standard scope of work template and GATE meetings, minimizing
scope creep: Thorough scope definition eliminates misunderstandings and scope additions
due to changes which are then confirmed by the PMO and management at GATE meetings.
5. Staff developed standard cost estimating methodology and guidelines to help in consultant
and contractor negotiations. Staff has negotiated approximately$10 million in reductions of
change orders and consultant costs over the past 3 years.
6. The PMO has been able to accurately forecast yearly cash Flow for the past three years which
helps finance borrow efficiently and keep interest payments minimized.
7. The Biosolids Management Plan completed in 2004, resulted in elimination of$200 million in
potential capital investments.
8. The new collections system hydraulic model identified several projects within the collection
system that could be eliminated or postponed from the FY 2006/07 CIP, resulting in a net
savings of$200 million.
9. The long term collection system monitoring program was cancelled when ongoing data results
became less beneficial, resulting in a savings of$200,000.
10. The recently completed Energy Master Plan, initiated by the Engineering Department, has
recommended effective and economical means of generating and purchasing electrical power
to meet our future needs, averting the need to expand our generating facilities at a potential
cost of$65 million.
11.A project review process has been developed utilizing asset management principles that has
reviewed $376 million in potential projects over the past three years and recommended only
$73 million of projects be implemented.
Technical Services
1. Ocean Monitoring Program (OMP) In-sourcing
With existing staff, Division 620 in-sourced the field sampling component of the OMP and
approximately 80% of prep work on the OMP annual report,saving several hundred thousand
dollars annually in consultant costs. The laboratory in-sourced the sediment and tissue
chemistry components of the program providing additional savings.
2. MN Nerissa Purchase
This purchase proved cost effective by eliminating the need to charter research boats.
Financial analysis comparing this purchase with the previous cost of leasing boats from
private vendors indicated a payback in approximately 5 years.
3. Source Control Automation
Source Control, along with the Information Technology Department,developed a computer-
generated permit fact sheet for industrial permittees allowing us to reassign one person to the
FOG control program in lieu of hiring new staff.
4. Lab Reorganization
Through reorganization, Technical Services was able to replaced one Supervisor position with
a Senior Analyst position, saving $40,000 annually.
5. Re-bid Laboratory Contract
This department successfully replaced a sole source contract for specialty gases with a bid
contract, resulting in reduced bid of$32.000 from 65,000, a$33,000 savings.
6. Biosolids Management
Staff provided technical and regulatory support to one of our biosolids contractors (Tule
Ranch)that allowed permitting in Kem County of a biosolids chemical stabilization process as
an'appurtenance to fanning"thus developing a low-cost biosolids management option.
7. In-County Compost Use Program
Working with Synagro to create an in-County compost use program, we were able to keep
biosolids management costs down.
8. Compost Contracts
Working with outside entities, OCSD locked-up the majority of the Class A biosolids
composting capacity available in Southern Califomia thus providing the District with a cost
avoidance strategy in light of county prohibitions limiting Class B land application.
Regional Assets and Services Costs Saving Efforts
1. High performance automotive finishes for painted steel
Benefits: More durable, longer life, appearance
Savings: Recurring labor savings due to longer life
2. Use of galvanized steel, aluminum, stainless steel &fiberglass for structural components.
Benefits: Eliminates the need for painting and more resistive to corrosion
Savings: Labor savings by eliminating painting resulting in longer life on base materials.
3. Eliminated ball type & split wedge non-rising stem valves in sewage applications
Benefits: Fewer failures and related sewer spills and process upsets
Savings: Labor savings and potential fines and service interruptions
4. Dezurik'True Eccentric'Plug Valves for sewage services
Benefits: Improved system performance and reliability, longer valve life
Savings: Labor savings due to less frequent exercising and maintenance needs, fewer
replacements needed due to longer fife due to lower wear rates
5. Dynamic balancing machine for rotating equipment
Benefits: Balanced impellers and shafts associated with critical plant process and pump
station equipment.
Savings: Costs saved by not having to outsouroe balancing to outside vendors.
6. Label and sign making machine.
Benefits:Ability to fabricate labels and signage quickly and in house for compliance in plant
process areas.
Savings: Costs saved by not having to outsource the fabrication of labels and signage
including contract administration and management.
7. Use of bicycles—"pedal power"
Benefits: Transportation within the plant facilities without the cost of fuel or electricity.
Savings: Savings on equipment, fuel, electricity,emissions, and ease of maintenance.
8. DuPont Process Area Maintenance Painting Program
Benefits: A turnkey managed program to keep exterior corrosion to acceptable levels based
on worldwide best practices.
Savings: Direct labor, contractor costs, materials, specification and safety engineers,
materials except for the OCSD staff overseeing the work and contract interface.
9. Standardized designs of service truck bodies
Benefits to OCSD: Lower costs and faster delivery of finished goods to customers by bidding
more uniform and complete packages.
Savings: Various craft hours and materials spent on customizing and finishing to various
customer needs.
10. Sole sourcing of Taylor Dunn electric personnel carriers and service carts
Benefits: Improved reliability, longer fife, less maintenance
Savings: Fleet services& painter's staff time on maintenance&corrosion management
11.Wemco Hydrostal screw centrifugal pumps for sewage pump stations
Benefits: Improved performance, efficiency, reliability, and lower maintenance costs
Savings: Payback on Edinger Pump Station was estimated at less than 3 years based on
straight time and O.T. savings"de-ragging'the
12. Specialized software and global positioning systems(GPS.equipment for Dig Alert Program
Benefits: improved data sharing and management of data and improved accuracy, ease of
locating facilities in rural areas, fewer sewer spills due to less damage by contractors
Savings: Staff time and ability to assist contractors to avoid damaging OCSD facilities.
13. Collection Facilities O&M Business Practice Reinvention Effort
Benefits: Formally sets up a focused production style business with improved efficiency and
business practices
Savings: Formal production schedules, improved data management, assists in regulatory
compliance, task standards and written standard operating procedures,etc. (a
complete staff report is in development.
Information Technology
1. Converting the Verizon/AT&T telephone contracts to the State of California negotiated SBC
contract at a savings of$50,000.00 over four years.
2. Copier/Printer consolidation (switching from leasing to buying. for a savings of$200,000.00
over four years
3. Staffing the CCSD Reproduction Center with Xerox Managed Services and in sourcing copy
jobs: potential savings of$50-$1OOK annually.
Human Resources
1. Leveraging professional association membership—(WEROC cost of$15,000 annually saves
OCSO an anticipated $185,000 for FY 2006-07 based on $140,000 hazard mitigation plan
cost and$60,000 Web EOC cost being avoided.
2. Managing hazardous waste on site through contractor($3,000 savings.
3. Combining safety training classes to reduce administrative costs
4. Attending on site medical screenings to reduce administrative costs
5. Dispensing prescription safety glasses on site to reduce administrative costs
6. Implementing Web Based Training
7. Consolidating advertising (on demand).
8. Sourcing—reduces time to fill(has a dollar value. and advertising
9. Reviewing annual benefits plan—changes in renewal cycles,etc
10.Changing costly past practices and misapplication of MOUs/policies reduces administrative
costs and unfunded liabilities.
11. Managing the LOA/Disability program limits liability and reduces loss time.
12. Ensuring compliance reduces legal costs associated with violations.
13. Managing the LOA/Disability program reduces absenteeism problems
14. Providing a thorough and consistent return to work process reduces liability
Finance
1. The in cooperation with Information Technology Department, we have begun implementation
of our new Electronic Timekeeping Entry System. This system will allow employees to move
away from paper timecards, thus reduce errors, allowing resources to be reallocated to other
more valuable activities and Is projected to have pay back period of less than two years.
2. Proper management of the recent debt issuance allowed the District to save interest and fees.
3. Prompt payment processing has resulted in freeing additional resources for other activities.
c: N.Arhontes
R. Ghirelli
J. Herberg
D. Ludwin
P. Miles
L.Tomko
L.Tyner
ROLL CALL
BOARD OF DIRECTORS
ORANGE COUNTY SANITATION DISTRICT
MEETING DATE & TIME: 06/28/06 - 7:00 p.m.
(SIMONIAN) .....................ANDERSON...................
��
(SHANKS) ........................ANTOS ......................... ✓ �L —
(WILSON) ........................BANKHEAD................... r�
(VACANT).........................CAVECCHE...................1/ _g�elld;E/3ot
(GARCIA)..........................CHRISTY.....................
(COLLINS)........................CRANDALL................... i —
(ROSEN)...........................DALTON....................... ''— ✓ —
(KAWASHIMA).................. DAVERT...................... ✓ gaxa 3 f 3, Eiar��Jll9u/
(WINDER).........................DUVALL...................... —
(UNDERHILL)...................ECKENRODE.................
�L —
(SCHAFER) ......................FERRYMAN................... ✓
(FAUTEUX).......................FRESCHI .............. ..... ✓
(CHOI)...............................KANG.......................... �L —
(SONDHI)..........................LUEBBEN.....................
�� —
(DOW)...............................MARSHALL.................. —
(REINHART).....................MILLER .........................�L — —
(BEAUMAN)......................MOORE........................ . —
(KIRKPATRICK-PILGER) .NEUGEBAUER.............. ✓ —
(DRISCOLL)......................PARKER....................... �L —
(WEBB) ............................RIDGEWAY...................
✓ _
(DONAHUE) .....................SHAWVER.................. -r� /�c/i 9 YYB
(HERNANDEZ) .................SIDHU..........................
�✓ ✓ —
(CORREA) ........................SILVA........................... —
(COOK) ............................SULLIVAN...................... ✓ ✓
(RODRIGUEZ)..................WALDMAN.................... ✓ ✓ _ 2_ _
STAFF: s- / S, e/d 9l, 5/ 3 r/`I, P/3 /i �0915
Arhontes
Colson ✓
Ghirelli ✓ ��QQ
Herber ✓ �� 3�ry .
Kovac
Kyle ✓ �iw lti '�c(L`
Ludwin
Miles ✓ eu
Ruth
Tomko
Tyner
OTHERS:
Ho in / r-
06/28/06
H:\tlepNdmin\BS\DIRECTOR\Directors Rail Call.doc
SIGN-IN SHEET
ORANGE COUNTY SANITATION DISTRICT
I I,w ��� BOARD MEETING
NAME ORGANIZATION/FIRM
leaseprint) leaseprint)
P eAec oC s a -/CuJEA
GGam: �,e
u F Gg
G8p-S
HAWRDWADMINGSWORMS,SIGN-IN FORM.DOC
EXCERPTS FROM THE MINUTES OF THE REGULAR
MEETING OF THE BOARD OF DIRECTORS OF
ORANGE COUNTY SANITATION DISTRICT
A regular meeting of the Board of Directors of Orange County Sanitation District was held
at the hour of 7:00 p.m., June 28, 2006, at 10844 Ellis Avenue, Fountain Valley,
California.
The Chair of the Orange County Sanitation District called the meeting to order at
7:00 p.m.
The roll was called and the Secretary reported a quorum present.
MOVED, SECONDED AND DULY CARRIED: Approve FY 2006/07 and 2007/08
Proposed Operating, Capital, Debt/COP Service and Self-Insurance Budgets for FY 2006-
07 and 2007-08, as follows:
2006-07 2007-08
Net Operations, Maintenance & Working Capital $129,054,210 $135,602,130
Worker's Compensation Self Insurance $526,200 $559,400
General Liability and Property Self-Insurance $1,766,100 $2,055,200
Net Capital Improvement Program $266,088,000 $338,818,000
Debt/COP Service $54,410,000 $65,462,000
Other Requirements $4,499,800 $2,645,300
Total $456,344,310 $545,142,030
STATE OF CALIFORNIA)
)SS.
COUNTY OF ORANGE )
I, PENNY M. KYLE, Secretary of the Board of Directors of Orange County
Sanitation District, do hereby certify that the above and foregoing to be a full, true and
correct copy of minute entries of the meeting of said Board of Directors on the 28th day of
June, 2006.
IN WITNESS WHEREOF, I have hereunto set my hand this 5th day of July, 2006.
Secretary \ ors- -
Orange County Sani LDijo
G-.\wp.dta\admin\SSWORMS\2003\Minutes Exmrpt.062503.dm -- _ -
STATE OF CALIFORNIA)
) SS.
COUNTY OF ORANGE )
Pursuant to California Government Code Section 54954.2, 1 hereby certify that
the Notice and Agenda for the Regular Board Meeting of Orange County Sanitation
District to be held on of , 2006, was duly posted for public inspection
in the main lobby of the Districts' offices on d d- 2006.
IN
WITNESS WHEREOF, I have hereunto set my hand this -2A day of
�, 2006.
` ,���
Penny M. Kyle, Secret
Board of Directors
Orange County Sanitation District
HADEPT\HR\PUBLIC AFFAIRSQ20\BS\FORMS\AGENDA CERTIFICATION.DOC
ORANGE COUNTY SANITATION DISTRICT
Date: June 21, 2006
0143 962-241411° To The Chair and Board of Directors
r,n; Orange County Sanitation District
1714)962D368
"'s' osel.. From: James D. Ruth
msa)s,add...: Interim General Manager
P.O. Bon B127
Pounteln Volley.CA
92728.8127 Subject: Board Letter
a..":dl
10844 Ellie Avenue
r'an92708-io a OCSD to Convert Biosolids to Renewable Energy
On June 5, 2006, OCSD announced a partnership with EnerTech
Member Environmental, Inc. to convert 200 daily tons of biosolids into renewable
A,.ncl.. energy. EnerTech is a renewable energy company based out of Atlanta and
the company's SlurryCarbTM process, converts biosolids and other high
c"as moisture wastes into a high-grade, renewable fuel with significant cost
Anaheim savings over alternative methods.
are
Buena Park
cvPreas Currently, EnerTech has existing contracts with four other municipalities to
°°aFwlae°o� convert their biosolids into E-fuel. EnerTech is scheduled to begin
Manu��ea.. construction on a SlurryCarbTM facility in Rialto, California this summer.
ach
brine
to Habra Le Palma National Water Research Institute (NWRI) Update
Los Alamitos Attached is an update on NWRI activities. OCSD is a member of the
Newport Beach organization which was founded in 1991 with the support o each 9 of Joan Irvine
Placentia Smith. NWRI is dedicated to creating new sources of water through research
Santa Ana
Seat Beach and technology, and protecting the freshwater and marine environments.
sue Director Norm Eckenrode is the Sanitation District's representative on the
Ville Park NWRI board of directors.
%nus Linda
D...t, of a...,. GWR System Wins PRSA Silver Anvil Award 2006
The Orange County Sanitation District and the Orange County Water District,
U.N., Dl.trl.t. along with Porter Novelli, were recently awarded the Silver Anvil Award by the
Costs Ms. Public Relations Society of America for the GWR System Community
Midway city Relations Program. This national award recognizes programs that aim to
Water Districts improve relations with people or organizations in communities in which the
lrNna Rench sponsoring organization has an interest, need or opportunity. It symbolizes
the forging of public opinion, and is annually awarded to organizations that
have successfully addressed a contemporary issue with exemplary
professional skill, creativity and resourcefulness.
To maintain worlddclass leadership in wastewater and we tar resource management.
Board of Directors
Page 2
June 21, 2006
OCSD is the First in the Nation to be Certified for our
Biosolids Environmental Management System
In July 2003, OCSD was the first agency in the nation to be certified by the
National Biosolids Partnership (NBP)for our Biosolids EMS. The NBP
provided OCSD with a certification flag to promote our accomplishment. As
part of our recent increase in EMS awareness and training efforts, we will be
flying the EMS flag under the American flag on our main flag pole. In addition,
EMS "critical control point" signs will be added to critical biosolids treatment
processes throughout the plants to make staff and the public more aware of
how the Biosolids EMS works.
Measure E, the Kern County Biosolids Initiative,
Passes with 83% Voting Yes on the Measure
With the passage of Measure E, the Kern County Board of Supervisors are
obligated to carry out the will of the people and adopt an ordinance, known as
the "Keep Kern Clean Ordinance of 2006."
The ordinance immediately prohibits the land application of all forms of
biosolids in the unincorporated area of Kern County with an exception for
three existing permit holders who have six months to discontinue the land
application of biosolids. An appeal procedure is in place for existing permit
holders to request an extension of no more than six months to discontinue
biosolids application if special circumstances exist, which create a hardship
for those who have installed or constructed permanent improvements relating
to the land application of biosolids. Biosolids packaged for routine retail sales
through regular retail outlets are excluded from the ban.
OCSD currently manages approximately 30%, or 200 tons per day of its
biosolids using a chemical stabilization process at Tule Ranch to comply with
Kern County's existing Class A biosolids requirements. If the initiative and the
ordinance survive the anticipated legal challenges, sufficient additional
biosolids management capacity for OCSD has been secured at Synagro's
existing composting facilities in Corona, California and La Paz County,
Arizona.
Staff also anticipates that 250 tons of capacity for composting OCSD's
biosolids at Synagro's South Kern Industrial Center (SKIC) will come on line
by December, 2006 and 200 tons of capacity for biosolids-to-fuel production
at the EnerTech facility in Rialto, California will be available by June, 2008.
Additional information regarding the initiative, the vote, and the ordinance is
located at hftp:l/www.keel)kernclean.com/.
Board of Directors
Page 3
June 21, 2006
Final Report on Private Sewer Laterals Rehab
The Water Environment Research Foundation (WERF) has recently
published its final report on Methods for Cost-Effective Rehabilitation of
Private Lateral Sewers.
Millions of sewer laterals exist throughout the U.S. and many allow the entry
of a significant amount of inflow and infiltration (1/I) into sewer systems.
Sewer laterals are often a significant contributor to sanitary sewer overflows
(SSOs), increased cost of wastewater conveying and treatment, and costly
damage to private property through sewer backups.
This report provides a clear understanding of problems and relevant issues,
and explains available options for inspection, evaluation and repair of sewer
laterals. It also addresses the financing and legal issues that affect the
means by which the work can be carried out.
Please contact Nick Arhontes, Director of the Regional Assets and Services
Department if you would like to have a copy of this report.
If you would like additional information on any of the above items, please call
me.
James D. Ruth
Interim General Manager
JDR:gg
HIDEPIlADMMIGMBOARD LETTERQW6W MBOARD LTR.DOC
Attachment
�lafionaQ �atet ResearA Onstitufe
MEMBER Ur
W W W.NWRI-USA.org
Dr. Philip Singer, Expert in Drinking Water Quality,
MeanFwn Qgeeuied to Receive the 2006 Clarke Prize
Inland Empire Utilities Agency N WRI is pleased to announce that drinking water expert
Philip C. Singer,Ph.D., P.E.,of the University of North
Irvine Ranch Water District Carolina at Chapel Hill,will be the thirteenth recipient of
the Athalie Richardson Irvine Clarke Prize for excellence
Los Angeles Department in water research.
of Water and Power
The 2006 Clarke Prim will be presented to Singer on
Orange County Sanitation District Thursday,July 13,2006,at the Thirteenth Annual Clarke '
Prize Award Ceremony and Lecture,to be held at Mission
Orange County Water District San Juan Capistrano in San Juan Capistrano,California.
West Resin Municipal A Professor of Environmental Engineering, Singer has devoted his 37-year
Water District career to increasing our knowledge of water chemistry and drinking water treat-
ment. His research activities have spanned a broad range of water quality issues,
9L0 from providing a fundamental understanding of the chemistry of ozone-allow-
ing for the development of chemical oxidation processes m a safe, reliable,and
NWRI cost-effective means to clean water-to understanding the formation and control
10500 Ellis Avenue of disinfection byproducts in drinking water.
P.O Box 20865
Fountain Valley,CA 92728 Fourth Microfiltration Conference Highlights Operations
Tel:(714)378.3278 and Innovations, Including Membrane Bioreactors
Fax:(714)378-3375
Regulations,real-world operations,and future innovations were just some of the
Jeff Mosher topics highlighted at Microfiltration IV,an international conference devoted to low-
Acting Executive Director pressure membrane(microfiltration and ultmfiltration)applications to water and
jmosher@nwri-usa.org wastewater treatment.
Tammy Russo
Senior Administrative Assistant Over 180 people from around the world attended Microfiltration IV,which was held
trusso@nwri-usa.org by N WRI in March 2006 and co-sponsored by M WH,Cranfield University,Zenon
Environmental Corporation, USFilter,Kruger Inc.,Corona Department of Water
Christina Futter and Power,and Orange County Water District.
Administrative Assistant
cfuller@nwri-usa.org A special feature of Microfiltration IV was its one-day short course on membrane
Gina Melin biereactors,a promising technology that uses microfiltration or ultrafiltration to
Communications Specialist enhance wastewater and reclaimed water treatment processes.
gmelin@nwri-usaorg
Member agencies can request complimentary copies of the abstracts,which include
CR-ROMs of the PowerPoint presentations,by emailing efullernn nwri-usa.ora.
June 2006
Orange County Water and Sanitation Districts
Honored for Reuse Project at Microfiltration IV
The Orange County Water District(OCWD)and Orange County Sanita-
tion District(OCSD)were honored asjoint recipients of the third NWRI
Award of Excellence for leadership on the Groundwater Replenishment
System,a world-class indirect potable reuse project.
NWRI established the Award of Excellence in 2000 to recognize projects
throughout the world that demonstrate leadership in the application of
technology to improve water supplies,protect public health,and enhance iFrom lea)Norm Eckenroae of OCSD,Phil Anthony
the value of water, or OCWD,eW Jeff Mosher or NWRI.
OCWD and OCSD received the award on March 21,2006,at NWRI's Microftltration IV Conference,which was
held at the Doubletree Hotel in Orange,California. OCWD Board Director Phil Anthony and OCSD Board
Director Norman Eckenrode accepted the award, in the form of two identical plaques,on behalf of their
districts.
NWRI to Fund Research Focused on
Youth Group Honors NWRI for Its Membrane Technology
Dedication to Protecting Water
and Supporting Young Scientists In the last three years,NWRI has focused considerable
interest on improving and expanding membrane technol-
ogy. The following are two new membrane-oriented
research projects that NWRI is now supporting:
Employment Service(YES)of the Harbor Area,
Inc.in California for its"dedication to our most Microporous Mixed Matrix Membranes for Water
valuable resources—our water and our youth." Purification,Phase I
A nonprofit,YES focuses on teaching youth, Worldwide,membrane technology is used to purify water
during the treatment process. Dr.Doug Lloyd(University
ages 14 to 22,the skills and attitudes needed to of Texas)and his team will strive to merge membrane tech-
attain,maintain,and grow in ajob. nology with nanotechnology—an emerging field—to im-
prove the water treatment process by developing a mem-
NWRI,who pas[away Executive
August Director,
was also brine that is more flexible,durable,and easier to use than
Linskyremembered at the event for his commitment and currently available membranes. The ultimate goal of their
innovative research is to develop a highly selective poly-
enthusiasm toward improving water resources mer—zeolite membrane that will remove salts and dissolved
and for implementing various educational pro- organics from water to produce an ultra-pure water product.
gram to support young people interested in water
science. Crossfow Sampler Fouling Index
m Particulate fouling of reverse osmosis(RO)and nanoftltra-
The award ceremony was held at the 33 Annual Lion membranes is a major concern during desalination,as
Roman Feast&Charity Auction in Costa Mesa, it can affect the cost and efficiency of this water treatment
California. process. The most commonly used indices for determining
NWRI co-founder,Mrs.loan Irvine Smith of the suitability of feedwater for RO treatment are the silt
density index and the modified fouling index,both of
San Juan Capistrano,California,was a past which are widely used,but are not considered to be repro-
recipient of the YES award,having been honored sentative of the particulate fouling potential of RO feedwa-
in 2004 for her dedication in supporting the ter in all cases. Under the direction of Dr.Samer Adham
Southern California community through Phil=- (M W H),this project aims to develop a method that can be
dopy' considered as a more representative index of particulate
RO fouling.
June 2006
June 21, 2006 iw
a
MEMORANDUM op
b
TO: Chair and Members of Board of Directors
Orange County Sanitation District
FROM: Jam24
eRuth
Interim General Manager, Orange County Sanitation District
SUBJECT: June Status Report
In addition to the major initiatives outlined in my status report to the Board, I have addressed
several additional issues impacting the Sanitation District.
1. Anonymous Letter Complaint
Investigation of an anonymous letter setting forth certain allegations against the Human
Resources (HR)department. The investigation has concluded. There were no findings
and the case is closed.
2. Completed Assessment of Information Technology(IT)
31 employees were interviewed by an outside consultant. An action plan to address
management and operational issues has been prepared along with accountabilities and
monitoring process to track progress.
3. Benefits Consultant
Personally secured outside consultant,John Bartel and Associates,to assist the General
Manager and FAHR Committee to explore benefits options designed to contain costs
and reduce long term financial liability.
4. Executive Positions
Assisted consultant, Barry Newton of Creative Management Solutions, Inc., in preparing
job description for the Assistant General Manager and General Manager positions.
5. Executive Search
Solicited proposals for executive search firm to conduct recruitment for Assistant General
Manager position. Interviewed two fines with extensive experience in the utility industry.
Am awaiting further direction from the Steering Committee before proceeding.
6. Independent Reviews
Met with Paul Jones, General Manager at Irvine Ranch Water District(IRWD)to discuss
their succession planning, goal setting and independent review process. Received
excellent guidelines which assisted our staff in preparing the RFPs for the District for
CIP, O&M and RAS Independent Reviews. Also reviewed their succession plan as well
as their performance appraisal system, and compared their data to our initiafives.
Board of Directors
Page 2
June 21, 2006
7. Management Training
Met with outside training consultant, Ray Burch, Louis Allen Worldwide, to explore
training options for the District's Management group based on my five month assessment
of our staff and what I believe our fundamental training needs are.
Based on the discussion with the consultant, I have chosen a program called"Profession
of Management",which is designed to develop the basic fundamentals of management
at the department head and administrative manager level. This training opportunity will
eventually be offered to supervisors as well.
This program will train approximately 30 managers and department heads at a cost of
less than $50,000. Presentations to HR, EMT and Managers group have been made
with strong support to proceed. Plan to launch training in August 2006.
8. Performance Reviews
Reviewed EMT individual performances for the past fiscal year 2005-06 and agreed to
specific goals for 2006-07 fiscal year.
9. Performance Evaluation System
Worked with consultant, Barry Newton, on the development and implementation of the
new Performance Evaluation System. Plan to be presented to the Steering Committee
on June 28.
10. Labor Management Committee
Met with the Labor Management Committee to outline the Board's concerns about
benefits cost control and reducing our long term financial liability.
11. Design Build Legislation
Met with representatives of I.B.E.W. and Plumbers Union regarding design build
legislation. Staff and I feel we made progress in presenting our view and addressing
union concerns. The union representatives have offered to have a follow-up meeting
and we are optimistic we can come to agreement to gain their support for AB 2850.
12. Joint Campus Study
Consultants are working with staff from both OCSD and OCW D to complete studies on
traffic, risk analysis and safety issues. All studies should be completed by July 31, 2006.
JDR:gg
KWepMdmin\1101RM JNMEMWes Report MOM21M JDR States mpon memo to Bam],tl
' AGENDA
BOARD OF DIRECTORS
ORANGE COUNTY SANITATION DISTRICT
DISTRICT'S ADMINISTRATIVE OFFICES
108" ELLIS AVENUE
FOUNTAIN VALLEY, CA 92708
REGULAR MEETING
June 28, 2006 — 7:00 P.M.
1. Invocation and Pledge of Allegiance
2. Roll Call
3. Consideration of motion to receive and file minute excerpts of member agencies relating
to appointment of Directors, if any.
4. Appointment of Chair pro tem, if necessary
5. Public Comments
6. The Chair, General Manager and General Counsel present verbal reports on
miscellaneous matters of general interest to the Directors. These reports are for
information only and require no action by the Directors.
a. Report of Chair; consideration of Resolutions or recommendations, presentations
and awards
b. Report of General Manager
C. Report of General Counsel
7. a. Nomination and election of Chair(effective July 1, 2006).
b. Nomination and election of Vice Chair (effective July 1, 2006).
8. If no corrections or amendments are made, the minutes for the regular meeting held on
May 24, 2006, will be deemed approved as mailed and be so ordered by the Chair.
9. Ratifying payment of claims of the District, by roll call vote, as follows:
ALL DISTRICTS 05/15/06 05/31/06
Totals $14,668,236.33 $32,520,553.31
06/28/06
Page 2
DIRECTORS: Pursuant to Government Code Section 84308, you are required to disclose
any campaign contribution greater than $250 received in the past twelve months from any
party to a contract involving OCSD. This requires that you identify the contributor by name.
Further, you may not participate in the decision making process to award a contract to such
party. For reference, you are directed to the Register of Warrants as to all current
contractors/vendors with OCSD. For the specks of Government Code Section 84308,
please see your Director's Handbook or call the office of General Counsel.
CONSENT CALENDAR
10. Consideration of motion to approve all agenda items appearing on the Consent Calendar
not specifically removed from same, as follows:
(a) Adopt Resolution No. OCSD 06-14, Establishing the Annual Appropriations Limit
for Fiscal Year 2006-07, for the District in accordance with the Provisions of
Division 9 of Title 1 of the California Government Code.
END OF CONSENT CALENDAR
11. Consideration of items deleted from Consent Calendar, if any.
COMMITTEE REPORTS AND RECOMMENDED ACTIONS
12. STEERING COMMITTEE
Consent Calendar
a. Order draft Steering Committee Minutes for the meeting held on May 24, 2006, to
be filed.
Non-Consent Calendar
b. Review and consideration of agenda items considered by the Steering
Committee re the June 28, 2006 meeting.
C. Consideration of items deleted from Steering Committee Consent Calendar, if
any
13. PLANNING, DESIGN AND CONSTRUCTION COMMITTEE (PDC)
PDC Consent Calendar
a. Order draft Planning, Design and Construction Committee Minutes for the regular
meeting held on May 24 2006, to be filed.
b. Ratify Change Order No. 27 to Primary Clarifiers 16-31 and Related Facilities,
Job No. P1-37,with Margate Construction, authorizing an addition of$314,921,
increasing the total contract amount to$72,676,520.
06/28/06
Page 3
C. Ratify Change Order No. 1 to Rehabilitation of the le Street Pump Station,
Contract No. 5-51, and Rehabilitation of the "A" Street Pump Station, Contract
No. 5-52, with Kiewit Pacific Company, authorizing an addition of$141,364 and
113 calendar days, increasing the total contract amount to$11,839,144.
d. Ratify Change Order No. 8 to Gisler-Redhill Trunk Improvements, Reach "A",
Contract No. 7-36; Orange Trunk Improvements, Contract No. 7-39;
Gisler-Redhill/North Trunk Improvements, Contract No. 7-41; and City of Tustin
Project Nos. 6106 and 6151, with ARB, Inc., authorizing an addition of$497,394
and nine calendar days, increasing the total contract amount to $20,891,680.
e. Ratify Change Order No. 7 to Trickling Filter Rehabilitation and New Clarifiers,
Job No. P1-76, with J.R. Filanc Construction Company, Inc., authorizing an
addition of$281,732, increasing the total contract amount to $34,991,510.
f. Ratify Change Order No. 13 to Effluent Pump Station Annex, Job No. J-77, with
J.F. Shea Construction, Inc., authorizing an additional amount of$65,276 and 50
calendar days, increasing the total contract amount to $44,597,334.
g. Item removed by staff.
h. Ratify Change Order No. 1 to Bushard Trunk Sewer Rehabilitation Pipe
Procurement, Job No. 1-24P, with Ameron International, authorizing an addition
of$184,948 and 15 calendar days, increasing the total contract amount to
$7,884,725.
i. Approve Amendment No. 2 to Professional Services Agreements with Berryman
& Henigar; Brinderson; HDR (CGvL) Engineers; Dudek &Associates, Inc.;
Jacobson Helgoth Consultants, Inc.; Lee& Ro, Inc.; RMS Engineering & Design,
Inc.; South Coast Systems, Inc.; SPEC Services, Inc.; and Washington Group
International for services related to Facilities Engineering projects, in amounts
not to exceed $200,000 for each agreement extension for a total amount not to
exceed $2,000,000.
Non-Consent Calendar
j. Consideration of items deleted from PDC Consent Calendar, if any.
14. FINANCE, ADMINISTRATION AND HUMAN RESOURCES COMMITTEE
FAHR Consent Calendar
a. Order draft Finance, Administration and Human Resources Committee Minutes
for the Benefits Workshop held on May 18, 2006 and the regular meeting held
June 14, 2006 to be filed.
b. Adopt Resolution No. 06-15, amending Resolution No. OCSD 98-33, amending
Human Resources Policies and Procedures Manual.
06128/06
Page 4 '
C. Renew the District's Boiler& Machinery Insurance Program for the period July 1, 2006 to
June 30, 2007, in an amount not to exceed $25,387.
d. Renew the District's Excess Workers' Compensation Insurance for the period
July 1, 2006 through June 30, 2007, at a rate not to exceed $0.00399 of actual
payroll.
e. Renew the District's All-Risk Property and Flood Insurance Program for the
period July 1, 2006 through June 30, 2007, in an amount not to exceed
$777,833.
f. Renew the District's Excess General Liability Insurance Program for the period
July 1, 2006 through June 30, 2007, in an amount not to exceed $391,233.
Non-Consent Calendar
g. Approve FY 2006/07 and 2007/08 Proposed Operating, Capital, Debt/COP
Service and Self-Insurance Budgets for FY 2006-07 and 2007-08, as follows:
2006-07 2007-08
Net Operations, Maintenance &Working Capital $129,054,210 $135,602,130
Worker's Compensation Self Insurance $526,200 $559,400
General Liability and Property Self-Insurance $1,766,100 $2,055,200
Net Capital Improvement Program $266,088,000 $338.818,000
Debt/COP Service $54,410,000 $65,462,000
Other Requirements $4,499,800 $2,645,300
Total $456,344,310 $545,142,030
(Directors: You have been previously provided a copy of the proposed budget with your
June committee packages. Please contact the Board Secretary should you require an
additional copy.)
h. Consideration of items deleted from FAHR Consent Calendar, if any.
15. LEGISLATIVE AFFAIRS COMMITTEE
Legislative Affairs Consent Calendar
a. Order Legislative Affairs Committee Minutes for the meeting held on June 13,
2006 to be filed.
Non-Consent Calendar
b. Consideration of items deleted from Legislative Affairs Consent Calendar, if any.
16. GWR SYSTEM STEERING COMMITTEE (GWRSSC)
GWRSSC Consent Calendar
a. Order Joint Groundwater Replenishment System Steering Committee Minutes for
the meeting held on May 8, 2006, to be filed.
O6128/06
Page 5
GWRSSC Non-Consent Calendar
C. Consideration of items deleted from GWRSSC Consent Calendar, if any.
NON-CONSENT CALENDAR
17. Receive and file Addendum No. 1 to the Final Subsequent Environmental Impact Report
for the Secondary Treatment and Plant Improvement Project for project modifications to
the 66kV Substation at Plant No. 1, Job No. P1-97, prepared by IPMC/CH2M Hill.
18. (1)Approve Plans and Specifications for Oil Well Excavation and Reabandonment,
Contract No. P2-90A, on file at the office of the Board Secretary;
(2) Approve Addenda Nos. 1, 2, and 3 to the plans and specifications;
(3) Receive and file bid tabulation and recommendation; and,
(4) Award a construction contract to J.F.Shea, Inc. for Contract No. P2-90A, Oil Well
Excavation and Reabandonment, for an amount not to exceed $250,853.
19. (1)Approve the Amended and Restated Job No. 1-2-4 Reimbursement Agreement with
the City of Huntington Beach, increasing the maximum allowable 24 hour period staffing
costs from $2,645 to$3,050 but keeping unchanged the maximum total staffing costs at
$238,000, in a form approved by General Counsel;
(2)Approve a Real Property License Agreement with the Fountain Valley School District
and the Huntington Beach Union High School District necessary for the location of a
temporary fire station for the Huntington Beach Fire Department during construction of
Bushard Trunk Sewer Rehabilitation, Job No. 1-2-4, in a form approved by General
Counsel; and,
(3) Approve an Indemnification Agreement with the Fountain Valley School District, the
Huntington Beach Union High School District, and the City of Huntington Beach
regarding the temporary fire station located on Fountain Valley School District real
property, in a form approved by General Counsel.
20. Award a contract to CCG Faster Systems, Inc. for purchase and implementation of a
Fleet Management Application, Specification No.CS-2005-215, in the amount of
$125,500 and a contingency amount of$45,000 for a total amount not to exceed
$170,500.
21. Adopt Resolution No. 06-16, Levying Assessment Installments In Lieu of the Payment of
Sewer System Annexation Fees and Capital Facilities Capacity Charges Incidental to
the Connection of Assessor's Parcel Nos. 502-353-05, 502-352-06, 502-353-01, 502-
361-04, 502-362-06, 502-362-05, 502-362-07, 502-362-09, 502-362-08, and 502-362-
11 to the Sewer System.
06/28/06
Page 6
22. Approve an agreement with the Irvine Community Development Company to retain and
pay engineering and environmental consultants for an amount not to exceed $200,000 to
provide engineering services relating to the SARI line shallow profile alternative study
and Mountain Park Sewer Line Connection, in a form approved by General Counsel.
23. Approve an agreement with the Santa Ana Regional Watershed Project Authority
(SAWPA) allowing the purchase of four(4) million gallons per day of Treatment and
Disposal Capacity rights at OCSD to be used for desalter brine discharge, for a total
amount of$17,136,120($4,284,030/MGD), in a form approved by General Counsel.
24. Closed Session
CLOSED SESSION: During the course of conducting the business set forth on this
agenda as a regular meeting of the Board, the Chair may convene the Board in
closed session to consider matters of pending real estate negotiations, pending or
potential litigation, or personnel matters, pursuant to Government Code Sections
54956.8, 54956.9, 54957 or 54957.6, as noted.
Reports relating to (a) purchase and sale of real property; (b) matters of pending or
potential litigation; (c) employment actions or negotiations with employee
representatives; or which are exempt from public disclosure under the California
Public Records Act, may be reviewed by the Board during a permitted closed
session and are not available for public inspection. At such time as the Board takes
final action on any of these subjects, the minutes will reflect all required disclosures
of information.
a. Convene in closed session, d necessary
1. Conference with Real Property Negotiators (Government Code Section
54956.8): One property:
Property: 7311 Doig Drive, Garden Grove, CA
Agency Negotiator: Terry B. Knapper, CB Richard Ellis
Negotiating Parties: Bernard Alfs, AHs Investment Group; Ryan Peterson, CB
Richard Ellis
Under Negotiation: Price, terms and conditions for the purchase and sale of
subject property
2. Conference with General Counsel—Anticipated Litigation
Possible initiation of litigation pursuant to subdivision (c) of Section
54956.9: (one case)
3. Conference with General Counsel— Existing Litigation
(Subdivision (a) of Section 54956.9)
Name of case: Travelers Insurance v. Orange County Sanitation District,
Orange County Superior Court Case No. 0BCC00086
b. Reconvene in regular session
C. Consideration of action, if any, on matters considered in closed session
06/28/06
Page 7
25. Matters which a Director may wish to place on a future agenda for action and
staff report.
26. Other business and communications or supplemental agenda items, if any
27. Future Meeting Date: The next Board of Directors regular meeting is scheduled for
July 19, 2006, at 7:00 p.m.
28. Adjournment
Agenda Posting: In accordance with the requirements of California Government Code Section 54954.2,this
agenda has been posted in the main lobby of the District's Administrative offices not less than 72 hours prior
to the meeting date and time above. All written materials relating to each agenda item are available for public
inspection in the office of the Board Secretary.
Items Not Posted: In the event any matter not listed on this agenda is proposed to be submitted to the Board
for discussion and/or action,it will be done in compliance with Section 54954.2(b)as an emergency item or
because there is a need to take immediate action,which need came to the attention of the Board subsequent
to the posting of agenda,or as set forth on a supplemental agenda posted in the manner as above, not less
then 72 hours prior to the meeting date.
Public Comments: Any member of the public may address the Board of Directors on specific agenda items or
matters of general interest. As determined by the Chair,speakers may be deferred until the specific item is
taken for discussion and remarks may be limited to three minutes.
Matters of interest addressed by a member of the public and not listed on this agenda cannot have action
taken by the Board of Directors except as authorized by Section 54954.2(b). If you wish to speak, please
complete a Speaker's Form(located at the table outside of the Board Room)and give it to the Board
Secretary.
Consent Calendar.All matters placed on the Consent Calendar are considered as not requiring discussion or
further explanation and unless any particular item is requested to be removed from the Consent Calendar by a
Director,staff member or member of the public in attendance,there will be no separate discussion of these
items. All items on the Consent Calendar will be enacted by one action approving all motions,and casting a
unanimous ballot for resolutions included on the consent calendar. All Items removed from the Consent
Calendar shall be considered in the regular order of business.
Members of the public who wish to remove an item from the Consent Calendar shall,upon recognition by the
Chair,state their name,address and designate by number the Item to be removed from the Consent
Calendar.
The Chair will determine if any items are to be deleted from the Consent Calendar.
Items Continued: Items may be continued from this meeting without further notice to a Committee or Board
meeting held within five(5)days of this meefing per Government Code Section 54954.2(b)(3).
Meeting Adjournment: This meeting may be adjourned to a later time and items of business from this agenda
may be considered at the later meeting by Order of Adjournment and Notice in accordance with Government
Code Section 54955(posted within 24 hours).
Accommodations for the Disabled: The Board of Directors Meeting Room is wheelchair accessible. If you
require any special disability related accommodations, please contact the Orange County Sanitation District
Board Secretary's office at(714)593-7130 at least 72 hours prior to the scheduled meeting. Requests must
soecifv the nature of the disability and the tvoe of accommodation requested.
06128/06
Page 8
.....................................................-................. ........... .......
NOTICE TO DIRECTORS: To place items on the agenda for the Regular Meeting of the Board of
Directors, items shall be submitted to the Board Secretary no later than the close of business 14 days
,preceding the Board meeting. The Board Secretary shall include on the agenda all items submitted by
'Directors, the General Manager and General Counsel and all formal communications.
.Interim General Manager James D. Ruth (714)593-7110 inith0ocrid win
.Board Secretary Penny Kyle (714)593-7130 Pkvle(a)ccsdLconn
.Director/Engineering David Ludwn (714)593-7300 dludwn(&ocsd.conn
;Director/Finance/Treasurer Lorenzo Tyner (714)593-7550 ItyneriWomd.corn
Director/Human Resources Use,Tomko (714)593-7145 ItomkoL'd_)ocsd.co
:Director/Information Technology Patrick Miles (714)593-7280 omilesO. sc.com
(Director/Operations
Maintenance Jim Herberg (714)593-7020 iherber06DocSd.com
Directorrrechnical Services Bob Ghirelli (714)593-7400 irghirellitaocrxi.com
:Director/Regional Assets&
Services Nick Arhontes (714)593-7210 narhontes(a)oc&d.com
General Counsel Brad Hoglin............................... (7141 bhogingDwss-law.com
KideptiagendaVEBoard Agendas%2006 Board Agendasr062806 agenda doc
tI
4
Orange County Sanitation District
MINUTES
BOARD MEETING
May 24, 2006
OJN� SAW
I Tgr�oN
9
o -a
�cr�N HE ENV`��0
ADMINISTRATIVE OFFICES
10844 ELLIS AVENUE
FOUNTAIN VALLEY, CALIFORNIA 92708-7018
Minutes for Board Meeting
Page 2
s 05/24/06
ROLL CALL
A regular meeting of the Board of Directors of the Orange County Sanitation District was held on
May 24, 2006 at 7:00 p.m., in the District's Administrative Offices. Following the Pledge of
Allegiance and invocation the roll was called and the Secretary reported a quorum present as
follows:
ACTIVE DIRECTORS ALTERNATE DIRECTORS
A Steve Anderson, Chair Steve Simonian
X James M. Ferryman, Vice Chair Arlene Schafer
X Charles Antos Vacant
X Don Bankhead Leland Wilson
X Carolyn Cavecche Vacant
X Alberta Christy Mike Garcia
X Larry Crandall John Collins
X Bill Dalton Mark Rosen
X Doug Davert Tony Kawashima
X Michael Duvall Jim Winder
X Norman Eckenrode Constance Underhill
X Richard Freschi Bob Fauteux
X Sukhee Kang Steven Choi
X Phil Luebben Lydia Sondhi
X Patsy Marshall Jim Dow
X Darryl Miller Douglas Reinhart
X Roy Moore John Beauman
X Joy Neugebauer Vivian Kirkpatrick-Pilger
X Ken Parker Catherine Driscoll
X Tod Ridgeway Don Webb
A David Shawver Brian Donahue
X Harry Sidhu Bob Hernandez
A Jim Silva Lou Correa
X Dave Sullivan Debbie Cook
X Mark Waldman Ralph Rodriguez
STAFF MEMBERS PRESENT: Jim Ruth, Interim General Manager; Penny Kyle, Board
Secretary; Nick Arhontes; Bret Colson; Jim Herberg; Dave Ludwin; Lorenzo Tyner; Jeff Reed;
Juanita Skillman
OTHERS PRESENT: Ken Smart, General Counsel; Don Hughes; Tom Dawes; Thom
Coughran; Charles Mitchell; Mark Miller; Tanveer Rao; Brian Keating
1
Minutes for Board Meeting
Page 3 r
05/24/06
PUBLIC COMMENTS
Brian Keating, representing Kimberly-Clark Corporation, expressed concerns on the late
delivery of results of the independent rate study and its impact on the rate review process prior
to rate adoption.
REPORT OF THE CHAIR
In the absence of Chair Anderson, Vice Chair Ferryman reviewed the committee meeting
schedule for the month of June, and noted a FAHR Committee Benefits Workshop would be
scheduled in mid-June.
REPORT OF THE GENERAL MANAGER
Jim Ruth, Interim General Manager, referred to the monthly status report included in the
Directors' meeting folders and briefly reviewed key issues.
REPORT OF THE GENERAL COUNSEL
General Counsel Ken Smart indicated a need to add an additional item needing immediate action,
and the need for said action came to the attention of the District subsequent to the posting of the
agenda. He reported that an additional Rem could be added pursuant to Government Code Section
54954.2(b) upon a two-thirds vote of the Directors.
MOVED, SECONDED AND DULY CARRIED: That the matter re Travelers Casualty and Surety
Company, at al. v. Orange County Sanitation District, Orange County Superior Court Case
No. O6CC00086, be added to the agenda; and,
MOVED, SECONDED AND DULY CARRIED: (1) Receive and file the summons and complaint
regarding Travelers Casualty and Surety Company, at al. v. Orange County Sanitation District,
Orange County Superior Court Case No. 06CC00086 in connection with Solids Storage and Truck
Loading Facility at Plant No. 2, Job No. P2-60; and
(2)Authorize General Counsel to appear and defend the interests of the Sanitation District.
NOMINATIONS FOR CHAIR OF THE BOARD OF DIRECTORS
This being the annual meeting fired by the Board at which nominations are to be made for the office
of Chair of the Orange County Sanitation District, the General Counsel declared the nominations
open.
Director Jim Ferryman was then nominated as a candidate for the office of Chair of the Orange
County Sanitation District. It was pointed out that nominations would remain open until the regular
June Board meeting. The Secretary reported that the election would be held on June 28, 2006 in
accordance with the Board's Rules of Procedure for the Conduct of Business of the District.
Nominations and elections of a vice Chair will also be held at the regular June meeting.
Minutes for Board Meeting
Page 4
05/24/06
APPROVAL OF MINUTES
MOVED, SECONDED AND DULY CARRIED: The Chair ordered that the minutes of the regular
meeting held April 26, 2006, be deemed approved.
RATIFICATION OF PAYMENT OF CLAIMS
MOVED, SECONDED AND DULY CARRIED: Ratify payment of claims set forth on exhibits "A"
and "B", attached hereto and made a part of these minutes.
ALL DISTRICTS 04/15/06 04/30/06
Totals $12,251,405.20 $13,214,189.32
Director Cavecche abstained from discussion and voting on Warrant Nos. 80228 and 80685.
Director Davert abstained from discussion and voting on Warrant Nos. 80174 and 80278,
Abstentions were pursuant to California Government Code Section 84308.
CONSENT CALENDAR
10. Consideration of motion to approve all agenda items appearing on the Consent Calendar
not specifically removed from same, as follows:
a. MOVED, SECONDED AND DULY CARRIED: (1) Receive and file summons and
complaint re Joel Lorenz vs. Orange County Sanitation District, Orange County
Superior Court Case No. 06CC05747, in connection with Standby Power and
Reliability Improvements, Job No. J-33-1A; and,
(2) Authorize General Counsel to appear and defend the interests of the
Sanitation District.
COMMITTEE REPORTS AND RECOMMENDED ACTIONS
12. STEERING COMMITTEE. A verbal report was presented by Vice Chair Ferryman re the
May 24, 2006 meeting.
Consent Calendar
a. MOVED, SECONDED AND DULY CARRIED: Order draft Steering Committee
Minutes for the meeting held on April 26, 2006, to be filed.
Non-Consent Calendar
No items were considered.
Minutes for Board Meeting
Page 5
05/24/06
13. OPERATIONS, MAINTENANCE AND TECHNICAL SERVICES COMMITTEE
OMTS Chair Cavecche announced there would not be a committee meeting in June.
The budget would be presented at the PDC and FAHR Committees and OMTS
Committee members were encouraged to attend either of those meetings.
OMTS Consent Calendar
a. MOVED, SECONDED AND DULY CARRIED: Order draft Operations,
Maintenance and Technical Services Committee Minutes for the meeting held on
May 3, 2006, to be filed.
b. MOVED, SECONDED AND DULY CARRIED: Adopt Resolution No. OCSD 06-
10, Support of Biosolids Recycling, and repealing Resolution No. OCSD 02-18.
C. MOVED, SECONDED AND DULY CARRIED: Receive and file the FOG Control
Study, Phase II -Final Report, dated March 2006, prepared by Environmental
Engineering and Contracting, Inc.
Non-Consent Calendar
No items were considered.
14. PLANNING, DESIGN AND CONSTRUCTION COMMITTEE
PDC Consent Calendar
a. MOVED, SECONDED AND DULY CARRIED: Order draft Planning, Design and
Construction Committee Minutes for the regular meeting held on May 4 2006, to
be filed, as corrected.
b. MOVED, SECONDED AND DULY CARRIED: Ratify Change Order No. 26 to
Primary Clarifiers 16-31 and Related Facilities, Job No. 131-37, with Margate
Construction, authorizing an addition of$272,749 and 142 calendar days,
increasing the total contract amount to$72,361,599.
C. MOVED, SECONDED AND DULY CARRIED: Ratify Change Order No. 2 to
Headworks Improvements at Plant No. 2, Job No. P2.66,with J.F. Shea
Construction, Inc., authorizing an addition of$356,647, increasing the total
contract amount to$192,724,912.
Director Davert abstained.
Minutes for Board Meeting
Page 6
' 05/24/06
d. MOVED, SECONDED AND DULY CARRIED: ((1)Approve a budget increase of
$1,251,353 for a total budget of$11,470,885 for Secondary Treatment Facilities
Process Upgrades at Plant No. 2, Job No. P247-3; and,
(2) Ratify Change Order No. 8 to Secondary Treatment Facilities Process
Upgrades at Plant No. 2, Job No. P2-47-3, with Morrow-Meadows Corporation,
authorizing an addition of$1,251,353 and a time extension of 17 calendar days,
increasing the total contract amount to$7,262,408, and extending the contract
completion to February 20, 2006.
Director Cavecche abstained.
e. MOVED, SECONDED AND DULY CARRIED: Approve a Professional Services
Agreement with Malcolm Pimie, Inc. providing for engineering services for the
Rocky Point Pump Station Replacement, Contract No. 5-50,for an amount not to
exceed $2,475,973.
f. MOVED, SECONDED AND DULY CARRIED: (1)Approve Amendment No. 1 to
the Professional Design Services Agreement with Malcolm Pirnie, Inc. for
preparation of construction documents and to provide construction support
services for the Coast Trunk Sewer Rehabilitation, Contract No. 11-26, providing
for additional engineering and construction support services at no additional cost
due to the savings realized during the preparation of the Preliminary Design
Report; and,
(2)Approve a reduction of$638,505 to the agreement reducing the total amount
to not exceed $1,580,825.
g. MOVED, SECONDED AND DULY CARRIED: Approve Amendment No. 2 to the
Professional Services Agreements with Geo-Matrix Consultants Inc., Kleinfelder
Inc., and Smith-Emery Laboratories, and Amendment No. 3 to the Professional
Services Agreements with Ninyo & Moore Geotechnical and Environmental
Sciences Consultants to provide for materials testing, inspection, and
geotechnical engineering services, Specification No. PSA-2003-175, for a one-
year period for an amount not to exceed $150,000 for each agreement(5600,000
total).
h. MOVED, SECONDED AND DULY CARRIED: Approve Amendment No. 2 to the
Professional Services Agreements with Forkert Engineering & Surveying, Inc.,
MDS Consulting, RBF Consulting, and Amendment No. 3 to the Professional
Services Agreement with Bush &Associates Inc. to provide for surveying
services for capital projects, Specification No. PSA-2003-176,for a one-year
period for an amount not to exceed $150,000 for each agreement ($600,000
total).
Director Davert abstained.
Minutes for Board Meeting
Page 7
05/24/06 r
i. MOVED, SECONDED AND DULY CARRIED: Approve Amendment No. 3 to the
Professional Services Agreement with Electrical Reliability Services, Inc. and
Amendment No. 2 to Professional Services Agreement with Hampton-Tedder
Electric Inc. to provide for electrical acceptance testing services, Specification
No. PSA-2003-177,for a one-year period for an amount not to exceed $150,000
for each agreement($300,000 total).
j. MOVED, SECONDED AND DULY CARRIED: Approve Amendment No. 7 to the
Professional Service Agreement with Train Consulting Engineers for additional
construction support services for Sunflower Interceptor Manhole Rehabilitation,
Contract No. 7-21, for an additional amount of$30,688, increasing the total
amount not to exceed $644,983.
k. MOVED, SECONDED AND DULY CARRIED: Approve funding for four new
Cooperative Projects with the Cities of Huntington Beach, Newport Beach,
Placentia, and Santa Ana, for a total amount not to exceed $1,515,297, as
recommended by the Cooperative Projects Grant Committee.
I. MOVED, SECONDED AND DULY CARRIED: Consider the following actions
relating to the purchase of certain real property interests in connection with
Replacement of Bitter Point Pump Station, Contract No. 5-49:
(1)Approve a Purchase and Sale Agreement with Horizontal Development LLC
regarding an approximate one-third acre parcel, in an unincorporated area that is
located near the Banning Ranch Pack Coast Highway entrance for an amount
not to exceed $160,000, in a form approved by General Counsel;
(2)Authorize the General Manager to execute all Deeds and other evidences of
title to the parcels of property, subject to the Purchase and Sale Agreement;
(3)Authorize the General Manager to execute any and all other instruments
related to the transaction with Caflrans for an amount not to exceed $40,000, in a
form approved by General Counsel;
(4)Approve an agreement with the City of Newport Beach to quitclaim the Bitter
Point Pump Station property in connection with Replacement of Bitter Point
Pump Station, Contract No. 549, for an amount not to exceed $90,000, in a form
approved by General Counsel; and,
(5)Authorize the General Manager to execute any other agreements necessary
to acquire said property for an amount not to exceed $20,000.
' Minutes for Board Meeting
Page 8
' 05/24/06
M. MOVED, SECONDED AND DULY CARRIED: Approve Amendment No. 6 to the
Professional Services Agreement with Integrated Program Management
Consultants, a joint venture of Parsons Infrastructure &Technology Group, Inc.,
and CH2M Hill, Inc., authorizing:
(1) Establish an amount not to exceed $14,999,656 for year five (Fiscal Year
2006-07) of the five-year contract; and,
(2) Increase the total amount of the five-year contract to an amount not to exceed
$60,092,039.
n. MOVED, SECONDED AND DULY CARRIED: Approve Change Order No. 1 to
Bushard Trunk Sewer Rehabilitation, Job No. 1-24A, with Mike Bubalo
Construction Company, Inc., authorizing a no cost value engineering change
proposal clause addition to the contract.
Non-Consent Calendar
No items were considered.
15. FINANCE, ADMINSTRATION AND HUMAN RESOURCES COMMITTEE
FAHR Consent Calendar
a. MOVED, SECONDED AND DULY CARRIED: Order draft Finance,
Administration and Human Resources Committee Minutes for the meetings held
on April 19, 2006, and May 10, 2006, to be filed.
b. MOVED, SECONDED AND DULY CARRIED: Receive and file report of General
Manager approved purchases in amounts exceeding $50.000 in accordance with
Board purchasing policies.
C. MOVED, SECONDED AND DULY CARRIED: Receive and file the FY 2005-06
Quarterly Financial Management Report for the period ended March 31, 2006.
d. MOVED, SECONDED AND DULY CARRIED: Approve extension of the
commercial lease with Nautical Enterprises, Inc., dba H & S Yacht Sales from the
original expiration date of May 31, 2006, to the extended expiration date of
December 31, 2007.
e. MOVED, SECONDED AND DULY CARRIED: Adopt Resolution No. OCSD 06-
11, Establishing a Policy Regarding Board of Directors' Business and Travel
Expense Reimbursement, and Meeting Attendance and Compensation; and
Repealing Resolution No. OCSD 06-09.
f. Item reconsidered after approval. See FAHR Non-Consent Calendar Item (i).
g. Item moved to FAHR Non-Consent Calendar Item (h).
Minutes for Board Meeting
Page 9
05/24/06 `
FAHR Non-Consent Calendar
h. Lorenzo Tyner, Director of Finance, reported on the results of the Independent
Rate Study. Based on the study results, it was recommended that the double-tax
credit be eliminated effective FY 2007-08.
MOVED, SECONDED AND DULY CARRIED: Receive and file Independent
Rate Study dated May 2006, prepared by Bartle Wells Associates.
i. This item was approved under the consent calendar. Directors requested the
item be reconsidered. Staff then provided a brief explanation on the cost savings
the District would realize for administering the existing Additional Retiree Benefit.
It was then:
MOVED, SECONDED AND DULY CARRIED: Approve the Second Amended
and Restated Memorandum of Understanding Agreement re: Additional Retiree
Benefit Account with the Orange County Employees Retirement System.
Directors Bankhead, Cavecche, Christy, Dalton, Duvall and Sidhu opposed.
16. LEGISLATIVE AFFAIRS COMMITTEE
Legislative Affairs Committee Consent Calendar
a. MOVED, SECONDED AND DULY CARRIED: Order Legislative Affairs Committee
Minutes for the meeting held on May 9, 2006 to be filed.
Legislative Affairs Committee Non-Consent Calendar
No items were considered.
17. GWR SYSTEM STEERING COMMITTEE (GWRSSC)
GWRSSC Consent Calendar
a. MOVED, SECONDED AND DULY CARRIED: Order Joint Groundwater
Replenishment System Steering Committee Minutes for the meeting held on April
10, 2006, to be filed.
b. MOVED, SECONDED AND DULY CARRIED: Approve Amendment No. 13 to the
Professional Services Agreement with Camp Dresser& McKee, Inc., providing
for the annual cost-of-Irving adjustment for 2006 and additional out of scope work
items for the Groundwater Replenishment System, Job No. J-36,for an
additional amount of$219,970, increasing the total amount not to exceed
$34,335,753 to be equally shared with the Orange County Water District.
GWRSSC Non-Consent Calendar
No items were considered.
' Minutes for Board Meeting
Page 10
' 05/24/06
NON-CONSENT CALENDAR
18. MOVED, SECONDED AND DULY CARRIED: Approve License for Access Purposes
Agreement with SWEPI LP for gathering geotechnical data for the Carbon Canyon
Sewer and Pump Station Abandonment, Contract No. 2-24-1, in a form approved by
General Counsel, at no cost to the Sanitation District.
19. MOVED, SECONDED AND DULY CARRIED: Approve a Three Party Out-of-Service
Area Sewer Service Agreement for the Aera Master Planned Community with Aera
Energy and Rowland Water District, in a form approved by General Counsel.
20. MOVED, SECONDED AND DULY CARRIED: (a)Adopt Resolution No. 06-12, Certifying
the Initial Study/Negative Declaration for the MacArthur Pump Station Rehabilitation
Project, Contract No. 7-49, prepared by CH2MHill; and,
(b)Approve the MacArthur Pump Station Rehabilitation Project, Contract No. 749.
21. MOVED, SECONDED AND DULY CARRIED: (a)Approve a progress payment to
Ameron International, Inc. for$75,169 in accordance with the contract terms for Bushard
Trunk Sewer Rehabilitation Pipe Procurement, Job No. 1-2413; and,
(b)Authorize the General Manager, or his designee, to approve all subsequent invoices
submitted by Ameron International, Inc. for payment under Job No. I-24P.
22. Adopt Ordinance No. OCSD-27, An Ordinance of the Board of Directors of Orange
County Sanitation District Establishing Specified Revenue Areas within the District, and
Repealing Ordinance No. OCSD-02:
a. OPEN MEETING: The Vice Chair declared the meeting opened at 7:54 p.m.
b. CLOSE MEETING: The Vice Chair declared the public meeting closed at
7:55 p.m.
d. 1. MOVED, SECONDED AND DULY CARRIED: Read Ordinance
No. OCSD-27 by title only and waive reading of said entire ordinance.
2. MOVED, SECONDED AND DULY CARRIED: Adopt Ordinance
No. OCSD-27,An Ordinance of the Board of Directors of Orange County
Sanitation District Establishing Specified Revenue Areas within the
District, and Repealing Ordinance No. OCSD-02.
23, Adopt Ordinance No. OCSD-29, An Ordinance of the Board of Directors of Orange
County Sanitation District Adopting Fees, Procedures, and Policies Concerning
Annexations of Territory to the District, and Repealing Ordinance No. OCSD-21:
a. OPEN MEETING: The Vice Chair declared the meeting opened at 7:59 p.m.
b. CLOSE MEETING: The Vice Chair declared the meeting closed at 8:00 p.m.
1
Minutes for Board Meeting
Page 11
05/24/06 '
C. Lorenzo Tyner, Director of Finance, stated that the purpose of the proposed
ordinance was to specify areas eligible for exclusion from annexation.
d. 1. MOVED, SECONDED AND DULY CARRIED: Read Ordinance
No. OCSD-29 by title only and waive reading of said entire ordinance.
2. MOVED, SECONDED AND DULY CARRIED: Adopt Ordinance
No. OCSD-29,An Ordinance of the Board of Directors of Orange County
Sanitation District Adopting Fees, Procedures, and Policies Concerning
Annexations of Territory to the District, and Repealing Ordinance
No. OCSD-21.
24. (a) Adopt Ordinance No. OCSD-30A, An Ordinance of the Board of Directors of
Orange County Sanitation District Establishing Sanitary Sewer Service Charges;
Establishing Capital Facilities Capacity Charges;Adopting Miscellaneous
Charges and Fees Relating to Industrial Charges, Source Control Permittees and
Wastehaulers, and Repealing Ordinance No. OCSD-26:
-----AND-----
(b) Adopt Ordinance No. OCSD-30B, An Ordinance of the Board of Directors of
Orange County Sanitation District Establishing Sanitary Sewer Service Charges;
Establishing Capital Facilities Capacity Charges;Adopting Miscellaneous
Charges and Fees Relating to Industrial Charges, Source Control Permittees and
Wastehaulers, and Repealing Ordinance No. OCSD-26.
Lorenzo Tyner, Director of Finance, provided a brief overview of the two
proposed ordinances. General Counsel Ken Smart advised that for either
ordinance to be adopted, it must be done by a two-thirds vote of the Board of
Directors.
1. OPEN MEETING: The Vice Chair declared the meeting opened at
8:08 P.M.
PUBLIC COMMENTS: Charles Mitchell and Brian Keating addressed the
Directors regarding the ordinances. Mr. Keating expressed appreciation
for the Board's consideration of the proposed new rate methodology, but
asked if the new method allows for tax relief for his permittee category.
He stated it would be appreciated if it would be adopted prior to FY 2007-
08.
2. CLOSE MEETING: The Vice Chair declared the meeting closed at
8:15 p.m.
3. Directors entered into brief discussion, with Lorenzo Tyner responding to
questions.
It was then moved and seconded to adopt Ordinance No. OCSD-308, An
Ordinance of the Board of Directors of Orange County Sanitation District
Establishing Sanitary Sewer Service Charges; Establishing Capital
Minutes for Board Meeting
Page 12
05/24/06
Facilities Capacity Charges; Adopting Miscellaneous Charges and Fees
Relating to Industrial Charges, Source Control Permittees and
Wastehaulers, and Repealing Ordinance No. OCSD-26.
MOVED, SECONDED AND DULY CARRIED: Read Ordinance
No. OCSD-30B by title only and waive reading of said entire ordinance.
Following a roll call vote, the motion to adopt Ordinance No. OCSD-30B
failed with a vote of 16 ayes and 5 nays.
Directors entered into brief discussion and a motion was made to
reconsider the adoption of Ordinance No. OCSD-30B.
MOVED, SECONDED AND DULY CARRIED: Adopt Ordinance
No. OCSD-30B, An Ordinance of the Board of Directors of Orange
County Sanitation District Establishing Sanitary Sewer Service Charges;
Establishing Capital Facilities Capacity Charges; Adopting Miscellaneous
Charges and Fees Relating to Industrial Charges, Source Control
Permittees and Wastehaulers, and Repealing Ordinance No. OCSO-26.
Ayes: Charles Antos; Carolyn Cavecche; Alberta Christy; Doug Davert; Mike
Duvall; Norm Eckenrode;Jim Ferryman; Rich Freschi; Sukee Kang; Phil
Luebben; Patsy Marshall; Darryl Miller; Roy Moore; Joy Neugebauer; Ken
Parker, Tod Ridgeway; Dave Sullivan; Mark Waldman
Nays: Don Bankhead; Larry Crandall; Bill Dalton; Harry Sidhu
Absent: Steve Anderson; Dave Shawver, Jim Silva
25. MOVED, SECONDED AND DULY CARRIED: Adopt Resolution No.OCSD 06-30B,
directing the County Tax Collector-Treasurer to include sanitary sewer service charges
on the 2006-07 property tax bill.
26. There was no closed session.
ADJOURNMENT: The Chair declared the meeting adjourned at 8:46 p.m.
Penny M. W
Secretary to the Board f Directors of
Orange County Sanitation District
H.WWNv\Pubhc ARaim\320%BSNAInut"\Q52006 DRAFr mint"".
Claims Paid From 04/01106 to 04116/06
Warren No. Vendor Amount Description
Accounts Payable-Warren
8OD64 Postmasler 6 868.00 Post Office Box Rental
80065 LA Chemical 610.27 Bleach
80066 A W Chesterton 143.06 Mechanical Paris&Supplies
80067 ADTECH 950.00 Electrical Pads&Supplies
80068 Angina Safety,Inc. 1,618.00 Safety Supplies
80069 Amlech Elevator Services 1,400.00 Monthly Elevator Maintenance at Pits.1&2
80070 Analysis,Inc. 108.00 Oil Test Kit&Analyses
80071 Anodyne,Inc. 53.00 Repair&Maintenance Service-Mast an Ocean Monitoring Vessel Nadi
80072 AppleOne Employment Service 503.73 Temporary Employment Services
80073 Archie Ivy,Inc. 2,410.00 Asphalt Patching at Plant 2
80074 Ashbrook Corporation 6.512.38 Sprayer Assembly-Upper Wash Box&Mechanical Pads&Supplies
80075 AWSI 33.00 Department of Transportation Program Management&Testing
M76 Baker Tanks 1.092.00 Tank Rentals
80077 Bentley Systems,Inc. 4,697.28 Software Maintenance Agreement Renewal
80078 Cal Glass,Inc. 556.42 Lab Equipment Service
80079 CALPLY 28,85 Ceiling Panels
80080 Camillo Engineers 8.299.39 Professional Services P2-60
80081 Casual Gourmet 151.17 Meeting Expenses
80082 CEPA Company 1.460.00 Maintenance Service-Semi-Annual Testing&Venificatlon of Fume Hoods
80083 Charles P.Crowley Co. 3.782.03 Electrical Pads,Supplies&Tools
80084 Ctngtlar Wireless Airtime 820.63 NBreless Services
80085 CMAA 75.00 Meeting Registration-Division 760
80086 Coast Fire Equipment 598.02 Fire Extinguishers
80087 Cole Primer Iasuardi Co. 343.32 Tubing
80088 Consumers Pipe&Supply Co. 864AI Plumbing Paris&Supplies
80089 Cooper Cameron Corporation 125.37 Engine Supplies
BOND Cooper Energy Services 418.64 Valves
80091 Corporate Express 633.04 Office Supplies
80092 Corporate Image Maintenance,Inc 168.00 Custodial Services Spec,No.91
80093 County Wholesale Electric Co. 411.36 Electrical Paris&Supplies
80094 CS-AMSCO 3,175.01 Mechanical Paris&Supplies
80095 Culligan of Orange County 1.25 MainL Agreement-Can Gen Water Scherer System
80096 CWEA Membership 100.00 Membership(Calif.Water Environment Assoc.)
BOB97 Damon Company 2.218.63 Pump,Motor&Mechanical Pads
80098 Del Mar Analytical 1.262.00 Analysis of Biosolitls
80099 Dosed Pumps&Paris.Inc. 145.00 Pump Pads&Supplies
WIN Domnlck Hunter,Inc. 356.60 Lab Pans&Supplies
80101 DS Waters 6,418.10 Reconciliation User Fee Rehmd Program
80102 Dunn Edwards Corporation 64.71 Paint Supplies
80103 Enchanter,Inc 2.900.00 Ocean Monitoring&Oulfall Inspection&Maintenance
80104 Environmental Compliance Inspection Sam. 1.040.00 Professional Services-Grease Interceptor Inspections-FOG
80105 Everyure Water Solutions,Inc. 3.511.OD Mechanical Paris&Supplies
80106 Ewing Irrigation Industrial 442.85 Landscape Irrigation Pads&Supplies
80107 FEDEX Corporation 232.42 Freight Services
80108 Filtedine Corporalion 61.19 Fillers
80109 First American Real Estate Solutions 450.00 On-Line Orange County Property Infotmalion
80110 Fisher Scientific Company,L.L.C. 4.062.02 Lab Pads&Supplies
H WeprOn1E%CEL oa12H SI RE1C1elmn Pab 98pOieei-DTCtalmc Pad Repel-OC-15.06 EXHIBIT
fli Page 1 of 8 a=ek,
Claims Paid Firm 04/01106 to 04115106
Warrant No. Vendor Amount Description
$0111 Franklin Covey 216.98 Office Supplies
80112 Frost Company 22,858.61 Repair&Main.Service-Hydraulic LlneMydmalic Power UrotiCake Transfer Pump at Pit.2
80113 Frys Electronics 204.67 Computer-Supplies
80114 Gamati Callahan Company 3.339.18 Chemicals
80115 GT Hell Company 221.59 Mechanical Pans&Supplies
80116 Gieditll-Mitchell,Inc 10,182.38 Mechanical Pans&Supplies
80117 GOkmnwest Window Service 620.00 Groundskeeping Services
80118 Grainger,Inc. 2.370.66 Electrical Pads&Supplies
80119 Hampton Tedder Technical Services 17,584.00 Professional Services-Electrical Acceptance Testing
80120 Hasce Oil Co..Inc. 173.31 Grease
80121 Hewlett Packard Company 8,776.82 Computer HardwarelSo8v2re-H.P.Server
80122 Hi Standard Automotive 211.10 Automotive Pads&Supplies
80123 Hill Brothers 10.818.19 Chemicals-Odor&Corrosion Control-Newport Trunkline
80124 Howard Ridley Company 2,907.38 Repair&Maintenance Services-Digester R Discharge Lines
80125 City of Huntington Beach 13,300.89 Water Use
80126 Industrial Dis rmaton Group 202.68 Mechanical Pads&Supplies
80127 Innerfine Engineering 4.717.50 Sewedine Video Inspections&Cleaning in Area 7
80128 Inorganic Ventures,Ina 15227 Lab Pads&Supplies
80129 Invensys Systems,Inc. 1.053.59 Electrical Pads&Supplies
80130 Jamison Engineering Contractors,Inc. 7,957.62 Repairs&Maint.Services-Replace Electrical Feed Line at 14th St.Pump Sta.
80131 Jays Catering 1,136.85 Meeting Expenses
80132 Johnstone Supply 356.77 Electrical Pads&Supplies
80133 JPL Compressor Service,Ina 9.079.60 Gas Compressor Pads&Supplies
80134 Kforce Professional Staffing 3,795.W Temporary Employment Services
W135 Kings County Tax Collector 11,840.11 Property Tans
80136 Microsemi Corp. 10,030.57 Reconciliation User Fee Refund Program
80137 Mandic Moms 115.00 Towing Services
80138 Manpower Professional 3,726.00 Temporary Employment services
80139 Materiel and Contract Services 4,960.00 Temporary Employment Services
W140 Maximus,Inc. 5,000.00 Professional Services-Update Cost Allocation Plan
80141 Mayer,Brawn,Rowe&Maw,L.LP. 14.978.41 Professional Services-Strategic Planning&Advocacy
80142 McMaster Can Supply Co. 766.81 Mechanical Parts&Supplies
W143 MCR Technologies,Inc. 23BAD Mechanical Pads&Supplies
801" Midway Mfg.&Machining Co. 5.776.48 Mechanical Pads,Supplies&Repairs
80145 Mine Safety Appliances Co. 1,76&02 Gas Monitors
80M Motion Industries,Inc. 476.49 Mechanical Pads&Supplies
80147 MWH Americas,Inc. 24,400,49 Professional Services P2-74
80148 National Filter Media Corporation 16.653.91 Filter Press Bells
W149 National Fire Protection Association 136.58 Publication
80150 National Plant Services,Ina 16,184.12 Vacuum Track Services
80151 Newark Electronics 191.58 Electrical Pads&Supplies
80152 Ninyo 8 Moore Corporate Accounting 210.00 Professional Services P1-76
80153 The Now Companies 335.72 Mail Delivery Service
80154 Orange County Water District 548.01 Meeting Registration-Division 110
$0155 OCS Reprographics 875.58 Printing Service-MO 1126100
80156 Office Depot Business Services Div. 4,171.66 Office Supplies
80167 Omega Indusbial Supply,Ix 1.133.16 Janitorial Supplies
80158 Onesource Distributors,Ira 636.85 Electrical Pads&Supplies
H Wei 1ESCEL41P22MPSHAAe C01ma Paid RepwM6fiTCINms Ped Reppn-a0.1 SOG E%HIBII A
ann10c Page 2 of scu2oce
Claims Paid From 041111106 W 04/15/06
Warrant No. Vendor Amount Description
80159 Orange County Hose Company 12.49 Hydraulic Hose Supplies&Parts
80160 Orange Fluid System Technologies,Inc. 1.059.43 Mechanical Pans&Supplies
80161 ORCO Constructed Supply 102.56 Marking Paint
80162 Oxygen Service Company 3,817.24 Lab Pads&Supplies
80163 PCG Industries 3,300.00 Pump Repairs
80164 Peak Technologies 362.66 Lab Pans&Supplies
80165 PerkinElmer Las 14,808.00 Lab Instrument Maintenance Agreement
80165 Piclometry Intemalienal Corp. 20,000.00 Image library Software Licerea/Raining
80167 Pixelpushers,Inc. 7,101.25 Temporary Employment Services
80168 Pmxair Distribution,Inc. 35.00 Demurrage
80169 Primary Source Office Furnishings,Inc. 9.382.87 Reconfiguration of Purchasing Div.Central Office Work Stations
80170 Printerguy 5,643.76 Printer Maintenance
80171 PROPIPE 8,242.M Sewer ine Cleaning-City of Tustin&Unincorporated County Property
80172 Pump Engineering 1,399.40 Pump Pans&Supplies
80173 Quinn Power System Assoc. 2.108.64 Maintenance Agreement-Ocean Monitoring Vessel Nerissa
80174 REF Consulting 3.833.37 Engineering Services 241&7-38
80175 Ribc Camera Centers,Inc. 122.77 Photo Processing&Single-Use Cameras
80176 Rockwell Engineering&Equipment Co. 8,676.25 Pump&Pump Paris&Supplies
80177 RPM Electric Motors 1,580.93 Pump Repairs
80178 Sancon Engineering,Inc. 3,000.00 Construction-Manhole Rehabilitation Program
80179 Rule 222 Filings 150.00 Meeting Registration-Division 660
80180 Schiff Associates 2.606.00 Engineering Services J-106&Time Failure Analysis
80181 Schwing America,Inc. 1,041.37 Pump Supplies
80182 Scientific Refrigeration 712.00 Relocalmn of Biological Safety Hood to Warehouse
80183 Sea Bird Electronics,Inc. 1.154.00 Lab Instrument Maintenance&Celibralion Services
80184 Sigma Aldrich,Inc. 214.21 Lab Pads&Supplies
801&5 SKC West.Inc. 267.60 Lab Pans&Supplies
80186 Smandan Supply Company 426.22 Valves
80187 Spec Services,Inc. 16,405.12 Engineering Services J-33-1
80188 Summit Steel 1,877.66 Metal
80189 Sunset Ford 414.57 Vehicle Pans&Service
80190 Sunset Industrial Pans 119.65 Mechanical Pads&Supplies
80191 TCH Associates.Inc. 7,777.32 Lab Pads&Supplies
80192 Terhno Coafvgs 11,800.00 Painting Services-Mach.Shop&PVC Piping at Norm If South Scrubber Complex
80193 Terminix International 165.00 Pest Control
$0194 Tetra Tech,Inc. 15.679.88 Professional Services 7-37
80195 The Walking Man,Inc. 400.00 Public Notice Printing&Mailing Services-7-21
80196 Thompson Industrial Supply,Inc. 604.54 Mechanical Pans&Supplies
W197 Time Warner Communication 55.82 Cable Services
B01% TMV Systems Engineering,Inc. 6.093.75 Software Maintenance
80199 Todd Painting,Ina 10,484.00 Painting Services
80200 Townsend Public Affairs 5.000.00 Legislative&Executive Advocate for Gran(Funding
80201 Trade Service Corporation 2,324.17 Electrical Paris&Supplies
80202 Traffic Control Service,Inc. 170.00 Traffic Safety Equipment Rental
80203 Tran Consulting Engineers 10,387.91 Engineering Services 7-21
80204 TRANSCAT 574.32 Instrument Supplies
80205 Tremco Incorporated 8,000.00 Repairs&Maintenance Services-Bioassay Trailer Drain&Roof Repairs
SO206 Truck&Auto Supply Inc. 289.72 Automotive Supplies
NlaepafnWXCEL.4WMMPSHM�ms Paul Re;,o B Claims Pak]Repoe-(WI 5-06 EXHIBITA
fimarMC Page 3 of 5 maws
Claims Paid From 04101/06 to 04N5/06
Warrant No. Vander Amount Description
80207 UC Riverside 7.802.09 Professional Services-Strategic Process Studies
8020a Underground Service Aled of So.Calif 1,943.10 Membership-Underground Utility ldentificetion/Notificetion Service
80209 The Unisource Corporation 9,101.59 Ofcs Supplies
80210 United Pacific Services,Inc 5.886.00 Landscape Maintenance 8 Roadway Clean-Up
80211 United Parcel Service 267.26 Parcel Services
80212 Vapex,Inc. 4.084.00 Immanent Parts 9 Supplies
90213 Varian,Inc. 5,568.96 Lab Instruments Maintenance Agreement
80214 Vedxpn Calitpmia 734.13 Telephone Services
00215 Village Nurseries 602.79 Landscaping Supplies
80216 Vortex Corp. 618.10 Gate Repairs-Exit at Engineering Trailers
80217 VWR Scientific Products 2,568.68 Lab Parts&Supplies
$0218 Wally Machinery And Tool Supply,Inc. 82.48 Mechanical Pads,Supplies 8 Tools
80219 Waste Markets 14.308,18 Maim.Agree.-Grit B Screenings Removal B Digester Mail Removal
80220 Water Environment Federation 69.75 Publication
80221 WeleReuse Association 275.00 Meeting Registration-Division 631
80222 Walem Corporation 540.00 Meeting Registration-Division 520
80223 WEF 614.00 Membership-Water Environment Federation
60224 Xyon Business Solutions,Inc. 9,800.00 Temporary Employment Services
80225 York International 1.288.53 Repair&Maintenance Service-Communication Equipment
80226 California Bank 8 Trust 1,909.00 Construction J-33.1,Retention
80227 Fleming Environmental,Inc. 4.254.75 Construction FE0549
80228 Morrow Meadows Cory. 6,896.00 Censlruclion P247-3
60229 Orange Community Bank 4,169.00 Construction P2-02,Retention
80230 Steve Anderson 3,039.74 Meeling/Training Expense Reimbursement
80231 Layne T.Baroldl 447.90 MeetingfTraining Expense Reimbursement
$0232 Shabblr S.Bernd 288.81 MeetingRraining Expense Reimbursement
60233 Rebecca A.Brooks 150.00 Meeting/Traanng Expense Reimbursement
80234 Paler Chefs 326.23 Meethrg/Trehdng Expense Reimbursement
80235 Yeom Choi 110.00 MeetingRraining Expense Reimbursement
80238 Kelly J.Christensen 734.60 MeetingRraining Expense Reimbursement
80237 Thomas D.Dodderer 123.42 MeetingRraining Expense Reimbursement
80238 Jamas Ferryman 776.22 Meeling/Treining Expense Reimbursement
80239 Victoria L.Francis 116.14 Meeting/Training Expense Reimbursement
80240 Robert P.Ghirelll 1.430.69 MeetingRraining Expense Reimbursement
$0241 Jesska Jones 385.00 Meeting/Training Expense Reimbursement
60242 Ludolph T.Lordmer 1.600.72 MeetingRraining Expense Reimbursement
80243 Efren G.Lucerw 1.221.48 MeelingtTraining Expense Reimbursement
80244 David Manning 613.58 MeetingRraining Expense Reimbursement
80245 Michael D.Masterson 301.30 Meeting?raining Expense Reimbursement
80246 Michael D.Moore 331.00 Meeting/Training Expense Reimbursement
80247 Andrew H.Neu 348.61 Meeling/Traimng Expense Reimbursemenl
80248 Curt V.Shelp 570.27 MeetingRraining Expense Reimbursement
50249 Chris A.Stacklin 31.00 Meeting/Training Expense Reimbursement
80250 Martin Talebi 898.69 MeetingRraining Expense Reimbursement
80251 Made A.Tomko 206.80 Meeling/Training Expense Reimbursement
80252 Jars H.Thin 889.02 MeelingRaining Expense Reimbursement
80253 Gary J.Tulasosopo-Kemper 418.11 MeetingRraining Expense Reimbursement
80254 Simon L.Watson 401.09 MeelingtTraining Expense Reimbursement
H WPPPAn'EXCEL dl.MMPSWRECIrlrns PPld ReP^m060TClaima Peld R,.ft-W 15-06 EXHIBIIA �1
f r]10/Ic Page 4 of 8 fi,som
Claims Paid From 04101106 to 04/15106
Warren No. Vendor Amount Description
BD255 Ken H.Wong 454.84 Meeting/Tralning Expense Relmbumemenl
80256 Employee Activity Committee 487.00 Serum Award Expense
80257 SCAOMD 1,450.68 Rule 301 End User Registration of Certified Equipment
80258 Bask Chemical Solutions,L.L.C. 32,417.81 Sodium Blsulfite&Sodium Hydroxide
80259 Brown&Cardwell 511,459.41 Professional Services P2-90
80260 City of Santa Ana 76,000.00 Cooperelive Projects Reimbursement Program
80261 ESRI,Inc. 25,114.73 Software Melnt.-Archdo.ArcGIS,ArcEdhar,ArcViaw,ArcSDE,ArcPad&Arcli
80262 GHD,L.L.C. 89,818.00 Professional Services-Asset Management Program
80263 HDR Engineering,Inc. 74,978.98 Professional Services PI-82&Sewer Comedian PermiVDals Development
80264 Kemiron Companies,Inc. 178,400.12 panic Chloride
80265 Lewis&Zimmerman Associates,Inc. 29,635.84 Engineering Services P2-90
$0266 Malcolm Pimie,Inc. 240,534.59 Professional Services J-79
80267 Mylhics,Inc. 87,647.20 Software-Perpetual License for Oracle Date Base-Enterprise Edition,Maid.&Support
80268 Occidental Energy Marketing,Inc. 77,489.10 Natural Gas for CenGenrCoGen
a0269 Olsson Construction,Inc. 37,518.00 Construction P2-82
80270 Orange County Water District 58,003.28 GAP Water Use
80271 Pioneer Adiences,Inc. 202,302.93 Sodium Hypomlonte
80272 Polydyne.Inc. 68,778.38 Calionic Polymer MO 3.11-92
80273 Southern California Edison 02,143.86 Power
80274 Synagro West,Inc. 200,738.63 Residuals Removal MO 3-29-95
80275 Tula RanWMagan Farms 229,831.11 Residuals Removal MO 3.29-95
W276 YalelChase Materials Handling,Inc. 90,143.81 (19)Electric Carta
80277 Dees&Some Constructions,Inc. 83,416.74 Construction J-88
80278 J F Shea Ci mlruction,Inc. 2,479,37128 Construction J-77&P2.66
80279 J R Fiknc Construction 1,700,10720 Construction Pt-62
80280 Kiewit Pacific Co. 555,277.40 Construction 5.51 &5.52
80281 Margate Construction,Inc. 521,187.00 Conalruclion PI-37
80282 Shasta Electric,L.P. 61,506.00 Conslnclion SP-94
80283 Southern Connecting Company 36,256.00 Construction J-33-1A
80284 Wells Fargo Bank Mac C7300-012 62.808.80 Construclion 5.52,Relealion
80285 Pairs Clark-Alkim Water 33,120.00 Anaerobic Baffled Reactor(ABR)Testing
80288 Geomatdz Consu]tanls,Inc. 27,574.64 Soils,Concrete&Other Materials Testing 7.36&741
80287 Inlene Empire Utllilies Agency 27,525.D7 Professional Services-Pradc Basin Regional Organics Management Project
80288 MWH Amences,Inc. 25,649.48 Probsaloml Services J-101
B0289 Plonder Americas,Inc. 82,545.13 Sodium Hypochkrite
BD290 So Cal Gas Company 40,085.68 Nature]Gas
50291 US Peroxide,L.L.C. 56.448.59 Odor&Corrosion Control Treatment for Coll.Syr:Hydrogen Peroxide&Ferrous Chloride
80292 Abalix Environmental Corp. 1,115.18 Hardware
80293 American Express 24.634.00 Purchasing Card Program,Misc.Supplies&Services
80294 Aquatic Bioassay and Consulting Labs,Inc. 1,130.00 Whole Effluent Toxicity Testing
80295 Arm Wireless 1,026.77 Paghtg Service-Aldime,Service&Equipment
80296 American Telephone&Telegraph Corp. 29.72 Telephone Service
80297 Awards&Trophies Company 18.92 Awards&Trophies
80298 Basic Chemical Solutions,L.L.C. 8,245.81 Sodium Blsulfite&Sodium Hydroxide
80299 BC Wra Rope&Rigging 32.33 Meehanlo it Pens,Supplies&Service
80300 Bell Pipe&Supply Co. 34.79 Mechanics]Parts&Supplies
80301 Black&Veatch Corporation 199.78 Engineering Services J-71-0
60302 Blue Marlin Group 388.98 Generator Oil&Fuel-Oman Monitoring Vessel Nenssa
H Aeddn1EXCELAIN201APSHAREUaimf Pa10 RepvnC50 Cklme Paid Repon-W-15A1 EXHIBITA
nn4lanc Page 5 of 8 5`12008
Claims Paid From 04/01/06 to 04HSI06
Warrant No. Vendor Amount Description
80303 Bush&Assodates,Inc. 1,006.00 Professional Services FE05-20
803M Court Trustee 90.89 Wage Garnishment
80305 CASA 1,200.00 Meeting Registration-Division 110
$0306 Casual Gou met 84.10 Meeting Expenses
80307 CELSOC 178.52 Publication
80308 Clu8lndustries 2,963.13 Lab Parts&Supplies
80309 Coast Fire Equipment 1,327.48 Fire Extinguishers
80310 Coast Rubber Stamp,Mfg. 328.22 Once Supplies
80311 Columbia Analytical Services,Inc 655.00 Analysis of Wastevter,Industrial Wastewater&Biosolids
80312 Compressor Components of California 4,480.00 Repairs&Maintenance-LSVB Plot fuel Check Valves
80313 Conerch Engineering 5.236.35 Pump Supplies
80314 County of Orange 150.00 Wage Gamishment
80315 County of Orange Auditor Controller 116.50 Enao.cl m ml Permit 7-36
80316 County of Orange Aud0er Controller 70.00 Encr0acharm nl Permit 741
80317 D.R.MCNaty&Associates 1,11I&M Training Registration
W318 Davits Tree Service 7,400.W Tree Maim.Service
80319 Del Mer Analyliral 68.00 Aneysk of Bmsolids
80320 Demanded of Child Support Services 300.00 Wage Gamishment
W321 Diamond Interims,Inn 990.00 Installation of Mini Blinds at Purchasing Building
80322 DLT Solutions,Inc. 9,1MA1 Map 2006 Nelwark Licenses&Web Support
80323 Ecology Control Industries 2,800.00 HauNous Waste Disposal
80324 Electra-Bond,Inc. 1,578.54 Repair&Maintenance Services-Epoxy Coating
80325 Employee Benefits Specialists,Inc. 10,342.30 Reimbursed Prepaid Employee Medical&Dependent Care
80326 ENS Resources,Inc 10.000.00 Professional Services-Legislative Advocate
80327 Equa-Chler 3,565.37 Hydrochloric Acid
80328 Equipco Saks&Service 5.183.00 Inshument Pads It Supplies
80329 Court Order 445.00 Wage Garnishment
W330 FEDEK Corporation 115.75 Freight Services
W331 Ferguson Enterprises.Inc. 347.19 Valves
80332 Forked Engineering&Surveying,Inc. 925.65 Surveying Services-P2-66
80333 Franchke Tax Board 50.00 Wage Garnishment
80334 Fry's Electronics 674.31 Computer Supplies
80335 Donald Lumber Company 74.61 LumberMaidware
80336 Gunned Callahan Company 2.152.20 Chemicals
80337 Greybar Electric Company 600.24 Electrical Repair&Maintenance Services
80338 Great Weaken Sanitary Supplies 20.90 Jamlorial Supplies
80339 Green Parrot 108.29 Meeting Supplies
80340 Hasce Oil Co.,Inc. 167.64 Grease
NMI NevAeB Packard!Company 4,016.43 (1)HP DL360 Server
80342 Hit Brothers 20,542.53 Chemicals-Odor&Corrosion Control-Newport Tmnkline
80343 Industrial Distribution Group MAII Mechanical Pads&Supplies
80344 Inatikde for International Research 2,093.00 Training Registration
80345 Internal Revenue Service 125.00 Wage Gamishment
80346 Intl.Union of Oper.Eng.AFL CIO Local Sot 4,552.30 Dues Deduction
80347 Irvina Ranch Water District SAS Water Use
803U K-Micro,Inc dba CogliMo Services 8,064.00 ACAD Govt.Client MulliStarege Server Maintenance Agreement Renewal
80349 LA Orange Area MSA 185.00 Training Registation
80350 Court Order 150.00 Wage Garnishment
N bepMnlE%CELEIeV3QNPSN EiL ins Paid Repwna6e Wims Paid Report-04.150a EXHIBITA
nnrzlom Page 6 of Worites �`
Halms Paid From 04101106 to 04/15106
Warrant No. Vendor Amount Description
80351 MCMssler-Cam 926.74 Mechanical Pars 8 Supplies
80352 MCMssler Can Supply Co. 471.48 Mechanical Paris B Supplies
W353 Measurement Variables,Inc. 1,466.72 Electrical Parts 8 Supplies
80354 Court Oder 225.00 Wage Garnishment
80355 National Bond 8 Trust 2,495.20 U.S.Savings Bonds Payroll Deductions
80356 National Plant Services,Inc. 1,035.0 Vacuum Truck Services
80357 Nexlel Communications 1.461.84 Cellular Phones B Air Time
80358 OCS Reprographics 449.05 Printing Service,-MO W6100
80359 OCEA WAS Dues Deduction
80360 Orange County Pest Control,Inc. 139.00 Pest Control
80361 Orange County Sheriff 85.00 Wage Garnishment
90362 Paul Cockrell Photography 752.50 Photographic Services-Trickling Filters B Secondary Clarifiers
80363 Peace Officers Council of CA 1,512.00 Dues Deducllon,Supervisors 8 Professionals
80364 Polydyne,Inc. 2.308.78 Cationic Polymer MO 3-11-92
80365 Pod Supply 55,36 Monitoring Vessel Pads 8 Supplies-Nerissa
80386 Professional Plaslics 1,792.40 Mechanical Paris 8 Supplies
80367 Restek Corp. 74727 Tubing
80368 RM Automation do RM Controls 287.79 Instrument Supplies
80369 Rockhursl College Continuing Education 1.197.00 Training Registration
80370 Sancon Engineering,Inc. 1.160.O0 Repair&Maint.Services-Devaering Manhole at Baker/Glaler Air Jumper
80371 SBC 1.592.11 Telephone Services
$0372 SBC Long Distance 1.10 Long Distance Telephone Services
60373 SSC/MCI 788.85 Telephone Services
80374 Sch ff Assodales 2.800.111) Engineering Services-Evaluation of Digester Gas Piping at Pit.2
80375 Scott Specialty Gases,Inc. 1 T1.2D Lab Parts,Supplies 8 Demurrage
80378 Secretary of State 20.00 Filing Fee-Statement of Inforn alionvDomestic Nonprofit Corporation
80377 SETAC 60.00 Meeting Registration-Division 631
80370 Sevier Equipment Company of Americs 196.11 Hose Guides
8037D Siemens Building Technologies 9,998.00 Soffware/Hardware Upgrade
80380 Smllh Pipe 8 Supply,Inc. 127.68 Landscape Irrigalion Supplies
80381 Court Oder 721.50 Wage Garnishment
80382 Southern California Edison 9,665.54 Power
80353 Super Chem Corporation 2,790.84 Chemicals
803M Thompson Industrial Supply,Ina 1,492.36 Mechanical Paris 8 Supplies
80385 T-Mobile 110.76 While.Air Time
80386 Tony's Lock 8 Safe Service 8 Sales 123.47 Locks 8 Keys
80387 Truck 8 Auto Supply,Inc. 145.60 Automotive Supplies
80388 The Unlsource Corporation 604.26 Office Supplies
80389 United Parcel Service 58.41 Parcel Services
80390 United Way 180.00 Employee Contributions
80391 University of Arizona 10.000.00 Membership-Industry/University Cooperative Research Ctr,(UANSF Why.Quality Clr.)
BD392 Veri2on California 444.27 Telephone Services
80393 Village Nurseries 18.85 Landscaping Supplies
80394 Waste Markets Corp. 14.073.99 Maint.Agree.-Gril 8 Screenings Removal 8 Digester Mal'I Removal
BD395 Count Order 597.50 Wage Garnishment
80396 Zimmerman yacht Mainlenance 118.00 Repair 8 Maintenance Service-Ocean Monitoring Vessel Nerissa
80397 Jeffrey Brown 99.45 Meeiing/Traming Expense Reimbursement
80398 Marcus 0.Dubois 245.08 Meeling/Trainirg Expense Reimbursemenl
Rwepnsm6xCELdmi22MPsrwREwleim3Pod Repo0 "neuime Paid Repon 04-15L6 EXHIBITA
nnI21. Page 7 of 8 502005
Claims Paid From 04/01/06 to 04/15/06
Warrant No. Vendor Amount Description
80399 Michele Farmer 56.43 Meeling/fraining Expense Reimbursement
BD400 Darius GhaB 570.00 Meeling/Tralning Expense Restabursemenl
80401 Wanda R.Hagerty 15.38 MeminglTraining Expense Reimbursement
80402 Dale O.Henderson 197.74 MeeOnglTraining Experise Reimbursement
BD403 Michele R.Hetherington 599.70 Meeling/Traii ing Expense Reimbursement
8D404 Ludophy T.Lonimer 352.70 Maeting/Training Expense Reimbursement
80405 Fred J.O'Bnen 7.11 MeetingRraining Expense Reimbursement
80406 Pamela A.Koester 1,013.94 Employee Computer Loan Program
80407 Maps Smith and Dell 3,000.OD Employee Computer Loan Program
80405 Orange County Sanitslion Dieeper 14,378.09 Worker's Camp.Reimb.
80409 Tag Lvl Environmental Services,Inc 4,554.00 Environmental Services
80410 Robyn A.Wdco r 862.09 Employee Computer Loan Program
Total Accounts Payable-Warrants $ 9.124.112.97
Payroll Dicburaements
33085 - W182 Employee Paychecks $ 13BA50.91 Bivreekty Payroll 04/1212006
33183 - 33199 Employee Paychecks 10.361.55 Reissues,Reims,IDEA,OCERS Reknit.,Comes.8 Term.Payroll D4/10 to 12/13108
124526 .125080 Direct Deposit Statements 1 07130409
3,040.90 Bivreekly Payroll04/12/06
Total Payroll Disbursements $$ 1 2 53.36
Win Transfer Payments
OCSD Payroll Taxes 8 Contributions $ 730.809.15 Brvdiekly Payroll 04/12/06
US Bank 410,528.03 Series 2006 A 8 B Refunding COPS March Interest Payment
US Bank 627.953.25 Series 2000 A&B Rebinding CON March Interest Payment
JP Morgan Chase Bank 138 348— 05.438.44 Series 1993 Refunding COPS March Interest Payment
Total Win Transfer Payment $$ 7
Total Claims Paid 04/01106-04/15106 $ 1 2251,40520
H dep11M\ENCELddiQ211WPSHAREiClelma Paid RepmN6DTC4xdn Pvd Repel-70.15-06 EKHIBI7 A
5nQ101k Page 8 of 8 54y20115
Claims Paid From 04116106 to 04100106
Warrant No. Vendor Amount Description
Accounts Payable-Wurents
80411 Air Products 8 Chemicals S 76,230.44 O 8 M Agreement Oxy.Gen.Sys.MO 8-849
80412 Black B Vea"Corporation 108.495.91 Englncadng Servicas J-778J-79-1
80413 Blue Grant of California 362,288.21 Metlkel Insurance Premium
80414 Camp Dresser 8 vicars,Inc. 111.356.03 Engineering Service J-714
80415 Delta Dental 57.287.36 Dental Insurance Plan
80416 Hev4etl Packard Company 77.303.50 (2)Servers(50)PCs and Miscellaneous Hardwaral5o8ware
50417 Wiser Foundation Health Plan 69,804.88 Medical Insurance Premium
80418 Kemlron Companies,Inc. 110.19075 Ferric Chlarlde
80419 Kenny/Jenks Consultants,Inc. 65,637.23 Professional Services 748
80420 Malcolm Firma,Inc. 310,120.10 Professional Services 1.10
80421 Mid West Associates 28,688.15 Pump Paris 8 Supplies
80422 Occidental Energy Marketing.Inc. 75.912.54 Natural Gee for CenGenlCOGen
80423 Orange County Water District 6,942,940.56 Joint GWRS Probed J36
BM24 Pioneer Americas,Inc. 158,581.21 Sodium Hypochbrlb
BN25 Polydyne,Inc. 39.065.36 Caliendo Polymer MO 3.11-92
80426 RBF Cansulling 41,508.1E Engineering Services 747
BU27 Science Applications Inlemallonal 26,167.31 Ocean Monitoring MO 64-94
80428 Solenoids Corp. 26,186.75 Sallwane
80429 Tula RancNMegan Farms 226.043.96 Residuals Removal M03-29.95
80430 US Peroxide.L.L.C. 90.907.65 Odor 8 Corrosion Control Treatment for Cali.Sys.:Hydration Peroxide 8 Ferrous Chloride
80431 ARB,Inc. 292,476.60 ComBuclted 7-36 8 741
80432 Klewlt Pacific Co. 473,355.00 Conelruclion 5.5185.52
80433 Samoan Engineering,Inc. 200,425.50 Constructed 7.21
80434 Union Bank of California 32,497.40 Conalrucltan 741 8 738,Retention
80435 Wells Fargo Bank Mac C7300S72 52,598.00 Construction 5.5785.52,Retention
80436 A W Chesterton 5,256.36 Mechanical Pals 5 Supplies
80437 ABB Automation,Inc. 393.30 Repair 6 Maintenance Service-Flow Meters
BM38 Accurale Envbmmental Services,Inc. 7.800.00 Professional Services-Relative Accuracy Teat Audll far(3)CGS Engines
SM39 AcglStandard 7272 Lab Pea.B Supplies
SM40 ACE Ergonomic 375.00 Professional Services-Ergonomic Workstation Evaluations
80441 ACGIH WarMMde 130.75 Publication
BN42 Acaplan Technical Company 142.59 Electrical Pads 8 Supplies
BD443 A9IMM Technologies,Inc. 361.79 Lab Paris 6 Supplies
BM44 AIHCE American lndusidel Hygiene 485.00 Training Registration
80445 Aligas Be",Inc. 5,00e.84 Safety Supplies
80446 Algas West 8.68 Demurrage
80447 Americed Airbus; 3.947.65 Travel Services
60448 Amedcen Concrete Institute 7,900.00 On-Site Seminar-Div.760-"TroublesM1opMg Concrete Construction"
80449 American Water Works Assec.IWaler Quality 129.50 Publication
80450 Ancon Marine 2.722.50 Hasardoua Material Disposal Services
80451 Anixter,Inc. 6,893.52 CCTV Camera Replacem dols
80452 Applied Industrial Technology 11.34 Mechanical Parts B Supplies
80453 Aboard.Doctor 116.21 Human Resources Aquarium Service
80454 Aquatic Bloassay and Cansulling Labs,Inc. 785.00 Melia Effluent Toxicity Testing
80455 Athena instrument 1,552.50 Instrument Repairs B Calibration Service
80456 Ashbrook Corporation 740.60 Mechanical Paris B Supplies-Wnklepress
80457 ASIS International 745.00 Training Registration
80458 Aurora Pictures,Inc. 495.00 Safety Vldeas-Defensive Driving
80459 Awards 8 Trophies Company 48.88 Awards 8 Trophies
80460 Bask Chemical Solutions,L.L.C. 21,631.50 Sodium BIsu1Ne 8 Sodium Hydroxide
80461 SC Wre Rape B Rigging 7.307.99 Mechanical Pads 6 Supplies
80462 Mothers"Vilek,Inc. 1,004.32 Lab Pads 8 Supplies
80453 Boyle Engineering Corporation 914.50 Professional Services 1.24
H Wacer E%CEL ditlRaNPSHLRFCIeIme PaIE RepoMMA71Clumr Paid needs-ai E%HIBdr 8
.rvawc Page 1 of 8 5r11com
Claims Paid From 0411SMS to 04I30106
Warrant No. Vendor Amount Description
80464 Bucknam&Associates.Inc. 1.422.50 Professional Services-Pavement Management
B0465 Bush&Associates,Inc. 6.404.00 Professional Services 741&7.36
80466 Cardiac Science Corporation 1.485.79 Safety Supplies
80467 CDWGovemmenl,Inc. 1.888.40 SoBware
80468 Chads,Inc. 59.97 Disposable Pens for Vokogawa Chad Recorder
80469 CMAA 340.00 Meeting RegislmBon-Division 760
80470 Cotentin Technologies 4,829A0 SaBwale License Upgrade
W71 Consumers Pipe&Supply Co. 2,531.88 Plumbing Pads&Supplies
W72 Cooper Energy Services 625.02 Valves
80473 Ccopmaie Express 634.40 Office Supplies
80474 Cormch Engineering 7,707.69 Pump
80475 Council on Edu.in Management 850.00 Training Registration
80476 County of Orange Auditor Controller 399.50 Encroachment Permit 1-10
80477 CRC Press,Inc. 506.23 Publication
n
M78 CWEA Annual Conference 400.00 Training Registration(California Water Emdminment Association)
80479 CWEA Membership 300.00 Membership(Cold.Water Envlronment Assoc.)
80480 Dell 216.13 Service Maintenance Agreement
80481 Dapper Tire Co. 753.06 Truck Tires
aoa82 Cards Tree Service 2,225.00 Tyre Maint.Sanow
80483 ODB Engineering,Inc. 625.01 Professional Services-Grant Management
80494 Del Mar Analytical 610.00 Analysis of Blosands
80485 Den Computer 298.66 Den Omm Ices
80486 DKG Construction 8.526.80 Constructor,FE04415
Iti Employers Group 200.00 Training Registration
80488 Employee Benefils Specialists.Inc. 1,025.70 Reimbursed Prepald Employee Medical&Dependent Care
W489 Employers Group 2.462.50 OnSBe Training: Customer Semce;Telephone Skills;Dealing wMinargel&Communicating w/Diplomary
W490 Enchanter.Inc. 5.600.00 Ocean Monitoring&DuOan Inspection&Maintenance
80491 Engineered Plastic Systems,L.L.C. 395.05 Bench&Hardware
80492 Environmental&Occupational Risk M9ml. 175.00 Professional Services-Indoor Air Quality ImMiligagon
80493 Environmental Resource Associates 1.416.58 Lab Parts&Supplies
80494 Ewing lmgaWn Industrial 589.10 Landscape lmgahon Pads&Supplies
80495 Express Lens Lab 2.001.08 Safety Glasses
$0496 Pinion ExWsion,Inc. 1.894.76 Mechanical Pens&Supplies
U497 Fisher Scientific Company,L.L.C. 9.389.99 Lab Palls B Supplies
$0498 Forestry Suppliers 501.35 Lab Pads&Supplies
80499 Ferked Engineering&Surveying.Inc. 673.20 Surveying Services-Various Capital Projects 5.51
80500 Fountain Valley Rancho Hand Wash 162.0) Vehicle Washing&Waxing Services
80501 Franklin Covey 171.14 Office Supplies
50502 Frys Electronics 193.94 Computer Supplies
80503 Definite Castle 1,096.00 Instrument Maintenance Service-Aulocleves
80504 Gotoenwest Wnddw Service 3,885.0) GrouMskeeping Services
80505 Grainger,Inc. 4.728.13 Pads Storage Cabinet
W506 Great Western Sanitary Supplies 744.64 Janitorial Supplies
80507 The Grimsled Company 706.8O Instmmenl Paris&Supplies
80508 Gdmsted,Inc. 2,659.38 Instrument Pans&Supplies
80509 Guarantee Records Management 294.69 OBSKe Records Storage
80510 Haaker Equipment Company 4.476.09 Miac.Vehicle,P.M.Repairs&Service
80511 Hall cho Ponton Industries 1.388.19 Lab Paris&Supplies
80512 Hill Brothers 6.654.90 Chemicals-Odor&Corrosion Control-Newport Trunkline
M13 Hills Boat Service,Inc. 605.55 Oil&Filler Change-Ocean Monitoring Vessel Neriess
80514 Home Depot 2.475.14 Misc.Repair&Maintenance Material
80515 Hub Auto Supply, 1,870.85 Vehicle Pads&Supplies
BO515 IBM Corporation 4,505.00 Computer Ne emking Services
80517 Ideas 2,678.07 Lab Pads&Supplies
XknonfnE%CEL drour.PSRMMIxma Pard Rqu Aclanne I'm RepM-041 E%HIBQB �I
nmfmo Page 2 of B alludes
Clelma Paid From 04/16106 to 0413om8
Warrant No. Vander Amount Description
80518 Industrial Distribution Group 2,232.50 Mechanical Pans,Supplies,Locks&Tools
80519 Industrial Metal Supply 496.16 Metet
80520 Industrial Threaded Products,Inc. 721.97 Inventory Fasteners
80521 Innovative Nei Systems 1.370.00 Lab Pads&Supplies
80522 Jaya Catering 1,137.30 Meeting Expenses
80523 JPL Compressor Service,Inc. 8.495.97 Gas Compressor Pads&Supplies
80524 Klelneloer,Inc. 15.080.15 Sale,Concrete&Other Materials Tearing
U525 LeMobe Company 925.32 Lab Paris&Supplies
80526 Lehigh Valet'Safety Supply Co.,Ina 201.48 Mobile Safety Shoe Service
80627 LINJER IIJ0WJ% Proeealonal Service-DART MO 9.22.99
W528 Lerman Education Sarvlcea 319.00 Training Registration
80528 Luccl's Gourmet Foods,Inc. 200.00 Meeting Expense
80530 LyMe Ordway Company,Inc. 302.50 Repair&Maintenance Services-Pit.2 Copy Center Electric Paper Cutter
80531 McMaster-Cart 70.38 Tools&Misc.Suppose
80532 Maintenance Technology Corp. 635.33 Mechanical Pans&Supplies
80533 Managed Health Network 1,285.16 Employees Assurance Program
80534 Maney's Boiler Inc. 575.00 Repair&Maintenance Services-Boller Explosion at Pa.2
80535 MassMulual Michel Financial Group 145.41 Executive DeeMI11y Plan Premium
80538 Matt Chlor,Inc. 4.545.88 Valves
80537 Maureen Kamm Associates $80.00 Meeting Registration-DWishon 320
80538 MBC Applied Environmental Sciences 1,498.00 Ocean Monitoring-Taxonomical Identification of Invertebrate Organisms
80539 McMaster Can Supply Co. 3,783.58 Mechanical Pare&Supplies
80540 M0B Consulting 4.900.80 Professional Services 1-24
80541 Measurement Control Systems,Inc. 2,043.82 Instrument Repair&Calibration Services
80542 Medlin Controls Co. 12971 Instrument Pads&Supplies
80643 Midway Mfg.8 Machining Co. 7,542.51 Mechanical Pens,Supplies&Repents
80544 Mine Safety Appliance Company 50576 Sensor Kits
60545 Mission Abusers Supples 378.96 Jambi Supplies
80546 Named Instrument Co. 75.71 Instrument Parts&Supplies
80547 National Fire Protection Association 29.91 Safety Supplies
80548 National Pent Services,Inc. 3,160.00 Vacuum Truck Servlcae
80548 National Seminars Group 798.00 Training Registration
80560 Neal Supply Co. 1.567.05 Plumbing Supplies
60551 Neeve Technology 178.00 Software License&Support
80552 Ninyo&Moore Carbonate Accounting 1.136.00 Sells&Other Mandate Testing P1.37&Pt-82
M53 The Norco Companies 339.96 Mial Delivery Service
W554 NRG Thermal Services,L.L.C. 1,481.01 Mechanical Pans&Supplies
80555 DOB Reprographics 306.76 Printing Service-MO 1Qfim0
W556 Office Depot Business Services Division 1,288.37 OMcs Supplies
M57 01 Analytical 902.95 Lob Pans&Supplies
80558 Olympus NOT,Inc. 4.305.70 Instrument Pert&Supplies
80559 Onespuma Distributors,Inc. 2.450.13 Electrical Pane&Supplies
W580 Operation Technology,Int. 3.036.32 Computer Hardware/Spttwme Upgrade&Support
60561 Orange Flue System Technologies,Inc. 5.315.16 Plumbing Pads&Supplies
80562 ORE Offshore 277.90 Batteries&71nc Anodes
80563 Oxygen Service Company 137.50 Specialty Gases
80564 Pacific Mechanical Supply 1,474.01 Plumbing Supplies
80565 PCG Industries 7,150.00 Repair&Malnunmce Services-Pump Shaft
80568 Pl.Hewn Company,Ina 46,81 Eeotreel Party&Supplies
60567 Primary Source Office Furnishings,Inc. 371.74 Office Furniture&Mac.Equipment
80568 Process Software Cm. 2,807.38 Software License-VAX Workgroup
60569 Prudential Overall Supply 6.241.87 Uniforms&Related Articles
80570 0 Alt Ce18.DN.Pump Engineering 5,974.22 Aiq 08&Separator Filters and Oil Coulomb,
80571 Outnn Shepherd Machinery 1,278.22 Fuel,Oil&Alt Fillers for Diesel Generators
H xk MA%E%CFl_dWaMPSHARP.CInmr Pad Rwnv640TC Wmr Palo Reno,-OV]OLe EXHIBIT 8
rm+sxc Page 3 of 8 &"v
Claim Paid From 04/15106 to 04130106
Warrant No. Vendor Amount Deacdptlon
80572 R L Abbe"8 Associates 3.000.00 Kam County 810501Ms Consulting Services
80573 Lawrence Ragan Communications.Inc. 895.00 Training Registration
80574 Rainbow Disposal Co. 2,973.12 Trash Removal
80575 Resm Cory. 2.600.38 Lob Parts 8 Supplies
80576 RMS Engineering 8 Design,Inc. 1,600.00 Engineemg Sam Ices P2418-3
80577 Rockwall Engineering 8 Equipment Co. 4.388.08 16'Onpenar,Pads 8 Supplies
$0578 Royale Cleaner 12.00 Dry Cleaning Services
80579 RS Hughes Co.,Inc. 152.99 Paint Supplies
80580 Slate of California 125.00 Mendership
80581 Salem Engineering,Inc. 3,475.OD Construction-Manhole Rehabilitation Project 8 Repairs 8 Main.Services
80582 Schwing America,Inc. 8.096.88 Pump Pens 6 Supplies
80583 Sae Bid Electronics,Inc. 716.00 Lab lnstmment Maintenance B Calibration Services
80584 Security Land 8 Right or Way Service 2.017.50 Professional Services 549
805M SETAC 60.00 Membership or Meeting Registration-Division 631
80586 Shamrock Supply Co.,Inc. 1,740.27 Simple Green Cha ned/Degreaser
80587 Shureluck Sales B Englneering 276.10 Mechanical Pans B Supplies
80588 Siemens do Jensen hormonal Co. 1,346.33 Instrument Repairs 8 Maintenance Services
80589 Skater,Inc. 435.63 Lab Pan B Instrument Repair 8 Maintenance Services
60590 Source Graphics 8.855.97 3V Color Ploltar,Installation a Training
80591 Sparkletls 2,170.54 Ddnking Water/Cooler Rentals
80592 Spading Instruments,Inc. 250.00 Repair&Maintenance Services-Final Effluent Flow Meter
a0593 St.Croix Sensory,Inc. 915.00 Olractometry,Testing Services
80594 State Board of Equallzation 90.68 Un den d Storage Tank Permit Fee
W595 The Slaywell Company 217.79 Selely Supplies
W596 Summit Steal 1AI9.00 Merl
80597 Sunset Industrial Pens 418.26 Mechanical Pans 8 Supplies
80598 Technical Service Group,Inc. 1.361.60 SCADA System VAX Service Agreement
80599 Teledyne RD Instumants,Inc. 518.70 Battery Packs
$0600 Temtinix International 126.00 Past Control
80601 The Standard Insurance Company 2,82D.23 Executive Disablliy Plan Premium
80602 Thermo Electron North America 343.25 Lab Pans 8 Supplies
80603 Thompson Industrial Supply.Inc. 9.72124 Mechanical Pads 8 Supplies
110604 TMV Systems Engineering.Inc. 3.031.25 Sollware Maintenance
80605 Tragc Control Smice.Inc. 571.08 Tragic Safety Supplies
80606 Ton Consulting Engineers 16.395.66 Engineering Services 7-21
80607 Tremor Incororled 2.450.00 Repair 8 Maintenance Services-Control Center Roof Leak at Roof Drain
80608 Truck 8 Auto Supply.Inc. 215.51 Automotive Pans 8 Supplies
80609 US Filler Corp. 1,337.66 Service Agreement-DI Water Systems at Plants 1 5 2
8061D UC Regents 125.00 Lab Paris 8 Supplies
80811 Ulmo Scientific 273.28 Lab Pans 8 Supplies
80612 United Pacific Services,Inc. 21,077.51 Landscape Maintenance 8 Tree Trimming Services
80613 United Pare]Service 1.505.77 Pineal Services
U614 University of Wscensin Madison 1,195A0 Training Registration
80615 Unmack Corporation 7,830.00 Profnsix.nal Services-Safety Training Audil Pmjecl
8061E US Composting Council 600.00 Membership
80617 US Equipment Co..Inc. 771.51 Fibers
80618 Varies.Inc. 3,197.50 Instrument Pads B Supplies
80619 Verizon Wheless 172.96 Warless Services
80620 Vision Service Plan CA 9,767.80 Vsion Service Premium
80621 Voiles Corp. 3.418.78 Repair 8 Maintenance Services-Ellis Ave.Exit Gate 8 Warehouse South Roll-Up Door
80822 VAR Scientific Products 1,721.03 Lob Pans B Supplies
50623 The Wackenhut Corporation 17,689.15 Secondly Guards
60624 Water Environment Federation 182.00 Membership
80825 Waxle Sanitary Supply 414.75 Janitorial Supplies
X WepmMFJICEL01N3PAPSHARSC4xmr Paid Reere084 LIMB Pad Raam'01J04a EXHIBIT
r Irv. Page 4 of 8 Y111ox
Claims Paid From 04/16106 to 04/30106
Warrant No. Vendor Amount Description
80626 WEF 728.00 Membership-Water Environment Federation
80627 West Lit.Supply Company,Inc. 372.32 Electrical Paris&Supplies
80628 Western Slates Controls 821.78 Electrical Pads It Supplies
80629 Weston Spokes,Inc. 14,055.00 Oulside Laboratory Services-Core Ocean Moniloring Program
80630 With Gas Equipment Co. 7.755.85 Gas Meter w10EX Transmitter
80631 World AI Work 1.970.00 Training Registration
80632 Wumbus Corporation 560.79 Safety Videos
BC633 Xerox Corporation 658.00 Full Service Maintenance-Xerox Sylrergix and Media Overages
80634 YalelChase Materials Handling,Inc. 781.40 Electric Carps&Parts
80635 Yokogawa Corp.of America 533.58 Instrument Supplies
80636 1-800-Conkrence(R) 178.48 Telephone Conference Calls
80637 Layne T.Baroldi 522.70 Meatirg/Training Expense Reimbursement
U638 Thomas M.Slanda 833.04 Meeting/Training Expense Reimbursement
W639 Frank Chavez 581.09 Minding/Traming Expense Reimbursement
80640 Yeom Choi 125.00 Meetirg/Traming Expense Reimbursement
80641 Kelly J.Christensen 358.10 Meeting/Traming Expense Reimbursement
80642 Margin A.Dix 20.00 MeetirgRraming Expense Reimbursement
80643 Thomas D.Dodderer 761.30 Meetingrtrelning Expense Reimbursement
80644 James M.Elo 18.00 Meetirg/fraining Expense Reimbursement
80645 Kimberly A.Erickson 74.23 Meeting/Tralning Expense Reimbursement
80646 Mark A.Esquer 620.46 Meetirg/lralning Expense Reimbursement
80647 W.Doug Hauser 1,082.72 Meatingffralning Expense Reimbursement
80648 David R.Hein 470.90 MeetingRralnirg Expense Reimbursement
80649 Ingrid G.Hellebrand 119.04 Meating/fralning Expense Reimbursement
SH50 Michelle R.Hetherington 495.00 Meetirgaralning Expense Reimbursement
80651 Penny M.Kyle 277.75 Meeting/Training Expense Reimbursement
80652 Michael D.Larkin 771.21 Meefirlglfraining Expense Reimbursement
80653 Linda Losurdo W.48 Maetingtrraming Expense Reimbursement
80654 William S.Malik 195.00 MeetingRraming Expense Reimbursement
80655 James W.Matte 450.00 Meetigaruning Expense Reimbursement
80656 Darryl G.Mi0er 1,168.34 Meetllgnmining Expense Reimbursement
60657 Sharon Nelius 97.57 MeeticeRraming Expense Reimbursement
80658 Pierre Wong 295.00 MBetIng/rraining Expense Reimbursement
80659 Paula A.Zeller 1,193.35 Meeting/Traming Expense Reimbursement
80860 Volded Check - -
80861 Orange County Sanitation District 1,205.18 Petry Cash Relmb.
80662 CH2M Hill 52,326.56 Engineering Services-Needs Assessment for Environmental Compliance Program
80663 HDR Engineering,Inc. 44,527.07 Prolossicinal Services P142
80664 Kemimn Companies,Inc. 52,520.97 Ferric Chloride
80665 Pioneer Americas,Ind. 159,260.45 Sodium Hypochlarile
80666 Southern Celikmia Edison 470.037.52 Power
80667 Spec Services,Inc. 41,532.40 Engineering Services 7-32-1
80668 US Metro Group.Inc. 30,322.50 Janitorial&Floor Maintenance at Plants 1&2
80669 US Peroxide,L.L.C. 189,692.12 Odor&Corrosion Control Treatment lor Coll.Sys.:Hydrogen Peroxide&Ferrous Chloride
80670 Accounting Options,Inc. 5.278.00 Temporary Employment Services
80671 Aware Seky,Inc. 969.43 Safely Supplies
80672 AppleOne Employment Bervim 4,644.43 Temporary Employment Services
60673 Aquatic Bioassay and Consulting Labs,Inc. 1.130.00 Whole Eguenl ToAcry Tesling
80674 Ashbrook Corporation 814.18 Woldepress Paris&Supplies
80675 AT&T Universal Biller 1,541.19 Telephone Service
80676 American Telephone&Telegraph Corp. 25.84 Telephone Service
80677 AMA 228.00 Membership(American Water Works Association)
80678 baker Tanks 1,662.00 Tank Rentals
80679 Basic Chemical Solutions,L.L.C. 5262.54 Sodium BisulMe
H, eVAAEXCEL.EYV3GNPSHARMIMMe PN0 RepprtN607d3wn Pail Report-O*RMN5 EXHIBIT
fronded Page 5 of 8 yr 1rzods
Clelma Palo From 04116106 W 0,UHaV6
Warren No. Vendor Amount Description
80680 Basler Electric 4,129AB Electrical Parts&Supplies
W681 Beltec Industries.am. 753.17 Fresh Air Purifier
60682 BtoMeneux Vilek,Inc. 655.78 Lab Parts&SUPPIKM
80663 Court Trustee 90.89 Wage Garnishment
80684 California Auto Collision 740.97 Minor Pool Vehicle Body Repairs
80685 Cmtlsck Fuel Systems,Inc 17.396.81 Fuel Card Program-Diisbicl Vehicles&Monitoring Vessel
BURNS Cingular Wireless Aware 5,335.60 Wireless Services
80687 Compressor Components of California 11.830.00 Repair&Maintenance Services-(32)Cods LSVB Ignition
80688 Consist mismalfonel.Inc. 10245.00 Legal Services-Construction Management P2-60
80689 Counryol Orange 150.00 Wage Gamishment
80690 County of Orange Auditor Controller 210.00 Inspection Service Pt-82&Encroachment Permit 7-22-1
80691 County Of Orange Auditor Controder 17.50 Encroachment Permit Pl-82
80692 CR&R,In. 1,575.00 Container Rentals
80693 Culligan of Orange County 45.30 stand.Agreement-Can Gen%Maier Softener System
W694 Cummins Allison Corp_ 373.44 Accounting Equipment Maint.Agreement
80695 Dell 2,478.98 Service Agreement
80696 Del Mar Analytical 320.OD Analysis of Biosolids
80697 Department of Child Support Services 300.00 Wage Garnishment
80698 Oickson's.Inc. 755.55 Heal PumplAir Conditioner
80699 DIRECN 47.28 Subscription
80700 Doug Horwood Supply 79.50 Acropdnl Tan.&Data Stamp Repairs
80701 Dunn Ed surds Corporation 327.57 Pahl Supplies
80702 Etecore Boost,Mc. 1.815.59 Repair&Maintenance Services-Fusion Bond Coating
W703 Electrical Reliability Services 767.50 Electrical Testing-Various Capital Pnjecls
80704 Employee Benefits Specialists.Inc. 10b14.W Reimbursed Prepaid Employee Medical B Dependent Care
80705 Equa-Chlor 3,20756 Chemicals
80706 Court Order 420.00 Wage Garnishment
B0707 ESRI,Inc. 1.849.00 Training Registration
80708 FEDEX Corporation 322.70 Freight Services
80709 Fast American Real Estate Solutions 375.00 Online Orange County Propedy Information
80710 Forked Engineering&Surveying,Inc. 5,966.80 Surveying Services-Various Capital Projects
60711 Founders Valley Pains,Inc. 528.89 Paint Supplies
W712 Franchise Tax Board 116.55 Wage Garnishment
W713 Franklin Covey 15.24 Office Supplies
80714 Frye Electronics; 969.63 Computer Supplies
80715 Gold Coast Awards.lac. 25.47 Name Badges
80716 Grainer Electric Company 5.499.85 Communications Equipment&Pans
80717 Hach do Ponton tMusul 4,427.76 Repair&Maintenance Services-Flow Meters
80718 Hasler,Inc. 150.85 Postage Meter Rental Fee
80719 H81 Brothers 14,424.84 Chemicals-Odor B Commum Control-Newport Trungmm
80720 Hone Depol 70.42 Misc.Repair&Maintenance Material
80721 Hummingbird Communications.Ltd. t,143.69 Annual Maintenance Agreement
60722 ICMA 103.03 Subscription
Wnil Internal Revenue Service 125.00 Wage Garnishment
8W24 IBM Corporation 5.103.66 Maintenance Agreement AS400
BD725 Md.Union of Oper.Eng.AFL CIO Local 501 4.550.46 Dues Deduction
80726 tvine Ranh Water District 43.37 Water Use
80727 K.P.McNamara of CA,Inc. 3,600.00 Hazardous Materiel Removal1Olsposal Services
BD728 Kinross,Inc. 3,656.40 Temporary Employmerd Services
80729 Meael Embonmenfal Lab 750.00 Outsloe Labarefory Services-Testing of Ferric Chloride
80730 Court Order 150.00 Wage Garnishment
80731 Manpower Professional 3,840.00 Temporary Employment Services
IBM Material and Contrast Services 4,960.00 Temporary Employment Services
80733 McMaster Can Supply Co. 625.49 Mechanical Pads&Supplies
X beovexEXCe1.MiNAP6rWVE`thim3 PSb iie3m AcWim3 Pep nevv i-DS3r EXHIBIT,B
rwlw Page 6 of 8 snlndos
Claims Pam From 04116106 to 0G30MG
Warrant No. Vendor Amount Description
80734 Medway Mlp.B Machining Co. 825.00 Mechanical Pans,Supplies&Repairs
W735 Member Uniform Service 107.96 Uniform Rentals
80736 Court Order 225.00 Wage Garnishment
80737 Na eudd Bond&Trust 2.445.20 U.S.Savings Bonds Payroll Duchre lam
80738 Natsource.L.L.C. 1.763.28 SCAGMD Emission Filing Fee
80739 New Vvodd Language Service 59.90 Training Registration
80740 COB Reprographics 21.741.95 Printing Service-MO 1126100
80741 OCEA 558.24 Dues Deduction
80742 Office Depot Business Services Division 56.03 Office Supplies
80743 Onesource Distributors,Inc. 23.65 Electrical Pads&Supples
807" Orange County Sheriff 85.00 Wage Garnishment
80745 Oxygen Service Company 40.51 Specially Gases
80746 Peace Officers Council of CA 1,521.00 Dues Deduction,Supervisors&Prehssbnals
50747 Peak Technologies 2291.54 Lab Pans&Supplies
80748 Polydin e,Inc. 10.626.27 Catbnlc Polymer MO 3-11-92
8O749 Pan Supply 16.48 Tools
M750 PROPIPE 5.769.02 SewedineCleaning-City of Tustin B Unincorporated County Property
W751 Prudential Overall Supply 1.542.W Uniforms&Rested Articles
80752 RMS Engineering&Design,Inc. 2.477.50 Engineering Services-Ph.2 Water Juncllon Box Slop Plate
80753 Roctohurst College Continuing Education 2AMM Training Registration
80754 IRS Hughes Co.,Inc. 372.58 Paint Supplies
80755 Ruben B Tucker Atbmeys at Law 2.O59A5 Legal Services
W755 SBC Long Distance 1.414.01 Lang Distance Telephone Services
80757 SBCIMCI 2.558.89 Telephone Services
90758 Scetlel Voice&Dam,Inc. 2,284.80 Telephone Services
80759 SCPLRC-So.Cal Public 200.00 Membership
80760 Siemens cfe Jensen Instrument Co. 2,283.97 Robicen Factory Service,Support&Stan-Up of VFD Drives
80751 Coed Order 721.50 Wage Gamishment
80762 SoOchNce Corp. 600.99 Software
80763 Southern Gemmel.Edison 24.65 Power
80764 Southern Counties Lubricants 3.039.97 09
80785 Strategic HR 180.00 Training Registration
80766 Summit Soon 610.59 Metal
80767 TST Verde and Instrument 3,156.76 Mechanical Pads&Supplies
807M TeIrSyslems 5,754.00 Temporary Employment Services
807N The Orange County Register 314.00 Nations&Ads
$0770 Time Warner Communication 51.07 Cable Services
80771 Townsend Public Affairs 5,000.00 Legislative&Executive Advocate for Grant Funding
80772 Trinity Consultants.Inc. 725.00 Software Maintenance
80773 Underground Service Alen of So.Calif 1,692.50 Membership-Underground Utility ldentificetioNNotiBcation Service
80774 United Parcel Service 59.26 Parcel Services
80775 Unned Way 200.V0 Employee Con ribullons
80776 Veriaan California 81.54 Telephone Services
80777 Wally Machinery and Tool Supply,Inc. 471.48 Mechanical Pans,Supplies&Tools
$0778 WEF 169.00 Membership-Wear Environment Federation
sting Weeam Pump,In. 1,064.90 Inspeclan 8 Repair UST Diesel Leak
SKIM Xemx Corporation 16.998.29 Copley Leases&Managed Services
W781 Xyon Business Solutions,Inc. 9.600.00 Temporary Employment Services
80782 Could Order 597.50 Wage Garnishment
80783 Gerardo Andreta 987.44 MeelingfTraining Expense Reimbursement
80784 David A.BIN 40.16 Meetlegrreuning Expense Reimbursement
W785 VMIam D.Cassidy 717.36 Meetingffraining Expense Reimbursement
W786 James E.Colston 1,138.51 MeetingRminbg Expense Reimbursement
80787 Steven R.DeW1Me 633.45 Mesting/Tmining Expense Reimbursement
H,Wwm MExp6L.dwV20wP611ARMI.me Pwd RepommanCwme Pool Rwwi-O a EXHIBITS
Ma+Mc Page 7 018 vi moos
Claims Paid From 04/16106 W 04f3OM6
Warrant No. Vendor Amount Description
80789 Cad.D.Dillon 939.07 Meetir19Rralning Expense Reimbursement
W789 Thomas D.Dodderer 53.00 MeetingRmining Expense Reimbursement
W790 Jeanie M.Fields 110.00 Meeting/Training Expense Rehnbursement
U791 Victoria L.Francis 625.61 MeetingRmining Expense Reimbursement
80792 Norbert Wna 491.31 MeetingrTrafring Expense Reimbursement
80703 David D.Halverson 20.00 MeetingrTraining Expense Reimbursement
80794 Vladimir A.Kogan 1.151.11 MeedngRralning Expanse Reimbursement
80795 Paul KreysialL 90.00 MeedngrTminin,Expense Reimbursement
80796 Michael D.Moore 231.00 MeetingRmtning Expense Reimbursement
80797 Jeffrey T.Reed 110.32 MeetinORraming Expense Reimbursement
80798 Roy J.Reynolds 870.40 Mee8n9(Tralning Expense Reimbursement
80799 Ernest S.Ruckmen 15.00 MeeBngrtraining Expense Reimbursement
WBeO Jeremy J.S.um 799.00 MeeBng)Trelning Expense Reimbursement
B0NI Mandrick S.Taylor BOOM Meetng(Treining Expense Reimbursement
80802 Ronald L.Men 622.90 MeehnglTralnirg Expense Reimbursement
80803 Michael 1.Zedek 162.75 Mee0nglTraining Expense Reimbursement
SH04 Farmers Insurance Group 4.914.23 VehkJe Damage Claim
80805 County of Orange Autl0or Controller 17.50 Encroachment Permli P142
Total Accounts Payable-Warrants S 10,908222.84
Payroll Disbursement
33200 - 33201 Employee Paychecks S 1,223.69 Tem0nati0ns VI 71118
33202 - 33282 Employee Paychecks 145,893.42 Binned,Payroll 04/26108
33283 - 33288 Employee Paychecks 13,395.86 Re",OCERS Reimbursement,COnection to EE Pay 8 Telminalion N124/06 tm 04/27106
125081 - 125627 Direct Deposl Statements 1A24,466.80 Bineekly Payroll 0428106
Total Payroll Disbursements $ 1,284,979.77
Wire Transfer Pavmenta
OCSD Payroll Taxes B Conmautions S 650,058.76 Bhyeekly Payroll 04125108
US Bank 370,927.95 Sense 2000 A 8 B Refunding COPS April Interest Payment
Total Wire Transfer Payments $ 1,020,985.71
Total Claims Paid 0VIGM6.0413010E $ 13.214.189.32
H.WepMMExCELdraMMPSHPRE1CImms Pad Roper dA(blma Pepe Repod-063046 EXHIBITgn
nuolonc Page 8 of 8 1111 m s
BOARD OF DIRECTORS Meeting Date TO Btl.:0 Dir.
O6/2 0fi
AGENDA REPORT Rem Nember Iem Numbe
Orange County Sanitation District
FROM: Penny Kyle, Board Secretary
SUBJECT: ELECTION OF CHAIR AND VICE CHAIR
GENERAL MANAGER'S RECOMMENDATION
(1) Nominations and election of Chair (effective July 1, 2006)
(2) Nominations and election of Vice Chair (effective July 1, 2006)
SUMMARY
As provided in the Board's Rules of Procedure, nominations and election of the
Chair shall take place at the June regular meeting.
Nominations and election of the Vice Chair will be conducted immediately
following the election of the Chair.
For the Directors information, included below is an excerpt from the current Rules
of Procedure relative to the election of the Chair and Vice Chair of the Orange
County Sanitation District:
"Chairperson and Vice Chairperson of the Board.
A Chairperson and Vice Chairperson of the Board shall be elected by a
majority vote of Directors at the regular meeting in June of each year, and
will assume office July 1st. The nominations for Chairperson shall be
made at the regular Board meeting in May of each year, and the nominees
may prepare a statement setting forth their qualifications for the office of
Chairperson. The statements shall be mailed to members of the Board of
Directors with the Agenda and other meeting material for the June regular
meeting.
The nominations and election for Vice Chairperson shall be made at the
regular Board meeting in June of each year and shall be made
immediately following the election of the Chairperson. The elected Vice
Chairperson will assume office July 1 st.
The Chairperson and Vice Chairperson shall serve at the pleasure of a
majority of the Directors. In the event the office of Chairperson becomes
vacant due to resignation or retirement of the incumbent prior to the
expiration of the regular term, the Vice Chairperson shall automatically
H'Wep(aWda�dPge �s�e d T9enda6R9e,Ma ftp 3�Ml ].EIWM d=
R-I.. aaoea Page 1
succeed to the office of the Chairperson and shall continue to serve
through the remainder of the regular term unless sooner removed by
action of a majority of the Directors. In the event the office of Vice
Chairperson becomes vacant prior to the expiration of the regular term,
nominations and the election of a Director to serve in that capacity shall be
conducted at the next regular Board meeting. The person so elected shall
serve the balance of the regularly-scheduled term unless sooner removed
as a result of action by a majority of the Directors.
Subject to the provisions about serving at the pleasure of a majority of the
Directors, the Chairperson shall not serve more than two consecutive one-
year terms for which he/she has been elected to the office of
Chairperson."
PROJECT/CONTRACT COST SUMMARY
N/A
BUDGETIMPACT
❑ This Rem has been budgeted. (Line item:
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
® Not applicable (information item)
ADDITIONAL INFORMATION
N/A
ALTERNATIVES
N/A
CEQA FINDINGS
N/A
ATTACHMENTS
N/A
H Wegwperws�dlpmEa RMa15�P d ).EM—Ox
R—i &0090 Page 2
BOARD OF DIRECTORS Meebng Date To 8d.or Dlr.
06/28/O6
AGENDA REPORT Rem Number Iem Number
g
Orange County Sanitation District
FROM: Lorenzo Tyner, Director of Finance/Treasurer
Originator Lenora Crane, Executive Assistant
SUBJECT: PAYMENT OF CLAIMS OF THE ORANGE COUNTY SANITATION
DISTRICT
GENERAL MANAGER'S RECOMMENDATION
Ratify Payment of Claims of the District by Roll Call Vote.
CONFLICT OF INTEREST NOTIFICATION
Pursuant to Government Code Section 84308, you are required to disclose any
campaign contribution greater than $250 received in the past twelve months from any
party to a contract involving the Orange County Sanitation District. Further, you may
not participate in the decision making process to award a contract to such party.
For reference, you are directed to the Register of Warrants as to all current
contractors/vendors with the District.
In general, you must disclose the basis of the conflict by identifying the name of the firm
or individual who was the contributor.
For the specks of Government Code Section 84308, please see your Director's
Handbook or call the office of General Counsel.
SUMMARY
See attached listing.
PRIOR COMMITTEE/BOARD ACTIONS
N/A
PROJECTICONTRACT COST SUMMARY
N/A
L.'Lmerrtl wW$M9gammYml 9etligeRn,w,sy I,Yw,M FiIn1IX1!]ONwn 9 Llvinn PaY(31 M1x
a.w.e: e\m= Page 1
BUDGETIMPACT
t
❑ This item has been budgeted. (Line item: �
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
® Not applicable (information item)
ADDITIONAL INFORMATION
N/A
ALTERNATIVES
N/A
CEQA FINDINGS
N/A
ATTACHMENTS
1. Copies of Claims Paid reports from 05/01/06 to 05/15/06 and 05116/06 to 05/31/06
C`Dacvnss vtl�9e sv T�LmM,1l1 Fi4PALl(]BWmm 9 Cb PW I219x
a.a..9 01 w Page 2
e
Claims Paid From 05101MG to 06115106
Warrant No. Vam1or Amount Description
Accounts Payable-Warrants
80806 Air Products&Chemicals 5 50,000.00 O is M Agreement Oxy.Gen.Sys.NO 8-8-69
80BD7 Black&Veatch Corporation 590.029.05 Engineering Services P1-76,Pi-102&179-1
809DB Brawn&Caldwell 629.0731 Professional Services P2-90&CMOMANDR Program
808D9 Carolle Engineers 119.001.35 Professional SeMoss P2E6
8081D Ceicate Air Pollution Control 35,828.15 Scrubber Fan Replacement-" Scrubber
80811 City of Newport Beach 158,902.02 Reimbursement Agreement-OCSD Think Sewer lmpmyerients
80812 Codech Engineering 45.822.78 Pumps&Pump Paris&Supplies
80813 Earth Tech,Inc. 55,769.76 Professional Services P2-79
80814 HDR Engineering,Inc. 51,309.65 Professional Services Pl-82
90816 IPMC do Parsons 1,260,014.00 Engineering Services-Integrated ProgramlProject Management.Temporary Stefing.Mail.&Supplies
80815 Kemlron Companies,Inc. 52,073.05 Chemicals
80817 Labwom,Inc. 26,100.00 Lab Equipment Maintenance&Support
80818 Lee&Ro,Inc 123,486.52 Professional Services 549,581,5.52,P247413
80819 Malcolm Finds,Inc. 204,341.12 Professional Services P2480&11-25
80820 MWH Americas,Inc. 62.792.80 Professional Services P244,J-101&Modification to Collection System Model
80821 Pioneer Amerind,Inc. 10ZSOO.A Sodium Hypochhuile
80822 Polydyne,Inc. 32.191.41 Cationic Polymer MO 3-11-92
80823 RBF Consulting 73,017.00 Engineering Services 241&2414
80824 Sancon Engineering,Inc 38,380.00 Construction-Manhole Rehabilitation Project If Fold and Refold PVC Pipe Rehabilitation Project
80825 Synagm West,Ina 332,024.87 Residuals Removal MO 3-29-95
80826 Tule RanchlMagan Farms 265,276.77 Residuals Removal NO 3-29-95
80827 US Peroxide,L.L.C. 41,125.25 Odor&COM05ton Control Treatment for Coll.Sys.;Hydrogen PeroxMe B Ferrous Chloride
80828 N/oodmB Spradltn&Smart 35.051.96 Legal Services MO 7-26-95
80829 Demmer Engineering&Construction 225.414.00 Construction 1`266d
80830 J F Shea Construction,Inc. 2,414,387.01 Construction J-77&P2466
80831 J R Filanc Construction 1,848,800.80 Construction Pl-52
80832 Margate Construction,Inc. 317,400.00 Construction P147
80833 Southern Contracting Company 115,360.00 Construction J33-1A
80834 LA Chemical 1.152.76 Bleach
80835 Aandema Instrument 10.281.00 Repairs&Maintenance Services-Coastal Monitoring Buoy
90836 Abmkm Engineering Tool&Equip. 99.79 Sandpaper
80837 Absolute Standards,Inc 675.00 Lab Parts&Supplies
80838 AccuStandard 80.72 Lab Parts&Supplies
80839 ADTECH 555.00 Electrical Parts&Supplies
80840 Agilenl Technologies,Inc 207.42 Lab Paris&Supplies
80841 AIHce American industrial Hygiene 155.00 Training Registration
80842 Aigas Safety,Inc. 3.528.98 Safety Supplies
80843 AKM Consulting Engineers 11.325.00 Professional Services-Part-Tone Dig Aled Technician
80844 AliMed,Inc. 87.45 Ergonomic Computer Supplies
00845 Applied Industrial Technology 527.39 Mechanical Parts&Supplies
80846 AT&T Unhlerml Biller 644.86 Telephone Service
80847 American Telephone&Telegraph Corp. 234.47 Telephone Service
80848 Baker Tanks 560.00 Tank Rentals
80849 Basle Chemical Solutions,L.L.C. 10.856.31 Sodium Bisulfite&Sodium Hydroxide
80850 Battery Specialties 529.09 Batteries
80851 Bennett Bowen Lighthouse 1,884.54 (5)PHD Gas Monitors
80852 Berendsen Fluid Power 68.98 Mechanical Pads&Supplies
80853 BNI Building News 148.08 Books&Publications
H WepwmlEXCELduc2014PSi-uAMlpmS Pep aa;xdW64AGW MPeE Rrmn-0S15-0a EXHIBITA
I.,. Page 1 of a MlnnoSa
Chips Paid From 06101/06 W 06I16106
Warrant No. Vapor Amount Description
80854 Bpmemann Pump.Inc. 1.241.28 Pump Paris&Supplies
80855 Botarl,Tactical 3,006.23 Safety Supplies
W856 Brenntag Padfic,Inc 1.385.07 Jaidlomu Supplies
80857 Bush&Assocates.Inc. 17.10.00 Professional Services 736&7.39
80858 California Recreation Company 2,588.90 Beal Slip Rental Fees for Ocean Monitoring Vessel Nerissa
80859 California Relocation Services.Inc. 300.00 Office Files Moving/Relocation Services
BONG Cambridge Isotope Labs 1,889.55 Lab Paris&Supplies
80861 Candela Corporation 60.65 Electrical Supplies
80862 Cad Warman&Co. 300.00 Insurance Claims Administrator
80863 Charles P.Crowley Co. 3,782.D3 Electrical Pads&Supplies
80884 CingularWrelsp Airtime 406.03 WMW5s Services
80865 Coast Fire Equipment 1,365.87 Fire Extinguishers
808M Coast Plumbbg 2.060A0 Plumbing Sences
80867 Columbia Analytical Services,Inc. 270.00 Analysis of Wastewater,Industrial Wastewater&Biosolss,
80N8 Communications Supply Corp. 113.25 Ekcbical Pans&Supplies
80869 CompuCom 570.01 Computer Hardware/Software
80870 Complicated Elect Distributors,Inc. 1,497.82 Electrical Pans&Supplies
80871 Consolidated Reprographics 78.73 Copier Paper
SM72 Consumers Pipe&Supply Co. 1201.18 Plumbing Parts&Supplies
8131 Cooper Cameron Corporation 871.91 Fglers
80874 CORRPRO Companies. no. 2,850.00 Professional Services-Cathodic Protection Survey B Testing-Baker Force Main
W875 County of Orange Autlitor Controller 17.50 Encroachment Permit 7-21
80876 County of Orange Auditor Controller 157.50 Encroachment Permit 741
80877 County of Omega Auditor Complier 70.00 Encroachment Permit 736
80878 CS-AMSCO 1,005.92 Mechanical Paris&Supplies
80679 CWEA Membership 100.00 Membership(Cafil.Water Emramment Assoc.)
W880 Dapper The Co. 346.87 Truck Tees
80881 David's Tree Service 2,900.00 Tree Mart.Senrice
80882 Del Mar Analytical 1208.00 Analysis of BlosolMs
SOB83 Desert Pumps&Pads,Inc. 2261 Pump Pads&Supplies
80884 Dezu*Water Controls 1.776.97 Mechanical Parts&Supplies
80885 Dudek&Associates.Inc. 22,465.80 Professional Services P2-68
B0NS Dunn Edwards Cmporegon 224.32 Palm Supplies
80887 Dwyer Instruments,Inc 215.61 Instrument Pads&Supplies
80888 Enchanfer,Inc. 6.100.00 Ocean Monitoring&Outfall Inspection&Maintenance
80889 ENS Resources,Inc. 10.000.00 Professional Services-Legislative Advocate
M90 Emmanmental Resource Association 1,416.58 Lab Parts&Supplies
80891 ESSCO(Engineering Sales Service) 5.973.65 Pump&Motor
80892 Excel Paving Company 11,090.00 Construction-Replace,Rake,Adjust OCSO's Manholes on PCH
80893 Ferguson Enferprises,Inc. 718.36 Valves
808g4 First American Real Estate Solutions 450.00 OrvLine Orange County Property Information
80895 Fisher Scientific Company.L.L.C. 9.143.70 Lab Parts&Supplies
80596 Flora.Product .Inc 690.36 Mechanical Pans&Supplies
80897 Franklin Covey 20.42 Office Supplies
80898 Gamab Callahan Company 248.25 Chemicals
80899 GBC)General Binding Corp) 29.87 Office Supplies
80900 George T.Hall 2,330.80 Motor
80901 Golden State Water Company 73.83 Water Use
8091)2 Goldenwest Wind..Service 960.00 Groundskeeping Services
�s Paa Re9o-noson[lsonz P.4 Rmon-o5-1 sa EXHIBIT A
rw2rwc Page 2 of 8 W'..M
Claims Paid From Oli IMB to 06115m9
Warrant No. Vendor Amount Description
801 Grainger,Inc 1,322.63 Mechanical&Electrical Paris,Supplies 6 Tools
809N Gni Electric Company 454.56 Instrument Repair 6Maintenance Salsas-Thermocouple Input
80905 Great Western Sanilery,Supplies 146.28 Janitorial Supplies
80906 The Grimslad Company 674.92 Instrument Paris 6 Supplies
80907 Haaker Equipment Company 117.40 Misc.Vehicle,Pads.Repairs&Service
80908 Hach do Ponton Industries 135.30 Lab Pads 8 Supplies
80909 Harrington Industrial Plastics,Inc. 4,054.62 Mechanical Pads 8 Supplies
80910 Hatch 6 Kirk,Inc. 3.326.48 Mechanics Pads&Supplies
80911 Hewlett Packard Company 8.380.63 (5)Notebooks
80912 Hi Standard Automotive 60.56 Automotive Pads&Supplies
80913 Hill Brothers 9.866.72 Chemicals-Odor&Corrosion Control-Newport Trunkhme
80914 Hill,Inc. 1,961.37 Hardware
80915 Home Depot 1.167.14 Misc.Repair 8 Maintenance Material
80916 Hookah Repair Service 499.96 Unlnslall and Relocation of Labconco Dishwasher from Lab Room 231 to 229
80917 Hose Express,LLC doe Pines Santa 192.97 Hose Supplies
80918 Hub Auto Supply 769.85 Vehicle Pads 6 Supplies
60919 City of Huntingron Beach 13,465.08 Water Use
80920 ICC lmomational Code Council 150.00 Membership
80921 [its.Laboratories,Inc. 2.004.15 Lab Pans&Supplies
80922 IEEE Institute of Electrical B Elec. 1112.10 Membership
60923 Industrial Distribution Group 1,BS9R9 Mechanical Pans,Supplies,Paint,Locks B Tools
80924 literature Engineering 445.65 Sowards Video Inspections
thi Inorganic Ventures.Inc. 270.67 Lab Pads 8 Supplies
80926 had Mountain 100.04) Storage Fee-Bid Documents P1-37
80927 ISA 960.B0 Books 6 Publications
80928 Jays Catering 967.96 Meeting Expenses
80929 John Bell Pool Servlcs 2,170.00 Seru ce Agreement-Admin.Bldg,Ali Pond
80930 Johnstone Supply 1,672.73 Electrical Pans&Supplies
80931 JPL Compressor Service,Inc. 5.714.46 Gas Compressor Pent 6 Supplies
80932 Kars Advance Materials,Inc, 2.321.90 Professional Services-Analysis of Non-0ostruct1w Testing
$0933 Lab Safety Supply,Inc. 54.74 Lab Pam A Supplies
80934 Lewis Nexus Matthew Bender 426.70 Books&Publications
80935 Lucci's Gourmet Foods,Ina, 91.35 Meeting Expense
80936 Material Control,Inc. 815.24 Mechanical Pens 8 Supplies
80937 McMaster Can Supply Co. 536.14 Mechanical Pads,Supplies B Repairs
80938 MCR Technologies,Inc. 2,692.21 Instrument Pads 6 Supplies
80939 Medlin Controls Co. 07.41 Instrument Pads&Supplies
80940 Mellon Trust 23,127.38 Investment Cuelodian Bank
80941 Metrolech Corp. 332.93 Electrical Pipe Markers
80942 Midway Mfg.8 Machining Co. 1,920.0D Repairs 8 Maintenance-High Rate Mixing Pump
80943 Mission Abrasine B Jandmial Supplies 161.40 JanBorial Supplies
80944 Mitchell Instrument Co. 75.71 Instrument Pads B Supplies
80945 National Electric Manufacturing Corp. 501.03 publication B Books
80946 National Fire ProfeGbn Association 187,43 Baoks 6 Publications
80947 National Plant Senlces,Inc 460.00 Vacuum Truck Services
BONS Neel Supply Co. 08.98 Plumbing Supplies
80949 City Of Newport Beach 117.67 Water Use
80950 OCB Reprographics 10,331.82 Printing Serum-MO 1126100
80051 Office Depot Business Services Division 213,43 Office Supplies
X WopNmIExCEL41a=&APSHARECIxims Pet Rey IVI60TCruims PeN Rei-051S EXHIBITA
riN 1. Page 3 of 8 wivase
Claims Pala From 05101/06 to 05116N6
Warrant No. Vendor Amount Description
80952 Onesource Distributors,Inc. 3.899.92 Electrical Pans B Supplies
80953 Oscle Corp. 14,418.74 Training Registration B Maintenance Agreement Renewal
80954 Orange Community Bank 1,111A0 Conslrucli n 1`2.82,Retention
50955 Orange County Water District 545.01 Joint GWRS Project J36
80956 Orange Fluid System Technologies,Inc. 525.89 Numbing Paris 8 Supplies
80957 ORCO Construction Supply 196.44 Marking Paint
90958 ORE Oashons 2,567J6e Zinc Anodes B Batteries
80959 Oxygen Service Company 143.50 Specially Gases
80950 PAC 521.60 Lab Paris B Supplies
80961 Padfic Mechanical Supply 3.230.96 Plumbing Supplies
80962 Parsons Water A Infrastructure,Inc. 14,017.87 Professional Services J35-1
80963 PCS Express,Inc. 226.74 Counter Service
80964 PL Hawn Company,Inc. 168.07 Electrical Paris B Supplies
80965 Primary Source Office Furnishings,Inc. 12.865.35 Office Furniture 8 Mi..Equipment
80966 Project Management Institute 164.00 Membership
80967 PROPIPE 8.623.84 Sewerllne Cleaning-City of Tuslin B Unincorporated County Property
80068 Pm0eMlal Overall Supply 3,130.05 Uniforms 8 Related Articles
M969 PS TEK,L.L.C. 1,207.46 Oil Fillers
80970 Pumping Solutions,Inc. 1.269.16 Pumps
80971 Raven Biological Laboratories 103.93 Lab Parts 8 Supplies
80972 R Company,L.T.D. 3.800.00 Software Maintenance Agreement-Image 2000
80973 Restek Corporation 551.30 Lab Pans 8 Supplies
SM74 RM young Company 235.00 Conversion of Wnd Indicator to Dual Station-Ocean Monitoring Vessel Nerissa Lab
W975 RMS Engineering 8 Design,Inc. 2,820.00 Engineering Services-Structural Evaluation of OAF Cover
M76 Rockf u et Collage Continuing Education 537.19 Books 8 Publications
80977 RPM Electric Motors 90.51 Motor
W978 Safe T Rad Systems,Inc. 999.43 Lab Pads 8 Supplies
W979 SBCIMCI 22.67 Telephone SeMces
W980 South Coast Environmental Co. 945.00 Air Quality Monitoring
80981 Shamrock Supply Co.,Inc. 1,153.36 Safety Supplies
80982 Shumiuck Sales B Engineering 886.69 Mechanical Pads B Supplies
80983 Siemens clo Jensen Instrument Co. 5,254.91 Instrument Paris 8 Supplies
809" Skater.Inc. 292.33 Lab Paris 8 Supplies
60955 Smith Emery Company 100.00 Soils,Canctete 80ther Materials Testing
80986 Snap-On Tools,Inc 555.25 Tools
80987 South..California Trans Service 3.584.00 Repair 8 Maintenance Service-Abserption Chillers at Pit.1
80988 Southern Counties Lubricant 3.670.74 Oil
80989 Sperling Instruments,Inc. 3.238.62 Magnetic Flow Meters 8 Parts
80990 Spec Services.Inc 24.274.69 Engineering Services J33-1
80991 Stanley Steamer International,Inc. 1.032.00 Carpel Cleaning Services
80992 Stratus Environmental,Inc. 8205.00 Professional Services-Groundwater Monitoring
80993 Summit Steel 1.561.38 Metal
80994 Burnet Ford 339.12 Vehicle Pans 8 Service
80995 The Carbon Products Co. 175.19 Orange Floats for Mooting
80996 Thermo Electron North Americe,L.L.C. 3,227.50 Lab Paris 8 Supplies
80997 Thompson Industrial Supply,Inc. 7,771.24 Motor 8 Mechanical Paris 8 Supplies
80998 Tony's Lod 8 Safe Service 8 Sales 21.66 Was 8 Keys
80999 Traffic Control Service,Inc. 285.54 Orange Traffic Vests
81000 Tremor PHE,Inc. 1,187.46 California Sales Tax-P.O.41421
rM aka gym. a im. r arms.05-i9w
Page4of8 M1 ••
Claims Paid From 0SM110610 U6f18/DS
Warred No. Vendor Amount Description
B10ot Truck&Auto Supply,Inc. 227.30 Aulor ive Pena&Supplies
81002 UNre Scientific 571.35 Lab Parts&Supplies
81003 The Unbource Corporation 716.14 Office Supplies
810M United Pacific Services,Inc. 5,480.00 Repair&Maintenance Services-Seal Beach Pump SM.
81005 United Pumping SeMce 2,711.61 Pumping Sam.
$1006 US Alroontlldoning Distributors,Ina 288.23 Thermostats
51007 Vapex.Inc. 2.620.00 Instrument Paris&Supplies
Blocs Veil Inc. 4.141.74 Lab Instrument Servloe/Cleaning
61009 Verhoon California ye5.B5 Telephone Services
81010 Vannes Plumbing 150.00 Senator Conked-Testing&Can.Backflow Devious at Phs.1&2&Pump SM.
$1011 Vortex Corp. 1.300.00 Door Repair&Maintenance-Power Bldg.B Roll-Up Door
61012 VWR Scientific Products 5,B20.01 Lab Pads&Supplies
61D13 Willingboro!Software,Inc. 6,288.29 Annual Software Maintenance
BID14 Water3 Engineering,Inc. 1,002.13 Engineering Services J-67
81016 Waterman Supply Co.,Inc 974.25 Chain
81016 Walers Corporation 1,214.31 Lab Paris&Supplies
81017 Waste Sanitary Supply 240.1E Janitorial Supplies
81018 WEF 288.00 Membership-Wafer Envimmrcnt Federation
81019 WEF Registralion Dept. 100.00 Meeting Registration-Dix.620
81020 West Lite Supply Company,Inc. 228.21 Electrical Paris&Supplies
81021 Weston Solution,Inc. 14.055.00 Outside Laboratory&arvloes-Core Ocean Monitoring Program
81022 Wilson Supply,Inc. 10.13 Plumbing Pads&Supplies
81023 XEROX Corporation 210.12 Stalmnary,
81024 California Bank&Trust 0A71.00 Consbuctian J-33-1A.Retention
81025 Olsson Cormtuction,Inc, 10,005.00 Construction P2-02
81026 Layne T.Sandal 542.10 MeetingRralning Expense Reimbursement
81027 Made Becema 60.73 Meelingfirelning Expense Reimbursement
81028 Ann H.BrandveM 346.13 Meetngf raining Expense Reimbursement
81029 Dean M.CaMco 392.02 Meeinglrralning Expense Reimbursement
81030 Doug M.Dyson 18.00 MeeliogrTraining Expense Reimbursement
81031 TMress Evans 168.79 Meelingfrmining Expense Reimbursement
$1032 Victoria L.Francis 282.55 Meeting?raining Expense Reimbursement
$1033 Pamela A.Koester 612.02 MeellrgRralning Expense Reimbursement
81034 Michael D.Masterson 358.10 MeelingRnlning Expense Reimbursement
81035 Johnny J.Roche 130.00 Meelingf mining Expanse Reimbursement
81036 Minorco S.Taylor 182.00 Meelingffmining Expense Reimbursement
81037 Simon L.Watson 44/.44 Meeling/Tralning Expense Reimbursement
81038 Voided Check - -
81039 Big Canyon Country Club MR,600.00 Construction 5-62
81 M0 Brawn&Caldwell 156.817.57 Professional Services P2-91
81041 City of Le Palma 64,350.00 Cooperative Pmjects
a1042 Kemiron Companies,Inc. 44,380.61 Fertic Chloride
81043 NALCO Company 32,807.93 Anionic Polymer
B1044 Orange County Water DISMCI 63,194.66 GAP Water Project
81095 Pacific Investment Management Co. 108.103.31 Investment Management Servloe Res.96-97
81046 Pars erAmericas,Inc. 102.253.55 Sodium HypoMlonle
81047 Southwn Cal6amia Edson 61.295.40 Power
81048 US Peroxide,L.L.C. 31,628.38 Oda&Camacinn Control Treatment for Coll.Sys.;Hydrogen Peroxide&Ferrous Chloride
81049 Waste Markets 35,311.69 Meat Agree.-Due&Screenings Removal&Digester Marl Removal
H tapVdn1EXm1 daQ20APSHFREICIe1me Pad RepM064ACIRims Pad Peron-MASAO EXHIBIT A
f dNlwk Page 5 of 8 wlnrmos
Claims Paid From 0610I1011 W UW1&108
warrant No. Vendor Amount Description
81050 J F Shea Construction,Inc. 1,035,866.25 Construction J-35-1
81051 Accounting Options,Ira. 3,26T.48 Temporary Employment SCMces
81052 ACEC 89.95 Publications&Books
81053 AETC 5,7U8.00 Air Quality Monllontq-RATA Testing of PEMS at Pit.1 CGS Engines
81054 Air Products B Chemicals,Inc. 998.00 Professional Servke5 P247-3
81055 American Express 22.618.97 Purchasing Card Program.Misc.Supplies&Services
61056 American Water Works Assoc.Maller 130.00 Membership
81057 Ashbroek Corporation 16,603.13 Mechanical Parts&Supplies for Wnklepress
$1058 AT&T Universal Biller 1,609.59 Telephone Servlce
81059 Bask Chemical Solutions,L.L.C. 8.247.73 Sodium Bisulfila&Sodium Hydroxide
81060 Bennett Bowen Lighthouse 127.00 (8)Blosyslems Mon0ors
81061 Court Trustee 98.62 Wage Garnishment
81062 California Hazardous Services,Inc. 502.50 Underground Storage Tank Momberng Certifications, Spill Bucket Test&Light Replacement
81063 Coast Transmission 1,870.25 Trammisrlon Replacement V483
81064 Cade Electrical Classes,Inc. 123.00 Publications&Books
81065 Compressor Components of California 1,248.00 Repair&Maintenance Sammons-(32)Coils LSVB Ignition
$1066 Construction Book Express 91.90 Publications It Books
81067 Consumers Pipe&Supply Co. 133.29 Freight Services
81068 Camara*Express 1,868.74 Omce Supplier
81009 County of Orange 13.60 Wage Garnishment
81070 CWEA Membership 100.00 Membershlp(Calif.Water Emaronment Assoc.)
81071 Department of Child Support Services 3DD.00 Wage Garnishment
81072 DHL Express USA,Inc. 38.82 Freight Services
81073 Ecology Control Industries 11.010.40 Hazaldous Waste Oisposal
$1074 Edinger Medical Group,Inc. 650.00 Medical Screenings
81075 Employee Benefits Specialists,Inc. 10.723.92 Reimbursed Prepaid Employee Medical&Dependent Care
81076 Employment Development Dept. 6.000.00 State Unemployment Tax
81077 Court Older 420.D0 Wage Garnishment
81078 FEDEK Corporation 172.66 Freight Sunman
81079 Franchise Tax Board 506.85 Wage Garnishment
81080 GaotMty,Inc. 3,450.00 Professional Services-Flow Monitoring at OCSD Manhole
81081 Gerard Daniel Worldwide 43.T2 Mechanical Paris&Supplies
81062 GoaVOPC 124.12 Publications&Books
81083 Heat Technology Products 2.745.00 Repair&Maintenance Services-Oil Heal Exchanger ae Blower
81084 Hill Brothers 9,137.87 Chemicals-Odor&Corrosion Control-Newport Trualme
81085 IEEE Institute of Electrical&Elect. 91.59 Books&Publlcetlons
61086 IESNA PuNications 425.00 Books&Publications and Membership
$1087 Inside EPA 320.00 ECM Publication
81088 internal Revenue Service 126.0U Wage Gamahment
81089 had.Union of Oper.Erq.AFL CIO Local 4.617.69 Dues Deduction
81090 mine Ranch Water Grand SAS Water Use
81091 ISI,Inc. 3.198.00 Software,Maintenance&Support-Infortel for Windows 1000 suppling Software
81092 Jamison Engineering Contractors,Inc. 9.770.61 Repairs It Maintenance Services-lath Street Pump Station
81IN3 Jays Catering 676.75 Meeting Expenses
81094 Kelly Paper 152.30 Paper
81095 Kforce,Inc. 5.303.03 Temporary Employment Series
81096 LA Testing 177.00 Asbestos Analyses
81007 Court Order 150.00 Wage Garnishment
81098 Lorman Education Seruices 319.00 Training Registration
nL imfPw Rayon-os.lsaa EXHIBIT
r uetwk onr Page 6 of wAQoV
Claims Paid From 05101106 to 05115N6
Warrant Mo. Vendor Amount Description
81M Manpower Professional 5.088.00 Temporary Employment Services
81100 Material and Contract Services 4,960.00 Temporary Employment Services
81101 McMaster Can Supply Co. 610.25 Mechanical Pans&Supplies
81102 Midway Mfg.&Machining Co. 3,129.81 Repairs&Maintenance Services-Hi-Rate Miring Pump
81103 Mission Uniform Service 284.39 Uniform Rentals
81IN Court Order 225.00 Wage Garnishment
81105 NACE International 165.00 Membership
811M National Bond&Trust 2.445.20 U.S.Savings Bonds Payroll Deductions
81107 Ninyo&Moore Corporate Accounting 200.00 Professional Services-Soils,Concrete&Other Materials Testing Pt-37
81108 0 C Tanner Recognition Company 1,100.93 Employee Service Awards Program
Will) OCEA 548.99 Dues Dedudlon
81110 Office Depot Business Services Division 3.557.75 Office Supplies
81111 Onesource Distributors,Inc. 45.37 Electrical Pans 8 Supplies
81112 Orange County Sheriff 85.00 Wage Gamishment
81113 Oxygen Service Company 1.458.88 Lab Parts&Supplies
81114 Padgett-Thompson 199.00 Training Registration
81115 Peace Officers Council or CA 1.512.00 Dues Deduction.Supervisors&Professionals
81116 Pinney Bowes 172.00 Postage Machine Service
81117 Polytlyne,Inc. 16,932.44 Catlonic Polymer MO 3.11-92
81118 Prudential Overall Supply 1.485.00 Uniforms&Related Articles
81119 REF Consulting 3,043.00 Engineering Services 241&2414
81120 Sancon Engineering,Inc. 11,950.00 Comimclion-PVC Sewer Pipe Rehabilitation Project
81121 SBCIMCI 745.22 Telephone Services
81122 Soon Specialty Gases,Inc. 7,604.71 Lab Pans 8 Supplies
81123 Shureluck Sales&Engineering 134.51 Mechanical Parts&Supplies
81124 Coast Order 721.50 Wage Gamishment
81125 So.Cal Gas Company 23,084.54 Natural Gas
81120 Soflohoice 599.54 Software
81127 SSPC The Society for Protective 95.00 Membership
81128 Steven Enterprises,Inc. $24.29 Office Supplies
81129 Systems Solution Company 170.00 Repairs&Maintenance Services-Access Controlli Security System
91130 Technocrat 1.151.00 CD ROM&Paperback CD-RPM-National Electrical Safety Code&IEEE Color Books Set-Div.760
$1131 The Standard Insurance Company 86.90 Executive Disability Insurance
81132 Thompson Industrial Supply,In. 2.607.63 Mechanical Parts B Supplies
81133 TPC Training Systems 450.00 Training Registration
81134 Truck&Auto Supply,Inc. 81.47 Automotive Parts&Supplies
91135 The Unlsource Corporation 568.89 Office Supplies
81136 United Direct Marketing 9,011.51 Public Outreach Printing&Distribution Costs&Postage Permit 1.24
81137 United Parcel Service 78.14 Parcel Services
81138 United Way 150.00 Employee Contributions
811M WEF 144.00 Membership-Wafer Environment Federation
81140 WEFTEC 675.00 Meeting Registration-Div.820
81141 Xyen Business Solutions,Inc. 8.520.00 Temporary Employment Services
81142 Court Order 597.50 Wage Garnishment
SI M Delke&Sons Constwolions,Inc. 12.226.50 Construction P2fi6-2
$11" Nicholas J.Arhontes 20.00 MeetitgRralnin9 Expense Reimbursement
81145 Layne T.Baroldi 611.54 Meelingi fraimng Expense Reimbursement
81146 James E.Colston 406A3 Meelingi(raining Expense Reimbursement
81147 Mark A.Eaguer 10.00 MeelingRraining Expense Reimbursement
HVIvartME%CEL Ne1230NP5HAdm ims Paid Ijdvd 4T Ixe Pad Report-0615C5 EXHIBITA
lai Page 7 of 8 enxaoce
Claims Paid From 0=1106 to OS/15N6
Warmest Be. Vendor Amount Descri
81148 Randy E.Harms 10.00 MestingNminirlg Expense Reimbursement
81140 Andrel loan 645.51 MeelingRreming Expense Reimbursement
81150 Terry W.Icrie 580.97 Ideeting(fraining Expense Reimbursement
81151 James McCann 170.00 McetinglTrainlrg EVernss Reimbursement
81152 Samuel L.MOWMay 23.00 MsetingRreining Expense Reimbursement
61153 Umesh N.Mumhy /50.00 Meeting/Training Expense Reimbursement
81154 Sharon Nefus 914.20 Mee11n8Rralning Expense Reimbursement
01155 Ellen Ray 559.23 Meeting/frelning Expense Reimbursement
81IN James G.Tintle 10.00 Meeling/Training Expense Reimbursement
81187 Rachel J.Van Erel 1,209.05 Meelingfrreining Expanse Reimbursement
81158 Memo Polo S.Velasra 661.22 Meeting?raining Expense Reimbursement
61159 Simon L.Watson 10.00 MeetingRraming Expense Reimbursement
81160 Moms C.Ying 139.00 ffeelingRreming Expense Reimbursement
Willi Paula A.Zeller 170.00 Meeling7rmining Expense Reimbursement
81162 Nan Corey 564.00 MeefngRralning Expense Reimbursement
81163 Orange County Sampson District 14.384.37 Worker's Camp.Relmb,
81164 Soulhem California Edison Company 11,300.22 Construction FE4)544
81165 Y.J.Shad, 100.00 MeefingrTminmO Expense Reimbursement
Total Accounts Payable•Warrants
Payroll Disbursements
33289 - 33388 Employee Paychecks S 143.589.50 Biweekly Payroll 051
33359 - 333M Employee Paychecks 10,809.17 Intend,Payrolls-Various 8 Terminations 61WOOS 8 5/1 WOOS
125628 -126184 Direct Deposit Statements 1,078,599.43 Birmekly Payroll 05110/06
Total Payroll Disbursements $ 1.232.798.10
Wire Transfer Payments
OCSO Payroll Taxes 8 Contribution $ 629,061.46 Biweekly Payroll OWl OMS
Deutsche Bank 488,324.97 Serbs 2006 Certificated;of Participation April Interest Payment
Lloyds TSP Bank plc 81,057.29 Serbs 2001 COPS Standby Purchase Agreement Commitment Fee(02/01I08-05 IMS)
Chase Manhattan Bank 64.411.31 Series 2000 Refunding COPS Standby Cedifcate Purchase Agreement Commitment Fee(02/01/064MOM
JP Mmgan Chase Bank 135.607.50 Series 1993 Refunding Certificates of Pamicipafon Apml interest Payment
Total Wire Transfer Payments 78.468.53
Total Claims Paid 05101106.061161O6 $14,668.236.33
SMRE101aims Pek Ropwll Cbms Pad Repon-05-15 EXHIB�I�TA
PW2i M Page 8 of W'.20 ej
Claims Paid From 081i6/08 to OSf3IM
Warrenllio. Vendor Amount Description
Accounts Payable-Warrants
81166 Air Products&Chemicals i 25,829.07 O&M Agreement Oxy.Gen.Sys.MO 1 8 59
81167 Black&Veatch Corporation 48.154.14 Engineering Services J-77
81168 Cantle Engineers 79,362.83 Professional Servlces 2005-06 Rate Study it
at 169 Carollo Engineers 149,853.20 Professional Services P2-66
81170 City of Fullerton 130.436.66 Cooperative Project Reimbursement Program
81171 GHD,L.L.C. 65.521.00 Professional Services-Asset Management Program
81172 Innedine Engineering 68,055.17 Sewetline Video Inspections-Vanous Locations
81173 Jamison Engineering Contractors,Inc. 41.615.32 Repairs&Maint.Svcs.-Pit.2 Headwork;C Slide Gale Auxiliary Lifting Sys.Project&Ougall Vent Pipe
81174 Kemiron Companies,Inc. 79250.96 Ferric Chloride
81175 Malcolm Pirate.Inc. 159,508.96 Professional Services J-79
81176 MetUs Uk Insurance Company 35.949.24 Group Life,Manager Addl.Life,Shod It Long-Tam Disability&Optional Term Life Ins.
81177 Orange County Business Couxil 25.000.00 Membership
81178 Orange County Water District 9,129,057.94 Joint GWRS Project J-36
81179 Pioneer Americas.Inc. 71,972.10 Sodium Hypociloule
81180 Tule RanWMagan Farms 242.750.01 Residuals Removal MO 3-M95
81181 US Pemxde.L.L.C. 113.787.17 War&Corrosion Control Treatment for Coll.Sys.:Hydrogen Peroxide&Ferrous Chloride
81182 Kiewit Pacific Co. 002.604.00 Construction 5-51&5.52
81183 Saracen Engineering.Inc. 121.698.00 Construction-Manhole Rehabilitation Project 7.21
81184 Shashi Electric.L.P. 491117.00 Conalrudion SP-94
81185 Wells Fargo Bank Mac C73MOl2 66,956.00 Construction 6.51&5-52.Retention
811W A W Chesterton 782.08 Mechanical Pads&Supplies
81187 Absolute Standards,Inc. 384.00 Lab Pads B Supplies
81188 ACE Ergonomics 956.30 Prof.Strikes-Ergonomic Vbddation Evals.;Training,Research,Reports and Office Chair
81109 Advanced Sealing&Supply Co.,Inc. 296.31 Mechanical Pads&Supplies
81190 AT..Sete1y,Inc, 434.85 Safety Supplies
81191 Aligns West 8.40 Demurrage
81192 AlhMed,Inc. 39.45 Ergonomic Computer Supplies +
81193 Amdcan Air Filler,Inc. 835.69 Air Fillers
81194 Amercan Fidelity Assurance Company 344.40 Employee Voluntary Cancer Insurance
81195 American Public Works Association 150.00 Training Registration
81196 Amend Seals West MAI !`caskets I
191197 Amtech Elevator Services 1.400.00 Monthly Elevator Maintenance at PIN.t&2
81198 APpleOme Employment Service 4.826.29 Temporary Employment Services
81199 Applied Industrial Technology 38.19 Mechanical Parts&Supplies
81200 Aquarium Doctor 11621 Human Resources Aquarium Service
81201 Arch Narekss 984.84 Paging Service-Airtime.Service&Equipment
$1202 ASCE Continuing Education 495.00 Meeting Registration-Division 740
81203 Ashbrook Corporation 18.360.13 Filer Press Pads B Supplies
812D4 American Telephone&Telegraph Corp. 26.51 Telephone SeMce
812D5 Awards&Trophies Company 188.99 Awards&Tropism I
812M AWSI 213.00 Department of Transportatkn Program Management Testing
81207 Balk Welk Associates 6.697.62 Professional Services-Sewer Rate Fee Review
81206 Battery Specialties 1.885.53 Batteries
51209 BC Me Rope&Rigging 1,831.32 Mechanical Parts&Supplies
81210 Gmel Financial.Inc.Vo Searing Metal 465.48 Meet
81211 Bell Pipe It Supply Co. 720.20 Mechanical Paris&Supplies
81212 Benz Engineering,Inc. 927.90 Air Filter Cartridge
81213 Blofferieux Vtiek,Inc. $67.85 Lab Paris&Supplies
B1214 Busphedcal Instruments.Inc. 1,319.11 Lab Pads B Supplies
61215 Boyle Engineering Corporation 9.00.03 Professional Services 1-24
81216 Beckmann B Associates.Inc. 1,984.75 Pavement Management Services
N vansculaCELee12XrAP61WiDCYem PW MpwnWUTCNma Pad Roots-MJ11A EXHIBITS
1pk Page 1 of 13 wypgs I`
Claims Paid From OWIMS to OWIMS
Wamarn N. Vendor Assistant Description
81737 Systems Solulion Company 8,778.08 Repairs&Maintenance SeMos-Access Conth&CCTV Seventy System
817M TekSystems 7,917.90 Temporary Employment Services
$1739 The Standard Insurance Company 2.82023 Executive Disability Insurance
81740 Thompson Industrial Supply.Inc. 10.666.18 Mechanical Parts&Supplies
81741 Tony s Lock&Safe Service&Sales 2.052.42 Locks&Keys
81742 Transcat 3.752.81 Instrument Supplies
81743 Trinity Consultants,Inc. 891 Training Registration
817M Truck&Auto Supply.Inc. 1.l MAI Automotive Parts&Supplies
81745 TO Skin 2.800.00 (8)Spray-In Truck Bed Liners
81746 US Fiber Corp. 4.002.92 Service Agreement-Dl Water Systems at Plants 1&2
81747 IIC Regents 8,520.02 Professional SeMces-Strategic Process Study Research Project
81748 Ubra Scientific 121.30 Lab Parts&Supplies
81749 Underground Service Alen of So.Calif 1."4A0 Membership-Underground Utility MenfincatioNNmificalion Service
81750 The Unisource Corporation 2.049.44 Ofte Supplies
81751 United Pacific Services,Inc 1225.00 Landscape Maintenance
81752 United Parfet Service 43.04 Parcel Services
81753 United Pumping Service 1,543.70 Pumping Service
81754 Vapex Inc 2.782.00 Pumps
81755 Verizon Califomia 714.22 Telephone Services
81755 Versus Plumbing 1,015.00 Service Contract-Tesling&Cert.BaGflow Devices at pHs.1 &2&Pump Sta.
$1757 Vortex Corp. 1.229.95 Ellis Exit Gain Repairs
81758 VWR Scientific Products 5.575.34 Lab Pads&Supplies
81759 The Wackenhut Corporation 4.071.54 Sawnty Guards
81760 Waters Corporation 2.147.76 Lab Pans&Supplies
$1761 Weber Scientific 504.32 Lab Parts&Supplies
81762 West Coast Analytical Service.Inc. 265.00 Outside Lab SeMces
81763 West Lee supply company.Inc. 508.02 Electrical Paris&Supplies
81764 Western Slates Controls 196.66 Instrument Pans&Supplies
81765 Valson Supply,Inc. 741.32 Plumbing Pane&Supplies
517N Workfpme Software,Inc. 8.000.00 Professional Services-J-104
81787 XWn Business Solutions.Inc. 9.720.00 Temporary Employment Services
81768 Yale/Chase Materials Handling,Inc. 1.212.16 Electric Can Paris
81769 California Bank&Trust 5,903.00 Construction J-33-IA.Retention
81770 Orange Community Bank 1.084.00 Construction P2.82,Retention
81771 Toney Pines Bank 9A87.20 Construction P1-76,Retention
81"2 Western Pump.Inc. 9,01.20 Construction FE05-34
81773 Jose C.Ani 81 MeelingRralning Expense Reimbursement
81774 Layne T.Baroldi 187.10 Meebng/rmining Expense Reimbursement
81775 Samuel L.Mowbray 516.34 Meelingn-mmull Expanse Reimbursement
81776 Daniel R.Tremblay 106.25 MeelingRraming Expense Reimbursement
81777 County of Orange Auditor Controller 16,090.49 Reimbursement Agreement-Steel Resurfacing Contract
$1778 Orange County Sanitation District 1.225.21 Petty Cash Reimb.
Irmo South Coast Air Quality Management Dist. 1,541.34 Permit Fee-Carbon Odor Control System at Pit.2
81780 The Public Retirement Journal 320.00 Training Registration
$1781 Basic Chemical Solutions,L.L.C. NADS.43 Sodium Bisulfite&Sodium Hydroxide
$1782 Black&Veatch Corporation W8,9417,48 Engineering Services Pt-102&J-100
81783 Brown&Caldwell 380,432.34 Professional Services P2-90
81784 Camp Dresser&Mckee,Inc. 90.315.39 Engineering Service J-71-8&Pt-97
81785 Earth Tech,Inc. 50.354.63 Professional Services Pt-100
81786 Hill Wolhers W.110.69 Chemicals-Odor&Corrosion Control-Newpon Trunkllns
81787 IPMC do Parsons 1.017.937.00 Engirpering Services-Integrated Progra haurolect Management,Temporary Slalfing.Marl.&Supplies
81788 Kemlam Companies,Inc. 97,438.56 Fe MC Chloride
RaIyMxEACELAN SMRegalmx Pab RpermaLTcleima Pea ReWn-osains EXHIBITS
"Im Page 12 of 13 bnw
Claims Paid From OBNBIOS W 05131106
Warrendale. Vendor Amount Desumpi
81685 LA CAD Corporation 1.100.00 Training Registration
81686 LINJER 5,518.45 Professional Service-DART MO 9-22-99
81687 Luccrs Gourmet Foods,Inc. 130.00 Meeting Expense
$1688 Manpower Professional 3.828.00 Temporary Employment Services
81689 Marcom Interactive 1.000.00 Conference Registration-Division 940
81690 Matheson Tri Gas,Inc. 1.356.85 Lab Pals&Supplies
81691 Medlin Controls Co. 1.989.92 Instrument Pala&Supplies
81692 Mission Uniform Service 226.23 Unllorm Remote
$1693 N.GlenK&Son,Inc. 515.78 Reflective Tape
$1694 NeHabit&Associates,Inc, 1.275.00 Training Registration
6160 Neal Supply Co. 862.59 Plumbing Supplies
81696 New Horarods,C.L.C.of Santa Ana 1.400.00 Training Registration
81697 Newark Electronics 763.29 Electrical Pala&Supplies
61698 Ninyo It Moore Corporate Accounting 2.358.00 Professional Services-Soils,Connele&Other Materials Testing Pt-37
81699 The Norco Companies 349.44 Mail Delivery Service
81700 COS Reprographics 264.68 Printing Service-MO 1I26MO
81701 Office Depot Business Services Division 3.433.09 OMce Supplies
81702 Ohson Constro0tion.Inc. 9.754.00 Construction P242
81703 Omega Industrial Supply,Inc. 1.133.16 Jani oral Supplies
81704 Onesounre Distributors,Inc. 1.419.40 Electrical Pals It Supplies
81705 Orange Fluid System Technologies,Inc. 412.65 Plumbing Pads&Supplies
817M Oxygen Service Company 698.75 Lab Pads&Supplies
81707 PAC 619.40 Lab Pans&Supplies
81708 Pacific Mechanical Supply 776.00 Plumbing Pane B Supplies
81709 Peedesa NBping Materials Co. 470.65 Janitorial Supplies
81710 PFE remotions,Inc. 631.93 Ink Carildges
81711 PL Hawn Company,Inc. 183.67 Fig.
81712 Power Bkclro Supply Co.Inc. 50.48 Electrical Pals&Supplies
81713 Pre-Paid Legal Services,Inc. 503.25 Employee Voluntary Legal ServMa Insurance Premium
81714 Primary Source Office Furnishings,Inc. 8,198.15 Office Furniture&Min.Equipment
81716 PROPIPE 9.881.48 Sewerilne Cleaning-City of Tustin&Unincorporated County Property
81716 Prudential Overall Supply 2.980.20 Unitomis&Related AdMJes
81717 Pyramid Fence Company,Inc. 200.00 Fencing Repairs
81718 Relidstar Life Insurance Company 7.843.64 Voluntary Life,Cancer 8 Supplemental Shad-Tenn Disability Insurance
81719 Relnln Instrument,L.L.C. 176.56 Lab Paris&Supplies
81720 Red Valve Company.Incorporated 1,633.16 Mechanical Pads&Supplies
81721 Restek Corp. 1.015.57 Lab Pans&Supplies
81722 RMS Engineering It Design,Inc. 1.020.00 Engineering Services P2-66-3
81723 SCAP 3.000.00 OCSD's Share-Kern County LBigation Fund
81724 Scimeng Blood 44.94 Mechanical Pads&Supplies
81725 See Bird Electronics,Ina. 103.50 Lab Instrument Maintenance&Calibration Services
81726 Seaventures 2.165.15 Ocean Monitoring
81727 Shami Supply Co.,Inc. 5.559.19 Mechanical Pans&Supplies
81728 Shureluck Sales&Engineering 280.05 Mechanical Parts&Supplies
81729 Siemens do Jensen Instrument Co. 3,387.42 Inshumerd Pads&Supplies
81730 SKC West,Inc. 6.818.05 Safety Supplies
81731 Smardan Supply Company 54.84 Plumbing Pans&Supplies
81732 Sohchoice Corp. 8.124.03 SOBware
81733 SPEX Cediprep,Inc. 309.72 Lab Parts&Supplies
81734 Summh Steel 114.97 Metal
81735 Sunset Ford 86.65 Vehicle Parts&Service
61736 Sunset Industrial Parts 148.70 Mechanical Pals&Supplies
Nopel,M CEL&nMcAPSXARDCW4m Pad RPlwmoaanaWlmB Peal Ra,awt 05�3146 EXHIBITS
flM iwd Page 11 of 13 6114cON
Claims Paid From 95116106 to 06131MG
Wamanl Mo. Vendor Amount Description
81737 Systems Solution Company 8.778.08 Repairs&Mairsommoe Services-Access ConiroVCCTV Secuny System
$1738 TekSystems 7.917.00 Temporary Employment Services
01739 The Standard Insurance Company 2.620.23 Executive Disability Insurance
81740 Thompson Industrial Supply,Inc. 10,655.18 Mechanical Pon&Supplies
81741 Tony's Loa&Safe Service Is Sales 2.052.42 Leas&Keys
81742 Transept 3.752.81 Instument Supplies
81743 Trinity Consultants,Inc 899.00 Training Registration
817M Truck&Auto Supply,Inc. 1.170.61 Automotive Pads&Supplies
81743 Tuff Skin 2,800.00 (8)Spray-In Truck Bad Liners
81746 US Filler Corp. 4.002.92 Service Agreement-DI Water Systems at Plante 1&2
81747 LIC Regents 8.520.02 Professional Services-Strategic Process Study Research Project
51748 Ulm Scientific 121.3D Lab Pads&Supplies
51749 Underground Service Alen of So.Calif 1.774.40 Membership-Underground Utility Idea ifmplioNNotificetaen Service
51750 The Unisource Corporation 2,049A4 Office Supplies
$1751 Uniled Pacific Services,Inc. 1,225.001 Landirape Maintenance
817M United Feral Service 43.64 Parcel Services
81753 United Pumping Service 1,543.70 Pumping Service
81764 Vapex Inc. 2.792.00 Pumps
81755 Verizon California 714M Telephone Services
81756 Vemes Plumbing 1,015.00 Service Contract-Testing&Cad.Bacclow Devices at Pits.1 &2&Pump Sta.
81757 Vorlex Corp. 1,229.95 Elge Exit Gals Repairs
$1756 V WR Scentific Products 5,376.34 Lab Paris&Supplies
$1759 The Wackenhut Corporation 4,071.54 Security Guards
SIMI) Walem Corporation 2.14776 Lab Pads&Supplies
81781 Weber Scientific 504.32 Lab Parts&Supplies
$1762 West Coast Analytical Service,Inc. 05.00 Outside Lab Services
81763 Weal We Supply Company,Inc. 508.02 Electrical Paris&Supplies
91764 Waste.States Controls 196.56 Instrument Paris&Supplies
81766 Wilson Supply.Inc. 741.32 Plumbing Paris&Supplies
81760 Workforce Software,Inc. BADD.00 Professional Services-J-104
81767 Xyon Business Solutions,Inc. 9,720.00 Temporary Employment Services
81768 YaaelChase Materials Handling,Inc 1212.18 Elead:Cad Parts
81769 Cali mla Bank&Trust 5.903.00 Construction J-33AA,Retention
81770 Orange Community Bank 1.084.00 Construction P2.82,Retention
81771 Torrey Pines Bank 9,087.20 Cmeri uaen Pid6,Retention
81772 Western Pump,Inc 9,651.20 Construction FE05-34
817M Jose C.Ambri2 88.26 Meetingfframing Expense Reimbursement
81774 Layne T.Barodi 187.10 Meelingfframing Expense Reimbursement
81775 Samuel L.Mowbrey 616.34 Meating/Traming Expense Reimbursement
817M Daniel R.Trembley 106.25 Meeting7fraini g Expense Reimbursement
81777 County of Orange Auditor Contrails, 16,090.49 Reimbursement Agreement-Street Resurfacing Contract
81M Orange County Sanitation District 1,225.21 Petty Cash Reimb.
BIRD South Coast Air Quality Management Mal. 1,541.M Permit Fee-Carbon Odor Control System at Mt.2
81780 The Public Retirement Joumal 320.00 Training Registration
81781 Basic Chemical Solutions,L.L.C. 26.306.43 Sodium Situate&Sodium Hydroxide
81752 Black&Veatch Corporation 626,9Q.48 Engineering Services P1-102&J-100
81783 Brawn&Caldwell 380,432.34 Professional Services P240
$1784 Camp Dresser&Mass,Inc. 90,318.39 Engineering Service J-71-8&P1-97
81786 Earth Tea,Inc. 50,384.63 Professional Services Pi-100
81786 Hill Brothers 36.110.69 Chemicals-Odor&Corrosion Control-Nmw on Trunkline
81787 IPMC do Parsons 1,017,937.00 Engineering Services-Integrated Pro9ram/Prolecl Management.Temporary Stffing,Mail&Supplies
817W Kemiron Companies,Inc. 97,438.56 Ferric Chloride
HWu nuiXCEL da=MPSHARSCIeIms Pad Repots Cbims use Repon-M31Sa EXHIBIT
1 ry 1.& Page 12 of 13 M1w20bd
Claims Pam From 0VISMS to 06A1108
Warrant No. Vendor Amount Description
817M Lee&Rs,Inc. 35,958.55 Professional Services 549
81M M.J.Schin and Associates.Inc. 27.027.02 Engineering Services J-1O0&Cathodic Protection Survey
81791 Malcolm Pimle,Inc. 247.105.18 Professional Samaras P240&1.10
81792 MetLift Lift Insurance Company 35,909.67 Group Life,Manager Add'L Life,Shod&Long-Term Disability&Optional Tom Llh Ins.
81M NRG Thermal Services,L.L.C. 296.730.00 Construction J-79
81794 PlorrearAmedcas,Inc. 110.457.97 Sodium Hypochferits
81795 Polydyne.Inc. 35.864.80 Cationic Polymer MO 3.11-92
817M Synagro West,Inc. 273,599.40 Residuals Removal MO3-29-95
817U Title RanciyMagan From; 267.093.27 Residuals Removal MO 3-29-95
81798 US Metre Group,Inc. 30.172.50 Janitorial&Floor Maintenance at Plants 1 &2
81799 Ameron International 67.653.79 Construction 1-24
81800 ARB,Inc. 527.928.30 Construction 736,7-39&741
81801 DaWe&Sons Constructions,Ina 53,208.50 Cansirucilon P2-654
61802 Denboer Engineering&Construction 54,000.00 Conshucilon P2.664
81803 Fleming Environmental,Inc. 37.512.00 Construction FE0532
81804 J F Shea Construction,Inc. 7.694.639.61 ConsWciion J-77,P2-66&J35-2
81805 J R Filanc Construction 2,131,094.40 Construction P132&Pl-76
81806 Margate Construction,Inc. 524,400.00 Censimcilen P137
81807 M..Meadows Corp. 1.128.740.00 Constmcilon P247-3
81808 Southern Contracting Company 112.161.00 Constmcilon J33-1A
81809 Union Bank of California 58.658.70 Conslmcilon 741&73&Retention
Total Accounts Payable-Warrants $ 30.083.839.17
Payroll Disbumamenls
33395 - 33475 Employee Paychecks S 139,958.41 Biweekly Payroll 0512"S
33476 - 33488 Employee Paychecks 14.732.51 Interim Payrolls-Voids.Reissues,Retro&IDFA Checks WWII&5125106
126185 - 126734 Direct Deposit Statements 1,149,242.66 Biweekly Payroll 06124/O6
Total Payroll Disbursements If 1,303,93J.80
Wife Transfer Payments
OCSD Payroll Taxes&Conmbutions 6 655.005.61 Shyeekly Payroll 05I24106
US Bank 476.574.93 Series 2000 A&B Refunding COPS May Interest Payment
Total Wire Transfer Payments 3 1.132.780.54
Total Claim.Pa1d 05116m6-0 altiB $ 32,820,553.31
H Wepl%r E%CELdx2N PSHAROClelme Ped RepwiQ64Mbima Pod Repp -05J1� EXHIBIT
fi m'. Page 13 of 13 654rKX6
BOARD OF DIRECTORS Mwbng Dare To Bd.of Dir.
06/2a/06
AGENDA REPORT Ilem Number Item Number
1Nu
Orange County Sanitation District
FROM: Lorenzo Tyner, Director of Finance/Treasurer
Originator: Julie Matsumoto, Accounting Manager
SUBJECT: GANN APPROPRIATIONS LIMIT FOR FISCAL YEAR 2006-07
GENERAL MANAGER'S RECOMMENDATION
Adopt Resolution No. OCSD O6-XX, Establishing the Annual Appropriations Limit for
Fiscal Year 2006-07, for the District in accordance with the Provisions of Division 9 of
Title 1 of the California Government Code.
SUMMARY
This routine annual action adopts a resolution establishing the spending limit for
"proceeds of taxes" in accordance with Article XII B of the Constitution of the State of
California (Section 7910 of the Government Code). The District's annual appropriations
are well below the limit.
In 1979, Proposition 4 (the Gann Initiative) was approved adding Article XIII B to the
State Constitution. The provisions of this article place limits on the amount of revenue
that can be appropriated by all entities of government. This initiative was designed to
constrain government expenditures by placing an annual limit on jurisdictions' revenue
and appropriation growth. The Appropriation Limit is based on actual appropriations
during the 1978-1979 fiscal year, as increased each year using specified population and
inflationary growth factors. This annual allowance growth is linked to changes in
population and cost of living. The passage of Proposition 111 in June 1990 amended
Article XIIIB, making changes in the base year upon which the appropriations limit is
based, establishing new cost of living factors and new population factors for use by local
governments, and increasing appropriations not subject to the limit (primarily qualified
capital outlay projects). The financial constraints of Article XIII B apply to the State, all
cities, counties, special districts and all other political subdivisions.
PRIOR COMMITTEE/BOARD ACTIONS
N/A
PROJECT/CONTRACT COST SUMMARY
N/A
ry GOIhWmWWmr4/qnm Fepm1l em,a npmmaogema eeyts`A�.6V,mm Ige)GaMyp,cLimn aoc
R«1. Page 1
BUDGETIMPACT
❑ This item has been budgeted. (Line item: I
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
® Not applicable (information item)
ADDITIONAL INFORMATION
None.
ALTERNATIVES
N/A
CEQA FINDINGS
N/A
ATTACHMENTS
1. Resolution No. OCSD 06-XX
LT:JM:lc
H Agenda ReddeaVCW Board Agenda&Agena R.pdde C Uwn Man GenMpprcUmiaMC
Raeaed oe,w,03 Page 2
i
RESOLUTION NO. 06-14
ESTABLISHING THE ANNUAL APPROPRIATIONS LIMIT FOR FISCAL
YEAR 2006-07 FOR THE ORANGE COUNTY SANITATION DISTRICT IN
ACCORDANCE WITH THE PROVISIONS OF DIVISION 9 OF TITLE 1 OF
THE CALIFORNIA GOVERNMENT CODE
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE ORANGE
COUNTY SANITATION DISTRICT ESTABLISHING THE ANNUAL
APPROPRIATIONS LIMIT FOR FISCAL YEAR 2006-07 FOR THE
DISTRICT IN ACCORDANCE WITH THE PROVISIONS OF DIVISION 9
OF TITLE 1 OF THE CALIFORNIA GOVERNMENT CODE
. . . . . . . . . . . . . .
WHEREAS, Article XIII B of the Constitution of the State of California as proposed by
the Initiative Measure approved by the people at the special statewide election held on
November 6, 1979, provides that the total annual appropriations limit of each local government
agency shall not exceed the appropriations limit of such entity for the prior year, adjusted for
changes in the cost of living and population, except as otherwise specifically provided for in said
Article; and,
WHEREAS, the State Legislature added Division 9 (commencing with Section 7900) to
Title 1 of the Government Code of the State of California to implement Article XIII B of the
California Constitution; and,
WHEREAS, Section 7910 of the Government Code provides that each year the
governing body of each local jurisdiction shall, by resolution, establish its appropriations limit for
the following fiscal year pursuant to Article XIII B at a regularly-scheduled meeting or a noticed
special meeting and that fifteen (15) days prior to such meeting, documentation used in the
determination of the appropriations limit shall be available to the public; and,
WHEREAS, Section 7902 (a) of the Government Code sets forth the method for
determining the appropriations limit for each local jurisdiction for the 2006-07 fiscal year; and,
WHEREAS, the Board of Directors wishes to establish the appropriations limit for fiscal
year 2006-07 for the District.
-1-
1
I
NOW, THEREFORE, the Board of Directors of the Orange County Sanitation District
DOES HEREBY FIND, RESOLVE AND ORDER:
Section 1: That it is hereby found and determined that the documentation used in the
determination of the appropriations limit for the Orange County Sanitation District, for fiscal year
2006-07, was available to the public in the Finance Department of said District at least fifteen
(15)days prior to this date.
Section 2: That the appropriations limit for fiscal year 2006-07 for the Orange County
Sanitation District, as established in accordance with Section 7902(b) of the California
Government Code is$71,515,000 which sum is within the maximum authorized spending
limitation for fiscal year 2006-07.
Section 3: That the Board of Directors of the Orange County Sanitation District, has
determined that the percent change in California per capita personal income from the preceding
year would be the cost of living factor to be used and the weighted average population change of
the cities within the District would be the population factor to be used in calculating the Orange
County Sanitation District's appropriations limit for the Fiscal Year 2006-07.
Section 4: The determination of the appropriation limit is based upon the best and
most complete information available at this time. The District reserves the right to review and re-
establish a new and different limit in the event that it subsequently determines that a modification
of the limitation amount is appropriate.
PASSED AND ADOPTED at a regular meeting held June 28, 2006.
Chair
ATTEST:
Board Secretary
-2-
MINUTES OF STEERING COMMITTEE MEETING
Orange County Sanitation District
Wednesday, May 24, 2006, at 5 p.m.
A meeting of the Steering Committee of the Orange County Sanitation District was
held on Wednesday,April 26. 2006 at 5 p.m., in the District's Administrative Office.
(1) The roll was called and a quorum declared present,as follows:
STEERING COMMITTEE MEMBERS: OTHERS PRESENT:
Directors Present: Kennard R. Smart,Jr., Counsel
Jim Ferryman, Vice Chair
Carolyn Cavecche, Chair, OMTS Committee STAFF PRESENT:
Darryl Miller, Chairman, FAHR Committee Jim Ruth, Interim General Manager
Tod Ridgeway, Chairman, PDC Committee Nick Arhontes, Director of Regional Assets and
Services
Directors Absent: Gail Garrett, Committee Secretary
Steve Anderson, Chair Juanita Skillman
Jim Silva, County Supervisor
(2) APPOINTMENT OF CHAIR PRO TEM
No appointment was necessary.
(3) PUBLIC COMMENTS
There were no comments by any member of the public.
(4) REPORT OF THE COMMITTEE CHAIR
In the absence of Chair Steve Anderson, Vice Chair Ferryman introduced Kennard R. Smart,Jr.who
is attending in Brad Hogin's absence. Mr. Ferryman reminded that nominations for Board Chair for
2006-2007 will be opened at tonight's meeting. A 213 vote of the full Board is needed to adopt the
rate increase.
Bob Ghirelli, Director of Technical Services, and Supervisor Silva attended the CASA Spring
Conference in Lake Tahoe last month. Mr.Anderson and Dr. Ghirelli are currently in Washington DC
to meet with legislative and congressional staff to promote support for District's legislative and grant
programs.
Mr. Ferryman announced the standing committee meeting dates for June. Director Carolyn
Cavecche informed that the OMTS Committee meeting may be cancelled in June. The only planned
Minutes of the Steering Committee
Page 2
May 24, 2006
OMTS action item for June regarding the approval of the Fleet Management Software for Regional
Assets and Services could be moved to the full Board for consideration if the meeting is cancelled.
Board members are invited to attend the PDC Committee meeting on June t"at 5:00 p.m.,or the
FAHR Committee meeting on June W at 5:00 p.m.,to hear the detailed briefing on the proposed
budget.
A Benefits workshop follow-up meeting for the FAHR Committee will be scheduled in mid-June.
(5) REPORT OF THE GENERAL MANAGER
Interim General Manager Jim Ruth reviewed activities included in his May Status Report which was
placed in the Directors' meeting folders that evening. The two-year budget which is based on a
proposed 9.8% rate increase for 2006-07 will be presented to the Board in June. He informed the
two proposed rate increase options will be considered by the Board tonight. Counsel Ken Smart
clarified the 2/3 adoption process.
Mr. Ruth explained that the Succession Plan process has been delayed due to key staff going on
two-week reserve duty. A report will be provided at the next meeting.
Nick Arhontes informed that the District has issued a letter of intent to purchase a 2.5 acre industrial
site in Garden Grove for$6.2 million for the proposed North County Yard. A Purchase and Sale
Agreement will now be negotiated for the Board's consideration in June.
Mr. Ruth, Directors Anderson and Miller, and Dave Ludwin will discuss SARI line funding with the
Orange County CEO on June 8.
The new Performance Evaluation program is a simpler and more effective system. Barry Newton,
Creative Management Solutions, Inc. will brief the Board on the performance evaluation prototype in
June.
Dr. Don Grayson, Management Consultant, has performed a comprehensive assessment of the IT
department.
Mr. Ruth has met with mid-management several times to discuss management leadership training
needs.
(6) REPORT OF GENERAL COUNSEL
Mr. Smart informed the District was served with a lawsuit by Travelers Insurance re a contract issued
in 2000.
(7) CONSENT CALENDAR ITEMS
a. The minutes of the April 26, 2006 Steering Committee meeting were approved as
drafted.
END OF CONSENT CALENDAR
Minutes of the Steering Committee
Page 3
May 24, 2006
(8) ACTION ITEMS
There were none.
(9) INFORMATIONAL ITEMS
a. Strategic Initiatives
Lorenzo Tyner, Director of Finance, gave a brief report on the ten new strategic
initiatives identified by Executive Management as highly strategic. Staff will not
increase resources to implement these initiatives. Any costs associated with the
initiatives are contained within the budget.
In response to Directors' questions, Nick Arhontes, Director of Regional Assets and
Services, briefed the Committee members on Initiative 1, Local Sewer Services as an
example of one of the initiatives. Mr. Ruth assured the Committee that staff will
provide the Board with a time frame and costs for those initiatives that do not overlap
ongoing initiatives.
b. The Agenda Items scheduled to be reviewed by the Board's working committees in
March were reviewed.
C. The agenda items scheduled to be presented to the Board at tonight's meeting were
reviewed.
(10) OTHER BUSINESS. COMMUNICATIONS OR SUPPLEMENTAL AGENDA ITEMS, IF ANY
There were none.
(11) MATTERS WHICH A DIRECTOR WOULD LIKE STAFF TO REPORT ON AT A
SUBSEQUENT MEETING
There were none.
(12) MATTERS WHICH A DIRECTOR MAY WISH TO PLACE ON A FUTURE AGENDA FOR
ACTION AND/OR STAFF REPORT
There were none,
(13) CONSIDERATION OF UPCOMING MEETINGS
The next Steering Committee meeting is scheduled for Wednesday, June 28, 2006 at 5 p.m.
The next Board Meeting is scheduled for Wednesday, June 28, 2006 at 7 p.m.
Minutes of the Steering Committee
Page 4
May 24. 2006 1
(14) CLOSED SESSION
The Committee convened at 6:24 p.m. in Closed Session, pursuant to Sections 54956.9(b)and
54957(b)(1), to discuss three matters. Minutes of the Closed Session are on file with the Board
Secretary. Confidential Minutes of the Closed Session held by the Steering Committee have
been prepared in accordance with Government Code Section 54957.2, and are maintained by
the Board Secretary in the Official Book of Confidential Minutes of Board and Committee Closed
Meetings. A report of the recommended actions will be publicly reported at the time the
approved actions become final.
At 7:00 p.m., the Committee reconvened in regular session.
(15) ADJOURNMENT
The Chair declared the meeting adjourned at 7:00 p.m.
Submitted by:
C
Gail Gartett
Steering Committee Secretary
HVe[lapmOslSYervFp CamWeel2IXTOPb,1&tl SCNNWex GOAFTS.t4'
i
MINUTES OF PLANNING, DESIGN, AND CONSTRUCTION
COMMITTEE MEETING
Orange County Sanitation District
Thursday, June 1,2006, at 5 p.m.
A meeting of the Planning, Design, and Construction Committee of the Orange County
Sanitation District was held on Thursday, June 1, 2006,at 5 p.m., in the Sanitation District's
Administrative Office.
(1) ROLL CALL
The roll was called and a quorum declared present, as follows:
PDC COMMITTEE MEMBERS:
Directors Present: Staff Present:
Tod Ridgeway, Chair Jim Ruth, Interim General Manager
Steve Anderson, Board Chair David Ludwin, Director of Engineering
Charles Antos Bob Ghirelli, Director of Technical Services
Larry Crandall Jim Herberg, Director of Operations and Maintenance
Doug Davert Lorenzo Tyner, Director of Finance
Patsy Marshall John Linder, Engineering Manager
Roy Moore Tod Haynes, Construction Manager
Harty Sidhu Matt Smith, Engineering Manager
Jennifer Cabral, Public Information Specialist
Directors Absent: Jim Burror, Engineering Supervisor
Jim Fenyman, Board Vice Chair Chuck Winsor, Engineering Supervisor
Norm Eckenrode, Vice Chair Brian Bingman, Engineer
Alberta Christy Juanita Skillman, Records Management Specialist
Kymbedy Forman,Acting Committee Secretary
OUTS COMMITTEE MEMBERS:
Ken Parker
Others Present:
Joe Forbath, General Counsel
Jon Hay, Black and Veatch
Mark Miller, Boyle Engineering
(2) APPOINTMENT OF CHAIR PRO TEM
No appointment was necessary.
(3) PUBLIC COMMENTS
There were none.
(4) REPORT OF THE COMMITTEE CHAIR
Committee Chair Tod Ridgeway did not make a report.
PDC Committee Minutes
Page 2
June 1, 2006
(5) REPORT OF THE GENERAL MANAGER
Jim Ruth, Interim General Manager, did not make a report.
(6) REPORT OF THE DIRECTOR OF ENGINEERING
David Ludwin, Director of Engineering, provided brief updates on the Bushard Trunk Sewer
project and pipe procurement, and the Santa Ana River Interceptor line.
Tod Haynes, Construction Manager, briefed the Committee on the status of the construction
activities for the Bushard Trunk Sewer project.
(7) REPORT OF GENERAL COUNSEL
General Counsel did not make a report.
(8) CONSENT CALENDAR
a. APPROVED MINUTES OF PREVIOUS MEETING
Approve minutes of the May 4,2006 Planning, Design, and Construction Committee
Meeting.
b. CHANGE ORDER REPORTS
Action on change orders that require PDC Committee or Board approval will be taken
separately. There are seven change orders this month for PDC approval.
C. PSA AND AMENDMENT REPORT
Action on PSAs and Amendments that require PDC Committee or Board approval will be
taken separately. There were no PSAs and no Amendments approved by the General
Manager from April 21, 2006 through May 18, 2006.
d. FACILITIES ENGINEERING CONSULTANT ACTIVITY REPORT
This report is an information only item.
e. SANTA ANA RIVER INTERCEPTOR RELOCATION AND PROTECTION STATUS
REPORT
This is an information only item.
f. BUSHARD TRUNK SEWER REHABILITATION REPORT
This is an information only item.
MOTION: It was moved,seconded, and duly carried to approve the recommended actions
specified as Items 8(a)through (f).
1
PDC Committee Minutes
• Page 3
June 1, 2006
END OF CONSENT CALENDAR
(9) INFORMATIONAL ITEMS
a. PDC06-61 2006-07 and 2007-08 Proposed Budget
Lorenzo Tyner, Director of Finance, reviewed highlights of the proposed
budget scheduled to be adopted by the Board of Directors at the June 28,
2006 meeting.
b. PDC06-52 66kV Substation at Plant No. 1, Job No. P1-97
Jim Burror, Engineering Supervisor, provided a brief overview of
Addendum No. 1 to the Subsequent Environmental Impact Report which
will be considered by the Board of Directors at their regularly scheduled
meeting on June 28, 2006.
(10) ACTION ITEMS
a. PDC06-53 MOVED, SECONDED AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No.27 to Primary Clarifiers 16-31 and
Related Facilities, Job No. P1-37,with Margate Construction, authorizing
an addition of$314,921, increasing the total contract amount to
$72,676,520.
The Committee directed staff to convey their concern to Margate
Construction regarding their unwillingness to negotiate the cost of the
future changes related to Item 4 that will have to be accomplished on a
time and materials basis.
b. PDC06-54 MOVED, SECONDED AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No. 1 to Rehabilitation of the 14'
Street Pump Station, Contract No. 5-51, and Rehabilitation of the"A'
Street Pump Station, Contract No. 5-52,with Kiewit Pacific Company,
authorizing an addition of$141,364 and 113 calendar days, increasing the
total contract amount to$11,839,144.
C. PDC06-55 MOVED, SECONDED AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No. 8 to Gisler-Redhill Trunk
Improvements, Reach"A', Contract No. 7-36; Orange Trunk
Improvements, Contract No. 7-39; Gisler-Redhill/North Trunk
Improvements, Contract No. 7-41; and City of Tustin Project Nos. 6106
and 6151, with ARB, Inc., authorizing an addition of$497,394 and nine
calendar days, increasing the total contract amount to$20,891,680.
d. PDC06-56 MOVED, SECONDED AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No.7 to Trickling Filter Rehabilitation
and New Clarifiers,Job No. Pt-76,with J.R. Filanc Construction
Company, Inc.,authorizing an addition of$281,732, increasing the total
contract amount to$34.991,510.
PDC Committee Minutes ,
Page 4
June 1, 2006
The Committee requested staff to clarify Orange County Water District's
responsibility for reimbursing Orange County Sanitation District 50 percent
of the costs associated with the Filtrate Pump Station (Item 8). Staff will
respond to the PDC Committee by e-mail early next week.
e. PDCO6-57 MOVED, SECONDED AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No. 13 to Effluent Pump Station
Annex,Job No. J-77,with J.F. Shea Construction, Inc., authorizing an
additional amount of$65,276 and 50 calendar days, increasing the total
contract amount to$44,597,334.
Director Davert Abstained.
f. PDCO6-58 MOVED, SECONDED AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No. 19 to Bushard Trunk Sewer
Rehabilitation, Job No. 1-2-4,with Steve P. Rados, Inc., authorizing a
credit of$4,459,889, decreasing the total contract amount to $30,426,817.
g. PDCO6-59 MOVED, SECONDED AND DULY CARRIED: Recommend to the Board
of Directors to ratify Change Order No. 1 to Bushard Trunk Sewer
Rehabilitation Pipe Procurement,Job No. 1-2-4P,with Ameron
International, authorizing an addition of$184,948 and 15 calendar days,
increasing the total contract amount to$7,884,725.
h. PDCO6-60 MOVED, SECONDED AND DULY CARRIED: Recommend to the Board
of Directors to approve Amendment No. 2 to Professional Services
Agreements with Berryman & Henigar; Brinderson; HDR (CGvL)
Engineers; Dudek&Associates, Inc.; Jacobson Helgoth Consultants, Inc.;
Lee & Ro, Inc.; RMS Engineering & Design, Inc.; South Coast Systems,
Inc.; SPEC Services, Inc.; and Washington Group International for
services related to Facilities Engineering projects, in amounts not to
exceed $200,000 for each agreement extension for a total amount not to
exceed $2,000,000.
(11) CLOSED SESSION
The Committee convened in Closed Session at 6:15 p.m. pursuant to Government Code Section
54956.9 to discuss and consider Agenda Item Nos. 11(a)(1)and (2). Confidential Minutes of the
Closed Session held by the Planning. Design and Construction Committee have been prepared in
accordance with California Government Code Section 54957.2. and are maintained by the Board
Secretary in the Official Book of Confidential Minutes of Board and Committee Closed Meetings.
RECONVENE IN REGULAR SESSION:At 6:40 p.m.,the Committee reconvened in regular session.
(12) OTHER BUSINESS,COMMUNICATIONS OR SUPPLEMENTAL AGENDA ITEMS, IF ANY
There were none.
v
PDC Committee Minutes
Page 5
June 1,2006
(13) MATTERS WHICH A DIRECTOR WOULD LIKE STAFF TO REPORT ON AT A
SUBSEQUENT MEETING
There were none.
(14) MATTERS WHICH A DIRECTOR MAY WISH TO PLACE ON A FUTURE AGENDA FOR
ACTION AND STAFF REPORT
There were none.
(15) FUTURE MEETINGS DATES
The next Planning, Design, and Construction Committee Meeting is scheduled for Thursday,
July 6, 2006 at 5 p.m.
(16) ADJOURNMENT
The Chair declared the meeting adjourned at 7:00 p.m.
Submitted by:
nEwAvalo
Ky bedy Forftn
Acting Committee Secretary
H.Wep0agenda%PDC0006N!nutesl060106 PDC Minutes.doc
1
Meeting Wee To BE.4 Dir.
PDC COMMITTEE owouas OV213106
AGENDA REPORT RanNp11W umnN--b-
PD Db53 13(b)
Orange County Sanitation District
Primary Treatment
FROM: David Ludwin, Director of Engineering
Originator: Michael Puccio, CIP Project Manager
SUBJECT: PRIMARY CLARIFIERS 16-31 AND RELATED FACILITIES,
JOB NO. P1-37
GENERAL MANAGER'S RECOMMENDATION
Ratify Change Order No. 27 to Primary Clarifiers 16-31 and Related Facilities, Job
No. P1-37, with Margate Construction, authorizing an addition of$314,921, increasing the total
contract amount to$72,676,520.
SUMMARY
• Job Number P1-37, Primary Clarifiers 16-31 and Related Facilities, includes the construction
of 16 new primary clarifiers with all support equipment, improvements to existing Primary
Clarifiers 6-15, and improvements to Primary Clarifiers 1-5.
• Brown and Caldwell prepared the plans and specifications and the contract was awarded to
Margate Construction on October 24, 2001.
• This change order includes six items of additional work. There are five non reimbursable
design errors associated with this change order. Liquidated damages on this project are
$3,000 per day and there are no bonus provisions. The project is 93.24%complete.
PRIOR COMMITTEE/BOARD ACTIONS
The contract was awarded by the Board of Directors on October 24, 2001. Please refer to the
attached Change Order Status Report for more information on previous change orders.
PROJECTICONTRACT COST SUMMARY
Original Contract Price $ 70,366,000
Previously Authorized Changes $ 1,995,599
This Change Order(Add) $ 314,921
Change Orders to Date $ 2,310,520
Percentage Increase to Date 3.26%
Amended Contract Price $ 72.676,520
1
BUDGETIMPACT
® This item has been budgeted. (Line item: Section 8, CIP, P1-37, Page 52)
❑ This item has been budgeted, but there are insufficient funds.
❑ This Rem has not been budgeted.
❑ Not applicable (information Rem)
ADDITIONAL INFORMATION
Contract Schedule
Contract Start Date January 7, 2002
Original Contract Completion Date November 7, 2005
Total Number of Change Orders to Date 27
Current Contract Completion Date February 15, 2007
Actual Completion Date N/A
Days Subject to Liquidated Damages 0
Chance Order No. 27 Content
Item Description Amount Days Type
No.
1 Raise Phase 2 Conduits—Additional 879 0 Staff Requested Design
Supports Change
Replace Existing Flow Switch in the Non-reimbursable
2 Polymer Facility 631 0 Design Error
Non-reimbursable
3 Survey Existing Primary Clarifiers 3,4,5 18.176 0 Design Error
Electrical and Mechanical Modifications Non-reimbursable
4 for Primary Clarifiers 3,4,5 273,753 0 Design Error
Modification of Existing Agitation Air Non-reimbursable
5 Piping esi n Emor
Redesign of Primary Clarifiers 1-5 Non-reimbursable
6 Electrical Room 7,728 0 Design Error
Total Change Order $314,921 0
Item 1. This item installs eight additional electrical conduit supports to maintain the required
spacing between supports and to avoid placing supports directly in front of the stairways. A
previous field change order, FCO 283, was issued to supply and install raised unistrut supports
to raise the phase 2 electrical conduits off of the existing concrete deck and to prevent a tripping
hazard. The initial FCO did not address the conflicts between the supports and the stairways.
Item 2. This item replaces an existing flow switch that requires four conductors, with a new flow
switch that only requires two conductors. The contract drawings required the existing conduit
and wiring to be demolished and replaced with two new conductors. However, the existing flow
2
J
switch,which was to be reused, requires four conductors to operate correctly. The new switch
will match all other new flow switches that were installed in the area.
Item 3. This item provides for survey of existing Primary Clarifiers 3, 4, and 5 in advance of a
structural modification in order to coordinate the revised design work. This survey will be used to
verify existing primary clarifier dimensions to prevent costly rework in the field due to unknown
dimensional inconsistencies with the as-built drawings. The structural modifications were not
part of the contract and thus the surveying was not included in the Contractor's bid.
Item 4. This item provides for demolition of the Primary Clarifiers 3, 4 and 5 bridges and
mechanical and electrical services attached to the bridges and replacement of these services on
top of the new flat cover to be installed under the P1-37 contract. The bridges are in conflict
with the new flat covers. The contract drawings did not provide any details for demolishing the
bridges and for relocating the mechanical and electrical services for the three Primary Clarifiers.
Item 5. This Rem provides for the use of 100 flexible pipe couplings to connect the new
agitation air(AA) piping to the existing agitation air piping. The contract drawings incorrectly
identified existing flanges to be used for extending the AA piping when in fact the flanges do not
exist. The flexible pipe couplings were more cost-effective than adding flanges.
Item 6. This Rem provides for demolition of a hom, emergency lighting fixture, electrical
receptacle, and modifications to the electrical room hardware servicing Primary Clarifiers 1
through 5. These items must be abandoned and/or relocated in order for the Contractor to
place a new control panel and a cabinet in the same location.
Additional Clarification for Primary Clarifiers 3,4 and 5(Items 3 and 4)
To reduce the volume of foul air to be treated by the existing odor control system, the P1-37
contract documents indude requirements for replacing the existing dome covers on Primary
Clarifiers 3, 4, and 5 with an option of either flat aluminum covers or flat fabric covers. Although
the bid prices for both options were comparable at bid time, aluminum was selected over fabric
by Sanitation District staff because of the safety benefits for maintenance staff. Since the bid, it
was discovered that additional work to install the aluminum covers is required that was omitted
from the contract documents. The additional work includes demolition, electrical, mechanical
and structural elements and is expected to total approximately$600,000 to $700,000.
Prior to the commencement of this additional work, Sanitation District staff evaluated alternative
methods of accomplishing this work on a low bid basis including adding the cover work to
another project in design or bidding R out as a small project. Both of these options were
estimated to be more expensive than doing the additional work on a P1-37 change order.
ALTERNATIVES
No alternatives are proposed.
CEQA FINDINGS
This project was included in the Strategic Plan EIR that was certified on October 27, 1999. A
Notice of Determination was filed on October 29, 1999.
3
Y
ATTACHMENTS
1. Budget Information Table
2. Change Order Status Report
3. Change Order Performance Report
4. Change Order
5. Location and Photo Description of Change Order
MP:eI
WmlglobaMgenda Draft ReponelPDMP1-37 CO-27AR.dw
4
BUDGET INFORMATION TABLE
Primary Clarifiers No. 16-31 and Related Facilities
Job No. P1-37
ORIGINAL CURRENT PROPOSED PROPOSED FUNDS THIS PROPOSED ESTIMATED ESTIMATED
PROJECTIPHASE AUTHORIZED PROJECT BUDGET REVISED AUTHORIZED AUTHORIZATION TOTAL EXPENDITURE TO EXPENDED
BUDGET BUDGET INCREASE BUDGET TO DATE REQUEST AUTHORIZATION DATE TO DATE(%)
Phase 1 -Pro ecl Development $ 173,000 S 173,000 $ 173,000 $ 173.000 $ 173,000 100%
Phase 2-Preliminary Design $ 317,000 S 317,000 $ 317,000 $ 317.000 $ 317.000 100%
Phase 3-Design $ 4.595.000 S 4.595,000 S 4.595,000 $ 4,595.000 $ 4.626,092 101%
Phase 4-Construction $ 81.974.068 $ 272.749 $ 82,217236 $ 81,928.292 $ 272749 $ 82.071.460 $ 76,411,998 93%
Phase 5-Commissioning $ 396.000 $ 396,000 $ 396.000 $ 396.000 $ 115.812 29%
Phase 6-Closeout $ 61,000 $ 61,000 $ 61.000 S 61,000 $ 11787 19%
Phase 7-Contingency $ 2,243,932 $ 272,749 $ 1,971.183 8
PROJECTTOTAL $ - $ 89,760.000 S - S 89,730,419 S 87,470.292 $ 272,749 $ 87.613.460 $ 81.655.689 93%
Reimbursable Costs
PROJECT NET $ - $ 89,760.000 1$ - $ 89.730.419 1 1 $ 87,470,292 1 $ 272,749 $ 87,613,460 1$ 81,655,689 1 93%
PSAIContract
Desi n PSA 3 6.198.861 $ 6,198.861 11 $ 6,198.861 $ 6.198,861 5 5,994,554 97%
:]
Construction Contract 1 $ 72.088,850 S 272749 $ 72,361,599 1 $ 72,088,850 $ 272749 $ 72.361,599 $ 66.083.086 91%
EDMS'.003807815
CHANGE ORDER PERFORMANCE REPORT
PRIMARY CLARIFIERS 16-31 AND RELATED FACILITIES
JOB NO.P1-37,CHANGE ORDER NO.26
Contractor:MARGATE CONSTRUCTION Project Type:PLANT EXPANSION
Design Consultant:BROWN B CALDWELL Contract%Complete:91.81% Original Contract Price: $70,366.000
CHANGE ORDER TYPES TRACKED INFORMATION ONLY
Reimbursable Design Non-Reimbursable Subto CO Types
Unknoam Condition Staff Requested Change W Errors Design Errors Tracked' Other Total
Change Orders to S700 100% $8.204 0.01% $186.389 0.26% $933.204 1.33% $1,828,741 2.50% ($iD5,891) -0.15% $1,722,650 2.45%
Date
Change Orders $37,221 0.05% $2,61 0.00% $3,110 0.00% S250,806 0.36% $293.74 0.42% ($21,00D) -0.03% $272,749 0.39%
this Period
Change Order Total $730,16 1.05% $10,81 0.02% 3189,499 0.27% $1.184,010 1.68% $2,122.49 3.02% ($126,891) -0.18% $1.995,599 2.114%
'The Change Order Management Plan tmeks the preceding four change order types
EDMti:003W6342
Page 1 of 5
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Margate Construction, Inc. C.O. No.: Twenty Seven (271
Date: June 28, 2006
Job: Primary Clarifiers 16-31 and Related Facilities Job No. P1-37
Consultant: Brown and Caldwell
Amount of this Change Order (Add)(DeducE) $314 921.00
In accordance with contract provisions, the following changes in the contract and/or contract
work are hereby authorized and as compensation, the following additions to or deductions
from the contract price are hereby approved.
ITEM 1 —RAISE PHASE 2 CONDUITS—ADDITIONAL SUPPORTS
This item adds 8 additional electrical conduit supports to maintain the required spacing between
supports and to avoid placing supports directly in front of the stairways. A previous field change
order, FCO 283,was issued to supply and install similar unistrut supports. The added supports
pursuant to FCO 283 and the additional supports added by this item are required to raise the phase 2
electrical conduits to an elevation of 7 feet off of the existing concrete deck to prevent a tripping
hazard for OCSD Operations and Maintenance personnel. The work associated with this Change
Order was negotiated with the Contractor pursuant to Section 48 (B) 1 of the General Requirements
(Reference FCO-P137-283.1).
ADDED COST THIS CHANGE ORDER ITEM: $879.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 2—REPLACE EXISTING FLOW SWITCH IN THE POLYMER FACILITY
This item replaces an existing flow switch that requires 4 conductors with a flow switch that only
requires 2 conductors. The contract drawings required the existing conduit and wiring to be
demolished and replaced with 2 new conductors. The existing switch was incompatible with the new
wiring and this corrects this problem. The work was accomplished on Contractor's force account
pursuant to Section 48 (B) 2 of the General Requirements(Reference FCO-P137-316).
ADDED COST THIS CHANGE ORDER ITEM: $631.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
Page 2 of 5
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728.8127
CHANGE ORDER
Contractor: Maraate Construction, Inc. C.O. No.: Twenty Seven (27)
Date: June 28,2006
Job: Primary Clarifiers 16-31 and Related Facilities, Job No. P1-37
Consultant: Brown and Caldwell
ITEM 3— SURVEY EXISTING PRIMARY CLARIFIERS 3 4 5
This item provides for dimensional survey of existing Primary Clarifiers 3, 4, and 5 not required by the
original contract documents. This survey is necessary to verify existing clarifier dimensions to prevent
costly rework in the field due to unknown dimensional inconsistencies with the as built drawings. This
was done in advance of a proposed structural modification in order to coordinate the revised design
and the Contractor's supplied structural members. The work was accomplished on Contractor's force
account pursuant to Section 48 (B)2 of the General Requirements (Reference FCO-13137-324).
ADDED COST THIS CHANGE ORDER ITEM: $18,176.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 4— ELECTRICAL AND MECHANICAL MODIFICATIONS FOR PRIMARY CLARIFIERS 3.4.5
This item provides for demolition of the existing bridges that provide personnel access and utilities to
the center mechanisms on Primary Clarifiers 3, 4, and 5. Also included in this change is the
demolition and relocation of the electrical and mechanical services that are currently located on the
bridges. These electrical and mechanical services will be relocated to the new aluminum flat covers.
The contract includes provision for replacing the existing dome covers on Primary Clarifiers 3, 4, and
5 with new flat aluminum covers. The existing access bridges were found to be in conflict with the new
flat aluminum covers and must be demolished before installafion of the new covers can proceed. The
contract drawings did not address demolition of the bridges or relocation of the electrical and
mechanical services. The work associated with this Change Order was negotiated with the
Contractor pursuant to Section 48(B) 1 of the General Requirements (Reference FCO-P137-331 and
FCO-P137-335).
ADDED COST THIS CHANGE ORDER ITEM: $273,753.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 5—MODIFICATION OF EXISTING AGITATION AIR PIPING
This item provides for the installation of 100 flexible pipe couplings to connect the new agitation air
piping to the existing agitation air piping. The contract drawings incorrectly identified 100 flanges on
the existing 4 inch agitation air piping as existing when, in fact, the flanges do not exist. It was
necessary to add either couplings or flanges in order for the Contractor to complete base contract
work and the couplings are more cost effective. The work associated with this Change Order was
negotiated with the Contractor pursuant to Section 48(B) 1 of the General Requirements(Reference
FCO-P137-333).
Page 3 of 5
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Margate Construction, Inc. C.O. No.: Twenty Seven (27)
Date: June 28, 2006
Job: Primary Clarifiers 16-31 and Related Facilities, Job No. P1-37
Consultant: Brown and Caldwell
ADDED COST THIS CHANGE ORDER ITEM: $13,754.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 6—REDESIGN OF PRIMARY CLARIFIERS 1-5 ELECTRICAL ROOM
This item provides for demolition of a hom, emergency lighting fixture, electrical receptacle and
modifications to the new electrical panel servicing Primary Clarifiers 1 through 5. The contract
demolition drawings did not show the demolition of these items. These items must be abandoned
and/or relocated in order for the Contractor to place a new control panel and Human-Machine
Interface cabinet in the same location. The work associated with this Change Order was negotiated
with the Contractor pursuant to Section 48 (B) 1 of the General Requirements (Reference FCO-P137-
334).
ADDED COST THIS CHANGE ORDER ITEM: $7,728.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
Additional Clarification for Primary Clarifiers 3, 4 and 5(Items 3 and 4)
To reduce the volume of foul air to be treated by the existing odor control system, the P1-37 contract
documents include requirements for replacing the existing dome covers on Primary Clarifiers 3, 4, and
5 with an option of either flat aluminum covers or flat fabric covers. Although the bid prices for both
options were comparable at bid time, aluminum was selected over fabric by Sanitation District staff
because of maintenance, safety and durability concerns with fabric. In addition, the only fabric cover
manufacturer went out of business after the bid and therefore the selection of the aluminum cover
option was inevitable. Since the contract drawings were designed around fabric covers, additional
work is required to install the aluminum covers including additional demolition, electrical, mechanical
and structural work. The total additional work, including Items 3 and 4 of this change order, is
expected to be approximately $600K to$7001K.
Prior to the commencement of this additional work, Sanitation District staff evaluated alternative
methods of accomplishing this work on a low bid basis including adding the cover work to another
project in design or bidding it out as a small project. Both of these options were estimated to be more
expensive than doing the additional work on a Pt-37 change order.
TOTAL ADDED COST THIS CHANGE ORDER: $314.921.00
TIME EXTENSION THIS CHANGE ORDER: 0 Calendar Days
Page 4 of 5
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 9272MI27
CHANGE ORDER
Contractor: Margate Construction, Inc. C.O. No.: Twenty Seven (27)
Date: June 28, 2006
Job: Primary Clarifiers 16-31 and Related Facilities, Job No. P1-37
Consultant: Brown and Caldwell
The additional work contained in the Change Order can be performed incidental to the prime work and
within the time allotted for the original Contract and any extensions to the Contract time made by this
and all previously issued Change Orders. The Sanitation District and Contractor agree that the added
cost and time described above constitutes full and equitable consideration for all direct costs and time
extension incurred by the Contractor and its subcontractors and suppliers, and that the right to and
amount of any other extra costs caused by or resulting from delays caused by the work pertaining to
Item 4 (FCO 331 and FCO 335), as described in this Change Order, that have been or will be incurred
by the Contractor, except as expressly granted and approved by this Change Order, are reserved by
the Contractor. Nothing contained herein shall be deemed as a waiver by OCSD of the Contractor's
contractual obligations set forth in the Contract with OCSD for this Project, including but not limited to,
Section 52 of the General Conditions and Section 31(1) of the General Requirements.
SUMMARY OF CONTRACT TIME
Original Contract Date: January 7, 2002
Original Contract Time: 1,400 Days
Original Completion Date: November 7,2005
Time Extension this C.O: 0 Days
Total Contract Time Extension: 465 Days
Revised Contract Time: 1,865 Days
Revised Final Completion Due Date: February 15, 2007
Time Subject to Liquidated Damages: N/A
Actual Final Completion Date: N/A
Original Contract Price $ 70,366,000.00
Prev.Authorized $ 1,995,599.00
This Change(Add) (Deduct) $ 314,921.00
Amended Contract Price $ 72,676,520.00
e
Page 5 of 5
ORANGE COUNTY SANITATION DISTRICT
108" ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Margate Construction, Inc. C.O. No.: Twenty Seven (27)
Date: June 28, 2006
Job: Primary Clarifiers 16-31 and Related Facilities, Job No. P1-37
Consultant: Brown and Caldwell
Board Authorization Date: June 28, 2006
ORANGE COUNTY SANITATION DISTRICT
Recommended by:
Michael Puccio, P.E. Date
CIP Project Manager
Approved by:
David A. Ludwin, P.E. Date
Director of Engineering
Accepted by:
MARGATE CONSTRUCTION
Contractor Date
MP:eI
EDM&
PDC COMMITTEE meeting Dare To W.of on.
^y/ 06/01/06 06/28/06
AGENDA REPORT Item Number Item Number
PDC06-54 13(c)
Orange County Sanitation District
1 ColleclIons
�- Facilities
FROM: David Ludwin, Director of Engineering
Originator: Umesh Murthy, CIP Project Manager
SUBJECT: REHABILITATION OF THE 14th STREET PUMP STATION, CONTRACT
NO. 5-51, AND REHABILITATION OF THE "A" STREET PUMP
STATION, CONTRACT NO. 5-52
GENERAL MANAGER'S RECOMMENDATION
Ratify Change Order No.1 to Rehabilitation of the141h Street Pump Station, Contract
No. 5- 51, and Rehabilitation of the "A" Street Pump Station, Contract No. 5-52, with
Kiewit Pacific Company, authorizing an addition of$141,364 and 113 calendar days,
increasing the total contract amount to $11,839,144.
SUMMARY
• This contract is for construction of a new 14th Street Pump Station at 1510 W.
Balboa Boulevard and construction of a new "A" Street Pump Station at 810 W.
Balboa Boulevard in the City of Newport Beach. The existing pump stations have
been operating since the 1930s and do not meet current standards of performance
and safety.
• Lee & Ro, Inc. prepared the plans and specifications, and the construction contract
was awarded to Kiewit Pacific Company on September 22, 2004.
• Change Order No. 1 includes eight items of added work and two items of deleted
work. There is no reimbursable design errors and three non-reimbursable design
errors associated with this change order. The contract includes liquidated damages
of$1000 per day and no bonus provisions.
PRIOR COMMITTEE/BOARD ACTIONS
The contract was awarded to Kiewit Pacific Company by the Board of Directors on
September 22, 2004. Please refer to the attached Change Order Status Report.
Page 1
PROJECT/CONTRACT COST SUMMARY
Original Contract Price: $ 11,697,780
Previously Authorized Change Order: $ 0
This Change Order (Add): $ 141,364
Change Orders to Date: $ 141,364
Percent Increase to Date: 1.21%
Amended Contract Price: $ 11,839,144
BUDGETIMPACT
® This item has been budgeted. (Line item: 2005-06 Budget Book, Page B-25&8-26)
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
The two new pump stations will replace the two existing pump stations that have been
operating since the 1930s.
The new W Street Pump Station will have a capacity of 1.2 mgd. The new 14" Street
Pump Station will have a capacity of 2.6 mgd. Both stations will have enhanced
instrumentation and controls equipment, improving the ability of the District to operate
and maintain the facilities remotely.
Contract Schedule
Contract Start Date: November 10, 2004
Original Contract Completion Date: June 7, 2006
Total Number of Change Orders to Date: 1
Current Contract Completion Date: September 28, 2006
Days Subject to Liquidated Damages: TBD
Liquidated Damages Assessment: N/A
Page 2
Chanoe Order No. 1 Content
Item No. Description Amount Days TPIS
Contract
No. 5-51
Architectural Redesign at 14
1 Street Pump Station $168,767 102 Other
Application of Fusion Bonded Non-reimbursable Design
2 Lining $4,649 0 Error
Inclement Weather Time
3 1 Extension $0 11 Other
Contract
No. 5-52
"A" Street Pump Station Sewer
4 Realignment $11407 0 Other
Staff Requested Design
5 Addition of Vitaulic Couplings $10 308 0 Change
Change in Piping Materials Non-reimbursable Design
6 Inside Pump Station $7 117 0 Error
Contract
No. 6-61
and
No. 6-52
Staff Requested Design
7 Change in Ball Valve Sizing $5 352 0 Change
Credit for Reduction in
8 Tremmie Slab Depth $ 60,000 0 Other
Credit for Removal of Weather Staff Requested Design
9 Stations $ 9,982 0 Change
Submersible Sump Pumps Non-reimbursable Design
10 Classification $3,746 0 Error
Total —Change Order No. 1 $141 364 113
Item 1 —This item is for extra labor, equipment and materials required to enhance the
look of the pump station. The City of Newport Beach requested the contract change in
scope. The changes will make the pump station more compatible with the architecture
of the surrounding buildings in the immediate vicinity.
Item 2 —The layout design for the piping at 14t^ Street Pump Station made it difficult to
apply the fusion bonded lining material to pipe spool areas that had acute angles and
bends. Additional breaks and flanges were provided in the shop to allow for the
application of the lining in the shop.
Page 3
Item 3—This item is to compensate the contractor for additional inclement weather days P
beyond the 12 days included in the contract.
Item 4—This item is for the realignment of the sewer installation scope of work adjacent
to the "A" Street Pump Station site. The City of Newport Beach (City) requested that the
District make the change to mitigate potential odor and construction impacts along with
the interference of a number of undisclosed utilities in the alley and in "A" Street.
Item 5—This item is for the addition of Vitaulic Couplings at "A" Street Pump Station.
These couplings were added at the request of Operations and Maintenance (O&M) to
make it easier for them to access valves and meters for preventative maintenance
reasons.
Item 6—This item is for changing piping materials from carbon steel to stainless steel at
the "A" Street Pump Station (piping penetrations into and out of the wet well). There
was an inconsistency in the contract drawings between the "A" Street Pump Station and
14t" Street Pump Station. At 141" Street Pump Station, these same lines were all shown
to be stainless steel.
Item 7 —This item is for changing the size of the ball valves from 1-inch to 2-inch on the
suction lines for each pump (six). Staff requested the change for preventative
maintenance reasons.
Item 8 —This item is for a credit to reduce the tremmie slab depth from 22-feet to 8-feet
at both "A" Street and 14s' Street Pump Stations. The contractor developed an
alternative method for the shoring system that was accepted by the District.
Item 9 —This item is a credit for the removal of weather stations from both "A" Street
and 14"' Street Pump Stations. Staff elected to arrange for a service contract with an
outside vendor.
Item 10—This item is to change the type of sump pumps at each pump station. The
model number that was included in the contract did not meet the Class 1 Division 2
classification requirement.
ALTERNATIVES
None
Page 4
e CEQA FINDINGS
A Mitigated Negative Declaration was filed with the Clerk-Recorder of the County of
Orange on December, 2002 for Contract No. 5-51. A Mitigated Negative Declaration
was filed with the Clerk-Recorder of the County of Orange on March, 2003 for Contract
No. 5-52.
ATTACHMENTS
1. Budget Information Tables — Contract Nos. 5-51 and 5-52
2. Change Order Status Report
3. Change Order Performance Report
4. Change Order No. 1
5. Photo Description of Change Order
DM:jo:lc:bm
HMlglobaMgenda Draft RepoftTDU"l &5.52 Agenda Report D92204 2.doa
Page 5
BUDGET INFORMATION TABLE
Rehabilitation of the 14th Street Pump Station
CONTRACT NO.5-51
ORIGINAL CURRENT PROPOSED PROPOSED FUNDS THIS PROPOSED ESTIMATED ESTIMATED
PROJECTIPHASE AUTHORZ 9UDGEED PROJECT REVISED AUTHORIZED TO AUTHORIZATION TOTAL EXPENDITURE EXPENDED TO
BUDGET BUDGET INCREASE BUDGET DATE REQUEST AUTHORIZATION TO DATE DATE(%)' '-
(DECREASE
Phase Pro c1 Dmla menl $ 8,965 $ 9,000 S 9,000 $ 9000 $ 9,000 S 8,965 100%
Phase 2-Pmfthvq OnIgn S 41000 S 41000 S 41,000 S 4L000 $ 41.000 $ 41510 101%
Phase 3.Daign S 1.113,1581 S 1.367.000 S 1,307.000 $ 1.307.000 $ 1,3117,0001 S 1,372,000 100%
Phm4-Consmu n S 2,907142 S 6,949,989 S 142974 S 7092963 $ 5949.909 S 143974 $ 7092950 $ 5.501.377 78%
Phge S-Cammlubn S 123.707 S 1GO,000 $ 100.000 S HIS000 $ 100.000 $ 350 0%
PS S-CbeeAut S 30,927 S 34000 S 341000 $ 34000 S 34000 0%
Phase]-Lan S 391654 S 387.011 S 142971 S 244,037 �_', $ - $ - 5
PROJECTTOTAL S 4,615.753 S 3,509,000 S - $ CUOMO $ 8500.989 $ 142,974 S 0.043,963 S aRVI' @ 00%
Reimbumabb Coe%
PROJECT NET $ 4,616.753 1 S 8.888.000 S - $ 8.888,000 11 S 8.500.989 I S 142,974 $ 8,643,963 1 3 6,924.302 60%
PSA/Contmal
DmIm PSA S 242795 $ 948,059 1 S -IS 949.853 1 $ 949,853 1$ - S 949,559 S 622,901 67%
Ca dbi,Comw 5 2,370729 1 S 0038490 1 S 142.974 S 5,181,454 'i:,;'.. S 6,030.490 1 S 142974 S 0181484 S 4500.000 1 73%
EOM8:0035055N
BUDGET INFORMATION TABLE
Rehabilitation of the"A"Street Pump Station
CONTRACT NO.5-52
ORIGINAL CURRENT PROPOSED PROPOSED FUNDS THIS PROPOSED ESTIMATED ESTIMATED,:
BUDGET PROJECTIPNABE gUTUDGETD PROJECT BUDGET AUTHORIZED TO AUTHORIZATION TOTAL EXPENDITURE EJI DATEj%TO.
INCREASE GUOOEt BUDGET /pECREA3E BUDGET GATE REQUEST gUTHORI2AT10N TO GATE OATEI%) ,
P0na I-Pjed O Praanl S 15.112 3 18000 $ 16,000 $ 16,000 S 16,000 $ 16,182 101%
Phne 2-PvO.Inaq Dn n 3 71000 $ 134.000 3 151000 S 134000 $ 134,n0 a 134A25 100%
Phan 3-Dean S 15160n S 1.920.0001 S 1920000 S 1,920000 $ 1.920,000 3 1.927901 1 100%
Phan 4-Con flan $ 2,831093 $ 6.961577 E (1.6101 $ 0549,967 $ 65515]] S 0,610 $ 8649907 S 6200000 79%
Phase 5-Commisslontna S 125,035 S 113000 S 113,000 S 119000 E 113.00 $ 1440 13%
Phan 6-Cbw-Out S 31.08 S 34000 S 34,000 -'r. S 34,000 S 34000 0%
Phan]-CoMln $ 323.096 $ 314,423 3 1610 $ 316,033 $ . 6 E
PROJECT TOTAL $ 5,012,685 3 9.003.000 S - 6 9,083,000 ":- $ 8.768,677 S 1610 S 8988,967 S 7,293,132 639%
RelmOumbla Coats
PROJECT NET S 5,012,685 1 S 9,083.000 1 $ - S 9.093,000 11 S 876S.R7 1 E 1610 $ 8,766.E67 1 S 7,293,132 83%
P&AlContrect
Deal nPER is 23]]90 1$ 1177.830 $ - $ 11]]830 ✓a $ 1177830 $ - 0 11770.T0 $ 1002,850 85%
ntr CouMn Conlract 6 2,931360 3 5659.290 E 1610 S 5657,680 S 5.659.290 S 181 S 5667
6n S 4,600,000 80%
EMS:00310409
CHANGE ORDER STATUS REPORT
REHABILITATION OF THE 14TH STREET PUMP STATION
REHABILITATION OF THE "A" STREET PUMP STATION
CONTRACT NOS. 5-51 AND 5.52
APPROVAL CONTRACT CONTRACT COST PERCENTAGE AUTHORIZED AUTHORIZED TIME
ITEM DATE COST TO DATE INCREASE TIME TO DATE
(DAYS) (DAYS)
CONTRACT 11/10/2004 $11,697,780 $11,697,780 0.00 575 575
CO NO. 1 Pending $141,364 $11,839,144 1.21% 113 688
EDMS:003808830
CHANGE ORDER PERFORMANCE REPORT
REHABILITATION OF THE 14TH STREET PUMP STATION
REHABILITATION OF THE"A"STREET PUMP STATION
CONTRACT NOS.5-51 AND 5-52,CHANGE ORDER NO.1
Contractor.KIEWIT PACIFIC COMPANY Project Type:COLLECTIONS
Design Consultant LEE S RO Contract%Complete:70% ..'nee�s61tlV1fnc'' g11,697,780
CHANGE ORDER TYPES TRACKED INFORMATION ONLY
Reimbursable Design NowRalnbursable Design Subtotal CO Types
Unknown Condition t1bM Requested Change Emm Errom Tracked' Other Total
kOrder
$0 0.DO% $5,678 0.05% $0 0.00% $16,612 0,13% $21,190 0.16 $120,174 1.03% $141.364 1.21%
$0 0.00% $0 0.00% $0 0.00% $0 0.00% $0 O.OD% $0 0.00% $0 0.00%
$00.00% $6.678 0.06% $0 0.00% $15,512 0.13% $21,190 0.18 $120.174 1,03% $141,364 1.21%
<3.00% 1.00% 0.00% < 1.00% c5.00% 0.00% c5.00%
Performance Goals
The Change Order Management Plan tracks the preceding bur change order types
EDMS:003808832
a
Page 1 of 7
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Kiewit Pack Company C.O. No.: One 1
Date: June 28, 2006
Job: Rehabilitation of the 140 Street Pump Station: Contract No. 5-51: and
Rehabilitation of the "A" Street Pump Station, Contract No. 5-52
Consultant: Lee& Ro. Inc.
Amount of this Change Order(Add) $141,364.00
In accordance with contract provisions, the following changes in the contract and/or contract
work are hereby authorized and as compensation, the following additions to or deductions
from the contract price are hereby approved.
Contract No. 5-51
ITEM 1 —ARCHITECTURAL REDESIGN AT 14T STREET PUMP STATION
This item is for extra labor, equipment and materials required to implement the change in the scope of
work defined in the plan change titled "l40 Street Architectural Redesign (Revision No. 4), dated
03128/09. The City of Newport Beach requested the aforementioned contract change in scope. The
extra work consisted of revising the architectural rendering or appearance for the pump station
building, Including revisions to the roof outline of the building to incorporate a short tower structure,
installing false glass windows, providing a decorative balcony feature on the south side of the building
with roof canopy and aluminum hand railings, modifications to the landscaping in front of the building,
reconfigure the irrigation system, adding a decorative field stone feature to the south landscaping
wall, etc. These changes will require alterations to the roof structural steel framing, CMU wall layout,
HVAC duct layout, electrical wiring changes, including revisions to the layout of electrical equipment.
The additional work for this item was accomplished by a negotiated price pursuant to Section No.
44(B)l of the General Requirements (Reference FCO No. 0020).
ADDED COST THIS CHANGE ORDER ITEM: $168,767.00
TIME EXTENSION THIS CHANGE ORDER ITEM: *102 Calendar Days
"NOTE: The contractor has reserved its rights to submit a time impact analysis for this Item at a later
time to support the extension of the completion date of the contract and to ascertain what portion of
the time extension is a compensable time delay.
ITEM 2—APPLICATION OF FUSION BONDED LINING
This item is for the application of fusion bonded lining material that could not be performed during the
normal shop fabrication procedure. The design layout of the pipe spools were either too long or had
difficult to reach angles. Several breaks in the steel pipe had to be inserted between pipe spool
bends and in the long pipe runs, since the application wand used In the coating process was only 6-
feet long and was not flexible enough to bend around 90 degree turns. The details and/or limitations
of the fabrication process were not known during design. The extra costs were primarily for the
installation
Page 2 of 7
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Kiewit Pack Company C.O. No.: One 1
Date: June 28, 2006
Job: Rehabilitation of the 10 Street Pump Station: Contract No. 5-51: and
Rehabilitation of the'A' Street Pump Station, Contract No. 5-52
Consultant. Lee& Ro. Inc.
and welding of flanges to provide the required breaks in the pipe. The additional work for this item
was accomplished by a negotiated price pursuant to Section No. 44(B)l of the General Requirements
(Reference FCO No. 009).
ADDED COSTS THIS CHANGE ORDER ITEM: $4,649.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 3—INCLEMENT WEATHER TIME EXTENSION
Item No. 7 of the Special Provisions in the bid documents includes 12 calendar days for inclement
weather for the time of final contract completion. There have been 11 inclement weather working
days beyond the 12 days included in the contract, which is equivalent to a total of 23 calendar days.
Pursuant to Section 48 of the General Conditions, an extension of time for 11 calendar days is
granted to the contractor for inclement weather days as of April 17, 2006.
ADDED COSTS THIS CHANGE ORDER ITEM: $0.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 11 Calendar Days
Contract No. 5-52
ITEM 4—"A" STREET PUMP STATION SEWER REALIGNMENT
This Rem is for extra labor, equipment and material costs to proceed with the scope of work defined in
the plan change titled "A" Street Pump Station Sewer Realignment— Final Drawings" dated 03/09/06.
The City requested the change in alignment to mitigate potential odors,the interference of a number
of undisclosed utilities in an adjacent alley and in "A" Street, and the vibration of sheeting (shoring) in
the alley to reduce the risk of damage to adjacent properties (i.e. original design was deeper versus
the redesigned shallower sewer in the alley). The extra work consisted of the installation of in-line
bypasses, additional traffic control, support of undisclosed utilities, re-channel of manhole bases and
core drilling, installation of another 60-inch manhole, etc. The additional work for this item was
accomplished by a negotiated price pursuant to Section No. 44(B)l of the General Requirements
(Reference FCC NO. 0019).
ADDED COSTS THIS CHANGE ORDER ITEM: $11,407.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
Page 3 of 7
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Kiewit Pacific Companv C.O. No.: One 1
Date: ,tune 28, 2006
Job: Rehabilitation of the 141° Street Pump Station Contract No. 5.51: and
Rehabilitation of the"A" Street Pump Station, Contract No. 5-52
Consultant: Lee& Ro. Inc.
ITEM 5—ADDITION OF VITAULIC COUPLINGS
This item is for the addition of eight Vitaulic Couplings at"A" Street Pump Station. Operations and
Maintenance (O&M) requested that the contractor install the couplings in order to disassemble valves
and flow meters when required for preventative maintenance. The O&M Staff believed that the hard
piped valves and meters would be difficult to unbolt and disconnect due to the long runs of pipe that
would have to be loosened and removed. The use of couplings would also minimize the time the
station would have to be shut down and the length of time that bypass pumping would be required.
The extra work included cutting the pipe, handling of pipe, grooving the ends, patching and repairing
the fusion bounded epoxy interior lining, and the installation of the couplings. The additional work for
this item was accomplished by a negotiated price pursuant to Section NO. 44(B)l of the General
Requirements(Reference FCO NO. 0015).
ADDED COSTS THIS CHANGE ORDER ITEM: $10,308.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 6—CHANGE IN PIPING MATERIALS INSIDE PUMP STATION
This item is for changing the piping materials inside the"A" Street Pump Station from carbon steel to
stainless steel. The impacted lines are the three suction lines from the flare in the wet well to the
flange at the plug valves, the two 8-inch drain lines from the force main to the wet well, and for the
4-inch recycle line from the force main to the wet well. There was an inconsistency in the contract
drawings. The 10 Street Pump Station showed these same lines to be stainless steel, but"A" Street
Pump Station plans showed them to be carbon steel. Staff elected to use stainless steel for the
aforementioned piping due to the proximity of the corrosive gases coming from the wet well. The
extra costs are for material price differences and for pipe fabrication. The additional work for this item
was accomplished by a negotiated price pursuant to Section No. 44(B)l of the General Requirements
(Reference FCO NO. 008).
ADDED COSTS THIS CHANGE ORDER ITEM: $7,117.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
Page 4 of 7 u
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Kiewit Pacific Company C.O. No.: One(1)
Date: June 28, 2006
Job: Rehabilitation of the 141° Street Pump Station: Contract No. 5-51: and
Rehabilitation of the W Street Pump Station, Contract No. 5-52
Consultant: Lee& Ro. Inc.
Contract No. 6-61 and No. 652
ITEM 7—CHANGE IN BALL VALVE SIZING
This item is for labor and material to change the size of six ball valves from 1-inch to 2-inch including
extra fittings and pipe for the drain valves, located on each pump suction line for both pump stations.
There was a conflict in the contract drawings; in some locations the valves were shown as 1-inch, and
in other locations the valves were shown as 2-inch. The Staff directed the contractor to install the
2-inch valves to minimize clogging when draining and cleaning the pipe. The additional work for this
item was accomplished by a negotiated price pursuant to Section No. 44(B)l of the General
Requirements (Reference FCO No. 006).
(50 percent to Contract No. 5-51, $2,676)
(50 percent to Contract No. 552, $2,676)
ADDED COSTS THIS CHANGE ORDER ITEM: $5,352.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 8—CREDIT FOR REDUCTION IN TREMMIE SLAB DEPTH
This hem is a credit for both pump stations to reduce the designed tremmie slab depth from 22-feet to
8-feet, which was part of the pump station shoring system. The tremmie slab is a bottom seal
designed to resist uplift forces. The contractor's shoring design firm determined through analysis that
it was feasible to reduce the concrete slab depth from 22-feet to 8-feet by use of an alternative
construction method, which lowered project risk and costs (i.e., ground anchors). District staff
reviewed the contractor's analysis of the tremmie slab depth and found their analysis acceptable. The
shoring design provided in the bid documents was to provide a basis of payment for bid purposes.
The District was aware of alternative and other acceptable shoring methods. The credit for this item
of work was accomplished by a negotiated price pursuant to Section No. 44(B)l of the General
Requirements(Reference FCO No. 001).
(50 percent to Contract No. 5-51, $(30,000))
(50 percent to Contract No. 5-52, $(30,000))
CREDIT THIS CHANGE ORDER ITEM: $(60,000.00)
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
F
Page 5 of 7
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Kiewft Pacific Company C.O. No.: One 1
Date: June 28, 2006
Job: Rehabilitation of the 140 Street Pump Station: Contract No. 5-51; and
Rehabilitation of the"A" Street Pump Station Contract No 5-52
Consultant: Lee& Ro. Inc.
ITEM 9—CREDIT FOR REMOVAL OF WEATHER STATIONS
This item is a credit for the removal of weather stations, as designed for the"A" Street Pump Station
and the 140 Street Pump Station. The design intent for having weather stations at each pump station
is as follows: 1) They would provide rain data that could be correlated to changes in the pump station
flows, before, during, and after an individual storm event; and 2) They could provide data for future
modeling efforts. After further evaluation, District Staff decided it would be more efficient and cost
effective to arrange for a service contract with an outside vendor. The credit for this item of work was
accomplished by a negotiated price pursuant to Section No. 44(B)l of the General Requirements
(Reference FCO No. 002).
(50 percent to Contract No. 5-51, $(4,991))
(50 percent to Contract No. 5-52, $(4,991))
CREDIT THIS CHANGE ORDER ITEM: $(9,982.00)
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 10—SUBMERSIBLE SUMP PUMPS CLASSIFICATION
The submersible sump pumps located in the dry well and included in the contract specifications are
required to be rated for a Class 1 Division 2 classification. Specific manufacturers with model
numbers that were listed in the specifications as or equal bid items, did not comply with this
classification requirement. Therefore, the contractor's supplier was able to provide an alternate type
or model of pump that meets the classification requirements. The additional work for this item was
accomplished by a negotiated price pursuant to Section No. 44(B)l of the General Requirements
(Reference FCO No. 007).
(50 percent to Contract No. 5-51, $1,873)
(50 percent to Contract No. 5-52, $1,873)
ADDED COSTS THIS CHANGE ORDER ITEM: $3,746.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
TOTAL ADDED COSTS THIS CHANGE ORDER: $141,364.00
TOTAL TIME EXTENSION THIS CHANGE ORDER: 113 Calendar Days
9
Page 6 of 7
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Kiewit Pacific Company C.O. No.: One 1
Date: June 28, 2006
Job: Rehabilitation of the 10 Street Pump Station; Contract No. 5-51: and
Rehabilitation of the"A" Street Pump Station, Contract No. 5-52
Consultant: Lee& Ro. Inc.
The additional work contained within this change order can be performed incidental to the prime work
and within the time allotted for the original contract and any extensions to the contract time made by
this change order and all previously issued change orders. It is, therefore, mutually agreed that a 113
calendar day extension of time to perform the work is required for this change order, and that no direct
or indirect, incidental or consequential costs, expenses, losses or damages have been or will be
incurred by the Contractor, except as expressly granted and approved by this change order.
SUMMARY OF CONTRACT TIME
Original Contract Date: November 10, 2004
Original Contract Time: 575 Calendar Days
Original Completion Date: June 7, 2006
Time Extension this C.O.: 113 Calendar Days
Total Contract Time Extension: 113 Calendar Days
Revised Contract Time: 688 Calendar Days
Revised Final Completion Due Date: September 28, 2006
Time Subject to Liquidated Damages: TBD
Actual Final Completion Date: N/A
Original Contract Price $ 11,697,780.00
Prev.Authorized Changes $ 0.00
This Change (Add) (Deduct) $ 141,364.00
Amended Contract Price $ 11,839,144.00
Page 7 of 7
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Kiewit Pacific Company C.O. No.: One 1
Date: June28. 2006
Job: Rehabilitation of the 10 Street Pump Station: Contract No. 5-51, and
Rehabilitation of the"A" Street Pump Station, Contract No. 5-52
Consultant: Lee& Ro. Inc.
Board Authorization Date: June 28, 2006
ORANGE COUNTY SANITATION DISTRICT
Recommended by:
Umesh Murthy, P.E. Date
CIP Project Manager
Approved by:
David A. Ludwin P.E. Date
Director of Engineering
Accepted by:
Kiewit Pacific Company
Contractor Date
EDMS:00380BB33
PDC COMMITTEE meeting Date TO Bd.01Dir.
06101/06 OG/28106
AGENDA REPORT own Numbe Itan Number
PDC06-55 131d1
Orange County Sanitation District
Collectim
raett•ttee
FROM: David A. Ludwin, Director of Engineering
Originator: Hardat Khublall, CIP Project Manager
SUBJECT: GISLER-REDHILL TRUNK IMPROVEMENTS, REACH "A", CONTRACT
NO. 7-36; ORANGE TRUNK IMPROVEMENTS, CONTRACT NO. 7-39;
GISLER-REDHILL/NORTH TRUNK IMPROVEMENTS, CONTRACT
NO. 7-41;AND CITY OF TUSTIN PROJECT NOS. 6106 AND 6151
GENERAL MANAGER'S RECOMMENDATION
Ratify Change Order No. 8 to Gisler-Redhill Trunk Improvements, Reach "A", Contract
No. 7-36; Orange Trunk Improvements, Contract No. 7-39; Gisler-Redhill/North Trunk
Improvements, Contract No. 741; and City of Tustin Project Nos. 6106 and 6151, with
ARB, Inc., authorizing an addition of$497,394 and nine calendar days, increasing the
total contract amount to $20,891,680.
SUMMARY
• Contract No. 741 located in the City of Tustin, City of Orange, and unincorporated
areas of the County of Orange, consists of improvements to relieve hydraulic
deficiencies on the Gisler-Redhill North Trunk Sewer along Newport Avenue, El
Camino Real, and Prospect Avenue. Contract No. 7-39 is located in the City of
Tustin and in the unincorporated areas of the County of Orange, and consists of
improvements to relieve hydraulic deficiencies on the Orange Trunk Sewer along
Holt Avenue, 17" Street, and Hewes Avenue. Contract No. 7-36, located in the City
of Tustin, consists of improvements to relieve hydraulic deficiencies on the Gisler-
Redhill Trunk Sewer Improvements along Redhill Avenue from Mitchell Avenue to
La Colina Drive. The 1999 Strategic Plan identified these reaches of sewers as
hydraulically deficient and in need of replacement.
• AKM Consulting Engineers prepared the plans and specifications and the
construction contract was awarded to ARB, Inc. on January 28, 2004.
• Change Order No. 8 includes nine items of added work to Contract No. 7-36,
Contract No. 7-39, and Contract No. 741. There is one nonreimbursable design
error and no reimbursable design errors associated with this change order. The
contract includes liquidated damages of$1,000 per day and no bonus provisions.
The contract is now 94% complete.
Page 1
PRIOR COMMITTEE/BOARD ACTIONS ,
The construction contract was awarded by the Board of Directors on January 28, 2004 '
for a lump sum amount of $18,375,999. Please see attached Change Order Status
Report for information on all previous change orders.
PROJECTICONTRACT COST SUMMARY
Original Contract Price $ 18,375,999
Previously Authorized Change Order $ 2,018,287
This Change Order (Add) $ 497,394
Change Orders to Date $ 2,515,681
Percent Increase to Date 13.69%
Amended Contract Price $ 20,891,680
BUDGETIMPACT
® This item has been budgeted. (Line item: Contract No. 7-39 FY 05/06, Section 8, page
36, and Contract No. 741 FY 05/06, Section 8, page 38 Capital Improvement Program,
Collections Facilities, Facilities Engineering Projects-Collections)
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
Contract Schedule
Contract Start Date April 5, 2004
Original Contract Completion Date November 25, 2005
Total Number of Change Orders to Date 8
Current Contract Completion Date March 31, 2006
Days Subject to Liquidated Damages 35
Liquidated Damages Assessment TBD
Page 2
Chanae Order No. 8 Content
Item No. Description Amount Days Type
Contract
No. 7-41
1 Inspection Fees City of $ 22,393 0 Other
Oran e
2 Fiber Optic Cable Conflicts, $243,996 0 Unknown
Sta. 124+50 To 159+40. Conditions
3 Additional Final Asphalt, Sta. $ 151,344 0 Unknown
72+29 To Sta. 107+50 Conditions
Contract
No. 7-39
& 7-36
Inspection Fees City of Tustin
4 Contract 7-36: $24,200 0 Other
Contract 7-39: $3,300
Contract
No. 736
Sewer Installation
5 Postponement, October 8, $28,500 0 Other
2005.
6 Additional 8-inch Lateral, Sta. $19,377 0 Unknown
14+75. Conditions
Electrical and Unknown
7 Communications Duct Bank, $4,284 1 Conditions
Sta. 30+50
8 Inclement Weather Time $0 8 Other
Extension.
9 Reduction in Retention $0 0 Other
Total —Change Order No. 8 $ 497,394 9
Item 1 —This item is to compensate the ARB, Inc. (Contractor) for paying inspection
fees required by the City of Orange. The amount provided in the contract documents
was expended in inspection fees required by the City of Tustin. All work within the City
of Orange has been completed.
Item 2 —This item is for additional costs due to an undisclosed Fiber Optic Cable
Encasement (FOCE) that conflicted with the proposed sewer alignment between sewer
stations 124+50 to 159+40. The FOCE is owned by Leve13 Communications and
Qwest Communications, and was installed within the Prospect Avenue public right-of-
way in a location that conflicted with the Sanitation District's existing sewer alignment
that the Contractor was required to use to install the proposed sewer. This cost will be
reimbursed through an agreement between Level 3 Communications and the Sanitation
District. The reimbursement agreement was approved by the Board of Directors at
the July 20, 2005 meeting. The FOCE was not shown on the design drawings because
it was installed after the design was completed by the Sanitation District's design
consultant. In addition, Leve13 Communications constructed their facilities within the
Page 3
Sanitation District's existing sewer trench envelope without the permission of the City of
Tustin and the County of Orange, and contrary to the permitted location that they were
assigned.
Item 3—This item is for additional final paving on Prospect Avenue from Miller Drive to
17th Street intersections, sewer stations 72+29 to 107+50. The proposed sewer
alignment was rerouted to avoid conflicts with an existing City of Tustin 6-inch asbestos
cement waterline that was incorrectly shown in contract drawings and an undisclosed
FOCE. As a result of the sewer alignment modifications, additional paving was required
to comply with City of Tustin final paving requirements.
Item 4—This item is to compensate the Contractor for paying inspection fees required
by the City of Tustin. The amount provided in the contract documents was expended in
inspection fees required by the City of Tustin. Work within the City of Tustin is 95%
complete and this deposit is expected to cover inspection fees for the remaining work.
Item 5 —This item is for standby costs due to a two-week postponement of the sewer
installation work at Redhill Avenue between Mitchell Avenue and Nisson Road
intersections, sewer stations 9+91.52 to 20+45.90. The City of Tustin did not authorize
the start of construction work under Contract 7-36 on September 24, 2005, until all work
under Contract No. 7-41, within the City of Tustin right of way was completed. This
included punch list items and final asphalt paving. Contract documents do not require
that completion of punch list items and remaining work on other contracts are a
condition to start work under Contract No. 7-36. A time extension for this item was
granted under Item 11 of previous Change Order No. 7, which was approved by the
Board of Directors at the April 26, 2006 Meeting.
Item 6—This item is for additional costs associated with the connection of an
undisclosed 8-inch sewer lateral found at sewer station 14+75. The sewer lateral
provides service to an apartment complex located at 14160 Redhill Avenue, and was
not shown in contract drawings.
Item 7—This item is a negotiated settlement for the additional costs to tunnel under an
existing electrical cable duct bank that was located at approximate sewer station 30+50,
During construction, it was found that the duct bank was located 3-feet below surface,
4-feet wide and 6-feet deep in size. The actual duct bank was much deeper and wider
than was shown on the contract drawings requiring additional tunneling work to install
the sewer line.
Item 8 —This item is to compensate the Contractor for additional inclement weather
days beyond the 15 days included in the contract.
Item 9—This item is for a reduction of retention from 10% to 5% at the request of the
contractor. This contract consist of five separate areas of work described as Contract
Nos. 7-36, 7-39, and 7-41, and Project Nos. 6106 and 6151. Work is complete on all
areas in accordance with contract requirements except Contract No. 7-36, which is 95%
complete. All contract work is anticipated to be complete in June of 2006
Page 4
ALTERNATIVES
None
CEQA FINDINGS
This project was included in the 1999 Strategic Plan Program Environmental
Impact Report certified on October 27, 1999. A Notice of Determination was filed on
October 29, 1999.
ATTACHMENTS
1. Budget Information Table— Contract No. 7-36
2. Budget Information Table— Contract No. 7-39
3. Budget Information Table—Contract No. 741
4. Change Order Status Report
5. Change Order Performance Report
6. Change Order
7. Location and Photo Description of Change Order No. 8
RC:eh
H:WglobaR4genda Daft ReportSTDCV-36 AR GO#8 6-28-06.dw
Page 5
l�
BUDGET INFORMATION TABLE
GISLER-REDHILL TRUNK IMPROVEMENTS, REACH "A"
CONTRACT NO. 7-36, CO#8
PROPOSED
ORIGINAL CURRENT auooEr PROPOSED - FUNDS "is PROPOSED ESTIMATED F.SiIIMIAT,ED
PR '.,
OJEGTA'HASE AUTNORI2ED PROJECT INCREASE REVISED - AUTMORIZ•EO TO AUINORIZA'f10N TOTAL EXPENDITURE EXPENOEU TO
BUDGET BUDGET .,.IDECREASE -BUDGET DATE REgUEST. AUTNOR WTON ' Tp DATE DATEI°SI
Phase 1 -Pro ed Development $ 45,000 $ 29.810 $ 29.810 $ 29,810 S 29.810 $ 29.810 100%
Phase 2-Prelimine Design $ 1,504 $ 1,504 $ 1.504 $ 1,504 $ 1,504 100%
Phase 3-Desi n $ 369.000 1 S 581.679 1 $ 581.679 $ 581.679 $ 581,679 1 $ 581,679 100%
Phase 4-Canslmcli0n $ 6,386,000 S 5.903.241 $ 76.361 $ 5,979.602 $ 5,903,241 $ 78,381 $ 5,979.602 S 2,954.268 49%
Phase 5-Co..issioning $ 94,272 $ 94,272 $ 94,272 $ 94.272 $ 14,449 15%
Phase 6-Close-Ou1 $ 23.050 $ 23,050 (' S 23,050 $ 23,050 $ 442 2%
Phase 7-Contincency $ 1.032.000 $ 423.877 8 76,361 $ 347.515
PROJECTTOTAL $ 7,832.000 S 7,057.433 $ - $ 7.057.433 -::n $ 6.633,556 $ 76,361 $ 6,709.917 S 3,582,152 53%
Reimbursable Costs
PROJECT NET 1 $ 7,832,000 1 $ 7,057,433 $ - $ 7.057.433 $ 6.633.556 $ 76,361 1 $ 6,709.917 1 $ 3.582,152 1 53%
PSAIContract
Desi n PSA $ 223,176 1$ 331,522 $ 331.522 7:P $ 331,522 5 331,522 1 $ 320485 97%
Conseudion Contrail $ 6.385.090 1$ 5.208,127 1$ 76,361 1 $ 5,284,488 �} $ 5,208,127 1 $ 76,361 1 $ 5.284,488 1 $ 3.993,166 1 76%
EONS.003WB738
C� n
BUDGET INFORMATION TABLE
ORANGE TRUNK IMPROVEMENTS
CONTRACT NO. 7-39, CO#8
ORIGINAL CURRENT PROPOSED PROPOSED FUNDS THIS PROPOSED ESTIMATED ' ESTIMATED
BUDGET
PROJECT/PRASE AUTHORIZED PROJECT REVISED AUTHORIZED TO AUTHORIZATION i TOTAL EXPENDITURE 'EXPENDED.TOI
INCREASE
BUDGET BUDGET /DECREASE BUDGET DATE REQUEST AUTHORIZATION TO GATE DAT21%)� ..
Phase 1 -Pro'ed Develo menl $ 46.000 S 46.564 $ 46,564 S 46.564 $ 46,564 $ 46.564 100%
Phase 2-Preliminary Design S 1,000 $ 1.391 $ 1,391 $ 1,391 $ 1,391 $ 1,391 100%
Phase 3-Desi n $ 396,000 $ 411.471 $ 411,471 $ 411.471 $ 411,471 $ 411.471 100%
Phase 4-Construction $ 4,250.000 S 4761,334 8 3,300 $ 4,764,634 $ 4.761,334 $ 3,300 $ 4.764.634 $ 4.764,275 100%
Phase 5-C...Issioning $ 61,000 $ 61,735 $ 61.735 $ 61,735 $ 61.735 $ 37735 61%
Phase 6-Close-O l $ 17,000 $ 15,434 $ 3,300 $ 12,134 $ 15,434 $ 3,300 $ 12,134 $ 3.505 29%
Phase 7-Contingency $ 527.000 S $ - $
PROJECTTOTAL $ 5,298,000 $ 5.297,929 $ - $ 5,297,929 $ 5,297,929 $ - $ 5,297.929 $ 6,264.941 99%
Reimbursable Costs
PROJECT NET S 5,298,000 1 $ 5,297,929 $ - $ 5297,929 'a $ 5,297,929 1 $ - $ 5,297,929 1 $ 5.264,941 1 99%
PSAIContraet
Desi n PSA 1 $ 224,098 $ 235.238 1 5 235,238 $ 235.238 $ 235,238 1 $ 235.238 100%
Construction Cenlracl is 4.113,733 1 $ 4,289,054 $ 3,300 1 $ 4,292,354 1 ] $ 4,289,054 $ 3,300 1 $ 4.292,354 1 $ 4,282,098 100%
EDMS: 003808741
CI -
BUDGET INFORMATION TABLE
GISLER-REDHILLINORTH TRUNK IMPROVEMENTS
CONTRACT NO. 7-41, CO#8
PROPOSED
oRIGINAL CURRENT PROPOSED FUNtl3. ,TI118 PROPOSED ESTIMATED, E87t1}1ATE0
PROJEOTIPHABE'' AUTHORIZED ED PROJECT REVISED '. AUTNDATE TAUTHORIZATION TOTAL EXPENDITURE E%bENOEO TO.
INCREASE GATE(%I ;. BUDGET BUDGET DATE REQUEST AUTHORIZATION TO DATE BUDGET
IDECREABE -
Phase 1-Project Development S 40000 $ 41,000 $ 41,000 $ 41A00 S 41000 $ 39.736 97%
Phase 2-Preftinag Design S 1.000 8 18.000 $ 18,000 $ 18,000 $ 18000 $ 15,429 as%
Phase 3-Deslan S 628.000 $ 680.000 S 680,000 $ 680,000 $ 680,000 S 644,071 95%
Phase 4-Construction S 13128.000 S 15,632717 $ 417.T33 $ 16.050,450 $ 15632,717 $ 417733 $ 16.050460 $ 13,381.575 83%
Phase 5-Commissionhg $ 183.000 S 216,000 $ 216,000 $ 216,000 S 216.000 S 21,283 10%
Phase 6-Close-Out It 45000 S 46,000 S 46,000 S 46000 $ 46,000 $ 3,305 7%
Phase 7-Contingency S 1.334.000 $ 858283 $ 417,733 It 440,550 $
PROJECT TOTAL $ 15.359.000 $ 17,492,000 $ - $ 17,492,000 S 16,633,717 S 417,733 $ 17,051,450 $ 14,105,399 1 83%
Reimbursable Costs $ 749,495 1 $ 749,495 $ 749,495 1 $ 749.495
PROJECT NET S 15,359,000 1 $ 16.742.505 $ - $ 16,742,505 " $ 15,884.222 $ 417.733 $ 16,301.955 $ 14,105,399 1 87%
PSAIContract
Des' nPEA $ 368,684 $ 420641 $ 420.641 11 $ 420,641 S 420641 1 S 415.530 99%
Construction Contract 1 $ 9,350,612 $ 12.092.637 S 417,733 $ 12.510,370 11 $ 12,092,637 $ 417,733 1 $ 12,510.370 S 10.922,232 1 87%
EDMS: 003808740
-Reimbursement from City of Tustin&Level 3 Communications
CHANGE ORDER STATUS REPORT
GISLER-REDHILL TRUNK SEWER IMPROVEMENTS, ORANGE TRUNK SEWER IMPROVEMENTS, AND
GISLER-REDHILL NORTH TRUNK SEWER
CONTRACT NOS. 7-36, 7-39, AND 7-41
AND CITY OF TUSTIN PROJECT NUMBERS 6106 AND 6151 - CO #8
APPROVAL CONTRACT CONTRACT COST PERCENTAGE
AUTHORIZED AUTHORIZED TIME
ITEM DATE COST TO DATE INCREASE TIME TO DATE
(DAYS) (DAYS)
CONTRACT 112812004 $18,375,999 $18,375,999 0.00% 600 600
CO NO. 1 11/24/2004 $349,612 $18,725,611 1.90% 20 620
CO NO. 2 2/23/2005 $169,223 $18,894,834 2.82% 15 635
CO NO. 3 4/27/2005 $571,975 $19,466,809 5.94% 20 655
CO NOA 7/20/2005 $493,263 $19,96b,072 8.62% 9 664
CO NO.5 9/28/2005 $209,252 $20,169,324 9.76% 21 685
CO NO.6 2/22/2006 $55,000 $20,224,324 10.06% 5 690
CO NO.7 4/26/2006 $169,962 $20,394,286 10.98% 27 717
CO N0.8 Pending $497,394 $20,891,680 13.699% 9 726
EDMS:
CHANGE ORDER PERFORMANCE REPORT
GISLER-REDHILL TRUNK SEWER IMPROVEMENTS,ORANGE TRUNK SEWER
AND GISLER-REDHILL NORTH TRUNK SEWER,CONTRACT N0S.7.36,749,AND 741
AND CITY OF TUSTN PROJECT NUMBERS 0106 AND 6151
CHANGE ORDER N0.8
CentracMr ARE,INC Project Type:C0LLECTIONS
Di eign Consultant:AKM CONSULTING ENGINEERS Contract%Complete:84 Original Contract Price: $1837S.999
CHANGE MOM TYPES TRACKED INFORMATION ONLY
RNmburesble Design Non4lahrbunsbN subtotal CO Types
Unknown Len411bn $1aNRa9wsN0 Change E. Weign Ewers Tracked' ONar Teed
Change Orden 3419,001 2,28% SO OAO% $0 O.W% $0 0.00 $419,001 2.28% 378,393 0.43% $497,394 2.71%
N P INedod
Change Orden to $1,085.188 SAM $197,071 1.07% $0 0.0054 $376,57 2.04% 31.837.829l8.91% $380,458 2.0]% $2,016.287 10,98%
D
Chang.Order Total $1,484,189 8.03% $19],071 1A7% $0 0.00% $375,570 2.04% $2,058,89 11.1941, $458,851 2.50% $2,515,881 13,69%
Program c3.00% <1.00% 000% c1.00% <5.00% 0.00% cS.W%
Performance Goad
Tea Chang.OMer Menegemeni Plan backs the preceaiw lour Ewnp pNer types
EDMSe003909764
Version 311n008
t Page 1 of 7
ORANGE COUNTY SANITATION DISTRICT
108" ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: ARB, INC. C.O. No.: Ei ht 8
Date: June 28, 2006
Job: Gisler Redhill North Trunk Sewer. Reach "A". Contract No. 7-36: Oranae
Trunk Improvements,Contract No. 7-39,Gisler Redhill/North Trunk Sewer Improvements'
Contract No. 7-41: and City of Tustin Proiecl Numbers 6106. and 6151
Consultant: AKM Consulting Engineers
Amount of this Change Order(Add) $497,394.00
In accordance with contract provisions, the following changes in the contract andlor contract
work are hereby authorized and as compensation,the following additions to or deductions
from the contract price are hereby approved.
Contract No. 7-41
ITEM 1 —INSPECTION FEES CITY OF ORANGE
This Rem compensates the Contractor for paying for inspection fees required by City of Orange under
Encroachment Permit No. 12270. The original amount provided in the Contract Documents was
expended in permit and inspection fees required by the City of Tustin. During construction, the City of
Orange requested the Contractor to pay for all inspection costs until project completion. All work
within the City of Orange has been completed. Fees were used to cover City of Orange's project
inspection, attendance at construction meetings, review of revised traffic control plans, traffic control
signal services, overtime work and final project inspection. This item was determined by the
Sanitation District pursuant to Division 1, Section 44(B)l of the General Requirements (Reference
FCO 82).
ADDED COST THIS CHANGE ORDER ITEM: $22,393.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days per OCSD
ARB reserving its rights as noted herein.
ITEM 2—FIBER OPTIC CABLE CONFLICTS, STA. 124+50 TO 159+40.
This item is for additional costs due to an undisclosed Fiber Optic Cable Encasement(FOCE) that
conflicted with the proposed sewer alignment between sewer stations 124+50 to 159+40. During
construction, the FOCE was found to interfere with the proposed sewer alignment. The FOCE is
owned by Level3 Communications and Qwest Communications, and was installed within the Prospect
Avenue public right-of-way in a location that conflicted with the Sanitation District's existing sewer
alingment that the Contractor was required to use to install the proposed sewer. The additional work
consisted of excavation, FOCE protection, equipment standby, additional slurry backfill and additional
asphalt replacement. This item was accomplished by Contractor's Force Account and was
determined by Sanitation District pursuant to Division 1, Section 44(B)2 of the General Requirements
(Reference FCO 45).
ADDED COST THIS CHANGE ORDER ITEM: $243,996.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days per
Page 2 of 7 °
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: ARB, INC. C.O. No.: Ei hl 8
Date: June 28, 2006
Job: Gisler Redhill North Trunk Sewer, Reach'K. Contract No. 7-36, Orange
Trunk Improvements Contract No.7-39: Gisler RedhilVNorth Trunk Sewer Improvements:
Contract No. 7-41: and City of Tustin Project Numbers 6106. and 6151
Consultant: AKM Consulting Engineers
OCSD; ARB reserving its rights as
noted herein.
ITEM 3—ADDITIONAL FINAL ASPHALT, STA. 72+29 TO STA. 107+50
This item compensates the contractor for additional final paving on Prospect Avenue from Miller Drive
to 17° Street intersections, sewer stations 72+29 to 107+50. The proposed sewer alignment was
rerouted between stations 72+29 and 107+50 to avoid conflicts with utilities encountered that were
either not shown on the contract drawings or found to vary from the location shown on the contract
drawings. The conflicting utilities are an existing 6-inch asbestos cement(AC)waterline that was
incorrectly shown on contract drawings between sewer stations 72+29.33 to 107+00, and an
undisclosed fiber optic encasement located between sewer stations 102+70 to 166+08. As a result of
these sewer alignment modifications, the City of Tustin final pavement requirements resulted in
additional final paving. The additional work consisted of additional grinding and installation of
additional paving. This item was accomplished by Contractor's Force Account and was determined
by Sanitation District pursuant to Division 1, Section 44(B)2 of the General Requirements (Reference
FCO 58).
ADDED COST THIS CHANGE ORDER ITEM: $151,344.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days per
OCSD; ARB reserving its rights as
noted herein.
Contract No. 739&736
ITEM 4—INSPECTION FEES CITY OF TUSTIN
This item compensates the Contractor for payment of additional inspection fees required by the City of
Tustin under Public Right of Way Encroachment and Construction Permit No. 3888. The original
amount provided in the Contract Documents was expended by the City of Tustin. An additional
deposit was requested to cover future costs. Funds are used to cover project inspection, attendance
at construction meetings, additional reviews of revised traffic control plans, traffic control signal
services, overtime work and final project inspection. Work within the City of Tustin is 95% complete
and this deposit is expected to cover inspection fees for the remaining work; after project completion,
funds not used by the City of Tustin will be reimbursed to the Sanitation District. This item was
determined by Sanitation District pursuant to Division 1, Section 44(B)1 of the General Requirements
(Reference FCO 84).
ADDED COST THIS CHANGE ORDER ITEM: $27,500.00
° Page 3 of 7
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor. ARB. INC. C.O. No.: Ei ht 8
Date: June 28, 2006
Job: Gisler Redhill North Trunk Sewer. Reach"K. Contract No. 7-36, Orange
Trunk Improvements.Contract No.73W Gisler Redhill/North Trunk Sewer Improvements:
Contract No. 741, and CRY of Tustin Proiect Numbers 6106, and 6151
Consultant: AKM Consulting Engineers
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days per OCSD
ARB reserving its rights as noted herein.
Contract No. 7-36
ITEM 5— SEWER INSTALLATION POSTPONEMENT, OCTOBER 8, 2005.
This Rem is to compensate the Contractor for equipment standby costs due to a two-week
postponement of the sewer installation work at Redhill Avenue between Mitchell Ave and Nisson
Road intersections, sewer stations 9+91.52 to 20+45.90. The contractor was delayed by 17 days
because the City of Tustin (City) did not allow the Contractor to start construction work under Contract
7-36 on September 24, 2005, until all work under Contract No. 7-41 was completed within the City
right of way, including punch list items and final asphalt paving. Contract documents do not require
that completion of punch list items and remaining work on other portions of the Contracts are a
condition to start work under Contract 7-36. The additional costs consist of equipment standby during
the two weeks standby period. A time extension for this item was granted by the Sanitation District to
the Contractor under item 11 of previous Change Order No.7,which was approved by the Board of
Directors at the April 26, 2006 Meeting. This Rem was accomplished by Contractor's Force Account
and was determined by Sanitation District pursuant to Division 1, Section 44(B)2 of the General
Requirements (Reference FCO 53).
ADDED COST THIS CHANGE ORDER ITEM: $28,500.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days per OCSD
ARB reserving its rights as noted herein.
ITEM 6—ADDITIONAL 8-INCH LATERAL, STA. 14+75
This item is for the extra cost associated with the connection of an undisclosed 8-inch sewer lateral
found at sewer station 14+75. During construction the contractor found an existing 6-inch sewer
lateral that was not shown on contract drawings. The sewer lateral provides service to an apartment
complex located at 14160 Red Hill Avenue. The additional costs consist of connecting the existing
8-inch sewer lateral to the proposed sewer and relocating a sewer manhole from sta. 15+00 to 14+75
which was not built at the time the 8-inch lateral was found. This Rem was accomplished by
Contractors Force Account and was determined by Sanitation District pursuant to Division 1, Section
44(B)2 of the General Requirements (Reference FCO 60).
ADDED COST THIS CHANGE ORDER ITEM: $19,377.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days per OCSD;
Page 4 of 7
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728.8127
CHANGE ORDER
Contractor. ARB. INC. C.O. No.: Eight(8)
Date: June 28, 2006
Job: Gisler Redhill North Trunk Sewer Reach W. Contract No. 7-36 Orange
Trunk Improvements,Contract No.7-39; Gisler Redhill/North Trunk Sewer Improvements:
Contract No. 7-41• and City of Tustin Proiect Numbers 6106 and 6151
Consultant AKM Consulting Enoineers
ARB reserving its rights as noted herein.
ITEM 7—ELECTRICAL AND COMMUNICATIONS DUCT BANK, STA. 30+50.
This item is a negotiated settlement for the additional cost to tunnel under an existing electrical and
communications cable duct bank that was located at approximate sewer station 30+50. During
construction it was found that the existing electrical and communications cable duct bank was located
3-feet below surface, and was 4-feet wide by 6-feet deep in size. Although the location of the duct
bank was shown on the contract drawings, the size and exact depth of the duct bank was not shown.
The Contractor claimed that this size of duct bank could not be anticipated and additional tunneling
was required. This is a negotiated settlement between the Sanitation District and Contractor for all
costs related to this item, and the Sanitation District and Contractor have agree that a 1-day time
extension to the contract is required as a result of this item. This item was accomplished by
Contractor's Force Account and was determined by Sanitation District pursuant to Division 1, Section
44(B)2 of the General Requirements(Reference FCO 74).
ADDED COST THIS CHANGE ORDER ITEM: $4,284.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 1 Calendar Day per OCSD
ARB reserving its rights as noted herein.
ITEM 8—INCLEMENT WEATHER TIME EXTENSION.
Item No.7 of the Special Provisions of the Bid Documents includes 15 calendar days of inclement
weather for the time of final completion. There have been 23 inclement weather working days beyond
the 15 days included in the contract, which are equivalent to 32 calendar days. A total time extension
of 24 calendar days was granted previously to the contractor in prior Change Orders Nos .4, 6 and 7.
Pursuant to Section 48 of the General Conditions, an additional extension of time for the completion of
8 calendar days is granted to the Contractor for inclement weather days as of March 10, 2006.
ADDED COST THIS CHANGE ORDER ITEM: $ 0.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 8 Calendar Days
Page 5 of 7
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: ARB, INC. C.O. No.: Eight 8
Date: June 28, 2006
Job: Gisler Redhill North Trunk Sewer. Reach "A". Contract No. 7-36: Orange
Trunk Improvements,Contract No.7-39:Gisler Redhill/North Trunk Sewer Improvements:
Contract No. 7-41: and City of Tustin Project Numbers 6106, and 6151
Consultant: AKM Consulting Engineers
ITEM 9—REDUCTION IN RETENTION
This contract consists of five separate portions of work described as Contract Nos. 7-36, 7-39 and
7-41 and Project Nos. 6106 and 6151. Work is now 95%complete under Contract No. 7-36 and
100%complete under Contract Nos. 7-39 and 7-41, and Project Nos. 6106 and 6151. Staff
recommends a reduction of the retention withheld from 10% to 5%.
ADDED COST THIS CHANGE ORDER ITEM: $0.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
TOTAL ADDED COSTS THIS CHANGE ORDER: $497,394.00
TOTAL TIME EXTENSION THIS CHANGE ORDER: 9 Calendar Days
Page 6 of 7
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728.8127
CHANGE ORDER
Contractor. ARB INC. C.O. No.: Eight 8
Date: June 28, 2006
Job: Gisler Redhill North Trunk Sewer. Reach "A". Contract No. 7-36: Orange
Trunk Improvements,Contract No.7-39: Gisler Redhill/North Trunk Sewer Improvements:
Contract No. 7-41: and City of Tustin Project Numbers 6106. and 6151
Consultant: AKM Consulting Engineers
The compensation set forth in this change order comprises the total compensation due to the
contractor by OCSD, including all of contractor's subcontractors and suppliers, for the direct cost to
perform the work or change described in this Change Order, but does not include any compensation
for contractor's, or its subcontractors and suppliers, extra costs caused by or resulting from delays,
impacts (including productivity impacts) and/or disruptions arising out of, related to and/or caused by
the work or change described in this change order, if any. By executing this change order, contractor
shall not be deemed to waive its right to seek additional time and/or compensation for delays, impacts
(including productivity impacts) and/or disruptions arising out of, related to and/or caused by the work
or change described in this Change Order, all such rights and/or claims are hereby expressly
reserved by Contractor for itself and its subcontractors and suppliers. Nothing contained herein shall
be deemed as a waiver by OCSD of the contractor's contractual obligations set forth in the contract
with OCSD for this project.
SUMMARY OF CONTRACT TIME
Original Contract Date: April 5, 20G4
Original Contract Time: 600 Calendar Days
Original Completion Date: November 25, 2005
Time Extension this C.O.: 9 Calendar Days
Total Contract Time Extension: 126 Calendar Days
Revised Contract Time: 726 Calendar Days
Revised Final Completion Due Date: March 31, 2006
Time Subject to Liquidated Damages: TBD
Actual Final Completion Date: N/A
Original Contract Price $18.375.999.00
Prev. Authorized Changes $ 2,018,287.00
This Change(Add) $ 497,394.00
Amended Contract Price 120,891,680.00
' Page 7 of 7
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: ARB, INC. C.O. No.: Ei ht 8
Date: June 28, 2006
Job: Gisler Redhill North Trunk Sewer. Reach "A". Contract No. 7-36: Orange
Trunk Improvements,Contract No. 7-39:Gisler Redhill/North Trunk Sewer Improvements:
Contract No. 741, and City of Tustin Project Numbers 6106, and 6151
Consultant AKM Consulting Engineers
Board Authorization Date: June 28, 2006.
ORANGE COUNTY SANITATION DISTRICT
Recommended by:
Hardat Khublall, P.E. Date
CIP Project Manager
Approved by:
David A. Ludwin P.E. Date
Director of Engineering
Accepted by:
ARB, INC.
Contractor Date
EDMS:OMBO fi23
PDC COMMITTEE 17n,Done ro ad0l)
O610,106 061j8106
AGENDA REPORT Rem Number Item Number
PDC06-56 13(e)
Orange County Sanitation District
kSecondary Treatment
FROM: David Ludwin, Director of Engineering
Originator: Dean Fisher, CIP Project Manager
SUBJECT: TRICKLING FILTER REHABILITATION AND NEW CLARIFIERS,
JOB NO. P1-76
GENERAL MANAGER'S RECOMMENDATION
Ratify Change Order No. 7 to Trickling Filter Rehabilitation and New Clarifiers,
Job No. P1-76, with J.R. Filanc Construction Company, Inc., authorizing an addition of
$281,732, increasing the total contract amount to $34,991,510.
SUMMARY
• Job No. P1-76, Trickling Filter Rehabilitation and New Clarifiers, includes the
construction of two new trickling filters and clarifiers, a pump station, a meter vault,
and all support equipment and piping.
• Black &Veatch prepared the plans and specifications and the contract was
awarded to J.R. Filanc Construction Company, Inc. on March 26, 2003.
• Change Order No. 7 includes eight items of additional work. There are two
nonreimbursable design errors and no reimbursable design errors associated with
this change order. Liquidated damages on this project are $3,000 per day and
there are no bonus provisions.
PRIOR COMMITTEEIBOARD ACTIONS
The contract was awarded to J.R. Filanc Construction Company, Inc. by the Board of
Directors on March 26, 2003. Please refer to the attached Change Order Status Report
for information on previous change orders.
PROJECTICONTRACT COST SUMMARY
Original Contract Price $ 33,037,000
Previously Authorized Changes $ 1,672,778
This Change $ 281,732
Change Orders to Date $ 1,954,510
Percentage Increase to Date 5.92%
Amended Contract Price $ 34,991,510
w„,b: 01M= Page 1
A significant portion of the work added to this project originated from the design of the
future Plant No. 1 secondary treatment projects, Job Nos. P11-102 and P1-82. Staff
determined that the inclusion of this work would avoid future conflicts and Y
constructability, issues while resulting in a cost savings to the overall construction
program. It should be noted that of the $1,954,510 change orders to date, $1,205,507
is attributed to "other" projects. If the "other" category is excluded, the total change
order percentage for P1-76 is 2.27%. Please refer to the attached Change Order
Performance Report.
BUDGETIMPACT
® This item has been budgeted. (Line item: section 8, CIP, 131-76)
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
Please refer to attached Budget Table for additional information.
ADDITIONAL INFORMATION
Contract Schedule
Contract Start Date June 2, 2003
Original Contract Completion Date February 26, 2006
Total Number of Change Orders to Date 7
Current Contract Completion Date February 26, 2006
Estimated Completion Date May 30, 2006
Days Subject to Liquidated Damages 0
Change Order No. 7 Content
Item Description Amount Days Type
No.
1 Chemical Piping to Trickling Filter $63,680 0 Staff Requested
Junction Box No. 1 Design Change
2 Upsize Plant Water Pipe at SUS $6170 0 Staff Requested
PumpStation Design Chan e
3 60-inch Pipe Thrust Supports $14,874 0 Non-reimbursable
Design Error
4 Install 72-inch Barrel and Pipeline $7 806 0 Unknown Condition
Sludge Removal
5 Exhaust Stack Modifications $4,743 0 Non-reimbursable
Design Error
6 Pipe Encasement at PEJB 48 and $.t 377 0 Unknown Condition
604nch Pipelines
7 484nch Vent Modifications $5,762 0 Unknown Condition
8 Filtrate Pump Station $174,320 0 Staff Requested
Design Change
Total Change Order No. 7 1 $281,732 0
a,� Page 2
Item 1 — is for the addition of two bleach lines from the new bleach facility to the new
Y Trickling Filter Secondary Effluent Junction Box 2. The bleach lines are to allow for
disinfection of the trickling fitter effluent when it is discharged to the ocean outfall. The
beach lines were not included in the original contract documents because the new
bleach facility was designed at the same time as the new trickling filter facility and it was
agreed to include the connection during construction once the proper locations and
tie-ins could be finalized.
Item 2 — is to upsize the plant water line which feeds into the trickling filter sludge and
scum pump station to allow for greater clean out capacity of the sludge and scum lines.
This Rem was requested by the Orange County Sanitation District operations staff
based on their experience with secondary sludge and scum lines. The original design
included a one-inch hose bid connection to help clean out the 8-inch line but based on
the experience of staff, the hose bib connection should be upsized to 4-inches in order
to adequately clean out a significant clog.
Item 3— is for the addition of pipe thrust supports on the 60-inch pipeline located at the
trickling filter pump station. The thrust supports will keep the flexible couplings from
separating when downstream valves are closed. The original contract documents did
not include the pipe thrust supports.
Item 4— is for the fabrication and installation of a 72-inch barrel (pipe form) within the
existing Junction Box B to remediate corrosion issues found within the structure.
Additionally, this Rem includes the removal of large amounts of sludge found within the
structure prior to fabricating and installing the barrel.
Item 5— is for exhaust stack modifications on the new generator exhaust pipe.
Modifications included additional structural supports and applying a high heat protective
coating in order to avoid excessive corrosion damage. These additional items were not
included in the original contract documents.
Item 6— is for pipe encasement on existing 48 and 60-inch pipelines which were found
severely corroded upon excavation for a new junction structure. The pipelines were
concrete encased to maintain their structural integrity and provide a solid connection to
the new junction structure.
Item 7— is for the addition of an isolation plate within an existing 48-inch vent line to
protect workers from potentially hazardous odors during the construction of a new
junction box. Additionally the vent line was rehabilitated to allow for the removal and
installation of the isolation plate to facilitate construction on Job Nos. P1-82 and J-36, as
well as any future projects which require work on either the 66 or 84-inch interplant lines
upstream of the Effluent Junction Box.
n�. 01MW Page 3
Item 8 —is for the final costs associated with the new Filtrate Pump Station. Change
Order No. 3 (October 2004), to this contract included the addition of the pump station v
and allowed for final costs to be rated within a future change order. The Filtrate Pump
Station was installed to pump Plant No. 1 filtrate (waste stream from dewatering
process) to a pipeline that conveys flow to Plant No. 2. The Orange County Water
District (OCWD) was exceeding their NOMA permit limit on their reclaimed water
because of filtrate in the Plant No. 1 effluent which OCWD uses for water reclamation.
The installation of the Filtrate Pump Station has relieved OCWD from exceeding their
NDMA permit limits.
ALTERNATIVES
None
CEQA FINDINGS
This project was included in the Strategic Plan EIR that was certified on
October 27, 1999. A Notice of Determination was filed on October 29, 1999.
ATTACHMENTS
1. Budget Information Table
2. Change Order Status Report
3. Change Order Performance Report
4. Change Order
DF:BB:bm:kf
H1nlglobaMgenda Draft ReportslPMP1-76 C0M7 NO
nam.w. 011.1a Page 4
E �
BUDGET INFORMATION TABLE
TRICKLING FILTER REHABILTATION AND NEW CLARIFIERS
JOB NO. P1-76
PROPOSED
ORIGINAL CURRENT PROPOSED FUNDS THIS ESTIMATED INCREASE ESTIMATED
`.BUDGET PROPOSEDTOTAL AUTHORIZATION
PROJECTIPNASE AUTHORIZED PROJECT REVISED AUTHORIZED TO AUTHORIZATION EXPENDITURE EX0ENbEDT9'
BUDGET BUDGET IOECREASE BUDGET DATE REQUEST - TO DATE DATEI3$I. '
' -
Phase t-Pto ed Development 5 55.000 S 55,000 $ 55.000 S 55.000 S 55.000 100%
Phase 2-Relminag Design $ 60.000 $ 60,000 $ 60.000 $ - $ 60,000 $ 60.000 100%
Phase 3-Deal n $ 4.382.000 $ 4.382,000 " $ 4,382,000 $ 4.382.000 $ 4.382,000 100%
Phase 4-Constmdion $ 40.181.963 $ 251.732 $ 40.463,695 $ 40,181,963 $ 281,732 S 40.463.695 $ 39.100,000 97%
Phase 5-C.ramssioning $ 637,000 $ 637.000 ',-. $ 637.000 S 637.000 S 1,200
Phase 6-Close-0ut $ 91=0 0 91.000
Phase 7-Contingency $ 1.443,037 E 281,732 $ 1,161.306 1.
PROJECT TOTAL $ 46.850.000 $ - $ 46.850.000 1 1 $ 45,315.963 1 $ 281.7321 $ 45.597,695 $ 43,598.200 96%
Relmbumable Costs
PROJECT NET S 46,850.000 $ - $ 46.850,000 1 1 $ 45,315.963 1 $ 281,732 1 $ 45,597.695 1 S 43,598.200 1 96%
PSA/Contract
Des1 .PSA $ 6.106,938 5 - $ 6.196,938 11 $ 6,169.938 1$ - $ 6,169.938 1 S 4.900.000 79%
Construdlon Contract $ 34,709.778 $ 281.732 $ 34,991,510 is $ 34,709778 $ 281732 $ 34.991,510 $ 34.400,000 98%
E.s:W]9ea017
CHANGE ORDER STATUS REPORT
TRICKLING FILTER REHABILITATION AND NEW CLARIFIERS
JOB NO. P1-76
APPROVAL CONTRACT CONTRACT COST PERCENTAGE AUTHORIZED AUTHORIZED TIME
ITEM DATE COST TO DATE INCREASE TIME TO DATE
(DAYS) (DAYS)
CONTRACT 3/26/2003 $ 33,037,000 $ 33,037,000 0.00 1000 1000
CO NO. 1 7/17/2003 $ 0.00 $ 33,037,000 0.00 0 1000
CO NO. 2 6/23/2004 $ (84,405) $ 32,952,595 (0.26) 0 1000
CO NO. 3 10/27/2004 $ 123,258 $ 33,076,853 0.12 0 1000
CCO NO 522005 $ 356,962 $ 33,432 1100
'0 No. 43 34219,8
/2005 $ 787,0 58 3.58 0 1000
CO NO. 6 12/21/2005 1 $ 489,920 $ 34,709,778 5.06 0 1000
CO,NO.,7 Pending .$ ?- 28IJ32,1 ,34,991,510 r ,,. 5.92 0 1000
EDM5003000020
m n
CHANGE ORDER PERFORMANCE REPORT
HEADWORKS CONSTRUCTION TRAILERS AT PLANT NO.2
JOB NO.P1-76,CHANGE ORDER NO.7
Contractor:J.R.FILANC CONSTRUCTION COMPANY,INC. Project Type:REHABILITATION
Design Consultant:BLACK S VEATCH CORPORATION Contract%Complete:97% a wee na4neum roue' f33.037,000
CHANGE ORDER TYPES TRACKED INFORMATION ONLY
Unknown Condition Stan Requested Change Reimbursable Design Non-Reinbursabb Design Subtotal CO Types Other TOYI
Errors Errors Tracked'
Change Orders $17945 0.05% 5244,17O 0.74% $0 0.00% $19.61 0.06% $281.73 0.86% $0 0.00% $261.73 0.85%
this Period
Change Ordersto $181,943 0.55% ($93,959) -0.28% $0 0.00% $379,24 1.15% 5467,231 1.41% $1,205,547 3.65% $1,672.77 5.08
Data
Change Order Total $199.88 0.61% $150,211 0.46% $0 0.00% $398.864 1.21% $748,983 2.27% $1,205,547 3.65% $7,950,510 6.B2%
Program <1.00% 0.00% <1.00% <6.00% 0,00% <6.00%
Performance Goals
The Change Order Management Plan tracks Me preceding bur change order types
EDM6403609e50
Verdun L1O006
V Page 1 of 6
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.R. Filanc Construclion Company. Inc. C.O. No.: Seven 7
Date: June 28, 2006
Job: Trickling Filter Rehabilitation and New Clarifiers Job No. P1-76
Consultant: Black&Veatch
Amount of this Change Order (Add)(OeducE) $281 732.00
In accordance with contract provisions, the following changes in the contract andlor contract
work are hereby authorized and as compensation, the following additions to or deductions
from the contract price are hereby approved.
ITEM 1 —CHEMICAL PIPING TO TRICKLING FILTER JUNCTION BOX NO. 1
This item is for all labor, material, and equipment to install two new one and one-half inch CPVC
chemical lines from the existing bleach station to the new Trickling Filter Secondary Effluent Junction
Box No. 1. The new chemical lines are installed within the tunnels for approximately 300 feet and
then run underground for approximately 100 feet. Where the new chemical pipelines are run
underground they include a four-inch containment pipe and slope back towards to tunnel to allow for
leak detection. Within the Trickling Filter Secondary Effluent Junction Box No.1 there are two ball
valves to allow for isolation of each line. The chemical lines are used to provide bleach to disinfect
the trickling fitter effluent when it is sent through the interplant pipelines to the ocean oulfall. All
exposed sections of piping are painted purple and labeled as"bleach" lines. This work was not
included in the original contract. The work was accomplished on Contractor's force account pursuant
to Section 43(B)2 of the General Requirements (Reference FCO-P176-30).
ADDED COST THIS CHANGE ORDER ITEM: $63,680.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 2—UPSIZE THE PLANT WATER PIPELINE AT THE SLUDGE AND SCUM PUMP STATION
This item is for all labor, material, and equipment to increase the size of the plant water feed pipeline
at the sludge and scum pump station. The plant water feed pipeline was increased from a one-inch
hose bib to a four inch quick connect fitting to enable the 8-inch sludge line to be cleaned out when it
becomes clogged. Additional material includes approximately 40-feet of new ductile iron pipe, a new
valve, the quick connect components, and some miscellaneous fittings. The costs associated with
this Change Order item were negotiated with the Contractor pursuant to Section 43 (B) 1 of the
General Requirements(Reference FCO-P176-53).
ADDED COST THIS CHANGE ORDER ITEM: $6,170.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
0
Page 2 of 6 9
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728 8127
CHANGE ORDER
Contractor: J.R. Filanc Construction Company. Inc. C.O. No.: Seven 7
Date: June 28, 2006
Job: Trickling Filter Rehabilitation and New Clarifiers. Job No. P1-76
Consultant: Black &Veatch
ITEM 3—60-INCH PIPE THRUST SUPPORTS
This Rem is for all labor, material, and equipment required to install thrust pipe supports against the
60-inch butterfly valves located within the Trickling Filter Pump Station. The thrust supports are
required to keep the flexible coupling located next to the butterfly valves from coming apart, or
expanding enough to produce a leak, when the valves are closed and the line is pressurized. The
thrust supports were not included in the original contract documents. The work was accomplished on
Contractor's force account pursuant to Section 43(B) 2 of the General Requirements (Reference
FC0-P176-54).
ADDED COST THIS CHANGE ORDER ITEM: $14,874.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 4—72-INCH BARREL AND CLEAN UP
This Rem is for all labor, material, and equipment to form a 72-inch diameter barrel (pipe form)within
the existing Junction Box B and then place 20-yards of concrete around the barrel to repair existing
corrosion related structural damage and to create a new section of pipe within the junction box which
reduces the potential for odors. Work also included the removal and wash down of approximately ten
cubic yards of sludge from the bottom of the junction box and a portion of the existing 72-inch
pipeline. The existing condition of Junction Box B was not known during the design of the new
trickling filter facility and could not be readily determined. The work was accomplished on
Contractors force account pursuant to Section 43 (B) 2 of the General Requirements(Reference
FCO-P176-55).
ADDED COST THIS CHANGE ORDER ITEM: $7,806.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 5—EXHAUST STACK MODIFICATIONS
This item is for all labor, material, and equipment to modify the diesel generator exhaust stack located
at Power Building 8. Additional structural supports which accounted for thermal expansion were
added and a heat resistant coating was applied to the stack which will increase the lifetime of the
exhaust system. The work was accomplished on Contractor's force account pursuant to Section
43 (B) 2 of the General Requirements(Reference FCO-P176-56).
ADDED COST THIS CHANGE ORDER ITEM: $4,743.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
Page 3 of 6
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.R. Filanc Construction Company, Inc. C.O. No.: Seven 7
Date: June 28, 2006
Job: Trickling Filter Rehabilitation and New Clarifiers. Job No. P1-76
Consultant: Black&Veatch
ITEM 6—PIPE ENCASEMENT AT PRIMARY EFFLUENT JUNCTION BOX 48 AND 60-INCH
PIPELINES
This Item is for all labor, material, and equipment to provide a concrete encasement around the
existing 48 and 60-inch pipelines located next to the Primary Effluent Junction Box which was
constructed as part of the contract work on P1-76, Work elements included removing severely
corrosion damaged sections of existing pipe, installing a short section of new surplus pipe, and
forming and placing a concrete pipe encasement around a portion of the damaged pipes. The
concrete encasement was required in order to provide structural stability at the point of connection to
the new Primary Effluent Junction Box. The existing condition of the pipelines was not known during
the design of the new trickling filter facility and could not be readily determined. The work was
accomplished on Contractor's force account pursuant to Section 43 (B) 2 of the General
Requirements(Reference FCO-P176-57).
ADDED COST THIS CHANGE ORDER ITEM: $4.377.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 7—48-INCH VENT LINE MODIFICATIONS
This item is for all labor, material, and equipment required to install an isolation plate within an
existing 48-inch vent pipe which equalizes the pressures between the 84 and Winch interplant lines.
As part of the contract work a portion of the 66-inch pipeline was removed so the new Junction Box
No. 2 could be constructed. Once the section of Winch pipeline was removed there was a significant
amount of potentially hazardous and odorous gas escaping through the vent line to the 84-inch
pipeline. The isolation plate was installed to remove the hazard. The isolation plate will be used on
future projects which perform work on the 66 or 84-inch pipelines. The Isolation gate can be removed
and reinstalled as needed. The work was accomplished on Contractor's force account pursuant to
Section 43 (B)2 of the General Requirements(Reference FCO-P176-58).
ADDED COST THIS CHANGE ORDER ITEM: $5,762.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
Page 4 of 6 0
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728.8127
CHANGE ORDER
Contractor: J.R. Flanc Construction Company. Inc. C.O. No.: Seven 7
Date: June 28, 2006
Job: Trickling Filter Rehabilitation and New Clarifiers, Job No. P1-76
Consultant: Black&Veatch
ITEM 8—FILTRATE PUMP STATION—FINAL COST ITEM
This item is for all labor, material, and equipment required to complete the installation of the new
Filtrate Pump Station. As part of Change Order 3 (Item No. 11) to P1-76, $350,000 was allocated as
a preliminary amount to provide contractor with some initial payment for work completed. All work on
the Filtrate Pump Station is now complete and the remaining compensation is$174,320.00. This
work was accomplished on Contractor's force account pursuant to Section 43(B) 2 of the General
Requirements(Reference FCO-P176-20).
ADDED COST THIS CHANGE ORDER ITEM: $174,320.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
TOTAL ADDED COST THIS CHANGE ORDER: $281,732.00
TOTAL TIME EXTENSION THIS CHANGE ORDER: 0 Calendar Days
j Page 5 of 6
ORANGE COUNTY SANITATION DISTRICT
108" ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.R. Filanc Construction Company, Inc. C.O. No.: Seven 7
Date: June 28. 2006
Job: Trickling Filter Rehabilitation and New Clarifiers, Job No. P1-76
Consultant: Black &Veatch
The additional work contained in this Change Order can be performed incidental to the prime work
and within the time allotted for the original Contract and any extensions to the Contract time made by
this and all previously issued Change Orders. It is therefore mutually agreed that no extension of time
to perform the work is required for this Change Order. District and Contractor agree that the added
cost described above constitutes full and equitable consideration for all the impacts incurred by the
Contractor, and no other direct or indirect, incidental or consequential costs, expenses, losses or
damages have been or will be incurred by Contractor, except as expressly granted and approved by
this Change Order.
SUMMARY OF CONTRACT TIME
Original Contract Date: June 2, 2003
Original Contract Time: 1,000 Days
Original Completion Date: February 26, 2006
Time Extension this C.O.: 0 Days
Total Contract Time Extension: 0 Days
Revised Contract Time: 1000 Days
Revised Final Completion Due Date: February 26, 2006
Time Subject to Liquidated Damages: N/A
Actual Final Completion Date: N/A
Original Contract Price $ 33,037,000.00
Prev.Authorized Changes $ 1,672,778.00
This Change(Add)(Bedust) $ 281,732.00
Amended Contract Price $ 34,991,510.00
iF
Page 6 of 6 I`
ORANGE COUNTY SANITATION DISTRICT
108" ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.R. Filanc Construction Company, Inc. C.O. No.: Seven 7
Date: June 28, 2006
Job: Tricklina Filter Rehabilitation and New Clarifiers Job No. P1-76
Consultant: Black&Veatch
Board Authorization Date: June 28, 2006
ORANGE COUNTY SANITATION DISTRICT
Recommended by:
Dean Fisher, P.E. Date
CIP Project Manager
Approved by:
David A. Ludwin, P.E. Date
Director of Engineering
Accepted by:
J. R. FILANC CONSTRUCTION COMPANY, INC.
Contractor Date
EDMS:008808875
PDC COMMITTEE Meetln,Date TO
Btl.Rr Dlr.
O6/01106 O6/2a/O6
AGENDA REPORT Item Number Item Number
PDC06-57 13(f)
Orange County Sanitation District
®Ocean Outlell
Ocean Systems
FROM: David Ludwin, Director of Engineering
Originator: Umesh Murthy, CIP Project Manager
SUBJECT: EFFLUENT PUMP STATION ANNEX, JOB NO. J-77
GENERAL MANAGER'S RECOMMENDATION
Ratify Change Order No. 13 to Effluent Pump Station Annex, Job No. J-77, with
J.F. Shea Construction, Inc., authorizing an additional amount of$65,276 and 50
calendar days, increasing the total contract amount to $44,597,334.
SUMMARY
• Effluent Pump Station Annex (EPSA), Job No. J-77, will replace the Foster Booster
Pump Station with a new pumping facility that is capable of providing adequate
backup capacity to the existing Ocean Outfall Booster Station (GOBS) during
excess flow events and routine maintenance. EPSA will also accommodate the
pumping of secondary treated water exclusively through the 78-inch ouffall during
excess flow events. This project also includes the construction of a standby power
facility which will provide backup power to EPSA.
• Black and Veatch Corporation prepared the plans and specifications for this project
and the construction contract was awarded to J.F. Shea Construction, Inc. on
September 24, 2003.
• Change Order No. 13 includes nineteen items of additional work and four items of
deleted work to Job No. J-77. There are thirteen nonreimbursable design errors and
one reimbursable design error associated with this change order. Liquidated
damages on this project are $5,000 per day and there are no bonus provisions. The
contract is now 81% complete.
PRIOR COMMITTEE/BOARD ACTIONS
The construction contract was awarded to J.F. Shea Construction, Inc. by the Board of
Directors on September 24, 2003. Please refer to the attached Change Order Status
Report for more information on previous change orders.
R«iwa 0610� Page 1
1
PROJECT/CONTRACT COST SUMMARY 'y
Original Contract Price $44,735,518
Previously Authorized Changes $ (203,460)
This Change (Add) $ 65,276
Change Orders to Date $ (138,184)
Percentage Decrease to Date (0.31%)
Amended Contract Price $44,597,334
BUDGETIMPACT
® This item has been budgeted. (Line item: Section 8, Page 69)
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
Contract Schedule
Contract Start Date November 24, 2003
Original Contract Completion Date June 30, 2007
Total Number of Change Orders to Date 13
Current Contract Completion Date September 11, 2007
Actual Contract Completion Date N/A
Days Subject to Liquidated Damages 0
Chance Order No. 13 Content
Item Description Amount Days Type
No.
Nonreimbursable Design
1 Conduit Re-Route in Can Gen $15,173 0 Error
Delete 12kV Manholes Nos. 5 and
2 13 $7,262 0 Unknown Conditions
Glass Fiber Roofing Felt and Nonreimbursable Design
3 Maintenance Walking Pads $5,366 0 Error
120VAC Power to the Bubbler Nonreimbursable Design
4 Panels $1,972 0 1 Error
Replacement Ground Current
5 Sensors at Can Gen $9,898 0 Unknown Conditions
Cooling Water Skid Instrument Nonreimbursable Design
6 Wiring $7,750 0 Error
Modify Termination Bus at the Can Nonreimbursable Design
7 Gen Switch ear $1,775 0 Error
Sluice Gate and Motor Operated Nonreimbursable Design
8 Valve Interlocks $9,060 0 Error
Page 2
,v
Y
Secondary Effluent Junction Box Staff Requested Design
9 Weir Wall Modification $24,679 0 Change
Drilling of Embed Steel at the
10 Electrical Building Switch ear $2,767 0 Unknown Conditions
Effluent Pump Speed Indicator Nonreimbursable Design
11 Communications Wiring $1,515 0 Error
Coaxial Cable Programmable Logic Nonreimbursable Design
12 Controller Communication Wring $1,231 0 Error
Undersized Generator Water Jacket
13 Wiring and Breakers $2,766 0 Reimbursable Design Error
Fiber Optic Tube Routing and
14 Terminations $19,938 50 Unknown Conditions
Factory Witness Testing
15 Reimbursement $11,200 0 Other
Nonreimbursable Design
16 Generator Fuel System Circuits $15,111 0 Error
Staff Requested Design
17 ID Tagging of Electrical Manholes $771 0 Change
3kVA Stand Alone Uninteruptible Nonreimbursable Design
18 Power System Installation $1,366 0 Error
Nonreimbursable Design
19 Bubbler Panel Level Signal $1,265 0 Error
Power Supply for Standby Power Nonreimbursable Design
20 Facility Building Door Locks $2 632 0 Error
Relocated Programmable Logic
Controller Panel at the Distribution
21 Center"B" Building $1,075 0 Other
Deletion in Scope at the Ocean Staff Requested Design
22 Outfall Booster Station Switch ear 1 13,735) 0 Change
Power for 1/0 Racks at EPSA"A" Nonreimbursable Design
23 and "B" $1 719 0 Error
Total -Change Order No. 13 $65,2761
Item 1 provides a credit to correct the double payment of Field Change Order (FCO)
No. 14. FCO No. 14 was first paid in Item 8 under Change Order No. 3 and was paid
again in Item 5 under Change Order No. 9. Staff has recently implemented a new
change order tracking system which will avoid this oversight in the future.
Item 2 provides for a net credit associated with replacing two electrical manholes with
continuous conduit runs in order to gain relief from existing underground utility
congestion.
Item 3 provides for upgrading the glass fiber roofing fell from the specified product and
for adding maintenance walking pads to the required roofing details. These changes
were required in order to receive and maintain the manufacturer's 20-year warranty as
specified in the contract documents for the roofing system.
n .e. m 3 Page 3
v
Item 4 provides for added 120VAC wire to the EPSA wet well bubbler panels. The D
power supply conduit as detailed in the contract drawings did not contain a sufficient
number of wires to complete the required power circuits.
Item 5 provides for replacing the existing ground current sensors (CTs) in the Can Gen
medium voltage switchgear with upsized CTs compatible with the new EPSA 15kV
power cables. Restricted access to this energized existing equipment in Can Gen and
limited as-built records prevented the need for this equipment change from being
identified in the design phase of the project.
Item 6 provides for added conduit, wire, terminal strips, and junction boxes that were
necessary to complete the cooling water skid instrument panel wiring for each effluent
pump back to the required terminations in the Electrical Building. The required conduit
and wiring details were omitted from the contract drawings.
Item 7 provides for modifying the copper termination bus at the existing Can Gen
switchgear with an expansion plate so that it could accept both the new EPSA power
cables and the up-sized surge arrestor cables. The expansion plate modification also
provided for the addition of a grounding stud to the termination bus. The required
expansion plate was not shown in the contract drawings.
Item 8 provides for the addition of interconnecting conduit and wiring from the wet well
local control panels to the sluice gates and effluent pump MOVs in order to complete
the required I&C interlocks. The required conduit and wiring details were omitted from
the contract drawings.
Item 9 provides for modifications to the weir wall in the secondary effluent junction box
in order to allow EPSA required flows to be achieved without having to operate the plant
at elevated effluent levels during Stage 2 construction. This change increases plant
operating flexibility and allows for heavier trial use of EPSA during the Stage 2
construction period while reducing exposure to potential plant overflow conditions.
Item 10 provides for the added labor necessary to drill holes through the concrete
embedded mounting channels for the Electrical Building switchgear. Costs associated
with furnishing and installing the mounting hardware remains the Contractor's
responsibility. The approved switchgear could not be weld-mounted to the specified
steel channels and had to be installed on anchor bolts to comply with the
manufacturer's installation requirements. The switchgear manufacturer's installation
details were not known during the design phase of the project.
Item 11 provides for added terminal strips and communications cable necessary to
complete the wiring in the pump building from the local speed control panel to the
remote 1/0 panel for each effluent pump. The required wiring details were omitted from
the contract drawings.
Item 12 provides for the added coaxial cable necessary to complete the communication
wiring between the Electrical Building main programmable logic controller panel and the
remote 1/0 panels for the MCCs, effluent pumps, and gates/valves. The wiring details
were incorrectly shown in the contract drawings.
�,.,. , Page 4
v Item 13 provides for replacing the wire and circuit breakers installed for the water jacket
system at each generator as detailed in the contract drawings with upsized wire and
breakers necessary to accommodate the specified equipment requirements. The wire
and circuit breakers were incorrectly shown in the contract drawings. This item involves
re-work and staff is seeking reimbursement from the designer.
Item 14 provides for modifying the fiber optic tube runs and terminations from the
central programmable logic controller in the Power Distribution Facility to the EPSA
Electrical Building because of deteriorated and overfilled existing conditions at the
plants existing tube distribution units (TDI J). Several of the existing TDIJ were found
with collapsed cells and conditions would not allow for the addition of new fiber.
Impacts to the scheduled critical path activities have been demonstrated in association
with this extra work and a Time Impact Analysis has substantiated the added contract
duration.
Item 15 provides for a credit to reimburse the Sanitation District as specified by contract
for costs incurred in sending Engineering staff to Japan for factory witness testing of the
effluent pumps.
Item 16 provides for the added conduit and wiring necessary to complete various
24VDC control circuits associated with the generator fuel system in the Standby Power
Facility (SPF) Building. The required conduit and wiring details were omitted from the
contract drawings.
Item 17 provides for the addition of number tagging of electrical manholes prior to
energizing the facilities in order to allow maintenance staff to safely identify the utilities.
Manhole tagging requirements are not included in the contract documents.
Item 16 provides for the addition of a junction box and terminal strip to accommodate
incorporation of the 3kVA uninterruptible power system provided under a previous
change order into the conduit and wiring system shown in the contract drawings. The
required wiring details were not included in the contract drawings.
Item 19 provides for the addition of conduit and wire necessary for conveying the level
signal between the local bubbler panel and the remote 1/0 panel. The required conduit
and wiring details were omitted from the contract drawings.
Item 20 provides for the added 120VAC/24VDC transformer, conduit, and wire needed
to provide power to the access control panel in the SPF for door locks. The required
power supply details were omitted from the contract drawings.
Item 21 provides for the additional conduit and cable necessary to extend the Primary
Effluent Pump Station level signal wiring to the programmable logic controller panel
relocated within Distribution Center "B" as part of changes associated with project
P2-47-3.
a« � W Page 5
Item 22 provides for a credit to the contract for the deletion of the work associated with
the intended automatic power transfer upgrades at the OOBS 12kV switchgear. An
alternative manual power transfer arrangement was implemented after significant extra
work costs were determined necessary for completing the original scope of work.
Item 23 provides for the additional conduit and wire necessary to complete
uninterruptible power supply from the Electrical Building Control Room to the MCCs in
the 480V Equipment Room. The required conduit and wiring details were omitted from
the contract drawings.
ALTERNATIVES
None
CEQA FINDINGS
The Rehabilitation of Foster Pump Station (FPS) was included in the 1999 Strategic
Plan Environmental Impact Report (EIR). The EIR was certified on October 27, 1999,
and a Notice of Determination was filed on October 29, 1999. A supplemental EIR
(SEIR) was completed for update of the Program EIR to reflect replacement of FPS
rather than the rehabilitation indicated in the Strategic Plan. The SEIR was approved by
the Board in December 2002.
ATTACHMENTS
1. Budget Information Table
2. Change Order Status Report
3. Change Order Performance Report
4. Change Order
5. Location and Photo Description of Change Order
SB:dm
H:WglobaMgenda Draft RewftTMJ-77 AR CO#13 060106,dm
n.,. o W Page
BUDGET INFORMATION TABLE
Effluent Pump Station Annex
JOB NO.J-77
ORIGINAL CURRENT PROPOSED pROPOSEO TMS ESTIMATED ESIIMAlE0
BUDGET FUNDS AUTHORIZED PROPOSEDTOTAL
PROJECTIPHASE AUTHORIZED PROJECT REVISED AUTHORIZATION EXPENDITURE EXPENDED TO
BUDGET BUDGET INCREASE BUDGET TO DATE REQUEST AUTHORGAnON TO DATE OATEI%)
DECREASE
Phase 1 -Prajed
Development_ $ 21000 5 4000 S 4,000 S 4.000 5 4.000 5 4000 100%
Phase 2-Preliminary
Design S 1,258000 S 62000 $ 62.000 $ 82000 f 620D0 5 62,000 100%
Phase 3-Desi n E J 501.000 S 4.446j000 1446 000 E 4 446 000 5 4.446 000 S 4.446 000 100%
Phase 4-Construction S 43,745,000 $ 54.418371 S 65276 S 54,483,647 S 54.418,371 S 65270 S 54,483647 S 40750.000 75%
Phase S-Commission S 376000 S 487000 S 487000
f 123000 .
. . E$ 45,312,00D
50,000 1
Phase 6-Close-Oul f 94.000 S 123,000 S 123000 f 123000 00%
6Phase 7-Contingen S 2000 E 4,130.353 $
PROJECTTOTAL S 50,757.000 S 63,736.000 $ 63.736.000 S 59540,371 S 65,276 S 59R067 %76%
Reimbursable Costs
PROJECTNET E 50.757,000 1 S 63.736,000 1 $ 63.736.000 I I S 59.540,371 $ 65.276 $ 59,805,647 5 45,312,000 78%
PSAIContract
Desj WConst.Su on PSA S 2208810 S 8164240 $ 6.154.240 S 6154240 $ 6164240 5 5020000 81%
Conslmchon Conhad $ 44735518 f M532058 65276 S 41597334 $ 44.532058 65276 1 S 44597334 1 S 35500000 80%
eousooleoeem
CHANGE ORDER STATUS REPORT
EFFLUENT PUMP STATION ANNEX
JOB NO. J-77 Change Order No. 13
APPROVAL CONTRACT CONTRACT CUMULATIVE AUTHORIZED AUTHORIZED
ITEM DATE COST COST TO DATE PERCENTAGE TIME TIME TO DATE
INCREASEIDECREASE (DAYS) (DAYS)
CONTRACT 9/24/2003 44,735,518 $44,735,518 0.00 1315 1315
CO NO. 1 2/25/2004 <1,967,158> $42,768,360 (4.40) 0 1315
CO NO. 2' 1 7/1/2004 185,000 $42,953,360 (3.98) 0 1315
CO NO. 3 9/22/2004 333,388 $43,286,748 3.24 0 1315
CO NO. 4 12/15/2004 174,549 $43,461,297 2.85 0 1315
CO NO. 5 2/23/2005 390,586 $43,851 883 1.98 0 1315
CO NO. 6 6/22/2005 102,475 $43 954 358 1.74 0 1315
CO NO. 7 7/20/2005 53,196 $44 007 554 1.63 0 1315
CO NO. 8 7/20/2005 220,133 $44,227,687 1.14 0 1315
CO NO 9 11/23/2005 32,514 $44 260 201 1.06 0 1315
CO NO. 10 12/21/2005 33,053 $44,293,254 0.98 23 1338
CO NO. 11 2/22/2006 100,302 $44 393,556 0.76 0 1338
CO NO. 12 2/22/2006 138,502 $44,532,059 0.46 0 1338
co N0. 13. Pendin 65 276 P $44 597 334 0.31 50 1388,d,,.v; r.
' PDC approval per OCSD Resolution 04-OB
EDMS 003808574
CHANGE ORDER PERFORMANCE REPORT
EFFLUENT PUMP STATION
JOB NO.J-77,CHANGE ORDER NO 13
Contractor:J.F.SHEA CONSTRUCTION,INC. Project Type:REHABILITATION
Design Consultant:BLACK It VEATCH CORPORATION Contract%Complete:90% Original Contract Price: $44,735.518
CHANGE ORDER TYPES TRACKED INFORMATION ONLY
Unknown Condition Staff Requested Change Reimbursable Design WwRelnburxble Subtotal CO Types Other Tmal
Errors Design Errors Traoketl
Change Orden $25.341 0.06% $11.715 0.03% $2,766 0.01% $35.579 0.08% $75,401 0,17 ($10,125) .0.02% $65,276 0.15%
this Period
Change Orders to $397.679 0.89% ($1,106,120) -2.47% SO 0.00% $317.222 0.71% ($391,219) -0.87% $187.759 0.42% ($203,460)
Date
Change Order Total $423,020 0.9596 ($1,094,405) -2.45% $2.766 0.01% $352.801 0.79% ($315,818) -O71% $177.634 0.4D% ($138,184) -0,31%
'The Change Order Management Plan tracks the prereding bur Mange order"
EDMS 00ea0e590
9 Page 1 of 11
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.F. Shea Construction, Inc. C.O. No.: Thirteen (13)
Date: June 28, 2006
Job: Effluent Pump Station Annex.Job No. J-77
Consultant: Black& Veatch
Amount of this Change Order(Add)(Dedrie4) $65,276.00
In accordance with contract provisions, the following changes In the contract and/or contract
work are hereby authorized and as compensation, the following additions to or deductions
from the contract price are hereby approved.
ITEM 1 —CONDUIT RE-ROUTE IN CEN GEN BASEMENT
This credit is to correct the double payment of FCO 14. FCO 14 was first paid in Item 8 under Change
Order No. 3 and was paid again in Item 5 under Change Order No. 9.
CREDIT COST THIS CHANGE ORDER ITEM: ($15,173.00)
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 2—DELETE 12kV MANHOLES NOS. 5 AND 13
This hem provides a net credit to the Sanitation District for the work associated with the elimination of
two 12kV manholes. Manholes Nos. 5 and13 were replaced with long radius conduit sweeps in order
to gain relief from existing underground utilities that were not shown on the contract drawings. These
existing utilities were not anticipated in the design because they were not shown on any plant as-built
records. This work is defined in FCO No. 24 and was negotiated with the Contractor pursuant to
Section 43 B (1) of the Contract General Requirements.
CREDIT COST THIS CHANGE ORDER ITEM: ($7,262.00)
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
ITEM 3—GLASS FIBER ROOFING FELT AND MAINTENANCE WALKING PADS
This hem compensates the Contractor for providing upgraded glass fiber felt and maintenance walking
pads for the roofing systems at the Pump Building and the Electrical Building. The contract
documents specified the roofing system to be built with Type IV glass fiber felt and be rated as UL
Class A with a 20-year warranty. The Type IV felt system only qualified for the manufacturer's 10-year
warranty. The specified 20-year warranty required the use of an upgraded glass fiber felt.
Additionally,the roofing plans in the contract documents did not detail walking pads for servicing the
HVAC roof equipment. These walking pads were also required to maintain the 20-year warranty. This
work is defined in FCO No. 52 and was negotiated with the Contractor pursuant to Section 43 B (1)of
the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $5,366.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
Page 2 of 11 Y
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.F. Shea Construction, Inc. C.O. No.: Thirteen (13)
Date: June 28, 2006
Job: Effluent Pumo Station Annex. Job No.J-77
Consultant: Black& Veatch
ITEM 4—120VAC POWER TO THE BUBBLER PANELS
This item compensates the Contractor for the work associated with completing the 120VAC power
supply wiring to the bubbler panels at the EPSA wet wells. The conduit system as detailed in the
contract drawings did not provide for a sufficient number of wires between the remote 1/0 panel and
the local bubbler panels. Wires were added and the conduit details were modified to achieve the
required power supply. This work is defined in FCO No. 57 and was negotiated with the Contractor
pursuant to Section 43 B (1) of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $1,972.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
IT —REPLACE GROUND CURRENT SENSORS AT CEN GEN
This item compensates the Contractor for the work associated with replacing the four existing ground
current sensors (CTs) in the Can Gen medium voltage switchgear. These CTs are needed to provide
the required ground-fault relay protection for the system. Restricted access to the energized Can Gen
gear and limited as-built records prevented identification of the need for larger replacement CTs until
after installing the new 15kV cable for the EPSA tie-in. This work is defined in FCO No. 58 and was
negotiated with the Contractor pursuant to Section 43 B (1) of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $9,898.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
ITEM 6—COOLING WATER SKID INSTRUMENT WIRING
This item compensates the Contractor for the work associated with providing the additional conduit,
wire,terminal strips, and junction boxes necessary for completing the cooling skid Instrument wiring for
each effluent pump. The contract documents did not provide for the correct routing of conduit and
wires between the cooling water instrument panels in the Pump Building and the VFD panels in the
Electrical Building. Interconnecting wiring from the cooling system panel to the speed control panel for
each pump was added so that existing spare wires could be utilized to complete the wiring to the VFD
panels. This work is defined in FCO No. 59 and was negotiated with the Contractor pursuant to
Section 43 B (1)of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $7,750.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
1 Page 3 of 11
ORANGE COUNTY SANITATION DISTRICT
108" ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.F. Shea Construction, Inc. C.O. No.: Thirteen (13)
Date: June 28, 2006
Job: Effluent Pumo Station Annex. Job No. J-77
Consultant: Black& Veatch
ITEM 7—MODIFY TERMINATION BUS AT THE CEN GEN SWITCHGEAR
This hem compensates the Contractor for the work associated with modifying the copper termination
bus at the existing Cen Gen switchgear to accommodate the larger surge arrestor conductors needed
for the EPSA connection and to allow for the addition of a grounding stud. The existing bus could not
accept the EPSA power cables and the up-sized.surge arrestor conductors. A copper extension plate
was therefore added to the existing termination bus so that all of the necessary connections could be
made. A grounding stud was also incorporated into this extension plate modification so that
maintenance grounding could be achieved more effectively. This work is defined in FCO No. 60 and
was negotiated with the Contractor pursuant to Section 43 B (1) of the Contract General
Requirements.
ADDED COST THIS CHANGE ORDER ITEM $1,775.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
ITEM 8—SLUICE GATE AND MOTOR OPERATED VALVE INTERLOCKS
This item compensates the Contractor for the work associated with adding the necessary
interconnecting conduit and wiring from the wet well local control panels to the sluice gates and the
effluent pump MOVs. This required I&C interlock wiring and conduit was omitted from the contract
drawing details and therefore needed to be added along with the necessary terminal connectors in the
panels. This work is defined in FCO No. 64 and was negotiated with the Contractor pursuant to
Section 43 B (1)of the Contract General Requirements.
CREDIT THIS CHANGE ORDER ITEM $9,060.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
Page 4 of 11
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.F. Shea Construction, Inc. C.O. No.: Thirteen (13)
Date: June 28, 2006
Job: Effluent Pump Station Annex, Job No.J-77
Consultant: Black & Veatch
ITEM 9—SECONDARY EFFLUENT JUNCTION BOX WEIR WALL MODIFICATION
This item compensates the Contractor for the work associated with modifying the weir wall in the
Secondary Effluent Junction Box in order to allow secondary flow to EPSA with greater operational
flexibility during the EPSA Stage 2 construction period. The work included building temporary access
scaffolding inside a 32 feet deep concrete vault, saw-cutting and removing approximately 44 square
feet of concrete from two top sections of the weir wall, mortar repair at exposed reinforcing steel, and
repair and application of a plastic protective concrete surface liner. Prior to these modifications,
secondary flow to EPSA during Stage 2 construction would require operation of the COBS wet well at
an elevated level 2.5 feet above normal plant operating level. This elevated operating level would only
be 1.5 feet below the plant overflow level and therefore EPSA would not be run in this condition for any
prolonged period of time because of the risk of discharge to the Santa Ana River. The Sanitation
District staff decided to implement the weir wall modification in order to allow for more significant run
time on the new pumps and systems during Stage 2, before the plant becomes more dependent on
EPSA during Stage 3 construction. This work is defined in FCO No. 71 and was negotiated with the
Contractor pursuant to Section 43 B(1) of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $24,679.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
ITEM 10—DRILLING OF EMBED STEEL AT THE ELECTRICAL BUILDING SW ITCHGEAR
This item compensates the Contractor for the extra labor associated with drilling anchor bott holes
through the concrete embedded steel channels in the equipment pad for the medium voltage
switchgear at the Electrical Building. The approved switchgear could not be weld-mounted as
specified and the manufacturers installation recommendations dictated that the equipment be
installed with embedded anchor bolts. The cost of fumishing and installing the mounting hardware
remains the Contractor's responsibility. The manufacturer's installation details were not known during
the design phase of the project. This work is defined in FCO No. 74 and was negotiated with the
Contractor pursuant to Section 43 B (1) of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $2,767.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
1 Page 5 of 11
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.F. Shea Construction, Inc. C.O. No.: Thirteen (13)
Date: June 28, 2006
Job: Effluent Pump Station Annex, Job No. J-77
Consultant: Black & Veatch
ITEM 11 — EFFLUENT PUMP SPEED INDICATOR COMMUNICATIONS WIRING
This Item compensates the Contractor for the work associated with adding the necessary terminal
strips and communications cable to complete the wiring from the local speed control panel to the
remote 1/0 panel for each effluent pump. The contract drawings omitted a portion of the required
speed control communications wiring. A conduit existing as part of the installed work was utilized to
complete the wiring with the addition of termination strips and cable. This work is defined in FCO
No. 76 and was negotiated with the Contractor pursuant to Section 43 B (1) of the Contract General
Requirements.
ADDED COST THIS CHANGE ORDER ITEM $1,515.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
ITEM 12—COAXIAL CABLE PROGRAMMABLE LOGIC CONTROLLER COMMUNICATION WIRING
This item compensates the Contractor for the work associated with completing the necessary coaxial
cable communication wiring, which Interconnects the Electrical Building main programmable logic
controller panel and the remote I/O panels for the MCCs, effluent pumps, and gatestvalves. The
Conduit and Cable Schedule detailed a single coax cable for the interconnecting conduit. Two cables
are required for complete systems communication. This work is defined in FCO No. 77 and was
negotiated with the Contractor pursuant to Section 43 B (1) of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $13231.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
ITEM 13—UNDERSIZED GENERATOR WATER JACKET WIRING AND BREAKERS
This Item compensates the Contractor for the work associated with replacing the generator water
Jacket wiring and breakers. The Contractor installed#10 wire and 20A breakers for each of the
standby power generator water jacket systems as shown in the contract drawings. It was later
discovered that the specified equipment required#6 wire and 60A breakers. This work is defined in
FCO No. 78 and was negotiated with the Contractor pursuant to Section 43 B (1)of the Contract
General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $2,766.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
Page 6 of 11 r
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.F. Shea Construction, Inc. C.O. No.: Thirteen (131
Date: June 28. 2006
Job: Effluent Pump Station Annex, Job No. J-77
Consultant: Black & Veatch
ITEM 14—FIBER OPTIC TUBE ROUTING AND TERMINATIONS
This item compensates the Contractor for the work associated with modifying the fiber optic tube
routing and terminations from the PDF Building to the EPSA Electrical Building. The existing tube
distribution units for the originally planned fiber optic routing were found to be overfilled and
deteriorated with collapsed cells that could not accept the additional EPSA tube fiber. This situation
was further compounded by fiber optic runs added to the EPSA project by Item 3 of Change Order No.
10 in order to accommodate components of the P2-47-3 project. Incomplete and lacking as-built
records for the plants existing fiber optic tube runs hindered recognition of this condition during the
design efforts for this work. The modifications were implemented to ensure the overall reliability of the
plant's main communication data highway system.
Completion of operational readiness testing for start-up of the facilities is directly dependent upon
completion of the PLC fiber optic communication systems. A Time Impact Analysis has demonstrated
delays to this scheduled critical path work in association with this change. This item includes the
following extensions to the specified Time of Completion requirements:
1. Stage 1 Substantial Completion: an additional 115 calendar days;June 21, 2006
2. Stage 2 Substantial Completion: an additional 63 calendar days;September 28, 2006
3. Stage 3 and Full Project Substantial completion: an additional 62 calendar days;July 30,2007
4. Final Project completion: an additional 50 calendar days;September 11, 2007
This work is defined in FCO No. 79 and was negotiated with the Contractor pursuant to Section 43 B
(1)of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $19,938.00
TIME EXTENSION THIS CHANGE ORDER ITEM 50 Calendar Days
ITEM 15—FACTORY WITNESS TESTING REIMBURSEMENT
This item reimburses the Sanitation District for the costs incurred to send two staff members to witness
the factory testing of the new effluent pumps in Haneda,Japan. The contract required the Contractor
to include these travel, accommodation, and subsistence costs in the bid price. This work is defined in
FCO No. 80 and was negotiated with the Contractor pursuant to Section 43 B (1) of the Contract
General Requirements.
CREDIT COST THIS CHANGE ORDER ITEM ($11,200.00)
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
0
4 Page 7 of 11
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY,CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.F. Shea Construction. Inc. C.O. No.: Thirteen (131
Date: June 28. 2006
Job: Effluent Pump Station Annex. Job No.J-77
Consultant: Black & Veatch
ITEM 16—GENERATOR FUEL SYSTEM CIRCUITS
This item compensates the Contractor for the work associated with providing additional conduit and
wire as necessary to complete several 24VDC control circuits at the SPF Building. The conduit details
in the contract drawings did not provide for the required conduit and wire between the local component
systems' panels located in the equipment room and the master control panels located in the adjacent
switchgear room. This work is defined in FCO No. 81 and was negotiated with the Contractor
pursuant to Section 43 B (1) of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $15.111.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
ITEM 17—ID TAGGING OF ELECTRICAL MANHOLES
This item compensates the Contractor for the work required to apply identification marking with spray-
paint stenciling to 25 electrical manholes. The Sanitation District Maintenance Supervisor required
that the manholes be tagged for safety identification reasons prior to allowing the facilities to be
energized. The contract documents do not provide for the manhole tagging. This work is defined in
FCO No. 82 and was negotiated with the Contractor pursuant to Section 43 B (1) of the Contract
General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $771.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
ITEM 18-3kVA STAND ALONE UNINTERRUPTABLE POWER SYSTEM INSTALLATION
This item compensates the Contractor for the work associated with providing the termination
components necessary for the appropriate installation of the 3kVA uninterruptible power system. The
contract documents did not contain specifications for the 3kVA uninterruptible power system and the
required equipment was supplied as a result of Change Order No. 4, Rem 8 (FCO No. 30). The proper
installation of this uninterruptible power system required the addition of a junction box and terminal
strip in order to be incorporated into the conduit and wiring system shown in the contract drawings.
This work is defined in FCO No. 83 and was negotiated with the Contractor pursuant to Section 43 B
(1) of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $1,356.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
r
Page 8 of 11 J
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.F. Shea Construction, Inc. C.O. No.: Thirteen (13)
Date: June 28, 2006
Job: Effluent Pump Station Annex, Job No. J-77
Consultant: Black 8 Veatch
ITEM 19—BUBBLER PANEL LEVEL SIGNAL
This item compensates the Contractor for the work associated with completing the level signal wiring
associated with EPSA bubbler panel 24HFCP002. The contract drawings omitted the necessary
interconnecting signal conduit between the local bubbler panel and the remote 1/0 panel. This work is
defined in FCO No. 84 and was negotiated with the Contractor pursuant to Section 43 B (1) of the
Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $1,265.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
ITEM 20— POWER SUPPLY FOR STANDBY POWER FACILITY BUILDING DOOR LOCKS
This item compensates the Contractor for the work associated with providing the additional conduit,
wire, and transformer necessary to complete the power supply for the security door locks at the
Standby Power Facility Building. The contract drawings did not provide for 24VDC power to the
access control panel and therefore, power had to be converted and conveyed from a 120VAC power
panel. This work is defined in FCO No. 86 and was negotiated with the Contractor pursuant to Section
43 B (1) of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $2,632.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
ITEM 21 — RELOCATED PROGRAMMABLE LOGIC CONTROLLER PANEL AT THE DISTRIBUTION
CENTER "B" BUILDING
This item compensates the Contractor for the work associated with extending conduit and cable to the
relocated programmable logic controller(PLC) panel at Distribution Center"B". The Contractor had
installed the conduit to the Distribution Center"B" PLC panel as shown in the contract. While
preparing to pull and terminate the level signal wiring associated with the conduit, approximately one
year later, it was discovered that changes associated with Project P2-47-3 had resulted in the PLC
panel being relocated within the building. This work is defined in FCO No. 87 and was negotiated with
the Contractor pursuant to Section 43 B (1) of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $1,075.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
r Page 9 of 11
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.F. Shea Construction, Inc. C.O. No.: Thirteen (13)
Date: June 28, 2006
Job: Effluent Pump Station Annex,Job No. J-77
Consultant: Black & Veatch
ITEM 22—DELETION IN SCOPE AT THE OCEAN OUTFALL BOOSTER STATION SW ITCHGEAR
This Rem provides a credit to the Sanitation District for the contract work at the Ocean Outtall Booster
Station switchgear associated with the intended automated power transfer upgrades. Limited
historical as-built records for the existing equipment and restricted access to the energized equipment
during the design phase of the project resulted in contract documents that did not contain the details
necessary to fully facilitate the work. After evaluating the additional costs that would be incurred for
completing the original scope of work, an aftemate manual key-interlocking arrangement was
developed and implemented. This work is defined in FCO No. 89 and was negotiated with the
Contractor pursuant to Section 43 B (1) of the Contract General Requirements.
CREDIT COST THIS CHANGE ORDER ITEM ($13,735.00)
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
ITEM 23—POWER FOR VO RACKS AT EPSA"A"AND'B"
This item compensates the Contractor for the work associated with installing additional conduit and
wire in the Electrical Building from the UPS-E power supply in the Control Room to each of the MCC
remote 1/0 panel boards located in the adjacent 480V Equipment Room. The contract drawings
omitted the required UPS power conduit and wire. This work is defined in FCO No. 91 and was
negotiated with the Contractor pursuant to Section 43 B (1) of the Contract General Requirements.
ADDED COST THIS CHANGE ORDER ITEM $1,719.00
TIME EXTENSION THIS CHANGE ORDER ITEM 0 Calendar Days
TOTAL ADDED COST THIS CHANGE ORDER $65,276.00
TOTAL TIME EXTENSION THIS CHANGE ORDER 50 Calendar Days
v
Page 10 of 11 r
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.F. Shea Construction, Inc. C.O. No.: Thirteen (13)
Date: June 28, 2066
Job: Effluent Pump Station Annex, Job No.J-77
Consultant: Black & Veatch
The additional work contained within this change order can be performed Incidental to the prime work
and within the time allotted for the original contract and any extensions to the contract time made by
this change order and all previously issued change orders. It is therefore mutually agreed that a 50
calendar day extension of time to perform the work is required for this change order, and that no direct
or indirect, incidental or consequential costs, expenses, losses or damages have been or will be
incurred by the Contractor, except as expressly granted and approved by this change order.
SUMMARY OF CONTRACT TIME
Original Contract Date: November 24, 2003
Original Contract Time: 1,315 Calendar Days
Original Completion Date: June 30, 2007
Time Extension this C.O.: 50 Calendar Days
Total Contract Time Extension: 73 Calendar Days
Revised Contract Time: 1,388 Calendar Days
Revised Final Completion Due Date: September 11, 2007
Time Subject to Liquidated Damages: N/A
Actual Final Completion Date: N/A
Original Contract Price $44.735.518
Prev. Authorized Changes $ (203,4601
This Change (Add) (Deduct) $ 65,276
Amended Contract Price $44,597,334
Page 11 of 11
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: J.F. Shea Construction, Inc. C.O. No.: Thirteen (13)
Date: June 28, 2006
Job: Effluent Pump Station Annex, Job No. J-77
Consultant: Black & Veatch
Board Authorization Date: June 28, 2006
ORANGE COUNTY SANITATION DISTRICT
Recommended by:
Umesh N. Murthy, P.E. Date
CIP Project Manager
Approved by:
David A. Ludwin P.E. Date
Director of Engineering
Accepted by:
J.F. Shea Construction, Inc.
Contractor Date
EDM5003808575
PDC COMMITTEE Meeting Care Ta Bd.of Dir.
06/01/06 O6/28/O6
AGENDA REPORT Item Number Item Number
PDCW-59 13(h)
Orange County Sanitation District
Collections
Facilities
FROM: David Ludwin, Director of Engineering
Originator: David May, Project Manager
SUBJECT: BUSHARD TRUNK SEWER REHABILITATION PIPE PROCUREMENT,
JOB NO. 1-24P
GENERAL MANAGER'S RECOMMENDATION
Ratify Change Order No. 1 to Bushard Trunk Sewer Rehabilitation Pipe Procurement,
Job No. I-2-4P, with Ameron International, authorizing an addition of$184,948 and 15
calendar days, increasing the total contract amount to $7,884,725.
SUMMARY
• Job No. I-2-4P, Bushard Trunk Sewer Rehabilitation Pipe Procurement, includes the
fabrication and delivery of 13,555 linear feet of 108-inch, and 185 linear feet of 96-
inch reinforced concrete pipe for the Bushard Trunk Sewer Rehabilitation project,
Job No. 1-24.
• Boyle Engineering Corporation prepared the plans and specifications, and the
contract was awarded to Ameron International on September 28, 2005.
• Change Order No. 1 includes one item of additional work, two items of time
extension, and one item of change to Section 22 of the General Requirements, to
Job No. 1-24P. There is one nonreimbursable design error associated with this
change order. There is a 15 calendar daytime extension associated with this
change order. Liquidated damages on this contract are$14,000 per calendar day if
Contractor's progress on Job No. 1-2-4 is delayed, and $5,000 if progress is not
delayed. The job is now 46% complete.
PRIOR COMMITTEE/BOARD ACTIONS
The contract was awarded by the Board of Directors on September 28, 2005.
PROJECT/CONTRACT COST SUMMARY
Original Contract Price $ 72699,777
Previously Authorized Changes $ 0
This Change Order (add) $ 184,948
Change Orders to Date $ 184,948
Percent Increase to Date 2.40%
Amended Contract Price $ 7,884,725
Page 1
BUDGET IMPACT
1
® This item has been budgeted. (Line item: FY 05/06 Budget Book, Page 8-47)
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
Contract Schedule
Contract Start Date November 7, 2005
Original Contract Completion Date July 24, 2006
Total Number of Change Orders to Date 1
Current Contract Completion Date August 8, 2006
Actual Completion Date N/A
Days Subject to Liquidated Damages N/A
Change Order No. 1 Content ..
kern No. Description Amount Days Type
Time Extension for Inclement
1 Weather $0 8 Other
Nonreimbursable
2 Welding of Pipe Liner Strip $184,948 7 Design Error
Milestone Time Extension for
3 Intersection Design Change $0 18* Other
Change of Approval Process
4 for Payment of Work $0 0 Other
Total—Change Order No. 1 1 $184,948 1 15
*This is an interim milestone time extension and does not extend the contract end date.
Item 1 is for a time extension for inclement weather delays which prevent pipe
fabrication to Sanitation District specifications. Rain and winds affect pipe curing, and
corrosion plastic liner placement in pipe forms. The time extensions extend the initial,
mid-point and contract end date milestones.
Item 2 is for welding of a plastic pipe liner strip to the new pipe. The strip is welded to
the end of one pipe. The other end is welded to the adjoining installed pipe in the field.
The strip is required for corrosion protection of the steel end rings on each pipe. The
cost to have Ameron weld the strip at the fabricating plant is believed to be significantly
less expensive than if the same weld were to be made in the field by Steve P. Rados
under more difficult working conditions and work space limitations.
Item 3 is for a time extension to the Ellis-Bushard intersection pipe fabrication
milestone. The Sanitation District recently negotiated a value engineering change
proposal with the intersection Contractor, which results in a new alignment of the
Page 2
1 96-inch diameter pipe to be installed in the intersection. Ameron is fabricating this pipe.
The new alignment requires several beveled pieces to be changed. The extension
allows the new alignment to be defined and the fabrication changes to be made by
Ameron before liquidated damages milestones become effective. This change is at the
Sanitation District's request.
Item 4 is for a contract language change to General Requirement 22 of the contract with
Ameron. At the May Board of Directors meeting, the General Manager or his designee
was delegated authority to make payments to the supplier. This change order makes
the contract language change to reflect the new delegation of authority.
Background for Item 4
Section 22 of the General Requirements, PAYMENT FOR WORK, requires that the
General Manager recommend monthly progress payments to the Board for approval.
Staff recommends the switch to standard construction contract progress payment
procedures with the General Manager or his designee as the highest approval authority.
This will simplify and accelerate the payment process.
ALTERNATIVES
The alternative for Item 4 would be to leave the contract procedure for progress
payments unchanged and obtain monthly Board approval.
CEQA FINDINGS
This project was included in the 1999 Strategic Plan Program EIR certified on
October 27, 1999. A Notice of Determination was filed on October 29, 1999.
Additional CEQA documentation for the project was included in Addendum No. 3 to the
EIR approved on December 19, 2001. Addendum No. 8 to the program EIR was
certified at the February 2006 Board meeting. These Addenda do not change CEQA
findings.
ATTACHMENTS
1. Budget Information Table
2. Change Order Status Report
3. Change Order Performance Report
4. Change Order
5. Location and Photo Description of Change Order
MB:dm
KWglobaMgenda Drag ReponMPDQI-2<PAR CO#1 0601M.dm
Page 3
BUDGET INFORMATION TABLE
Bushard Trunk Sewer Rehabilitation Pipe Procurement
JOB NO. 1-2-4P CO No. 1
ORIGINAL CURRENT PROPOSEDPROPOSED FUNDS THIS O ESTIMATED ESTIMATED
PRDJECT/PHASE AUTHORIZED PROJECT BUDGET REVISED AUTHORIZED TD AUTHORIZATION PROPOSED TOTAL
EXPENDITURE EXPENDED TO
IOECREA9E
BUDGET BUDGET INCREASE BUDGET DATE REQUEST AUTHORIZATION TO DATE DATE(%).
Phase I-PrOect DevelO mend $ 74.000 $ 74,000 $ 74,00D 5 74000 S 74,000 $ 74.649 101%
Phase 2-PmUrnine Desl n $ 10,000 $ 10000 $ 10000 $ 10.000 $ 10000 $ SA48 91%
Phase 3-Desl n S 2188000 $ 2168,000 $ 2168000 $ 2108.000 $ 2168000 $ 2178812 100%
Phase 4-COnatmdlon IS 48,142,00D S 58.142000 $ 184.901 $ 58328,94E $ 53034.054 $ 184948 $ 54,119,002 1 $ 26.051.405 48%
Phase 5-CommisslonIng $ 416.000 $ 416.000 $ 416.000 $ 326.000 $ 328.000 $ 251.609 77%
Phase B-Close-Out $ 72000 S 72000 $ 72.000 $ 40.000 $ 40000 $ 1,657 4%
Phase 7-Contingency $ 2,698D00 $ 2098000 f 18494E $ 2513.052 �'', $ 2.698,000 S 2.698,000 0%
PROJECTTOTAL $ 63.580.000 $ 63,580,000 $ $ 63,580,000 $ 5925D 054 $ 164,948 $ 5@435,002 S 2B,594,180 48%
Reimbursable Coati E 60,796
PROJECT NET $ 53.580.000 $ 63.580.000 $ - $ 63.580,000 ..;9 $ 59,260,064 1 E 184,94E S 59.435,002 1 E 28.664.975 48%
PSAIContract
PDSA-Boyle E 845300 $ 2467826 S 2.467.825 / $ 2.467.825 $ 2,457825 $ 2,165,745 68%
PDSA-Eadh Tech E 2000000 $ 2,052593 S 2062.593 S 2.052.593 $ 2062.593 $ 0%
PDSA-Melcalln Pimle - $ 223045 $ 223045 ;i $ 223.045 $ 223.045 $ 79267 30%
PDSA-Albed Grover $ - $ 153.000 $ 153A00 iy' E 15300a $ 153,000 $ 88.000 58%
Contred 1-24P-Amemn $ - $ 7,698777 184948 $ 7884725 '' $ ]699,77] 18494E $ 7.884726 $ 0%
-2 d 30280.09a3o4 3221039 Y $ 3 .28413E 1824739E 50%%
f0A0 H, 018I-2 d-Bubalo ,
600
Southern Caldomia Edison Is -is 350,0001 1 $ 3WDD0 1 1$ 360,0001 $ 350.000 $ 0%
MOMS 003800M
CHANGE ORDER PERFORMANCE REPORT
BUSHARD TRUNK SEWER REHABILIATION PIPE PROCUREMENT
JOB NO.I-2-4P,CHANGE ORDER NO.1
Contractor:AMERON INTERNATIONAL Project Category:COLLECTIONS
Design Consultant BOYLE ENGINEERING Contract%Complete:46% Original Contract Price: 57.699.777
CHANGE ORDER TYPES TRACKED INFORMATION ONLY
Unknown Condition Staff Requested Change rtelmbunabta Design Non-Reimbunabla Subhead CO Types Other Total
Error Design Errors Trashed
Change Orders $0 0.00% $0 0.00% $0 0.00% $184,948 2.40% $184,948 2.40% $0 0.00% $184,948 2.40%
this Period
Change Orden to $0 0.00% $0 0.00% $0 0.00% $0 0.00% $0 0.00% $0 0.00% $0 0.00%
Data
Charing.Order Total $0 0.00% $0 0.00% $0 0.00% $184,948 2.40% $184,948 2AO% $0 0.00% $184,948 2.40%
Program <300% <1.00% 0.00% <1.00% <5.00% 0.00% <5.00%
Performance Goals
The Change Order Management Plan tracks the Preceding four charge order types
Version 3/1/2006
EDMS 003SM7O
CHANGE ORDER STATUS REPORT
BUSHARD TRUNK SEWER REHABILITATION PIPE PROCUREMENT
JOB NO. 1-2-4P CO No. 1
APPROVAL CONTRACT CONTRACT COST PERCENTAGE AUTHORIZED AUTHORIZED TIME
ITEM DATE COST TO DATE INCREASE TIME TO DATE
(DAYS) (DAYS)
CONTRACT November7, 2005 $7,699,777.30 $7,699,777.30 260 260
CO.NOz1 Pending $184;948.00 !:'$7,884,725.30 2.40% 15 °275
EDMS 003609694
Page 1 of 5
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Ameron International C.O. No.: One 1
Date: June 28, 2006
Job: Bushard Trunk Sewer Rehabilitation Pipe Procurement
Job No. 1-2-4P
Consultant: Boyle Engineering Corporation
Amount of this Change Order(Add)(Oeduct) $184,948.00
In accordance with contract provisions, the following changes in the contract and/or contract
work are hereby authorized and as compensation,the following additions to or deductions
from the contract price are hereby approved.
ITEM 1 —TIME EXTENSION FOR INCLEMENT WEATHER
Pursuant to Section 41 of the General Conditions,the Contract time of completion and specific
fabrication milestones are extended due to inclement weather as follows:
Original Completion Time Extension Adjusted Completion
Date Calendar Da Date
Initial Fabrication Milestone February 20,2006 3 February 23, 2006
Mid-Point Fabrication
Milestone Aril 26 2006 8 May 4, 2006
Final Fabrication
Milestone/Contract End Date July 25 2006 8 August 2,2006
It is agreed that all time extensions granted shall be non-compensable.
ADDED COST THIS CHANGE ORDER ITEM: $0.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 8 Calendar Days
ITEM 2—WELDING OF PIPE LINER STRIP
This item is for welding of a four-Inch PVC liner strip to each bell of 735 sections of new 108-inch, and
33 sections of new 96-inch reinforced concrete pipe. This work is done at the place of manufacture.
This will match the conditions of the original 1-2-4 contract and avoid a more costly change order with
the 1-2-4 Contractor Rados. Under the 1-2-4 contract, only one weld had to be done on the four-inch
liner strip because the old pipe was delivered with integral liner extensions. The liner in the new pipe
supplied under the 1-2-4P contract is flush at the bell, such that a strip would have to be installed in the
field by Rados with two welds. Completion of one of those welds at the manufacturer's yard is less
costly than in the field. The work for each weld consists of setting up scaffolding, cleaning the existing
liner, and welding the liner strip to the existing liner. This change is an increase in the scope of work
and causes delays to the critical path. Noncompensable time extensions are granted as follows:
Page 2 of 5
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Ameron International C.O. No.: One (1)
Date: June 28. 2006
Job: Bushard Trunk Sewer Rehabilitation Pipe Procurement
Job No. 1-2-4P
Consultant: Boyle Enalneerino Corporation
Original/Current Time Extension Adjusted Completion
Completion Date Calendar Da Date
Mid-Point Fabrication
Milestone May 4 2006 7 Ma 11 2006
Ellis-Bushard Intersection
Fabrication Milestone May 15 2006 7 May 22 2006
Final Fabrication
Milestone/Contract End Date Au ust 2 2006 7 Au ust 9 2006
The additional work for this item was negotiated with the Contractor pursuant to Sections 23 and 24 of
the General Requirements. (Reference FCO 124P-1)
ADDED COST THIS CHANGE ORDER ITEM: $184,948.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 7 Calendar Days
ITEM 3—MILESTONE TIME EXTENSION FOR INTERSECTION DESIGN CHANGE
Pursuant to Section 40 of the General Conditions,the Ellis-Bushard Intersection Pipe Fabrication
Milestone is extended as follows:
Current Completion Time Extension Adjusted Completion
Date Calendar Da Date
Ellis-Bushard Intersection
Fabrication Milestone May 22 2008 1 18 June 9 2006
The work in the intersection has been delayed due to a pending design change to Job 1-2-4A (refer to
Change Order No. 1 to Job 1.2.4A). This design change also modifies some of the pipe sections to be
manufactured under this contract for the Intersection. The time extension extends the milestone as
required to accommodate the design change. This Item does not extend the contract and date, and is
non-compensable.
ADDED COST THIS CHANGE ORDER ITEM: $0.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
Page 3 of 5
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728.8127
CHANGE ORDER
Contractor: Ameron International C.O. No.: One(l)
Date: June 28, 2006
Job: Bushard Trunk Sewer Rehabilitation Pioe Procurement
Job No. I-2-4P
Consultant: Boyle Engineering Corporation
ITEM 4—CHANGE OF APPROVAL PROCESS FOR PAYMENT OF WORK
This item is for a change to Section 22 of the General Requirements, PAYMENT FOR WORK. The
first paragraph is changed to read the following: "Based on written recommendations by the
ENGINEER, the General Manager or his designee will accept monthly progress payment requests by
the SUPPLIER." This is done to simplify the progress payment process and ensure timely payments
to the SUPPLIER.
ADDED COST THIS CHANGE ORDER ITEM: $0.00
TIME EXTENSION THIS CHANGE ORDER ITEM: 0 Calendar Days
TOTAL ADDED COST THIS CHANGE ORDER: $184,948.00
TOTAL TIME EXTENSION THIS CHANGE ORDER: 15 Calendar Days
v
Page 4 of 5
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Ameron International C.O. No.: One 1
Date: June 28, 2006
Job: Bushard Trunk Sewer Rehabilitation Pipe Procurement
Job No. I-2-4P
Consultant: ale Enaineerina Corporation
The additional work contained within this change order can be performed incidental to the prime work
and within the time allotted for the original contract and any extensions to the contract time made by
this and all previously issued change orders. It is therefore mutually agreed that a 15 calendar day
extension of time to perform the work is required for this change order, and no other direct or indirect,
incidental or consequential costs, expenses, losses, or damages have been or will be incurred by
Contractor, except as expressly granted and approved by this change order.
SUMMARY OF CONTRACT TIME
Original Contract Date: November 7,2005
Original Contract Time: 260 Calendar Days
Original Completion Date: July 24, 2006
Time Extension this C.O.: 15 Calendar Days
Total Contract Time Extension: 15 Calendar Days
Revised Contract Time: 275 Calendar Days
Revised Final Completion Due Date: August 8, 2006
Time Subject to Liquidated Damages: WA
Actual Final Completion Date: WA
Original Contract Price $ 7,699,777.30
Prev. Authorized Changes $ 0.00
This Change (Add) (Deduet) $ 184,948.00
Amended Contract Price $ 7,884,725.30
Page 5 of 5
ORANGE COUNTY SANITATION DISTRICT
10844 ELLIS AVENUE, P.O. BOX 8127
FOUNTAIN VALLEY, CALIFORNIA 92728-8127
CHANGE ORDER
Contractor: Ameron International C.O. No.: One 1
Date: June 28, 2006
Job: Bushard Trunk Sewer Rehabilitation Pipe Procurement
Job No. 1-2-4P
Consultant: Boyle Engineering Corporation
Board Authorization Date: June 28,2006
ORANGE COUNTY SANITATION DISTRICT
Recommended by:
Tod E. Haynes, P.E. Date
Engineering and Construction Manager
Approved by:
David A. Ludwin P.E. Date
Director of Engineering
Accepted by:
Ameron International
Contractor Date
EDMS 003809697
r PDC COMMITTEE Nee06ere o� TO Bd.dDr.
loll0606/23/O6
AGENDA REPORT Item Number loan Number
VDCO660 13(1)
Orange County Sanitation District
Mist.6
Support Projects
FROM: David Ludwin, Director of Engineering
Originator: Christopher MacLeod, Project Manager
SUBJECT: PROFESSIONAL SERVICES AGREEMENT AMENDMENTS FOR
FACILITIES ENGINEERING CONSULTING SERVICES
GENERAL MANAGER'S RECOMMENDATION
Approve Amendment No. 2 to the Professional Services Agreements with Berryman
& Henigar; Brinderson; HDR (CGvL) Engineers; Dudek &Associates, Inc.; Jacobson
Helgoth Consultants, Inc.; Lee& Ro, Inc.; RMS Engineering & Design, Inc.; South
Coast Systems, Inc.; SPEC Services, Inc.; and Washington Group International for
services related to Facilities Engineering projects, in amounts not to exceed $200,000
for each agreement extension for a total amount not to exceed $2,000,000.
SUMMARY
• A "Facilities Engineering Project" is defined as a "miscellaneous capital improvement
or facility modification, replacement, or repair project, related to plant safety,
reliability, and efficiency enhancements, where professional consulting services are
not to exceed $100,000 ($75,000 for the original Task Order and $25,000 for any
additional amendments) for each project."
• Ten consulting firms have been selected to do this work with a maximum annual
limitation of$200,000 each. It also allows the extension of the Professional Service
Agreements (PSA) for two additional one-year extensions for a total maximum of
three years.
• The initial PSAs were approved at the June 23, 2004, Board of Director's meeting.
The first one year amendment was granted at the June 22, 2005 Board of Director's
meeting. This Amendment No. 2 is for the final one year extension. For Fiscal Year
2007/2008, a new selection process will be undertaken for these services.
PRIOR COMMITTEEIBOARD ACTIONS
Please refer to the attached PSA Status Report.
PROJECT/CONTRACT COST SUMMARY
Each of the ten firms under contract will be given a $200,000"not to exceed"
authorization on an as-needed basis. Specific project spending authorizations follow
the Delegation of Authority and are reported to the PDC each month in the facilities
engineering status report.
Page 1
BUDGET IMPACT •'
® This item has been budgeted. (Line item: CIP v2005-2006 Budget Section 8, pages 45, •�
108, 109, and 110)
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
Background
The Project Management Office (PMO) directs the work of each consultant. As each
individual facilities engineering project is developed, the PMO will define the Scope of
Work and produce a Task Order that will be submitted to a minimum of two consultants.
The consultants will propose a method, fee, and services required to complete the Task
Order.
The construction of all small projects follows the established Policies and Procedures
for the acquisition of contracting services. The PMO provides to the PDC Committee a
summary of the work authorized through the PSA on a monthly basis. The report
provides information related to the use of these consultants.
ALTERNATIVES
Decline the Amendment, thereby causing a slowdown or cessation in completing some
small projects. This would increase the small project backlog.
CEQA FINDINGS
Not Applicable - Each individual project will be subject to CEQA review.
ATTACHMENTS
1. Budget Information Table
2. PSA Status Reports
CM:kf
KV4globaMgenda Draft ReponsWDCTE Projects Agenda RepoM1dm
Page 2
BUDGET INFORMATION TABLE
FACILITIES ENGINEERING CONSULTING SERVICES
THIS REQUEST
ORIGINAL CURRENT PROPOSED PROPOSED FUNDS PROPOSED ESTIMATED ESTIMATED
PR;Consultants
AUTHORIZED PROJECT BUDGET REVISED AUTHORIZED BUDGET TOTAL EXPENDITURE COMPLETE
BUDGET BUDGET INCREASE BUDGET TO DATE INCREASE AUTHORIZATION AUTHORIZATION TO DATE TO DATE(%)
FE Pr
Desig(10 firS 2.004000 S 2.000.000 $ - $ 2,000,000 $ 2000.000 S IS - $ 2,000.000 $ NA
TOTAL IS 2.000,000 1 $ 2,000,000 1 $ - S 2,000.000 $ Z000.000 $ - S -is 2.000000 1 S NA
H beplbWN Gld MIaCFadlilies EWIM nr,G rsulliryalulgeanlofmaAonTeCk
Professional Services Agreement Status Report
Professional Services Agreement for Facilities Engineering Program
Job No. 99.29000
PO #101968-OB
Total Project Budget: $200,000
Consultant: Berryman & Henigar
Start Date of Project: 7/1/06
Date Amendment Description Cost Authorized
Costs
7/1/04 Original Provide on-call professional engineering services
for FY 04-05 $200,000 $200,000
7/1/05 1 Extend on-call professional engineering services
for FY 05-06 $200,000 $200,000
Pending 2 Extend on-call professional engineering services
for FY 06-07 $200,000 $200,000
CM:kf
H:Wept` nglCM MiscTadlhies Engineering ConsuginglProfessional Services Agreement Slelus Repon(Chds).doc
05/25/06
Professional Services Agreement Status Report
Professional Services Agreement for Facilities Engineering Program
Job No. 99.29000
PO #101969-OB
Total Project Budget: $200,000
Consultant: Brinderson
Start Date of Project: 7/1/06
Date Amendment Description Cost Authorized
Costs
7/1/04 Original Provide on-call professional engineering services
for FY 04-05 $200,000 $200,000
7/1/05 1 Extend on-call professional engineering services
for FY 05-06 $200,000 $200,000
Pending 2 Extend on-call professional engineering services
for FY 06-07 $200,000 $2001000
CM:kf
H:UeptUng\CM MlsclFacilities Engineering ConsugingWrotesslonal Services Agreement Status Repod(Chris).doc
05/25/06
Professional Services Agreement Status Report
Professional Services Agreement for Facilities Engineering Program
Job No. 99.29000
PO #101970-OB
Total Project Budget: $200,000
Consultant: HDR
Start Date of Project: 7/1/06
Data Amendment Description Cost Authorized
Costs
7/1/04 Original Provide on-call professional engineering services
for FY 04-05 $200,000 $200,000
7/1/05 1 Extend on-call professional engineering services
for FY 05-06 $200,000 $200,000
Pending 2 Extend on-call professional engineering services
for FY 06-07 $200,000 $200,000
CM:kf
RVIepVeng1CM Ma;6Facilities Engineering ConsultinglpmMsslonal Services Agreement Status Report(Chris).doc
05/25/06
Professional Services Agreement Status Report
Professional Services Agreement for Facilities Engineering Program
Job No. 99.29000
PO #101971-OB
Total Project Budget: $200,000
Consultant: Dudek & Associates, Inc.
Start Date of Project: 7/1/06
Date Amendment Description Cost Authorized
Costs
7/1/04 Original Provide on-call professional engineering services
for FY 04-05 $200,000 $200,000
7/1/05 1 Extend on-call professional engineering services
for FY 05-06 $200,000 $200,000
Pending 2 Extend on-call professional engineering services
for FY 06-07 $200,000 $200,000
CM:kf
M:beptlengtCM Misc\Facllgies Engineering ConsugingTrafessioral Services Agreement Status Report(Chns)Aoc
05/25/06
Professional Services Agreement Status Report
Professional Services Agreement for Facilities Engineering Program
Job No. 99.29000
PO #101972-OB
Total Project Budget: $200,000
Consultant: Jacobson Helgoth Consultants, Inc.,
Start Date of Project: 7/1/06
Date Amendment Description Cost Authorized
Costs
7/1/04 Original Provide on-call professional engineering services
for FY 04-05 $200,000 $200,000
7/1/05 1 Extend on-call professional engineering services
for FY 05-06 $200,000 $200,000
Pending 2 Extend on-call professional engineering services
for FY 06-07 $200,000 $200,000
CM:kf
H:Weplleng\CM MlscTacilitles Engineering ConsultingTmIessional Services Agreement Status Report(Cluis).doc
05/25/06
Professional Services Agreement Status Report
Professional Services Agreement for Facilities Engineering Program
Job No. 99.29000
PO #101973-OB
Total Project Budget: $200,000
Consultant: Lee & Ro
Start Date of Project: 7/1/06
Date Amendment Description Cost Authorized
Costs
7/1/04 Original Provide on-call professional engineering services
for FY 04-05 $200,000 $200,000
7/1/05 1 Extend on-call professional engineering services
for FY 05-06 $200,000 $200,000
Pending 2 Extend on-call professional engineering services
for FY 06-07 $200,000 $200,000
CM:kf
H:WeppengZM MisffaclNties Engineering Consuginglprofessional Services Agreement Stales ReporgChris).doc
05/25/06
Professional Services Agreement Status Report
Professional Services Agreement for Facilities Engineering Program
Job No. 99.29000
PO #101974-OB
Total Project Budget: $200,000
Consultant: RMS Engineering & Design, Inc.
Start Date of Project: 7/1/06
Date Amendment Description Cost Authorized
Costs
7/1104 Original Provide on-call professional engineering services
for FY 04-05 $200,000 $200,000
7/1/05 1 Extend on-call professional engineering services
for FY 05-06 $200,000 $200,000
Pending 2 Extend on-call professional engineering services
for FY 06-07 $200,000 $20010 00
CM:kf
H:Wept%eng1CM Misffacitilies Engineenng Consullingl rofessional Services Agreement Status Repod(Chns).doc
O5/25/06
Professional Services Agreement Status Report
Professional Services Agreement for Facilities Engineering Program
Job No. 99.29000
PO #101975-013
Total Project Budget: $200,000
Consultant: South Coast Systems, Inc.
Start Date of Project: 7/1/06
Date Amendment Description Cost Authorized
Costs
7/1/04 Original Provide on-call professional engineering services
for FY 04-05 $200,000 $200,000
7/1/05 1 Extend on-call professional engineering services
for FY 05-06 $200,000 $200,000
Pending 2 Extend on-call professional engineering services
for FY 06-07 $200,000 $2001000
CM:kf
H:depAenglCM Misffacilities Engineenng ConsultingTwfesslonal Services Agreement Status Report(Chris).doc
05/25/06
Professional Services Agreement Status Report
Professional Services Agreement for Facilities Engineering Program
Job No. 99.29000
PO #101976-OB
Total Project Budget: $200,000
Consultant: SPEC Services
Start Date of Project: 7/1/06
Date Amendment Description Cost Authorized
Costs
7/1/04 Original Provide on-call professional engineering services
for FY 04-05 $200,000 $200,000
7/1/05 1 Extend on-call professional engineering services
for FY 05-06 $200,000 $200,000
Pending 2 Extend on-call professional engineering services
for FY 06-07 $200,000 $200,000
CM:kf
H:beptlengtCM MlscWacilities Engineenng ConwltingtPMfenional Services Agreernenl Status Reporl(Chris).doc
05/25/06
Professional Services Agreement Status Report
Professional Services Agreement for Facilities Engineering Program
Job No. 99.29000
PO #101977.OB
Total Project Budget: $200,000
Consultant: Washington Group International, Inc.
Start Date of Project: 7/1/06
Date Amendment Description Cost Authorized
Costs
7/1/04 Original Provide on-call professional engineering services
for FY 04-05 $200,000 $200,000
7/1/05 1 Extend on-call professional engineering services
for FY 05-06 $200,000 $200,000
Pending 2 Extend on-call professional engineering services
for FY 06-07 $200,000 $2001000
CM:kf
H:%deppeng\CM MinTacilgies Enginexing ConsusingTroressional Services Agreement Status Report(Chris).doc
05/25/06
(
MINUTES OF THE JOINT MEETING OF THE
FINANCE, ADMINISTRATION AND
HUMAN RESOURCES COMMITTEE & STEERING COMMITTEE
SPECIAL MEETING—BENEFITS WORKSHOP
Orange County Sanitation District
Wednesday, May 18, 2006, 5:00 p.m.
A joint meeting of the Finance,Administration and Human Resources Committee and the
Steering Committee of the Orange County Sanitation District was held on May 18,2006,at
5:00 p.m., in the Sanitation District's Administrative Office.
(2) The roll was called and a quorum declared present, as follows:
FAHR COMMITTEE MEMBERS: STAFF PRESENT:
DIRECTORS PRESENT: Jim Ruth, Interim General Manager
Darryl Miller, Chair Lisa Tomko, Director of Human Resources
Mike Duvall,Vice Chair Lorenzo Tyner, Director of Finance
Bill Dalton Jeff Reed, Human Resources Manager
Rich Freschi Rich Spencer, Human Resources Supervisor
Phil Luebben Lilia Kovac, Committee Secretary
Joy Neugebauer
Mark Waldman
Steve Anderson, Board Chair OTHERS PRESENT:
Brad Hogin, General Counsel
Norbert Gaia
DIRECTORS ABSENT: Juanita Skillman
Jim Ferryman,Vice Board Chair
James W. Silva
(3) APPOINTMENT OF CHAIR PRO TEM
No appointment was necessary.
(4) PUBLIC COMMENTS
There were no public comments.
(5) OCSD BENEFITS PROGRAM OVERVIEW
Lisa Tomko, Director of Human Resources, presented the District's employee demographics
and an overview of the current insurance and retirement benefits program with its associated
costs to both the District and to the employees. Ms. Tomko and Richard Spencer, Human
Resources Supervisor, also reviewed possible cost reductions recommendations based on
market trends for consideration by the Committee to mitigate other cost increases.
Minutes of the Regular Joint meeting of the Finance,Administration and Human
Resources Committee and Steering Committee Meeting
May 18,2006
Page 2
(6) CLOSED SESSION
The Committee convened in Closed Session at 6:05 p.m. pursuant to Government Code Section
54957.6 to confer with designated representatives Lisa Tomko, Director of Human Resources;
Jeff Reed, Human Resources Manager; and Rich Spencer, Human Resources Supervisor, re
Meet and Confer Update re contract negotiations for employees represented by 1).Orange
County Employees Association; 2). International Union of Operating Engineers, Local 501, and
3). Supervisors, Professional Management Team (part of Peace Officers Council of California),
Government Code Section 54957.6. Confidential Minutes of the Closed Session held by the
Finance,Administration and Human Resources Committee have been prepared in accordance
with California Government Code Section 54957.2, and are maintained by the Board Secretary
in the Official Book of Confidential Minutes of Board and Committee Closed Meetings. No
reportable actions were taken re Agenda Item No. 6(a).
RECONVENE IN REGULAR SESSION: At 7:15 p.m., the Committee reconvened in regular
session.
(7) ADJOURNMENT
The Chair declared the meeting adjourned at 7:18 p.m.
Submitted by:
14 Act,—
Lille Kovac
Committee Secretary
K%tlepragendaT-A R\FA R20061051806 Benefits WoMshop�,051806 Benefits Workshop Minutes.doc
MINUTES OF THE REGULAR JOINT MEETING OF THE
FINANCE, ADMINISTRATION AND
HUMAN RESOURCES COMMITTEE& STEERING COMMITTEE
Orange County Sanitation District
Wednesday,June 14, 2006, 5:00 p.m.
A joint meeting of the Finance, Administration and Human Resources Committee and the
Steering Committee of the Orange County Sanitation District was held on June 14, 2006, at
5:00 p.m., in the Sanitation District's Administrative Office.
(1) The roll was called and a quorum declared present, as follows:
FAHR COMMITTEE MEMBERS: STAFF PRESENT:
DIRECTORS PRESENT: Jim Ruth, Interim General Manager
Darryl Miller, Chair Nick Arhontes, Director of Regional Assets and
Mike Duvall, Vice Chair Services
Bill Dalton Bob Ghirelli, Director of Technical Services
Rich Freschi Jim Herberg, Director of Operations and Maintenance
Jim Ferryman, Vice Board Chair Patrick Miles, Director of Information Technology
Phil Luebben Lorenzo Tyner, Director of Finance
Joy Neugebauer Jeff Reed, Human Resources Manager
James W. Silva Mike White, Controller
Mark Waldman Bret Colson, Public Information Manager
Lilia Kovac, Committee Secretary
OMTS COMMITTEE MEMBERS
DIRECTORS PRESENT
Carolyn Cavecche, Chair OTHERS PRESENT:
Don Bankhead, Vice Chair Brad Hogin, General Counsel
Sukhee Kang Don McLean, Driver Alliant
Dave Shawver Juanita Skillman
Dave Sullivan Ryal Wheeler
Norbert Gaia
DIRECTORS ABSENT:
Steve Anderson, Board Chair
(2) APPOINTMENT OF CHAIR PRO TEM
No appointment was necessary.
(3) PUBLIC COMMENTS
There were no public comments.
(4) REPORT OF THE COMMITTEE CHAIR
Chair Miller had no report.
Minutes of the Regular Joint meeting of the Finance, Administration and Human
Resources Committee and Steering Committee Meeting
June 14, 2006
Page 2
(6) REPORT OF THE GENERAL MANAGER
Jim Ruth, Interim General Manager, had no report
(6) REPORT OF DIRECTOR OF FINANCE/TREASURER
Director of Finance, Lorenzo Tyner,had no report
(7) REPORT OF DIRECTOR OF HUMAN RESOURCESPUBLIC INFORMATION OFFICE
Jeff Reed, Human Resources Manager, had no report.
(8) REPORT OF GENERAL COUNSEL
Brad Hogin, General Counsel, had no report.
(9) CONSENT CALENDAR ITEMS
a. Approve minutes of the May 10,2006 and May 18, 2006 joint meetings of the Finance,
Administration and Human Resources Committee and Steering Committee regular
meeting, and Benefits Workshop special meeting.
b. FAHR06-43 Receive and file Employment Status Report as of May 22, 2006.
C. FAHR0B-44 Receive and file OSHA Incidence Rates and Workers' Compensation
Claims and Costs Report.
d. FAHRO6-45 Recommend to the Board of Directors to adopt Resolution No. 06_,
amending Resolution No. OCSD 98-33, amending Human Resources
Policies and Procedures Manual.
Motion: It was moved, seconded and duly carried to approve the recommended
action for the item specked as 9(a) through 9(d) under consent calendar.
END OF CONSENT CALENDAR
(10) ACTION ITEMS
a. FAHR0646 Approve FY 2006/07 and 2007/08 Proposed Operating, Capital,
Debt/COP Service and Self-Insurance Budgets for FY 2006.07 and
2007-08, as follows:
2006-07 2007-08
Net Operations, Maintenance & Working Capital $129,054,210 $135,602,130
Worker's Compensation Self Insurance $526,200 $559,400
General Liability and Property Self Insurance $1,766.100 $2,055,200
Net Capital Improvement Program $266.088,000 $338,818,000
Debt/COP Service $54,410,000 $65,462,000
Other Requirements $4,499,800 $2,645,300
Total $456,344,310 $545,142,030
Minutes of the Regular Joint meeting of the Finance, Administration and Human
Resources Committee and Steering Committee Meeting
June 14, 2006
Page 3
Lorenzo Tyner, Director of Finance, presented the highlights of the
District's two-year budget for approval based on the recommended CIP
cost reductions and newly-adopted rate increase approved at the May
Board of Directors meeting.
Motion: It was moved, seconded and duly carried to recommend approval to the
Board of Directors
b. FAHRO647 Recommend to the Board of Directors to renew the District's Boiler&
Machinery Insurance Program for the period July 1, 2006 to June 30,
2007, in an amount not to exceed $25,387.
Mike White, Controller, introduced Don McLean of DriverAlliant, who
briefly presented the insurance program for the District's boiler and
machinery. Concern was expressed by the Directors on the timing of this
proposal, and was requested that these proposals be submitted to the
FAHR committee for approval in Mayof future years, so that time is
allowed to review or seek more competitive bids prior to recommending to
the full Board for approval.
MOTION: It was moved, seconded and duly carried to recommend approval to the
Board of Directors.
C. FAHRO6-48 Recommend to the Board of Directors to renew the District's Excess
Workers' Compensation Insurance for the period July 1, 2006 through
June 30, 2007, in an amount to be determined at the June28, 2006 Board
of Directors' meeting.
MOTION: It was moved, seconded and duly carried to recommend approval to the
Board of Directors.
d. FAHRO"9 Recommend to the Board of Directors to renew the District's AII-Risk
Property and Flood Insurance Program for the period Julyl, 2006 through
June 30, 2007, in an amount not to exceed $777,833.
MOTION: It was moved, seconded and duly carded to recommend approvalto the
Board of Directors.
e. FAHRO6-50 Recommend to the Board of Directors to renew the District's Excess
General Liability Insurance Program for the period Julyt, 2006 through
June 30, 2007, in an amount to be determined.
MOTION: It was moved, seconded and duly carried to recommend approval to the
Board of Directors.
Minutes of the Regular Joint meeting of the Finance, Administration and Human I -.
Resources Committee and Steering Committee Meeting
June 14, 2006
Page 4
(11) INFORMATIONAL ITEMS
There were none.
(12) CLOSED SESSION
There was no closed session.
(13) OTHER BUSINESS. COMMUNICATIONS OR SUPPLEMENTAL AGENDA ITEMS, IF
ANY
There were none.
(14) MATTERS WHICH A DIRECTOR MAY WISH TO PLACE ON A FUTURE AGENDA FOR
ACTION AND STAFF REPORT
Chair Miller requested that a presentation of the insurance selection process be given at the July
FAHR Committee meeting.
(15) CONSIDERATION OF UPCOMING MEETINGS
The next regular FAHR Committee meeting is scheduled forJuly 12, 2006, at 5:00 p.m.
(16) ADJOURNMENT
The Chair declared the meeting adjourned at 6:17 p.m.
Submitted by:
Lilia Kovac
Committee Secretary
H:Wept%f\Pub11c Aflaintl320tBSVAinutesl061406 DRAFT FAHR Minutes.dac
i
FAHR COMMITTEE Meeting Date Tu Vj.0f Dir.
O6Jt4/06 1 06/2a 6
AGENDA REPORT Item Number Item Number
FAHR06-45 14(b)
Orange County Sanitation District
FROM: Lisa L. Tomko, Director of Human Resources
Originator: Paul Loehr, Human Resources Supervisor
SUBJECT: CHANGES AND ADDITIONS TO HUMAN RESOURCES POLICIES AND
PROCEDURES MANUAL AS AUTHORIZED BY RESOLUTION 98-33.
GENERAL MANAGER'S RECOMMENDATION
Adopt Resolution No. OCSD 06-15, amending Resolution No. OCSD 98-33, amending
the Human Resources Policies and Procedures Manual.
SUMMARY
Policy B150.00 (Recruitment and Selection) is being updated with focus placed on the
Interview Process and Employment Offers sections. The recommended changes listed
in the table below are intended to streamline the recruitment process, expedite staffing
placement, reduce interview panel costs, reinforce process fairness and consistency,
and establish Department Head hiring authority.
Policy Number and Subject Summary of Policy Changes
• Reduce the number of interview panel members
from five (5)to three (3).
• Separate the role of Human Resources
representatives from active panel members to
B150.00, Recruitment and Selection facilitators, consultants, and process monitors.
• Provide a process that places the final selection
decision with the Department Head (or designee).
• Outline the process for salary placement of selected
candidates.
PRIOR COMMITTEEIBOARD ACTIONS
• Human Resources Policies and Procedures Manual revisions were presented at the
April 2006 FAHR Committee and Board of Directors meetings.
PROJECT/CONTRACT COST SUMMARY
N/A
X:keWWenEaBw,E 1penCa Repo�s20C68oarp g9en0a 8 Fgentle 11BgMSN3O3u.1C(G)XR Vdlry Gcc
Page 1
BUDGET IMPACT
❑ This item has been budgeted. (Line item: )
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
Policy changes are provided in a format, whereby, new language is highlighted and
deleted language is struck. Aside from the changes denoted in the summary section of
this report, policy B150 also includes minor language revisions for consistency and
clarification of policy definitions/procedures.
Changes and additions to the Human Resources Policies and Procedures Manual are
done on a quarterly basis. The next quarterly update is tentatively scheduled for
September 2006.
ALTERNATIVES
N/A
CEQA FINDINGS
N/A
ATTACHMENTS
1. B150.00 (Recruitment and Selection)
2. Resolution No. OCSD 06-15
HtlM�a'1'aaG Poam AM Ham.�erE RY+^aa6Mnla HRa '�EMNmm 1N0)HNPyryOx
Page 2
as
RESOLUTION NO. OCSD 06-15
AMENDING RESOLUTION NO. OCSD 98-33
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE ORANGE
COUNTY SANITATION DISTRICT AMENDING THE HUMAN RESOURCES
POLICIES AND PROCEDURES
The Board of Directors of the Orange County Sanitation District,
DOES HEREBY RESOLVE, DETERMINE AND ORDER:
Section 1: That Exhibit"A" of Resolution No. OCSD 98-33 is hereby amended by
amending Policy No. B150.00, Recruitment and Selection, set forth in Attachment No. 1,
attached hereto and incorporated herein by reference.
Section 2: That all other terms and conditions of Resolution No. OCSD 98-33, as
previously recommended, shall remain in full force and effect.
Section 3: That all future amendments to Resolution No. OCSD 98-33 be made by
Resolution.
PASSED AND ADOPTED at a regular meeting held June 28, 2006.
Chair
ATTEST:
Board Secretary
Orange County policy Number: B150.00
Sanitation District Effective Date: June 28, 2006
MaFsh23,280g
Subject: RECRUITMENT AND SELECTION Supersedes: March 23, 2006
July i-4, 2004
Approved by: Lisa L. Tomko
1.0 PURPOSE
1.1 The purpose of this policy is to establish uniform guidelines and procedures for
Orange County Sanitation District(OCSD)recruitment activities.
2.0 ORGANIZATIONAL UNITS AFFECTED
2.1 This policy applies to all OCSO departments,divisions, seat an and employees.
3.0 DEFINITIONS
3.1 Recruitment is the process of attracting qualified individuals to apply for employmeiil
opportunities jabs that are advertised open by withia the organization,whether internal
or open extemal.
3.2 Internal recruitment means considering only current preseaE employees as applicants
for job openings within the organization.
3.3 Open recruitment means attracting applicants from outside the organization,as well
as internally to apply for job openings within the organization.
3.4 Planned Recruitment is the process of recruiting a candidate for a position held by an
existing OCSD employee who plans to retire or leave the agency.
3.5 Probationary Period-Initial as defined in applicable Memorandum of Understanding
(MOU)provisions, includes at least the first 6 months or 26 weeks of employment with
OCSD beginning with the date of hire. This period is regarded as an extension of the
hiring process, and provides an opportunity for both the employee and OCSD
management to assess, over a substantial period of time,whether or not the hiring
decision was appropriate. Employees who have not yet successfully completed their
initial probationary period serve"at-will"and may be released from employment
without cause or recourse to any appeal or grievance procedures.
3.6 Probationary Period-Promotional as defined in applicable MOU provisions,includes
at least the first 6 months or 120 days of employment with OCSD, beginning with the
effective date of promotion. This period is regarded as an extension of the selection
process, and provides an opportunity for both the employee and OCSD management
to assess, over a substantial period of time,whether or not the decision was
appropriate. "At-will"employees do not serve a promotional probationary period.
3.7 Probationary Period—Reassignment or Lateral Transfer as defined in applicable
MOU provisions, includes at least the first 26 weeks of employment with OCSD,
Page 1 of 13
I
beginning with the effective date of the reassignment or lateral transfer. This period
provides an opportunity for both the employee and OCSD management to assess,
over a substantial period of time,whether or not the decision was appropriate.
3.8 Relative is any person related by one of the following familial relationships to any
employee at OCSD: spouse, mother, father, brother, sister,child,step child, step
parent, grandmother, grandfather, grandchild, cousin, aunt, uncle, mother-in-law,
father-in-law, brother-in-law or sister-in-law.
4.0 POLICY
4.1 OCSD is an Equal Opportunity Employer(EDE). OCSD does not discriminate on the
basis of race, religion, color, national origin, disability, pregnancy, martial status, age,
gender, sexual orientation, or participation in any protected classlactivity.
4.2 It is OCSD's polity to provide nondiscriminatory, lawful, and consistent guidelines and
procedures to all recruitment processes, whether internal or open.
5.0 PROCEDURE
5.1 PERSONNEL REQUISITION
5.1.1 A personnel requisition is the first step for the DepetmerthHeedjord`eeignee)
to communicate staffing needs to the Human
Resources Department. If the recruitment requires testing(hands-on, written,
essay, etc.)as part of the recruitment process,the testing methods must be
reviewed for validity and reliability by the Human Resources Department prior
to the initiation of a personnel requisition.
5.1.2 The Department Head(or designee)i managerisupew so completes the
personnel requisition and routes for the required reGaiveii the api ate
signatures Fequi red-before sending it to the Human Resources Department.
5.1.3 The Human Resources representative resaster reviews the requisition to
make sure the qualifications are appropriate for the position. If changes are
necessary, the Human Resources representative will work with the
appropriate Department Head(or designee)manager/supervisev.
5.2 EMPLOYMENT OPPORTUNITY BULLETINS/POSTINGS
5.2.1 The Human Resources representative resraiIs prepares the employment
opportunity bulletin, also known as a posting. Each posting will include the
following information:
• Wage range
• Department
• Brief job description
• Required qualifications
• Desired qualifications
• Posting/closing dates
• Procedure for applying
• Brief benefits overview
5.2.2 The Humen'Resources representative resrader provides the draft posting to
the Department Head(or designee) h FiRg MAAags4supaN so for approval.
Page 2 of I 1
5.2.3 Upon approval, all ether job postings are shall-be advertised as internal
recruitments for ten business days, unless an open recruitment is authorized
by the Director of Human Resources, or designee. Upon-approval;All job
postings for Student Intern and Executive Management positions may be
advertised as an open recruitment(internal aad-exteraay at the beginning of
the recruitment process.
5.2.4 During the internal or open recruitment pasting process, if there is at least one
internal applicant and he/she meets the minimum qualifications for the
position,that applicant will be interviewed. If an internal applicant is not
selected or if there are no internal applicants,the position is shall be
advertised as an external open recruitment.
5.2.5 Internal job opportunities will be posted to the intranet which is accessible to
all OCSD employees.
5.2.6 Internal Job Announcement Notifications are sent via e-mail to all OCSD
employees for internal and open extental recruitments.
5.3 ADVERTISING
5.3.1 Advertising for positions at OCSD ensures positions are filled with the best-
qualified candidate for the job. OCSD shall make every reasonable effort to
advertise open exlemal positions to all segments of the public to ensure EDE
guidelines are followed.
5.3.2 All positions are advertised on the internet and may be posted in other media
when deemed appropriate. Technical and hard-to-fill positions are advertised
on trade specific websites.
5.3.3 Trade magazines and other forms of advertising may be used for hard-to-fill
or specialized positions.
5A APPLICANT SCREENING
5.4.1 Applications and resumes are shag only be accepted electronically,afW
Marsh-2005. All other application material will be accepted at the Interview
pre086 . Unsolicited application material will not be accepted at anytime.
5.4.2 Once an application and/or resume is received and reviewed, it will only be
selected for further consideration if the minimum job requirements for the
open position are met.
5.4.3 The Department Head"(or designee) is given
access to files within en the online application program pertinent to the job
opening for which the Department Head (or designee)manager submitted a
personnel requisition. The Department.Head'(or designee)manager may
review applications that meet the minimum qualifications to determine which
candidates may be interviewed.
5.4.4 All materials(e.g., applications, resumes, interviewer notes, interview
packets, packets, etc.)submitted by applicants/candidates or`g'enerated.by
OCSD staff during the interview process are confidential and are considered
OCSD property and must be returned to the Human Resources Department
Page 3 of I 1
upon completion of the hiring process. PJI recruitment files are maintained by
OCSD in accordance with established record keeping guidelines.
5.5 INTERVIEW PROCESS
5.5.1 The interview panel members are selected along with the interview date(s).
Applicants are scheduled, interview questions are prepared, and the interview
panel conducts the actual interview.
5.6.2 A Human Resources representative and the hiring supervisor shall the
work together to select the interview panel,
which consists of three:panel members. Howeve;,the mG�tar makes the
panel. The interview panel will becompdsed
of the hiring supervisor, one additional member from within the department,
and one from outsidethe department. The Human Resources Department
representative will facilitate and monitor the interview process, but will not
have a vote.
5.5.3 The Human Resources Department monitors pahef�com"p'osition to ensure
that there is no conflict of interest when a candidate is;known to a current or
former employee.
5.5A The Human Resources representative reGpAter and the Department Head(or
designee)shall hiring-manager work together to establish a set of interview
questions and criteria for the candidates.
5.5.5 The Human'Resources,representative mnri tiler prepares interview packets
and distributes them to the interview panel. Packets include:
• An overview of the interview process
• A copy of the interview schedule
• A copy of the employment bulletin opporunitylposting
• Copies of candidate applications
• Interview questions and evaluation forms for each candidate
5.5.6 The interview panel will meet at least one half hour before the interview to
gain an understanding from the hiring supervisor about the criteria with which
to rank the ideal candidates. The hiring supervisor,in consultationwith the
Human Resources Representative,may add or delete questions providing
they are related to the pre-established criteria. The panel :^"`..,.final ze the
FBGFU tSF. The panel may add oF delete quest GAS. The panel will ga n a
5.5.7 The Human Resources representative reeraiis facilitates the interview
process.When interviews are completed,the interview panel members
evaluate each candidate interviewed. The top thme Gand dates am identilie
the interview,
interview presess-The panel will-rank a list of the top candidates(no more
than three)based on a majority decision.The hiring supervisor will then
Page 4 of 1 I
choose from among the lop candidates with the.concurrence of the.General
Manager(or designee).,TherDepartment Headl(or designee)will.report the
final hiring:decision to the.Human Resources Department, to include:all
applicable interview.materials(e.g.,applications resumes, interviewer notes,
interview packets, etc.).
5.5.8 The fine' .-ndidate ,.sAig............. the top thF..e sandidate_ heR a . ajeF.
MaaageF OF d8migaea
5.6 RECRUITMENTAPPEALS PROCESS
5.6.1 Employees should bring recruitment process and decision-making issues to
the attention of the Human Resources Manager as soon as possible. The
manager will review the issue and provide a written response within five
business days from the issue notification date.
5.6.2 If the issue is not resolved to the employee's satisfaction,the employee may
file a written statement concerning the problem to the Director of Human
Resources within ten business days of receipt of the manager's decision.
Upon request by either party, a meeting may be held to discuss the issue and
establish remedies.
5.6.3 The employee will be provided a written response from the Director of Human
Resources(or designee);eFdesignse,within ten business days after the
employee's their statement is received. The decision of the Director of
Human Resources, or designee,is final (see policy F50.00, Problem Solving
Procedure and F60.00, Grievance Procedure).
5.6.4 Time limits may be extended for cause upon mutual consent of the parties.
5.7 EMPLOYMENT OFFERS
5.7.1 The Human Resources to"presentative resnuteF and Department'Head_(or
designee)hiring-supewisecdetermine an appropriate starting salary for all
candidates, except those designated as"at-will"employees, based on a
Salary Offer Analysis. This analysis will include the applicant's:
• Qualifications
• Years of experience
• Educational background
• Salary history
• Parity within the Department
5.7.2 The Human Resources Compensation Analyst reviews Me-recommended a
job candidate's salary request prepares an analysis,and approves F makes
a additienai recommendations on placement in theapplicable salary range.
All salary affem that am either at eF beyeAd step 4 of the�ange w 11 reqU F8 th
, oF deg gnes. If market or other
conditions nece, itateroffering a job candidate a pay rate up to the salary
range mid-point, a department head may recommend,and with the
concurrence of the Director of Human Resources, may approve the proposed
Page 5 of 11
r
hire rate.-:The General Manager, or designee,shall approve all recommended
salary offers that would result in anew hire pay rate at Step 4 or greater.
Under no circumstances should panel members (excluding the Human
Resources representative)or any other OCSD employee discuss salary
offers with candidates or make promises of any kind. Human
Resources staff are the only employees authorized to engage in salary
discussions with job candidates.
5.7.3 The Human Resources representative renR I Wr completes a status change
form for the candidate and initiates the background investigation. Background
investigation results are provided to the candidate by OCSD's background
screening firm.
63A When the status change form is approved,the Human Resources
representative recruiter makes a verbal employment offer to the candidate,
which is contingent upon results of a background investigation, pre-
employment physical and drug screening. Upon acceptance of the
employment offer,the Human Resources representative resneter sends
letters of_regret regre4leaem to unsuccessful candidates. Internal candidates
are contacted personally prior to receiving letters of regret regretletters.
5.7.5 The Human Resources representative maRider schedules the pre-
employment physical and drug screen for the candidate, works with the
Department`Heard_(ordeslgnee)suparwso to establish a potential start date
and prepares a formal offer letter for the candidate.
5.7.6 When the Human Resources representative reswitev(or designee)has
cleared the background investigation, pre-employment physical and drug
screening results,the applicant will be contacted to confirm the employment
offer.
5.7.7 The Human Resources representative coordinates the candidate's start date.
5.7.8 In the event that a candidate is selected and voluntarily or involuntarily
vacates the position prior to completing the required six month probationary
period,the Human Resources Department,at the request of the Department
Head(or dasignee}gidag-maaager, may exercise the option to extend an
offer to the second candidate from the original interview process.
5.8 PLANNED RECRUITMENT
5.8A In instances where an existing OCSD employee plans to retire or leave the
agency,the Department Head may request to initiate the planned recruitment
process by notifying the Director of HR,or designee. If approved,the Human
Resources Department shall begin the recruitment process for the anticipated
vacancy using the internal recruitment process. The Human Resources
Department must have a minimum of six months notice to consider a planned
recruitment, a signed memo from the existing OCSD employee stating his/her
retirement or leave date, and at least one budgeted but vacant position that
OCSD can borrow from.
5.8.2 The Planned Recruitment process will be initiated,as scheduling permits,
prior to the individual leaving OCSD in order to allow for an adequate amount
of cross training.
Page 6 of I 1
5.8.3 If a candidate is selected from the internal recruitment process,the candidate
shall remain in his/her existing position with the same salary and benefits
while cross-training in the new position as scheduling permits.
5.8.4 The candidate shall assume the salary, benefits and full range of duties of the
vacant position the first business day that the position is vacant. The position
used to initiate the planned recruitment will than be returned to the poor
within the Division 540 full-time equivalent(FTE)budget for use with other
planned recruitments.
5.8.5 The date the candidate assumes the vacant position shall be the first day of
the candidate's six-month probationary period. The six-month probationary
period will be utilized as an opportunity for the candidate and OCSD
management to assess whether or not the decision was appropriate. The
candidate may be returned to his/her previous position if the decision is
determined to be inappropriate.
5.8.6 If a candidate is not selected from the internal recruitment process, the
position will be posted for external candidates immediately to ensure an
adequate amount of time for cross-training.
6.0 EXCEPTIONS
6.1 EMPLOYMENT OF FORMER EMPLOYEES
6.1.1 Employment of former employees for full-time equivalent or part-time
positions shall be subject to and conducted in accordance with this policy.
6.1.2 Employment of a former employee is subject to the approval of the General
Manager and the Director of Human Resources.
6.1.3 In all cases, approval of the General Manager and the Director of Human
Resources shall be received prior to an offer of employment to a former
employee.
6.1.4 OCSD policy prohibits the rehire of former full-time, regular employees or"at-
will"employees who:were terminated for workplace misconduct; resigned
while charges were pending against the employee; resigned while serving a
suspension;failed to provide two weeks written notice in advance of
resignation depending upon employment status, unless approved by the
Director of Human Resources, or designee; or failed to return to work
following an absence without leave of 40 consecutive work hours without
notifying the immediate supervisor or the Human Resources Department with
an acceptable reason for their absence.
6.1.5 If any former employee commences doing business wherein the employee,
his/her spouse, or members of his/her immediate family are sole proprietors,
or majority or controlling shareholders or owners of a corporation, partnership
or other business entity, such business shall not be retained as an
independent contractor or consultant to provide service directly to OCSD for a
period of one year after leaving OCSD's employment. Thereafter, said
business entity shall be allowed to contract with OCSD upon compliance with
all resolutions and regulations of OCSD then in effect, relating to the
procurement of services.
Page 7 of I 1
7.8 INITIAL PROBATIONARY PERIOD
7.8.1 Unless designated as an"at-will" Executive Management Team(EMT)
member or Student Intern,all new employees and employees who are
reassigned or laterally transferred serve a probationary period. In accordance
with applicable MOUs and policies, the probationary period begins with the
date of hire, reassignment, or transfer and extends to at least the first day of
the pay period following twenty-six weeks of employment without a break in
service. For new employees, this probationary period is regarded as an
extension of the hiring process, and provides an opportunity for both the
employee and OCSD's management to assess, over a substantial period of
time,whether or not the hiring decision was appropriate and resulted in a
relationship that adequately meets the needs of both the individual and
OCSD.
7.8.2 The probationary period may be extended by mutual agreement between
OCSD and the employee, prior to the expiration of the probationary period.
An employee's probationary period may be extended when there is a need to
further assess the individual's abilities to satisfactorily perform the duties
required for their job classification. Probationary employees may be released
by OCSD at any time during the probationary period(including any extension)
without cause or reason.
7.8.3 A probationary employee's work performance is closely monitored during this
period to ensure that the employee understands the duties, responsibilities
and management expectations of the position, and to allow an opportunity for
the supervisor or manager to provide proper direction and guidance.
Employees who do not demonstrate the potential for meeting performance
expectations for their position within a reasonable period of time may be
released prior to the completion of the Probationary Period. Probationary
employees shall serve at the will of OCSD during this period. In the event of
release of a probationary employee,the employee shall not be entitled to
receive any severance pay.
7.9 PROMOTIONAL PROBATIONARY PERIOD
7.9.1 All promoted employees, except those designated as"at-will"employees,
shall serve a promotional probationary period lasting at least 120 days or 6-
months,depending upon the applicable MOU provisions, beginning with the
effective date of promotion. This period is regarded as an extension of the
selection process,and provides an opportunity for both the employee and
OCSD management to assess,over a substantial period of time, whether or
not the decision was appropriate.
7.10 REFERENCE CHECKS
7.10.1 Employment with OCSD is contingent upon a pre-employment screening
process which includes a physical examination, drug/alcohol test and
background investigation. Candidates must also be able to provide
documentation authorizing their legal right to work in the United States as per
the Immigration Reform and Control Act of 1986.
7.10.2 OCSD may verify information contained in the job application of a prospective
employee with the prospective employee's authorization.
Page 10 of I I
5.8.3 If a candidate is selected from the internal recruitment process, the candidate
shall remain in his/her existing position with the same salary and benefits
while cross-training in the new position as scheduling permits.
5.8.4 The candidate shall assume the salary, benefits and full range of duties of the
vacant position the first business day that the position is vacant. The positron
used to initiate the planned recruitment will then be returned to the"pool"
within the Division 540 full-time equivalent(FTE) budget for use with other
planned recruitments.
5.8.5 The date the candidate assumes the vacant position shall be the first day of
the candidate's six-month probationary period. The six-month probationary
period will be utilized as an opportunity for the candidate and OCSD
management to assess whether or not the decision was appropriate. The
candidate may be returned to his/her previous position If the decision is
determined to be inappropriate.
5.8.6 If a candidate is not selected from the internal recruitment process,the
position will be posted for external candidates immediately to ensure an
adequate amount of time for cross-training.
6.0 EXCEPTIONS
6.1 EMPLOYMENT OF FORMER EMPLOYEES
6.1.1 Employment of former employees for full-time equivalent or part-time
positions shall be subject to and conducted in accordance with this policy.
6.1.2 Employment of a former employee is subject to the approval of the General
Manager and the Director of Human Resources.
6.1.3 In all cases, approval of the General Manager and the Director of Human
Resources shall be received prior to an offer of employment to a former
employee.
6.1.4 OCSD policy prohibits the rehire of former full-time, regular employees or"at-
will"employees who: were terminated for workplace misconduct; resigned
while charges were pending against the employee; resigned while serving a
suspension;failed to provide two weeks written notice in advance of
resignation depending upon employment status, unless approved by the
Director of Human Resources, or designee;or failed to return to work
following an absence without leave of 40 consecutive work hours without
notifying the immediate supervisor or the Human Resources Department with
an acceptable reason for their absence.
6.1.5 If any former employee commences doing business wherein the employee,
his/her spouse, or members of his/her immediate family are sole proprietors,
or majority or controlling shareholders or owners of a corporation, partnership
or other business entity,such business shall not be retained as an
independent contractor or consultant to provide service directly to OCSD for a
period of one year after leaving OCSD's employment. Thereafter, said
business entity shall be allowed to contract with OCSD upon compliance with
all resolutions and regulations of OCSD then in effect, relating to the
procurement of services.
Page 7 of I
I
6.1.6 If any former employee becomes employed by any firm or business entity in Y
which the former employee, his/her spouse or members of his/her immediate
family own less than the majority or controlling interest in said entity, said
entity shall not be prohibited from contracting with the OCSD. However,the
former employee shall not perform work on OCSD projects for a period of one
year after leaving OCSD employment; nor shall such former employee
contact OCSD officers or employees for the purpose of attempting to
influence any OCSD decision, including but not limited to, the award of
contract, issuance of permits, or compromise of administrative civil penalties,
for a like period of one year. Said services shall be obtained only in
accordance with all rules and procedures of OCSD relating to procurement.
6.1.7 Any OCSD employee who receives an offer of employment or a request to
discuss potential employment from any person or business entity performing
services for OCSD shall report such contact to his or her immediate
supervisor,who shall decide whether any change in assignment is necessary
or appropriate while the offer or discussions are pending.
6.1.8 The prohibitions of this policy may be waived by the Finance,Administration
and Human Resources Committee of the Boards of Directors if,on a case-by-
case basis, it is determined to be in the best interests of OCSD to do so.
6.1.9 All former employees who are rehired will be placed on an initial probationary
period as defined in this policy. All prior service with OCSD will not be
counted for accrual purposes including, but not limited to, leaves of absence
and seniority.
6.2 RE-EMPLOYMENT OF OCSD RETIRED EMPLOYEES
6.2.1 The General Manager may, with the written approval of the Board Chair,
employ on an as-needed basis, a former employee retired from OCSD when
the individual possesses knowledge and expertise of unique and particular
benefit to OCSD. The length of service performed in any one year shall be
limited in accordance with the provisions prescribed by the Orange County
Employees' Retirement System(currently 120-day maximum).
6.2.2 As-needed service, by a former employee retired from OCSD, shall be
compensated at the same current hourly rate of the retired employee's
position classification, or if no such classification exists,at a rate not to
exceed that paid for the most comparable classification. The retired
employee shall not be entitled to receive any benefits otherwise payable to
OCSD employees. in the event any employment under this provision involves
work assignments outside of Orange County,the current expense
reimbursement policy established for regular employees will apply.
6.2.3 On occasion, OCSD may offer an early retirement incentive to staff under
economic conditions in which it is deemed necessary. Employees who select
an early retirement incentive offered by OCSD may not be eligible for rehire.
6.3 EMPLOYMENT OF RELA TIVES
6.3.1 Except as otherwise provided by law, no employee, prospective employee or
applicant shall be denied employment or benefits of employment solely on the
basis of his or her familial relationship with an employee of the agency or a
member of the Board of Directors.
Page 8 of I I
1
• 6.3.2 OCSD will make reasonable efforts to assign job duties to eliminate any
potential for an adverse impact on supervision, safety, security or morale, or
potential conflicts of interest.
6.4 LATERAL TRANSFERS
6.4.1 Employees may request a lateral transfer to a budgeted vacant position within
the same classification of another department. For a lateral transfer to be
considered,the employee must have demonstrated satisfactory performance
within the last six months of the request and have no pending disciplinary
action.The lateral transfer must be of benefit to OCSD.
6.4.2 Employees who wish to be considered for a lateral transfer shall notify the
Human Resources Department in writing of their intent prior to recruitment of
the budgeted position. Employees who are interested in a lateral transfer, but
are unaware of any budgeted vacant positions within the same classification,
may contact the Human Resources Department. The employee's written
intent must be approved by any affected department head and the Director of
Human Resources. In the event a transfer is approved and accepted by the
employee,the department from which the employee is transferring may
determine the effective date based upon operational requirements and a
reasonable period of time to acquire a suitable replacement.
6.4.3 Lateral transfers do not normally involve increased levels of duties and
responsibilities,or otherwise qualify as promotions, and therefore do not
involve salary adjustments.
6.4.4 In the event an adjustment appears warranted based on extenuating
circumstances,the adjustment must have written approval from the
department head prior to being extended to the employee.
7.0 PROVISIONS AND CONDITIONS
7.1 The interview process for Student Intern positions shall be an abbreviated version of
the process outlined in section 5.5 and will be administered by the appropriate division
manager/supervisor and a Human Resources representative.
7.2 OCSD's Board of Directors must approve unbudgeted positions for new hires or
promotions before any internal or open recruitment effort is initiated.
7.3 Hiring an individual into a budgeted position requires the approval of the Department
Head and General Manager.
7.4 Promoting an individual into a budgeted position requires the approval of the Division
Manager, Department Head or General Manager.
7.5 OCSD retains the right to refuse to place a relative under the direct supervision of an
OCSD employee where such has a potential for creating an adverse impact on
supervision, safety, security or morale.
7.6 OCSD retains the right to refuse to place relatives in the same department, division, or
facility where such has a potential for creating an adverse impact on supervision,
safety, security or morale, or involves potential conflicts of interest.
7.7 Employees on Performance Improvement Plans are not eligible for promotional
opportunities.
Page 9 of I I
P
7.8 INITIAL PROBATIONARY PERIOD
7.8.1 Unless designated as an"at-will" Executive Management Team(EMT)
member or Student Intern, all new employees and employees who are
reassigned or laterally transferred serve a probationary period. In accordance
with applicable MOUs and policies,the probationary period begins with the
date of hire, reassignment, or transfer and extends to at least the first day of
the pay period following twenty-six weeks of employment without a break in
service. For new employees, this probationary period is regarded as an
extension of the hiring process,and provides an opportunity for both the
employee and OCSD's management to assess, over a substantial period of
time,whether or not the hiring decision was appropriate and resulted in a
relationship that adequately meets the needs of both the individual and
OCSD.
7.8.2 The probationary period may be extended by mutual agreement between
OCSD and the employee, prior to the expiration of the probationary period.
An employee's probationary period may be extended when there is a need to
further assess the individual's abilities to satisfactorily perform the duties
required for their job classification. Probationary employees may be released
by OCSD at any time during the probationary period(including any extension)
without cause or reason.
7.8.3 A probationary employee's work performance is closely monitored during this
period to ensure that the employee understands the duties, responsibilities
and management expectations of the position, and to allow an opportunity for
the supervisor or manager to provide proper direction and guidance.
Employees who do not demonstrate the potential for meeting performance
expectations for their position within a reasonable period of time may be
released prior to the completion of the Probationary Period. Probationary
employees shall serve at the will of OCSD during this period. In the event of
release of a probationary employee, the employee shall not be entitled to
receive any severance pay.
7.9 PROMOTIONAL PROBATIONARY PERIOD
7.9.1 All promoted employees,except those designated as"at-will"employees,
shall serve a promotional probationary period lasting at least 120 days or 6-
months, depending upon the applicable MOU provisions, beginning with the
effective date of promotion. This period is regarded as an extension of the
selection process, and provides an opportunity for both the employee and
OCSD management to assess, over a substantial period of time, whether or
not the decision was appropriate.
7.10 REFERENCE CHECKS
7.10.1 Employment with OCSD is contingent upon a pre-employment screening
process which includes a physical examination, drug/alcohol test and
background investigation. Candidates must also be able to provide
documentation authorizing their legal right to work in the United States as per
the Immigration Reform and Control Act of 1986.
7.10.2 OCSD may verify information contained in the job application of a prospective
employee with the prospective employee's authorization.
Page 10 of I 1
7.10.3 Inquiries to OCSD employees regarding reference or employment verification
checks of former or present employees shall be discussed with or referred to
Human Resources prior to any response.
8.0 RELATED DOCUMENTS
8.1 OCSD Student Inte n Program guidelines
8.2 Policy B160.00, EMT Recruitment
8.3 Policy F50.00, Problem Solving Procedure
8.4 Policy F60.00,Grievance Procedure
8.5 Policy C180.00,Al-Will Policy
8.6 Local 501, Operations and Maintenance Unit MOU
8.7 Administrative and Clerical Unit MOU
8.8 Engineering Unit MOU
8.9 Technical Services Unit MOU
8.10 Professional Group MOU
8.11 Supervisor Group MOU
Page 11 of 11
FAHR COMMITTEE Neeungoare TOBd.orDir.
06/19/06 O6/28/06
AGENDA REPORT Item Number Item Number
FMR0647 14(Q
Orange County Sanitation District
FROM: Lorenzo Tyner, Director of Finance/Treasurer
Originator: Michael White, Controller
SUBJECT: ANNUAL RENEWAL OF BOILER & MACHINERY INSURANCE
PROGRAM
GENERAL MANAGER'S RECOMMENDATION
Renew the District's Boiler & Machinery Insurance Program for the period July 1, 2006
to June 30, 2007, in an amount not to exceed $25,387.
SUMMARY
Staff recommends the annual renewal of Boiler & Machinery insurance coverage for the
District covering the period from July 1, 2006 through June 30, 2007. The Boiler &
Machinery insurance program provides comprehensive coverage for loss caused by
machinery breakdown and explosion of steam boilers or other covered process
equipment, including damage to the equipment itself and damage to other property
caused by covered accident. Sufficient funds have been budgeted within the FY 2006-07
budget to cover premium costs.
PRIOR COMMITTEE/BOARD ACTIONS
Board approved annual renewal for FY 2005-06.
PROJECT/CONTRACT COST SUMMARY
Sufficient funds are contained in the current budget to cover premium costs of$25,387.
BUDGETIMPACT
® This item has been budgeted. (Line item: )
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
The District's FY 2006-07 Boiler & Machinery insurance program provides coverage
($100 million per occurrence/with deductibles ranging from $25,000 to $350,000) for
losses caused by covered machinery breakdown (e.g., motors, steam turbines,
digesters, co-gen engines). Damages to the equipment, as well as damages to other
property and improvements caused by the machinery breakdown, are covered by the
n:Lepiupenaavwae n enaa ReponN1006 Baa.a ageraaanpenm FegXaNEOGVIem talc,aubr Metlm,ey In-.
aevnea o6rou03 Page 1
boiler& machinery insurance. This program augments the District's all-risk property
insurance that covers perils such as fire and flood. _
July 1. 2006—June 30, 2007 Renewal Cycle
Driver Alliant Insurance Services, the District's Broker of Record, has reviewed the
current state of the Boiler& Machinery insurance market and recommends that the
District renew Boiler& Machinery insurance coverage with Lexington Insurance
Company for the primary layer of$10 million and with two group of carriers, CNA
Insurance Company, and two foreign excess insurance companies, providing coverage
jointly on the second layer of$90 million for the period of July 1, 2006 through June 30,
2007.
The combined proposed insurance premium of$25,387 is a 6.9 percent increase over
the prior year premium of$23,753.
Following are the reserve levels, A.M. Best Guide Rating (the insurance industry rating
agency), and the Standard and Poor's rating for each of the three insurance groups:
Proposed Schedule of Insurers
Reserve A.M Best Standard California
Company Level Rating and Poor's Status
Lexington >$2 billion A+, Superior AA+ Non-Admixed
CNA >$2 billion A, Excellent A- Admitted
Great Lakes Reinsurance UK >$2 billion A+, Superior A+ Non-Admitted
uo ds of London >$2 billion A, Excellent A Non-Admitted
Conclusion
All proposed insurance carriers are strong insurance companies and can offer Boiler &
Machinery insurance with high coverage levels for operations as large and complex as
the District. As of the date of this report, they offer the most competitive pricing for the
upcoming renewal period. Staff concurs with Driver Alliant's findings and
recommendation. Sufficient funds are contained in the current budget to cover premium
costs of$25,387
ALTERNATIVES
N/A
ATTACHMENTS
None.
N.'EyMlpspeV3%d Aomm R< S> Me dIw.^m aA aRepna`lr M1<ICla WMxJ,nN,y�Nu'Meaoc
n.�..e. aeiwro� Page 2
FAHR COMMITTEE meebng Date To ad.of Dlr.
06/14/06 06/28/06
AGENDA REPORT Item Number Itern Number
FAH-06-48 1 d
Orange County Sanitation District
FROM: Lorenzo Tyner, Director of Finance/Treasurer
Originator: Michael D. White, Controller
SUBJECT: ANNUAL RENEWAL OF THE DISTRICT'S EXCESS WORKERS'
COMPENSATION INSURANCE
GENERAL MANAGER'S RECOMMENDATION
Renew the District's Excess Workers' Compensation Insurance for the period
July 1, 2006 through June 30, 2007, in an amount to be determined.
SUMMARY
The District's Excess Workers' Compensation insurance coverage with the Califomia
Public Entity Insurance Authority (CPEIA), the third year the District has participated in
this program, expires on June 30, 2006 and is now up for renewal for fiscal year 2006-
07. The District's Excess Workers' Compensation Program currently provides coverage
to $150 million with a self-insured retention (SIR), or deductible of$500,000.
The proposed renewal maintains the existing $150 million coverage limit and self-
insured retention of$500,000. As of the date of this report, CPEIA is still negotiating
Premiums for this enhanced policy and the final rate should be known by the Board
meeting of June 28, 2006. The District's broker of record, Driver Alliant, is projecting a
10 percent rate increase over the prior year's rate per actual payroll of$0.003993.
In addition, Driver Alliant has searched the market place for competitive alternatives and
has determined that no other insurance carriers are able to offer significant limits of
coverage beyond $10 million and/or with less than $1 million self insured retentions, and
rates on the programs they do offer are universally higher.
Staff recommends the annual renewal of All-Risk Property and Flood insurance
coverage for the District covering the period from July 1, 2006 through June 30, 2007.
Sufficient funds have been budgeted within the FY 2006-07 budget to cover premium
costs.
PRIOR COMMITTEE/BOARD ACTIONS
Board last approved renewal for the period July 1, 2005 through June 30, 2006.
HWepl� genda�d Agenda FappdeTD B rd AP-M6ABeM Hepw BMW%Um 14(d)W ke,s LompwWi Insurnm. c
Hemeed aawma Page 1
,i
PROJECT/CONTRACT COST SUMMARY
The premium cost for FY 2006-07 will be reported at the Board Meeting of June 28,
2006, prior to obtaining the Board's approval.
BUDGETIMPACT
® This item has been budgeted. (Line item: I
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
Background
The District's use of Excess Workers' Compensation insurance dates back to 1989-90.
At that time, the Fiscal Policy Committee approved a self-insured retention (SIR), or
deductible, of$250,000, for such coverage.
Due to the hardening of the workers' compensation market, this deductible was raised
to $500,000 beginning in FY 2002-03 through a policy with Employers Reinsurance
Corporation (ERC) that provided coverage to $25 million with a self-insured retention
(SIR), or deductible of$500,000. The premium cost charged by ERC for the period July
2005 to June 30, 2006 was $69,090.
Staff has reviewed the District's most recent five-year workers' compensation loss
history with Cambridge Integrated Services Group, the District's third-party workers'
compensation administrator, and has verified that the District has not incurred a loss
which exceeded the $500,000 SIR.
In FY 2003-04, the District joined the California Public Entity Insurance Authority
(CPEIA), the lowest responsible provider, and approved the District's Excess Workers'
Compensation Insurance, with limits of$50 million, a self-insured retention of$500,000,
in an amount totaling $168,720.
In FY 2004-05, the District again renewed with CPEIA with increased limits from $50
million to $100 million while maintaining the self-insured retention of$500,000, in an
amount totaling $208,384.
In FY 2005-06, CPEIA negotiated an increase in the $100 million coverage limit to $150
million, with the same $500,000 self-insured retention, at a rate of$.00370 per actual
payroll, or a total estimated premium of$196,772. Even with the $50 million increase in
H.WeppeemtlaV3oe,E ft-.R.P. .9ae,d PBend.6 RB d. IXmpen.I—Inw—Ex
Revi»tl WW03 Page 2
y
the coverage limit, this is a 14.5 percent reduction from the prior year rate of$0.00433
per actual payroll.
FY 2006-07 Renewal Cycle
Staff is seeking workers' compensation insurance renewal with coverages and
deductibles at the current levels. The CPEIA proposed renewal rates are expected to
be finalized by the end of June. As previously indicated, Driver Alliant is projecting a 10
percent rate increase over the prior year's rate per actual payroll of$0.003993 providing
that the coverage is renewed at the same limits and self-insured retentions.
Some additional risk is associated with the CPEIA joint powers authority in that a
premium surcharge can be assessed to individual members based on an unusually
large number of losses occurring outside of the actuarial evaluation estimates.
However, only once has an actual surcharge ever been made to the County
Supervisors Association of California (CSAC), the parent organization to CPEIA that
has been in existence for over 20 years. The premium surcharge was assessed
following the first year of CSAC's existence and prior to the use of an actuary for the
determination of rates and assumptions. Rates have been based on actuarial
evaluations ever since the shortfall in the first year. CPEIA itself has only been in
existence for five years and has never initiated a premium surcharge.
RECOMMENDATION
Excess Workers' Compensation Program is recommended for renewal through CPEIA.
This policy will provide limits of$150 million, depending on final CPEIA Board action,
with a self-insured retention of$500,000.
The premium cost for FY 2006-07 is being proposed at an approximate 10 percent
increase with the final quote being presented at the Board Meeting of June 28, 2006.
Based on preliminary information on premiums, staff is certain that sufficient funds have
been budgeted to cover premium costs.
ALTERNATIVES
N/A
CEQA FINDINGS
N/A
ATTACHMENTS
None.
X 4Mp,MpnE. d1 Ja R�B dApBnE06lypMY RBpa1aN9MNmm Ia141 MbaeR Cu^ia^--Insw.we Nc
.....a, mom, Page 3
FAHR COMMITTEE Needng Date Tuad.Of Dr.
O6/19/06 O6/2R/06
AGENDA REPORT item Number nem Number
FAHR0649 14 e
Orange County Sanitation District
FROM: Lorenzo Tyner, Director of Finance/Treasurer
Originator: Michael D. White, Controller
SUBJECT: ANNUAL RENEWAL OF THE DISTRICT'S ALL-RISK PROPERTY AND
FLOOD INSURANCE PROGRAM FOR FY 2006-07
GENERAL MANAGER'S RECOMMENDATION
Renew the District's All-Risk Property and Flood Insurance Program for the period
July 1, 2006 through June 30, 2007, in an amount not to exceed $777,833.
SUMMARY
The District's All-Risk Property and Flood insurance coverage expires June 30, 2006
and is now up for renewal for FY 2006-07. The All-Risk insurance program provides for
comprehensive coverage for the District's real and personal property from all perils
including fire, flood, and business interruption.
This renewal proposes to decrease the current year's $1 billion blanket loss limit for
most perils including fire damage to $500 million while maintaining the existing $300
million blanket loss limit for flood. The decrease in perils other than fire is the result of
the reduced capacity in this year's renewal market. Driver Alliant, the District's broker of
Record, is continuing to negotiate for the higher $1 billion limit, however as of this
writing, only $500 million can be confirmed. Premiums for this policy will increase from
the prior year's $656,158 to $777,833, or 18.5 percent. Staff recommends the annual
renewal of All-Risk Property and Flood insurance coverage for the District covering the
period from July 1, 2006 through June 30, 2007. Sufficient funds have been budgeted
within the FY 2006-07 budget to cover premium costs.
PRIOR COMMITTEE/BOARD ACTIONS
Board approved annual renewal for FY 2005-06.
PROJECTICONTRACT COST SUMMARY
Sufficient funds have been proposed within the FY 2006-07 Budget to cover premium
costs in an amount not to exceed $777,833.
H Ws,nsgenda�0 Mena Rennns�005 a dAgm 6Aau,do Repnsl Item 14Ie)NI Rnx PmiMy Ina 0ac
R„sad. oe,oa,On Page 1
BUDGETIMPACT
® This item has been budgeted. (Line item: )
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
Background
For an eighth consecutive year, Driver Alliant, the District's Broker of Record, marketed
renewal of the District's All-Risk Program through a nationwide joint purchase property
insurance program called Public Entity Property Insurance Program (PEPIP). It is
important to note that the joint purchase property insurance program involves no pooling
or sharing of coverage with any other public entities.
Multiple insurance carriers underwrite the All-Risk program to distribute risk exposure
and to ensure competitively bid premiums. Thus, the District's premium costs are
controlled, while obtaining maximum coverage levels for the District.
The District's FY 2004-05 All-Risk Program covered the District's property with a $300
million blanket loss limit for flood and $750 million blanket loss limit for all other perils,
including fire damage. The deductible for flood perils is $100,000 per occurrence and
the deductible for all other perils is $25,000 per occurrence for a total premium of
$729,388.
In FY 2005-06, the coverages and deductibles remained the same except for an
increase in coverage for all perils except for flood from the $750 million blanket loss limit
to $1 billion. In addition, premiums were reduced to $656,158.
FY 2006-07 Renewal Cycle
As a result of the significant purchasing power (in excess of$70 million in combined
annual premiums) of the PEPIP joint purchase program, the FY 2006-07 renewal option
is being proposed to maintain the existing $300 million blanket loss limit for flood.
However, due to the reduced capacity in this year's renewal market, a decrease of the
current $1 billion million blanket loss limit for most other perils, including fire damage, to
$500 million is being proposed. The deductibles for perils of flood and the deductibles
for all basic risk perils are proposed to remain at $250,000 and $25,000, respectively.
The premium increase to $777,833 is an increase of$121,675, or 18.5 percent over the
prior year's total of$656,158, and an increase of$48,445, or 6.6 percent from the
premium paid two years ago. The 18.5 percent increase from FY 2004-05 to FY 2005-
06 represents a 6.9 percent increase in insurable property values and an 11.6 percent
increase in rates.
N'tlePl`e0erda'Ha'ONpenGe RepatlsVIXG Bw,tl Ppentle B POe^ae RBp.'LWGPbVIem 191ej NI flieF P,rywly Inf Ox
RevlxP o ,o Page 2
Recommendation
The FY 2006-07 All-Risk Property Insurance Program is recommended for renewal
through the PEPIP joint purchase program with a $300 million blanket loss limit for
perils of flood and a $500 million blanket loss limit for all other perils.
Sufficient funds have been budgeted to cover premium costs in an amount not to
exceed $777,833.
ALTERNATIVES
None.
CEQA FINDINGS
N/A
ATTACHMENTS
None
X Wap snftl d Aasn"ResssnsIa'8 BaeM AWIWI- eMelieple`D9PlNmm 14(.) dR Rapxly Ins Ox
Rsw ..WPIM3 Page 3
FAHR COMMITTEE Mee,ng Dab' 70Bd ur .Dir.
O614/06 061jS 6
AGENDA REPORT Rem Number Rem Number
FAHR06-50 14(n
Orange County Sanitation District
FROM: Lorenzo Tyner, Director of Finance/Treasurer
Originator: Michael D. White, Controller
SUBJECT: ANNUAL RENEWAL OF THE DISTRICT'S EXCESS LIABILITY
INSURANCE PROGRAM, FY 2006-07
GENERAL MANAGER'S RECOMMENDATION
Renewthe District's Excess General Liability Insurance Program for the period
July 1, 2006 through June 30, 2007, in an amount to be determined.
SUMMARY
Staff recommends the renewal of the District's $25 million Excess General Liability
Insurance Program for FY 2006-07. The coverage is provided through the California
Municipal Excess Liability Program (CAMEL). The District has participated in the
CAMEL program since FY 1996-97 after completing a competitive bid selection
process.
Approval of this agenda item will extend the District's $25 million liability coverage
through the CAMEL program for an additional year. At this time, final premium costs
are being negotiated and will be presented to the Committee on June 14.
PRIOR COMMITTEE/BOARD ACTION
Board last approved renewal for the period July 1, 2005 through June 30, 2006.
PROJECT/CONTRACT COST SUMMARY
N/A
BUDGETIMPACT
® This item has been budgeted. (Line item:
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
H:WepNOsnaeae pwft neAnHs�B Apm BPpmtle PBpp19'C CWWm 14(n.Euaee Genw Lai*Ina.Xc
Page 1
ADDITIONAL INFORMATION
Background
The current liability insurance program provides the District with a $25 million policy of
comprehensive coverage for municipal liability, bodily injury and property damage, and
personal injury. The program was structured to also include Employment Practices, and
Public Officials Errors & Omissions coverage. The $25 million coverage is per
occurrence, with a self-insured deductible of$250,000 per occurrence. Since 1997, the
Employment Practices portion of coverage was enhanced from a $2 million sub-limit, to
the full $25 million policy limit.
This insurance program is provided through the California Municipal Excess Liability
program (CAMEL) and consists of two separate layers of coverage. The first layer is
the "Basic" $10 million program with self-insured retention of$250,000. The second
layer consists of$15 million of coverage in excess of the first layer of$10 million.
In FY 2005-06, the CAMEL program utilized American International Group (AIG) for
renewal of the "Basic" $10 million program with a Best Guide Rating of A+. The second
layer was placed with Traders and Pacific Insurance Company, a carrier that held a
Best Guide Rating of A. Total premium cost for these two layers of coverage, including
terrorism coverage, totaled $408,330, a 3.2 percent increase over the prior year total of
$395,632.
FY 2006-07 Renewal Cycle
The District's Broker of Record, Driver Alliant, is still in the process of negotiating
several renewal options and is hoping to be able to provide a formal proposal prior to
the FAHR Committee Meeting of June 141". At this time, they are estimating premium
increases to be limited to less than 10 percent over the FY 2005-06 premium of
$408,330 and are diligently working towards a much smaller increase, with the
possibility of renewing at approximately the same rate as the prior year.
Recommendation
The FY 2006-07 Excess General Liability Insurance Program is recommended for
renewal through the CAMEL joint purchase program. This policy provides for$25
million of comprehensive coverage for municipal liability, bodily injury and property
damage, and personal injury, with a self-insured deductible of$250,000 per occurrence.
The premium cost for FY 2006-07 will be reported on June 14, 2006 prior to obtaining
the Committee's approval. Based on preliminary information on premiums, staff is
certain that sufficient funds have been budgeted to cover premium costs.
H d.gaq.waoae wales nepauwos mra wade n wad.rtw+•esosx„ ,an E®..cax,a�m,ry�".ex
Page 2
ALTERNATIVES
N/A
ATTACHMENTS
1. Letter dated May 31, 2006 from the District's Broker of Record, Driver Alliant, on the
renewal status for excess liability insurance.
N'Aapll.pmOOBmE ApM R,Ws2]C0B MMmW IRY^^b R. .�41.m„m.Ertn.Gngel LmWN In$ft
Page 3
driver.alliant NSURANCE SERVICES
INTEGRATED INSURANCE&FINANCIAL SERVICES
May 31, 2006
Mr. Mike White
CPA/Controller
Orange County Sanitation District
P.O. Box 8127
Fountain Valley,CA 92728-8127
RE: California Municipal Excess Liability Program(CAMEL)
and Optional Excess Liability
Dear Mike:
The current excess liability insurance program affords a$25 million limit of liability subject to a
$250,000 self-insured retention at a current annual premium of$408,330. We enclose policy
summaries for the excess liability and optional excess liability for reference.
We are in the process of finalizing the July 1, 2006 renewal negotiation and anticipate providing
you a formal quotation within the next 2 weeks. Although we are optimistic of maintaining
current premium levels, you may wish to use a conservative 10%cost increase or$449,163 for
current planning and budget purposes.
Thank you for your continuing patience as we conclude our marketing efforts on your behalf.
Sincerely,
DRIVER ALLIANT INSURANCE SERVICES, INC.
Don McLean,
Senior Vice President
Enclosures
Driver Alllaal Insurable Se M, hic
u Allwl Rruerro Group rampant'
1301 Dove St.Suae 200,Newport Beady CA 92660-2436 a 949-756-0271
Lic 0006861 . www.driveralGantmm
FAHR COMMITTEE Mewing Date Toed mr .Dir.
O6/14/06 is
,
6
AGENDA REPORT item Number item Number
FAHR06-46 14fc1
Orange County Sanitation District
FROM: Lorenzo Tyner, Director of Finance/Treasurer
SUBJECT: PROPOSED FY 2006-07 and 2007-08 OPERATING, CAPITAL,
DEBT/COP SERVICE, SELF-INSURANCE BUDGETS AND OTHER
REQUIREMENTS BUDGET
GENERAL MANAGER'S RECOMMENDATION
Approve proposed Operating, Capital, Debt/COP Service and Self-Insurance Budgets
for FY 2006-07 and 2007-08, as follows
2006-07 2007-08
Net Operations, Maintenance &Working Capital $129,054,210 $135,602,130
Worker's Compensation Self Insurance $526,200 $559,400
General Liability and Property Self-Insurance $1,766,100 $2,055,200
Net Capital Improvement Program $266,088,000 $338,818,000
Debt/COP Service $54,410,000 $65,462,000
Other Requirements $4,499,800 $2,645,300
Total $456,344,310 $545,142,030
SUMMARY
The FY 2006-07 and 2007-08 Budget is enclosed for the Committee's consideration.
The Budget has been presented to the OMITS and PDC Committees at their regular
June meetings in order to allow each Standing Committee an opportunity to review the
proposal prior to the June Board meeting.
Although each Committee has had an opportunity to review the proposal, it remains the
responsibility of the Finance, Administration and Human Resources Committee to
recommend approval.
The FAHR Committee is requested to recommend that the Board of Directors approve
this budget.
PRIOR COMMITTEE/BOARD ACTIONS
Board approved 2005-06 Budget for the period July 1, 2005 through June 30, 2006.
Budget overviews were presented to the FAHR, PDC and OMITS Committees in May
and June 2006.
PROJECT/CONTRACT COST SUMMARY
N/A
BUDGETIMPACT
❑ This item has been budgeted.
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
® Not applicable (information item)
ADDITIONAL INFORMATION
None.
ALTERNATIVES
N/A
CEQA FINDINGS
N/A
ATTACHMENTS
Proposed 2006/07 and 2007/08 Budget
(Directors: You have been previously provided a copy of the proposed budget with your
June committee packages. Please contact the Board Secretary should you require an
additional copy.)
H.Weq`+p�a'�dK�Fe�nSO'JGBwrCPqu le 6 Mho HTra'�Nem 1N9).�'MMc
w:eea. aswm Page 2
MINUTES OF LEGISLATIVE AFFAIRS
COMMITTEE MEETING
Orange County Sanitation District
Tuesday,June 13, 2006, 8:00 a.m.
A meeting of the Legislative Affairs Committee of the Orange County Sanitation District was held
on June 13,2006, at 8:00 a.m., in the Sanitation Districts Administrative Office.
(1) The roll was called and a quorum declared present,as follows:
LEGISLATIVE AFFAIRS STAFF PRESENT:
COMMITTEE MEMBERS: Jim Ruth, Interim General Manager
Bob Ghirelli, Director of Technical Services
Directors Present via Penny Kyle, Committee Secretary
Teleconference: Michael Gold, Legislative Affairs Liaison
Jim Colston, Legal & Regulatory Affairs Liaison
Steve Anderson, Board Chair Layne Baroldi, Legal &Regulatory Affairs Liaison
Jim Ferryman,Vice Board Chair Dean Fisher, Engineering Supervisor
James W. Silva
OTHERS PRESENT
DIRECTORS ABSENT: Christopher Townsend
Heather Dion
OTHERS PRESENT via Teleconference:
Eric Saperstein
Sean Fitzgerald
Scott Baugh
(2) APPOINTMENT OF CHAIR PRO TEM
No appointment was necessary.
(3) PUBLIC COMMENTS
There were no public comments.
(4) REPORT OF THE COMMITTEE CHAIR
Chair Anderson had no report.
(5) REPORT OF THE GENERAL MANAGER
Jim Ruth, Interim General Manager, had no report.
(6) REPORT OF DIRECTOR OF TECHNICAL SERVICES
Bob Ghirelli, Director of Technical Services, introduced Michael Gold, Legislative Affairs Liaison,
to the Committee.
Minutes of the Legislative Affairs Committee Meeting
ti Page 2
June 13, 2006
(7) REPORT OF GENERAL COUNSEL
General Counsel was not present.
(8) CONSENT CALENDAR ITEMS
Consideration of motion to approve all agenda items appearing on the Consent Calendar not
specifically removed from same, as follow:
a. Approve minutes of the May 9, 2006 Legislative Affairs Committee meeting.
MOTION: It was moved,seconded and duly carried to approve Item 8(a) under
Consent Calendar.
END OFCONSENTCALENDAR
(9) ACTION ITEMS
a. No items were considered.
(10) INFORMATIONAL PRESENTATIONS
a. LEGO6-05 Legislative Affairs Update
Eric Saperstein, Sean Fitzgerald and Scott Baugh provided updates on current legislative
issues to include clarification and coordination with the County of Orange on pursuit of
federal money for the SARI Realignment and Protection Project, infrastructure bond
proposals, design-build legislation (AS 2580)and conversion technology(AB 2118).
Michael Gold, Legislative Affairs Liaison, advised he would be scheduling a legislative
planning session in October to establish goals for the coming year with the committee
members and lobbyists. He also gave an update on SB 419 (Simitian)dealing with
hazardous materials and is working with CASA to coordinate the District's opposition and
message.
Chairman Anderson announced he would be visiting Washington, D.C., the week of
June 19'", along with representatives of Orange County Water District,to seek increased
funding for the GWRS project.
(11) CLOSEDSESSION
There was no closed session.
(12) OTHER BUSINESS. COMMUNICATIONS OR SUPPLEMENTAL AGENDA ITEMS IF
ANY
There were none.
Minutes of the Legislative Affairs Committee Meeting
y Page 3
June 13, 2006
(13) MATTERS WHICH A DIRECTOR MAY WISH TO PLACE ON A FUTURE AGENDA FOR
ACTION AND STAFF REPORT
There were none.
(14) CONSIDERATION OF UPCOMING MEETINGS
The next Legislative Affairs Committee meeting is scheduled for July 11, 2006, at 8:00 a.m.
(15) ADJOURNMENT
The Chair declared the meeting adjourned at 8:50 a.m.
Submitted by:
A" e VI
Penny Wkyle
Committee Secrets
H:1dep1%gendMLEGISLATIVE AFFAIRWOOK6061061306 Minuleedoc
GWR System Steering Committee
May 8,2006
MINUTES
GROUNDWATER REPLENISHMENT SYSTEM STEERING COMMITTEE
STEERING COMMITTEE
(A Committee of Orange County Water District
and Orange County Sanitation District Directors)
OCWD Boardroom, 10500 Ellis Avenue, Fountain Valley
Monday, May 8, 2006, 5:30 p.m.
Committee Members
Philip L.Anthony OCWD Director, Chairman .............Present
Kathryn Bar OCWD Director ..............................Present
Roger Yoh OCWD Director...............................Present
Steve Anderson OCSD Director .........................Not Present
Mike Duvall OCSD Director, Vice Chairman.......Present
Carolyn Cavecche OCSD Director ...............................Present
Alternates
Jan Debay OCWD Director(No. 1)....................Present
Denis Bilodeau OCWD Director(No. 2)..............Not Present
Steve Sheldon OCWD Director(No. 3)..............Not Present
Jim Ferryman OCSD Director(No. 1)....................Present
Don Bankhead OCSD Director(No.2) ..............Not Present
Larry Crandall OCSD Director(No.3) ....................Present
Other Directors Present
None
CONSENT CALENDAR(ITEM NO.1) MOTIONIVOTE ACTION TAKEN
1. MINUTES OF PREVIOUS MEETING ANTHONY— AYE
RECOMMENDATION:Approve Minutes of the April 10,2006 BARR— SECOND,AYE APPROVED
Groundwater Replenishment System Yon— AYE
Steering Committee Meeting as mailed DWALL— Aye
CAVECCHE—AYE
FERRYMAN— MOTION,AYE
2. ISSUANCE OF CHANGE ORDER NO.ITO ANTHONY— MOTION,AYE
TWINING.GOVIL.RYAN(TGR)FOR FIELD AND BARR— AYE APPROVED
LABORATORY SOILS&MATERIALS TESTING SERVICES YoH— AYE
FOR THE GROUNDWATER REPLINISHMENT SYSTEM DUVALL— SECOND,AYE
ADVANCED WATER PURIFICATION FACILITY PROJECT CAVECCHE—AYE
RECOMMENDATION:Agendize for May 17 OCWD Board meeting: FERRYMAN— AYE
Authorize Issuance of Change Order No. 1
In an amount not to exceed$410.000 to
Twlning.Govil.Ryan(TGR)for additional
field and laboratory soils&materials testing
services for the Groundwater
Replenishment System Advanced Water
Pudlication Facility Project.
_ 1 _
GW R System Steering Committee
May 8, 2006
3. ISSUANCE OF CHANGE ORDER NO.ITO ARROYO ANTHONY— AYE
GEOTECHNICAL FOR FIELD AND LABORATORY SOILS& BARR— SECOND,AYE APPROVED
MATERIALS TESTING SERVICES FOR THE YOH— AYE
GROUNDWATER REPLINISHMENT SYSTEM UNIT I DUVALL— AYE
PIPELINE PROJECT CAVECCHE— AYE
RECOMMENDATION:Agendize for May 17 OCWD Board meeting: FERRYMAN— MOTION,AYE
Authorize Issuance of Change Order No. 1
in an amount not to exceed$75,000 to
Arroyo Geotechnical for additional field and
laboratory soils&materials testing services
for the Groundwater Replenishment System
Unit I Pipeline Project.
4. ISSUANCE OFA PROFESSIONAL SERVICES AGREEMENT ANTHONY— AYE
TO SRJ BUSINESS SERVICES LLC TO ASSIST IN THE BARR— AYE APPROVED
IMPLEMENTATION OF THE COMPUTERIZED YOH— SECOND,AYE
MAINTENANCE MANAGEMENT SYSTEM W ITH THE DUVALL—AYE
DISTRICT'S FINANCIAL INFORMATION SYSTEM CAVECCHE— AYE
RECOMMENDATION:Agendize for May 17 OCWD Board meeting: FERRYMAN— MOTION,AYE
Authorize Issuance of Professional Services
Agreement in an amount not to exceed
$158,900 to SRJ Business Services LLC for
the services of a Financial System
Specialist to assist in the implementation of
the Integrated Information System.
END OF CONSENT
MATTERS FOR CONSIDERATION
5. ADDENDUM NO. 13 TO PROFESSIONAL SERVICES ANTHONY— AYE
AGREEMENT WITH CAMP DRESSER&MCKEE,INC. BARR— SECOND,AYE THE COMMITTEE
RECOMMENDATION: Agendize for the May 17 OCWD and May YOH— AYE ASKED THAT ITEMS
24 OCSD Board meetings: Approve and DuvALL-AYE AND 7 Be BROUGHT
authorize Issuance of Addendum No. 13lD CAVECCHE— MOTION,AYE BACKWRHFURRIER
FERRYMAN— AYE DOCUMENTATION
AND the Professional Services Agreement with EDTH
Camp Dresser&McKee,Inc.,Increasing A ITEMS
the authorized amount by$374,773 from REMAININGWING
OF
$34.115,783 to an amount not to exceed FORAM INCREAEASESE
E
$34,490,556,for the annual cost-of-living PROFESSIONAL
O
adjustment and changes In the Scope of PROFESSSIONAALL
Work SERVICES
AGREEMENT.
6. CONTRACT NO.GWRS-2004-1 -GROUNDWATER ANTHONY— AYE
REPLENISHMENT SYSTEM ADVANCED WATER BARR—SECOND,AYE APPROVED
PURIFICATION FACILITY(J.F.SHEA CONSTRUCTION, YOH— AYE
INC.): CHANGE ORDER NOS. 16&17 DUVALL— AYE
RECOMMENDAITON:Agendize for May 17 OCWD Board meeting: CAVECCHE— MOTION,AYE
Authorize Issuance of Change Order Nos. FERRYMAN— AYE
16& 17 for an increase in contract price
totaling$42,517 and no Increase in contract
time.
-2 -
GWR System Steering Committee
May 8,2006
7. RESTARTING GENERAL MANAGER'S SIGNING AUTHORITY ANRIONY— AYE
ON GWR SYSTEM PROJECTS BARR— SECOND,AYE APPROVED
RECOMMENDATION:Authorize restarting the General Manager's YOH— AYE
signing authority for additive and deductive DuvALL—AYE
change orders on Contract No.GWRS- CAVECCHE— AYE
2003-6(Unit l Pipeline),Contract GWR& FERRYMAN— McmON,AYE
2003-4(Unit II Pipeline),GWRS-2003-3
(Barter Facilities)and GWRS-2004-1
(Advanced Water Purification Facility).
INFORMATIONAL ITEMS
8. ADVANCED WATER PURIFICAITON FACILITY COST INFORMATIONAL
SAVINGS UPDATE
9. PROJECT SCHEDULE AND BUDGET UPDATE INFORMATIONAL
10. CONSTRUCTION PROJECTS PROGRESS INFORMATIONAL
11. MONTHLY CHANGE ORDER UPDATE INFORMATIONAL
12. STATUS REPORT INFORMATIONAL
• Grants and Loans Update
• Public Information and Education Update
DIRECTORS'ANNOUNCEMENTSIREPORTS
GENERAL MANAGERS'ANNOUNCEMENTSI REPORTS
ADJOURNMENT 6:35 P.M.
- 3-
BOARD OF DIRECTORS Meeting Doe TO Btl.of Dlr.
OW28/06
AGENDA REPORT Item Number Item Number
n
Orange County Sanitation District
FROM: David Ludwin, Director of Engineering
Originator: Ann Tobin, Engineer
SUBJECT: 66KV SUBSTATION AT PLANT NO. 1, JOB NO. P1-97
GENERAL MANAGER'S RECOMMENDATION
Receive and file Addendum No. 1 to the Final Subsequent Environmental Impact Report
for the Secondary Treatment and Plant Improvement Project for project modifications to
the 66kV Substation at Plant No. 1, Job No. P1-97, prepared by IPMC/CH2M Hill.
SUMMARY
• Pursuant to the California Environmental Quality Act (CEQA), the Orange County
Sanitation District's (Sanitation District) Board of Directors (Board) must consider
modifications to the project description for the 66kV Substation at Plant No. 1, Job
No. P1-97. The Planning, Design, and Construction (PDC) Committee has
requested that all such CEQA action considerations be presented to the PDC
Committee prior to the Board.
• The modifications include the addition of several power poles within the adjacent
Southern California Edison (SCE) property and underground transmission wires
from the SCE site to Plant No. 1 under Garfield Avenue. These facilities are being
described at this time because the exact locations were not available when the
Subsequent Environmental Impact Report (SEIR) for the Secondary Treatment Plant
Improvement Project was prepared.
• Addendum No. 1 to the SEIR was prepared to describe these proposed project
changes. The Addendum concludes that substation components constitute minor
technical changes and additions to the SEIR. Moreover, these substation
components do not present new significant environmental effects, or a substantial
increase in the severity of the significant effects, documented in the SEIR and
related documents.
PRIOR COMMITTEE/BOARD ACTIONS
On March 22, 2006 the Board approved a sole source agreement with Southern
California Edison (SCE) for engineering services, fees, materials and labor for the
design and construction of the SCE owned and operated 66kV substation proposed at
HWae,WgeMa`amtl Fgantla RaFd,W B-rdAanda&A Ma RepalalWlVWam 1111-.1 bx
R—i .11. G Page 1
Reclamation Plant No. 1 and improvements to the SCE distribution and transmission
systems required for service to the proposed substation.
Staff presented the proposed P1-97 substation and associated improvements to the
Planning, Design, and Construction Committee (PDC) at its regular meeting on June 1,
2006 as an informational item.
PROJECT/CONTRACT COST SUMMARY
N/A
BUDGET IMPACT
® This item has been budgeted. (Line item: 2005rz006 ciP Budget, section s, page 90.)
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
The proposed substation will accommodate loads to the existing electrical distribution at
Reclamation Plant No. 1 resulting from new treatment facilities currently under
construction. The loads will be served by a double-ended substation owned and
operated by SCE. The proposed 66 kV substation will consist of two redundant 66kV to
12kV transformers with two independent 66kV primary feeders. The substation will be
primarily fed from the SCE Ellis substation located across Garfield Street and adjacent
to the nursery. If the SCE Ellis substation fails, the new 66 kV substation will be
capable of being fed from at least one other SCE substation.
The proposed 66kV pump station was initially analyzed in the SEIR which was certified
by the Board in May 2005. Addendum No. 1 to the SEIR, prepared by the Integrated
Program Management Consultants, documents changes to the SEIR to address
modifications to the proposed substation, which include additional improvements to the
SCE distribution and transmission system required for service to the proposed
substation. Addendum No. 1 and the SEIR will be considered by the California Public
Utilities Commission (CPUC), in conjunction with its General Order 131-D permitting
process.
The modifications described in Addendum No. 1 for Job No. P1-97 includes:
• a 200 by 75 square-foot building
• two 25-foot high by 12-foot wide switchracks
• a fence around the substation up to 8 feet high
• up to six existing SCE 12KV poles along Garfield Avenue would be removed and
circuits installed underground to facilitate substation construction
H WeplNgenGe'8 dPpmga RapMS3 E dPp ab fg PgvlS[ 'Jlem 17 PI-97 dJc
R-.. 01ro,. Page 2
c
i
• an underground segment of 66kV line across Garfield Avenue from Reclamation
Plant No. 1 to the SCE property, two underground substructure systems and
three new pole switches
• approximately five wood or steel poles and up to four spans of overhead
conductor on the SCE property
• a block wall up to 10 feet high along Garfield Avenue to provide visual screening
• landscaping along Garfield Avenue
In May 2006, Sanitation District staff met with City of Huntington Beach staff and with
City of Fountain Valley staff to present information on the proposed substation and
associated improvements.
ALTERNATIVES
There are no alternatives to constructing a 66kV substation due to the significant
increase in electrical loads through 2012. SCE is the only electrical utility that can
supply the required 66kV service.
CECA FINDINGS
The proposed substation was initially described and analyzed in the SEIR. Pursuant to
CEQA Guidelines section 15164, some changes and additions are required to the
previously certified SEIR to address project modifications to the 66kV substation. At the
same time, none of the conditions calling for the preparation of a subsequent EIR that
are described in CEQA Guidelines Section 15162 have occurred. Consequently, a brief
explanation of the decision not to prepare a SEIR is included in Addendum No. 1.
Addendum No. 1 completes CEQA documentation of the proposed substation and
associated improvements.
ATTACHMENTS
Addendum No. 1 to the Orange County Sanitation District Subsequent Environmental
Impact Report for the Secondary Treatment and Plant Improvement Project.
AT:sa
Hmtg1o1,aMgenda Draft ReportWoint Boards,D62806 P1-97 Board AR-Addendum to SEIR.doc
x'•m�Wa•`�eAee.m aeon»aaseoaeM�•a Wmw new�sosasmem»Pl-elm
n..ma: mmws Page 3
V
ADDENDUM NO. 1 TO THE
ORANGE COUNTY SANITATION DISTRICT
SUBSEQUENT ENVIRONMENTAL IMPACT REPORT FOR THE
SECONDARY TREATMENT AND PLANT IMPROVEMENT PROJECT
STATE CLEARINGHOUSE NO.: 2004031076
LEAD AGENCY: Orange County Sanitation District
PREPARED BY; Integrated Program Management Consultants
DATE; May 2006
PURPOSE OF ADDENDUM:
On May 25, 2005, the Orange County Sanitation District(Sanitation District) Board of
Directors certified the Final Subsequent Environmental Impact Report(SEIR)for the
Secondary Treatment and Plant Improvement Project(Project) (SCH No. 2004031076).
The SEIR analyzed the environmental impacts of numerous improvements at
Reclamation Plant No. 1 (Plant No. 1) and Treatment Plant No. 2 (Plant No. 2) required
to achieve secondary treatment standards. Where appropriate, the SEIR incorporated
by reference relevant environmental analysis from the Sanitation District's 1999
Strategic Plan Program Environmental Impact Report. This addendum, prepared in
accordance with the California Environmental Quality Act(CEQA) (Public Resources
Code Section 21000 at seq.) and its implementing Guidelines (California Code of
Regulations Title 14, Chapter 3, Section 15000 at seq.), addresses modifications to the
proposed 66kV(kilovolt)substation facility described in the SEIR. The Sanitation District
Board of Directors and the California Public Utilities Commission (CPUC) will consider
this addendum in conjunction with CPUC permitting of the 66kV substation facility.
PROJECT DESCRIPTION:
Southern California Edison (SCE) proposes to construct a new outdoor 66/12kV
substation to provide electrical service for the secondary treatment upgrades planned for
the Sanitation District Plant No. 1. The new substation would be located at 10844 Ellis
Avenue, Fountain Valley, California at the site of the existing Plant No. 1. See Figure 1.
The Project would construct a new electrical substation to provide power from SCE at
66 W. The substation would be constructed in a rectangular area approximately 200-
feet by 75-feet, which would be enclosed with a fence up to 8-feet high. Along the
Garfield Avenue facing side of the site, a block wall up to 10-feet high would be placed to
provide visual screening. The substation would include two 25-foot-high by 12-foot-
wide, open steel structures(switch racks)to support 66kV switches and breakers.
A new segment of 66kV line required to serve the new substation, would be constructed
underground and would originate from SCE property on the south side of Garfield
Avenue in the City of Huntington Beach and extend to the north side of Garfield Avenue
in the City of Fountain Valley. This new 66kV line construction would require the
OCSDAPMC PAGE I OF 6 MAY 2006
1
e
installation of approximately five wood and/or steel poles on SCE property, and up to
four spans of 954 stranded aluminum conductor(sac) overhead conductor. Two
separated underground substructure systems of 3,000 thousand circular mils(kcmil)
underground cable would be installed. Three new pole switches would be required to
tap the existing Ellis-Gisler 66kV line and the new 66kV underground line from Ellis
Substation to the new proposed substation at Plant No. 1. Up to six existing SCE 121kV
poles along Garfield Avenue would be removed and circuits installed underground to
facilitate substation construction. Following construction, landscaping would be provided
along Garfield Avenue for the length of the substation site.
ENVIRONMENTAL IMPACT ANALYSIS:
A new 66kV substation facility at Plant No. 1 is described in Section 2.2.3 of the SEIR.
Environmental impacts associated with a new 66kV substation facility are evaluated in
Chapter 3 of the SEIR. The SEIR does not include several components related to the
proposed substation, as at the time of certification of the SEIR, detailed engineering had
not been accomplished. This addendum describes and evaluates the environmental
impacts of modifications to the 66 kV substation facility described in the SEIR. These
modifications include the related components listed below, which comprise minor
technical changes and additions necessary to implement the proposed 66kV substation
facility.
• The substation would be constructed in a rectangular area approximately 200-feet by
75-feet,whereas the SEIR stated a footprint of approximately 150-feet by 100-feet.
• The substation would be enclosed with a fence up to 8-feet high.
• The substation would be equipped with two 25-foot-high by 12-foot-wide switch
racks.
• Up to six existing SCE 12kV poles along Garfield Avenue would be removed and
circuits installed underground to facilitate substation construction.
• An underground segment of 66kV line would be constructed from SCE property on
the south side of Garfield Avenue in the City of Huntington Beach to the north side of
Garfield Avenue in the City of Fountain Valley. Two separated underground
substructure systems of 3,000 kcmil underground cable would be installed and three
new pole switches would be required.
• Approximately five wood and/or steel poles would be placed on SCE property, and
up to four spans of 954 sac overhead conductor.
• A block wall up to 10-feet high would be placed along Garfield Avenue to provide
visual screening.
• Landscaping would be provided along Garfield Avenue for the length of the
substation site.
The related components, including the 66kV line and poles, would be placed within a
developed area and would not substantially degrade the existing character or quality of
the environment at the site or its surroundings. Additionally, all related components, with
the exception of the subsurface line, would be placed either within the footprint of Plant
OcSDIPMc PAGE 2OF6 MAY 2036
No. 1 or the Ellis Substation and would be consistent with the existing land uses at these
facilities. These minor technical changes and additions would not result in new
significant environmental effects or a substantial increase in the severity of significant
effects from those determined by the SEIR certified by the Sanitation District Board of
Directors on May 25, 2005 for the Project.
Provided below is a review of the conclusions included in the SEIR and an evaluation of
the environmental impacts of changes to the 66 kV substation facility described herein.
Aesthetics:
The SEIR concluded that although several new structures would be visible from adjacent
residential neighborhoods, the Project would not substantially alter or degrade the
existing visual character of the site and surroundings. The minor technical changes and
additions to the 66 kV substation, including the 66kV line and poles, would be placed
within a developed area and would not substantially degrade the existing character or
quality of the environment at the site or surroundings. Additionally, all related
components, with the exception of the subsurface line, would be placed either within the
footprint of Plant No. 1 or the Ellis Substation and would be consistent with the existing
land uses at these facilities. These minor technical changes and additions would not
result in new significant environmental effects or a substantial increase in the severity of
significant effects related to aesthetic from those determined in the SEIR.
Air Quality:
The SEIR concluded that construction and operation of the Project would exceed
significance thresholds set by the South Coast Air Quality Management District
(SCAQMD)for nitrogen oxides(NOx) emissions. The SEIR also concluded that neither
construction nor operation of the Project would result in objectionable odors affecting a
substantial number of people. The minor technical changes and additions to the 66 kV
substation would not result in an increase in emissions described in the SEIR.
Additionally, the minor technical changes and additions would not result in objectionable
odors affecting a substantial number of people. These minor technical changes and
additions would not result in new significant environmental effects or a substantial
increase in the severity of significant effects related to air quality from those determined
in the SEIR.
Geology and Soils:
The SEIR concluded that the Project could expose people or structures to potential
adverse effects due to geologic and seismic hazards. The SEIR also concluded that
dewatering could create unstable soil conditions, creating potential risk of property
damage to proposed and nearby existing structures. The minor technical changes and
additions to the 66 kV substation would not result in new or substantially more severe
exposure of people or structures to potential adverse effects due to geologic and seismic
hazards. Additionally, the minor technical changes and additions would not increase the
possibility of unstable soil conditions associated with dewatering. These minor technical
changes and additions would not result in new significant environmental effects or a
substantial increase in the severity of significant effects related to geology and soils from
those determined in the SEIR.
OCSDIIPMC PAGE 3 OF 6 MAY 2006
Hazards and Hazardous Materials:
The SEIR concluded that the Project would increase quantities of the existing hazardous
materials used in the treatment process. The SEIR also concluded that abandoned oil
wells could be encountered during excavation at Plant No. 2 and represent both a safety
hazard for workers as well as a potential conduit for surface contamination to reach
groundwater if wells are not properly abandoned. Lastly, the SEIR concluded that soils
contaminated from previous activities in the area could be encountered during
excavation activities and create a significant hazard to the public or environment If not
property contained and disposed of. The minor technical changes and additions to the
66 W substation would not result in an increase in the quantities of hazardous materials
described in the SEIR. The minor technical changes and additions described herein
would occur at Plant No. t and would have no impact related to hazards at Plant No. 2.
Additionally, these minor technical changes and additions would not result in a new or
substantially more severe impact associated with encountering contaminated soils.
These minor technical changes and additions would not result in new significant
environmental effects or a substantial increase in the severity of significant effects
related to hazards and hazardous materials from those determined in the SEIR.
Hydrology and Water Quality:
The SEIR concluded that construction of the Project could result in erosion and receiving
water quality impacts. The SEIR also concluded that the Project area would be
susceptible to potential flooding impacts that could damage facilities. The minor
technical changes and additions to the 66 W substation would not result in an increase
in erosion and receiving water quality impacts, or an increase in potential flooding
impacts that could damage facilities,from those described in the SEIR. These minor
technical changes and additions would not result in new significant environmental effects
or a substantial increase in the severity of significant effects related to hydrology and
water quality from those determined in the SEIR.
Marine Environment:
The SEIR concluded that the secondary effluent produced as a result of the Project
would improve effluent quality. The minor technical changes and additions to the 66 W
substation would have no effect on the secondary effluent quality described in the SEIR.
These minor technical changes and additions would not result in new significant
environmental effects or a substantial increase in the severity of significant effects
related to the marine environment from those determined in the SEIR.
Noise:
The SEIR concluded that operation of the Project treatment facilities would generate
noise but, with mitigation, noise levels would not exceed established standards or result
in a substantial permanent increase above ambient conditions. The SEIR also
concluded that Project construction would generate noise that could result in substantial
temporary increases in ambient noise levels in the vicinity, and that Project construction
could generate groundbome vibration that could temporarily expose persons to vibration
above ambient conditions. The minor technical changes and additions to the 66 W
substation would not increase construction or operation noise levels, or result in a new
source of groundbome vibration, from those described in the SEIR. These minor
OCSOIIPMC PAGE 4 OF 6 MAY 2006
technical changes and additions would not result in new significant environmental effects
or a substantial increase in the severity of significant effects related to noise from those
determined in the SEIR.
TransoortatioNTraffic:
The SEIR concluded that periods of peak Project construction would add traffic along
local access streets (including freeway access)causing temporary but substantial
increases in traffic over existing conditions. The SEIR also concluded that Project
operation would increase vehicle trips on local access roads only slightly and would not
substantially Increase traffic levels over existing conditions or road capacity. The minor
technical changes and additions to the 66 kV substation would not result in an Increase
in construction or operation related transportation and traffic impacts from those
described in the SEIR. These minor technical changes and additions would not result in
new significant environmental effects or a substantial increase in the severity of
significant effects related to transportation and traffic from those determined in the SEIR.
FINDINGS OF APPROVAL FOR ADDENDUM NO. 1 TO THE SUBSEQUENT
ENVIRONMENTAL IMPACT REPORT FOR THE SECONDARY TREATMENT AND
PLANT IMPROVEMENT PROJECT:
1. Environmental impacts of the proposed 66kV substation facility were evaluated in the
SEIR certified by the Sanitation District Board of Directors on May 25, 2005, for the
Project.
2. Minor technical changes and additions to the SEIR are required to address
modifications to the proposed 66kV substation facility.
3. The project modifications would not result in new significant environmental effects or
a substantial increase in the severity of significant effects from those determined by
the SEIR certified by the Sanitation District Board of Directors on May 25, 2005 for
the Project. In addition, no new information of substantial importance, which was not
known and could not have been known with the exercise of reasonable diligence at
the time the SEIR was certified, has surfaced that shows (1)any new or
substantially more severe impacts; (2) any mitigation measures that were considered
infeasible in the SEIR are now feasible; or(3) mitigation measures or alternatives
that are considerably different from those identified in the SEIR would substantially
reduce one or more significant effects.
OCSDIIPMC PAGE 50F 6 MAY 2006
OCSD RECLAMATION PLANT NO. 1Elm Mil
elm =is
=r{
� 1 Ward Avenue
Proposed Underground SCE 66KV Line - _ Proposed 200 x 75'66KV SCE Substation -
I ,
Garfield Street
4M„ Proposed Underground SCE 66KV Line
VIA
Ho° 00o� I f�tl �: , , Proposed (4) New SCE Wood Poles
_ y [
• - 4� � '"OP
Proposed New SCE Steel Pole
� 11.1 Existing SCE Steel Towers
Proposed New SCE Manholes, 4 , ..
l
96
SCE FACILITY
!' irk
Figure 1
P1-97 66KV Substation and Associated Improvements
OCSDIIPMC 6 of 6 May aQ6
K017546706.00ZZ Figl gi 506 -
BOARD OF DIRECTORS rnmoxe rr,Bd.ofot.
6M06
AGENDA REPORT Rem N be NuntW
to
Orange County Sanitation District
kSecondary Treatment
FROM: David Ludwin, Director of Engineering
Originator: Kathy Millea, CIP Project Manager
SUBJECT: CONTRACT NO. P2-90A, OIL WELL EXCAVATION AND REABANDONMENT
GENERAL MANAGER'S RECOMMENDATION
(1)Approve Plans and Specifications for Contract No. P2-90A, Oil Well Excavation and
Reabandonment, on file at the office of the Board Secretary; (2) Approve Addenda Nos. 1,2, and
3 to the plans and specifications; (3) Receive and file bid tabulation and recommendation; and
(4)Award a construction contract to J.F.Shea, Inc. for Contract No. P2-90A, Oil Well Excavation
and Reabandonment, for an amount not to exceed $250,853.
SUMMARY
• Contract No. P2-90A is related to Job No. 132-90, Trickling Filters at Plant No. 2. Job
No. P2-90 is one of four projects designated by the Capital Improvement Program (CIP) as
required in order to meet the Orange County Sanitation District's (Sanitation District)goal of
Secondary Standards. Job No. 132-90 has an EPA Consent Decree date of February 15,
2011 to complete construction.
• The purpose of Contract No. P2-90A is to remove the top portion of previously abandoned oil
wells that will interfere with the excavation and installation of the structures for Job No. 132-90.
• Brown and Caldwell completed the plans and specifications for Contract No. P2-90A in
April 2006. Sealed bids were received on May 30, 2006. Bid Summary information on
Contract No. 132-90A is as follows:
Project Budget: $253,125,000
Construction Contract Budget: $ 185,500,000
Engineer's Estimate: $ 500,000
Lowest Responsive Bid: $ 250,853
High Bid: $ 462,109
Number of Bids: 2
• The Director of Engineering recommends the award of the construction contract for Contract
No. P2-90A, Oil Well Excavation and Reabandonment, to the lowest responsible bidder, J.F.
Shea, Inc., in an amount not to exceed $250,853.
PRIOR COMMITTEE/BOARD ACTIONS
Approval of Professional Services Agreement(PSA)with Brown and Caldwell in June 2004.
Page 1
PROJECT/CONTRACT COST SUMMARY '
Authorization of$250,853 for construction is being requested. This contract was budgeted under
Job No. P2-90.
BUDGETIMPACT
® This item has been budgeted. (Line item: 2005-06 cIP Budget,section s.Page 59)
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
• Job No. P2-90 will be constructed on a site that is known to have four abandoned oil wells.
The project excavation will require the tops of these oil wells to be cut down by up to 30-feet.
These oil wells are hundreds, if not thousands, of feet deep. They were abandoned in the
usual method of filling the pipeline with concrete. The reabandonment process consists of
cutting the concrete filled pipeline, testing the newly revealed concrete top to ensure no gas
leakage, and welding a steel plate over the well.
• The reabandonment process on Contract No. P2-90A will be inspected and approved by the
State of California, Division of Oil, Gas and Geotechnical Resources (DOGGR) as well as the
City of Huntington Beach Fire Department, Oil Field Inspection.
• The oil well work of Contract No. P2-90A is being performed before the construction of Job
No. P2-90 to ensure that unknown conditions common with underground work will not delay
the construction of a schedule critical project that must meet an EPA Consent Decree date.
ALTERNATIVES
Perform the oil well abandonment work in the construction contract for Job No. P2-90. This
alternative is not recommended as it would have a negative impact on the construction schedule
for an EPA Consent Decree project.
CEQA FINDINGS
Job No. P2-90, Trickling Filters at Plant No. 2, was included in the Secondary Treatment and
Plant Improvement Project Subsequent Environmental Impact Report (SEIR). The SEIR was
certified on May 25, 2005, and a Notice of Determination was filed on May 26, 2005.
ATTACHMENTS
1. Budget Information Table
2. Bid Tabulation
KM:kf
R ntglobaMgenda Draft ReWesuoint BoardsXP2-"Oil well Ezw hon and ReabandmwntAm
Page 2
BUDGET INFORMATION TABLE
Contract No. P2-9OA, Oil Well Excavation and Reabandonment
(Job No. 132-90, Trickling Filters at Plant No. 2)
ORIGINAL DORRENT PROPOSED PROPOSED FUNDS . THIS PROPOSED ESTIMATED ESTIMATED
PROJECT/PHASE AUTHORIZED PROJECT BUDGET REVISED AUTHORIZED TO AUTHORIZATION TOTAL EXPENDITURE EXPENDEDTO
BUDGET BUDGET INCREASE(DECREASE BUDGET DATE REQUEST. AUTHORIZATION TO DATE DATE(%)
Phase 1 -Preject Development $ 100.000 $ 292,000 $ - $ 292,000 $ 292,000 $ - $ 292000 $ 292.000 100%
Phase 2-Preliminary Design 1305.0G0 $ 3,80 .000 $ 3,800,000 It 3,800,000 $ 3.800000 $ 3800000 100%
Phase 3-Design 5 12,188000 $ 8707000 $ 8.707.000 S 8.707.000 S 8707.000 $ 6,500,000 75%
Phase 4-Constucton $ 98632.000 $ 200857.000 $ - $ 200.857.000 $ 81200.000 $ 260.853 $ 8.450,853 $ 0%
Phase S-Commissionin $ 871000 S 11957000 $ - $ 1.967.000 $ 850,000 $ $ 850000 $ 0%
Phase B-Close-Out $ 219000 $ 405,G00 $ - E 405,000 $ 110,0DO $ - $ 110.000 $ 0%
Phase 7-Contingency 17412000 $ 37,094p00 $ - $ 37.094.000 ", $ - $ - $ $ 0%
PROJECTTOTAL $ 128.727.000 $ 253,122,000 $ $ 253.122.000 $ 21,959,ODO $ 250,853 $ 22,209,853 $ 10.592,OD0 48%
Reimbursable Costs
PROJECT NET $ 128.727.000 $ 253,122.000 1 $ - $ 253,122,000 1 $ 21.959,000 $ 250.853 $ 22.209,853 1 $ 10,592,000 48%
PSAIContract
Design PSA It 12078353 $ 9.586,445 $ - $ 9,586,445 ':'.�` $ 9,586A45 $ - $ 9588445 $ 7,450.000 78%
Construction Contract P2-90 $ 87,761.082 S 186500,OOO $ 249147 $ 186.749.147 $ - $ - $ - $ D%
Construction Contract P2-90A $ - $ 500.0m $ 249147 $ 250,853 $ - $ 250853 $ 250853 $ 0%
Ne2006a Aw
FANS:00N11299
V
ORANGE COUNTY SANITATION DISTRICT
BID TABULATIONS
CAPITAL IMPROVEMENTS PROGRAM: CONSTRUCTION CONTRACTS
JOB NO. P2-90
TRICKLING FILTERS AT PLANT NO. 2
CONTRACT NO. P2-90A
OIL WELL EXCAVATION AND REABANDONMENT
May 30, 2006
11:00 a.m.
Total Addenda: (3)
Engineer's Estimate $500,000 Engineer's Budget $500,000
CONTRACTOR TOTAL BID
1. J.F. Shea Construction, Inc. $ 280,853
2. Mike Prlich & Sons, Inc. $ 462,109
The Bid Evaluation Team has determined that J.F. SHEA CONSTRUCTION, INC. is the
Lowest Responsive, Responsible Bidder. A recommendation is made to execute a
contract with J.F. SHEA CONSTRUCTION, INC. in the amount of$280,853, subject to
concurrence of the Board of Directors. This amount is within the approved project budget.
0-7 -
Natasha Dubrovski
SENIOR CONTRACT ADMINISTRATOR, Evaluation Team Chairperson
Contracts, Purchasing & Materials Management
ND:KM:jo
003811678
Page 1 of 1
BOARD OF DIRECTORS Meeting Date I Ta Bd.or Din
O6/28/O6
AGENDA REPORT Item Number Ism Numbs
19
Orange County Sanitation District
q Collections
Facilities
FROM: David Ludwin, Director of Engineering
Originator: David May, IPMC Project Manager
SUBJECT: BUSHARD TRUNK SEWER REHABILITATION, JOB NO. I-24
GENERAL MANAGER'S RECOMMENDATION
(1) Approve the Amended and Restated Job No. 1-2-4 Reimbursement Agreement with
the City of Huntington Beach, increasing the maximum allowable 24 hour period staffing
costs from $2,645 to $3,050 but keeping unchanged the maximum total staffing costs at
$238,000, in a form approved by General Counsel. (2) Approve a Real Property
License Agreement with the Fountain Valley School District and the Huntington Beach
Union High School District necessary for the location of a temporary fire station for the
Huntington Beach Fire Department during construction of Bushard Trunk Sewer
Rehabilitation, Job No. 1-24, in a form approved by General Counsel; and (3) Approve
an Indemnification Agreement with the Fountain Valley School District, the Huntington
Beach Union High School District, and the City of Huntington Beach regarding the
temporary fire station located on Fountain Valley School District real property, in a form
approved by General Counsel.
SUMMARY
• The Bushard Trunk Sewer project is located within the Cities of Huntington Beach
and Fountain Valley. The trunk sewer is in Bushard Avenue between Ellis Avenue
and Banning Road, Banning Road between Bushard Avenue and Brookhurst, and
Brookhurst between Banning Road and Plant No. 2. The project consists of
approximately four miles of 108-inch sewer pipe.
• In 2003, the City of Huntington Beach (City) determined that the construction of the
Bushard Trunk Sewer will impact its Fire Department's emergency response ability,
as defined by the City's General plan, while construction is on Bushard Street
between Adams Avenue and Yorktown Avenue. The City determined that a
temporary fire station facility located on the east side of Bushard Street will eliminate
any impact the construction of the Bushard Trunk Sewer may have on City Fire
Department's emergency response ability.
• Project construction was delayed and suspended from its original schedule in 2003,
such that construction between Adams Avenue and Yorktown Avenue is now
scheduled to take place from August 2006 to November 2006. Labor costs to staff
the temporary fire station have increased. The Amended and Restated Job No. 1-2-4
Reimbursement Agreement addresses this change.
n ..a. almm Page 1
The Fountain Valley School District (FVSD) owns the real property being utilized for
the temporary fire station. The Huntington Beach Union High School District r
(HBUHSD) leases the property where the temporary fire station is located. A real
property agreement is needed with FVSD, and HBUHSD. A new indemnification
agreement is needed with FVSD, HBUHSD and the City.
PRIOR COMMITTEE/BOARD ACTIONS
The Board of Directors approved the Job 1-2-4 Reimbursement Agreement with the City
on April 23, 2003 for an amount not to exceed $264,500.
The Board of Directors approved the Real Property License Agreement with the
HBUHSD on September 24, 2003.
The Board of Directors approved the Indemnification Agreement with the City and
HBUHSD on September 24, 2003.
PROJECT/CONTRACT COST SUMMARY
The total budgeted amount of the Reimbursement Agreement with the City is $264,500.
The remaining project cost information is shown on the attached Budget Information
Table.
BUDGETIMPACT
® This item has been budgeted. (Line item: 2005-06 Budget Book, page 8-47)
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
Funds for the recommended actions have been budgeted and no additional funding is
requested. See attached Budget Information Table.
ADDITIONAL INFORMATION
The Bushard Trunk Sewer project is located within the Cities of Huntington Beach and
Fountain Valley. The trunk sewer is in Bushard Avenue between Ellis Avenue and
Banning Road, Banning Road between Bushard Avenue and Brookhurst, and
Brookhurst between Banning Road and Plant No. 2. The project consists of
approximately four miles of 108-inch sewer pipe.
In 2003, the City determined that the construction of the Bushard Trunk Sewer will
impact its Fire Department's emergency response ability, as defined by the City's
General plan, while construction is on Bushard Street between Adams Avenue and
Yorktown Avenue.
The City determined that a temporary fire station facility located on the east side of
Bushard Street will eliminate any impact the construction of the Bushard Trunk Sewer
may have on City Fire Department's emergency response ability.
nm. o„w. Page 2
Within the Reimbursement Agreement, the Sanitation District agreed to provide and
Y directly pay for installation and maintenance expenses for the temporary fire station in
an amount not to exceed $26,000. The Sanitation District also agreed to reimburse the
City for staffing the station for a period of 3 months in an amount not exceed $238,000.
Project construction was delayed and suspended from its original schedule in 2003,
such that construction between Adams Avenue and Yorktown Avenue is now scheduled
to take place from August 2006 to November 2006. Labor costs to staff the temporary
fire station have increased. Approval of the Amended and Restated Job No. 1-2-4
Reimbursement Agreement is requested to address these changes.
HBUHSD does not own the real property where the temporary fire station is located.
HBUHSD leases it from FVSD, the current real property owner. Thus the real property
agreement and indemnification agreement between the Sanitation District and the
HBUHSD are not valid and need to be terminated. A real property agreement is needed
with FVSD.
A new indemnification agreement is also needed with FVSD, HBUHSD, and the City.
ALTERNATIVES
Enter into the real property and indemnification agreements with the FVSD and the City.
Amend the Job No. 1-2-4 Reimbursement Agreement with the City. There are no other
reasonable alternatives that may be developed and executed prior to work starting in
August 2006.
CEQA FINDINGS
This project was included in the 1999 Strategic Plan Program EIR certified on
October 27, 1999. A Notice of Determination was filed on October 29, 1999.
Additional CEQA documentation for the project was included in Addendum No. 3 to the
EIR approved on December 19, 2001. Addendum No. 8 to the program EIR was
certified at the February 2006 Board meeting. These Addenda's do not change CEQA
findings.
ATTACHMENTS
Budget Information Table
DM:kf:sp
H:t gbbaMgenda Drell Repamuoint Boanlsg-24 AR_HBFD_FVSD Agmts_M280 d.
..atmwa Page 3
BUDGET INFORMATION TABLE
Bushard Trunk Sewer Rehabilitation
JOB NO. 1.2-4
ORIGINAL 'CURRENT PROPOSEDPROPOSED - FUNDS THIS ESTIMATED ESTIMATED
BUDGET PROPOSED TOTAL
PROJECT/PHASE AUTHORIZED PROJECT REVISED AUTHORIZED TO AUTHORIZATION EXPENDITURE EXPENDED TO
/DECREASE
BUDGET BUDGET INCREASE BUDGET DATE REQUEST AUTHORIZATION TO DATE DATE(%)
Phase l-Project Development $ 74,000 $ 74,000 $ 74.000 $ 74.000 $ 74,000 $ 74.649 101%
Phase 2.Prelimina Design $ 10 ODD $ 10.000 S 10,000 $ 10.000 $ 10.000 $ 9.148 91%
Phase 3-Oast n $ 2,189,000 $ 2,168.000 $ 2,168,OUO $ 2,168.000 $ 2,166,000 S 2,175,812 100%
Phase 4-Conslrudbn IS 46.142.0DO $ 0.142.000 1 $ 58.142,090 $ 53.934,054 $ 53.934,054 1 S 26.133.987 48%
Phase 5-CommissioniN $ 416,000 $ 416.000 S 416,000 $ 326,000 $ 326.000 $ 251509 ]]%
Phase 6-Cbso-0 $ 72,000 $ 72,000 $ 72.000 S 40.000 $ 40,000 $ 1,657 d%
Phase]-Con9 e $ 2.698.000 $ 2,698,000 $ 2.698.000 $ $ #DNN!
PROJECT TOTAL S 53,580,000 $ 63.580,000 S - $ 63,580.000 $ 56.552.054 $ - $ 56.552,054 $ 28,646,762 51%
Reimbursable Costs I I I I I I 1 $ (60,796
PROJECT NET $ 53,580.OD0 1 $ 63,58D000 1$ - $ 63,580,000 11 $ 56,552,054 $ -IS 56,552.054 1 $ 28.707557 51%
PSAIContract
PDSA-Bob $ 845.300 5 2,46T825 $ 2467.825 $ 2,467.825 $ 2,d67,825 $ 2.166.745 88%
PDSA-Earth Tech $ 2.000,000 S 2,052,593 $ 2.062.593 S 2.052.593 S 2.052.593 $ 0%
PDSA-Makolm Pimle S - $ 223.045 $ 223.046 $ 223,045 S 223,045 $ 79.267 38%
PDSA-Albert Grover $ - $ 153.000 $ 153.000 $ 153.000 S 153,000 $ 88.000 58%
Coned 1-24P-Ameron $ - S 7,699.777 $ 7.699777 $ 7,699.7]] S 7,699.777 $ 0%
1-24 Contract-Rados $ 30260834 $ 32284,139 $ 32,264,139 $ 32.214,139 3 32.284139 $ 1624],398 50%
1-24A Conlmd-Bubab S 10=00U $ 11:19115M 4 11,191.500 $ 11.191,500 8 11,181,500 $ 0%
Some.CaB!nmia Edison Is -is 350,000 I Is 350A00 I Is 350A00 I Is 35a000 $ 0%
EDW OMIO618
BOARD OF DIRECTORS rneenoewre aollfo
AGENDA REPORT Item Numbe [rem Nombe
Orange County Sanitation District
FROM: Nick Arhontes, Director of Regional Assets and Services
Originator: Chuck Forman, Sr. Supervisor, Facilities Maintenance Services
SUBJECT: Approval for Fleet Management Software Procurement and
Implementation for Fleet Services Division.
GENERAL MANAGER'S RECOMMENDATION
Award a contract to CCG Faster Systems, Inc. for purchase and implementation of
Fleet Management Application, Specification No.CS-2005-215, in the amount of
$125,500 and a contingency amount of$45,000 for a total amount not to exceed
$170,500.
SUMMARY
The Fleet Services Division (431) is responsible for providing cost-effective and reliable
services including equipment maintenance, motor pool management, regulatory
compliance, and replacement and disposal decision recommendations. Staff is
responsible for 578 equipment items at this time. The current computerized
maintenance management system (CMMS) is inadequate for our business needs.
• In October 2004, a project team was assembled to evaluate various types of fleet
management software. The team included staff from Information Technology,
Finance, CMMS support, and Fleet Services. In January 2005 a Scope of Work
and Request for Proposal was developed to procure and implement a fleet
management software system. All activities were conducted through the
Purchasing /Contracts Division to ensure that all policies were followed.
• Thirty-six firms on a national level were invited to participate including RJN, our
current CMMS supplier, and also Peoplesoft /JDE, who furnishes our current
Financial Information System (FIS). In July 2005, a five-member panel
representing Information Technology, Finance, CMMS, and Fleet Services (two
representatives) reviewed the proposals and conducted demonstrations with the
two most responsive firms: Chevin / Fleetwave and CCG Faster Systems Inc.
CCG Faster Systems, Inc.was selected as the best overall respondent. The
summary document covering the results of the RFP process is provided as an
attachment. Staff recommends awarding the contract to CCG Faster Systems,
Inc.
• Information Technology staff recommends that a contingency amount of$45,000
be included to address unforeseen needs that may arise during implementation,
start up, and testing. This allowance is customary for these types of projects.
Page 1
PRIOR COMMITTEE/BOARD ACTIONS
N/A
PROJECT/CONTRACT COST SUMMARY
Simple payback is estimated at thirty three months based on purchase cost and
ongoing annual user fees of$9,600 per year. Labor cost savings are based on savings
from various staffs time including management needed to support the existing systems,
run queries and produce reports.
BUDGETIMPACT
® This Rem has been budgeted. (Line Rem: 2005-06 Budget Section 8-Pages 118,Asset
Management Program-SP-68-2, Miscellaneous&Support Projects.)
❑ This Rem has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item)
ADDITIONAL INFORMATION
• In 1992 Fleet Services staff was requested to abandon its specialized fleet
management software and migrate to the new RJN Computerized Maintenance
Management System (CMMS) being implemented for assisting in managing
treatment plant and collection system assets. However, the RJN CMMS did not
have a Fleet Management module. In October 2002 a staff-driven, consultant—
supported, reinvention team utilizing the District Assessment and Reinvention
Team (DART) process reviewed Fleet Services' work practices, including all
information and data management needs. The team's recommendation was to
proceed with the selection and purchase of a commercially available stand-alone
fleet management software. These types of systems are used by cities, public
agencies, universities and the private sector throughout the nation.
• The existing RJN CMMS was modified to capture relevant information on the
current treatment plant and the collection systems. However, the current CMMS
does not provide adequate financial and asset data management of the fleet
equipment. These include but are not limited to: determining the equipment
needs, user accountability, asset maintainability, utilization history, current
operating and Iifecycle costs, and revenue from asset disposal.
• The forward plan for Regional Assets and Services and the Finance Department
includes implementing a Vehicle Replacement Fund as soon as practical. This
software system will provide the necessary data, and with minimal staff support,
we can move ahead with that plan.
• CCG Faster Systems, Inc. currently has a users group of 276 installations
nationally and in Canada. Of 225 users that staff analyzed, their average fleet
size was 1,022 items. Of those, 93 had a fleet size ranging from 70 to 550 items.
This brackets OCSD's inventory of 578 items well. Our current inventory is made
up of 578 assets: 77 bicycles, 170 electric carts, 164 light, medium, and heavy
Page 2
1 duty service trucks, 37 sedans and 130 other pieces of specialized stationary
equipment and rolling stock including emergency generators and pump systems.
• The reduction of Fleet Services Technicians from 6 in 1994 to 4 in 2006 requires
efficient processes such as the retrieval of data that can be accessed from one
remote location to assist the technicians and optimize current staffing levels.
• The CCG Faster Systems software includes over 100 standardized reports for
staff and management use. These reports are modified and new ones added
based on input from their users group.
• The final due diligence consisted of two final visits in May 2006 by the
Information Technology Manager and the Senior Facilities Supervisor who
oversees Fleet Services. They visited staff from the cities of Anaheim and
Inglewood to learn about actual support labor needed by I.T. staff after
installation. They both agreed that CCG Faster systems, Inc. is a reputable
company with a useful product and no additional routine support is needed
beyond implementation start-up and testing.
• A significant amount of due diligence has been performed by many staff to
support this recommended purchase. The Orange County Fire Authority, city of
Burbank, Ventura Fire Department and the city of Santa Ana are all monitoring
OCSD's process and are awaiting our selection to move ahead with their
procurements of the CCG Faster Systems, Inc. product.
ALTERNATIVES
A decision was made in 2002 not to invest additional public time and money into the
current CMMS or FIS software systems that are not adequately designed to aid staff
and management in managing fleet assets. Continuing with the current CMMS which
does not meet our current or long range needs is viewed as not acceptable.
CEQA FINDINGS
N/A
ATTACHMENTS
Fleet Management Application, Specification No. CS-2005-215, RFP RE-CAP
Page 3
1
Fleet Management Application
SPECIFICATION NO. CS-2005-215
RFP RE-CAP
Evaluators provided the following scoring:
Maximus MRO Chevin CCO Faster
Evaluator"A" B60 690 760 775
Evaluator"B" 440 440 530 590
Evaluator"C" 480 400 430 660
Evaluator"0" 550 550 580 640
Evaluator"E" 460 240 430 650
SUB-TOTAL 2590 2320 2730 3335
COST SCORES FOR
SHORTUST 750 536
Total 3480 3871
Chevin CCG Faster
Vendors Cost $72,160.00 $101,000.00
Total Points Available
(Weighting'10)"Number of
evaluators 750 750
Total Cost Score 750 536
Recommendation for award: CCG Faster
Approval for award: Marc Dubois C.P.M. Contracts/ Purchasing Manager
H vteptvasWiMtontesOOARD ITEMSUune'%Fleet Software RFP ReK p.dm
BOARD OF DIRECTORS Meeting Date TOBd.WDir,
06/2a/06
AGENDA REPORT Ienn Number Item Numbe
zI
Orange County Sanitation District
FROM: Lorenzo Tyner, Director of Finance
Originator: Mike White, Controller
SUBJECT: INSTALLMENT PAYMENTS FROM 10 PROPERTY OWNERS
ABANDONING THEIR SEPTIC TANKS FOR ANNEXATION AND
CAPITAL FACILITIES CAPACITY CHARGES
GENERAL MANAGER'S RECOMMENDATION
Adopt Resolution No. OCSD 06-16, approving the Orange County Sanitation District
levying assessment installments in lieu of the payment of sewer system annexation fees
and capital facilities capacity charges (CFCC) incidental to the connection of assessor's
parcel Nos. 502-353-05, 502-352-06, 502-353-01, 502-361-04, 502-362-06,
502-362-05, 502-362-07, 502-362-09, 502-362-08, and 502-362-11 to the sewer
system.
SUMMARY
Currently our records show there are approximately 2,000 properties within the
Sanitation District service area on septic tanks, rather than sanitary sewers. A smaller
number is estimated to exist within the County but not currently annexed to our service
area.
These septic tanks can be shown to contribute to the bacterial contamination of urban
runoff. This could be a result of failing systems or of contamination leaching through the
soil and emerging to be carried away as urban runoff.
There are many steps required of a property owner who desires to move from an on-site
septic tank to the regional sanitary sewer system. If not in the service area, the property
must be annexed to a local sewering agency as well as to the Sanitation District. A
lateral must be constructed from the building on the property to the local sewer and a
local and OCSD CFCC, or"connection fee," must be paid. If a local sewer is not
available, then that sewer must be constructed. The septic tank must be emptied and
then properly abandoned by a licensed contractor. The total cost for these services
varies by property and proximity to a local sewer, but it is always substantial. District
staff has estimated the cost to abandon a septic tank and to build a 100-foot vitrified
clay pipe connection to an existing local sewer to be between $12,000 and $15,000.
from No.M-IN Agenda Report-Board
DapL 220 RVlwd. 6Y 12006
Page 1
r
In the past, Directors have discussed methods of encouraging property owners to
abandon their septic tanks and to connect to the sanitary sewers. General Counsel has
consistently advised that our existing Ordinance does not allow fees to be waived or set
aside.
In order to minimize the impact and encourage property owners to move off of septic
tanks and onto the local sewer system, the Board approved in September 2003, the
payment of annexation and CFCC through installments, by levy on the County tax rolls
and included on the property tax bill, over a five-year period at zero percent interest.
Since Board approval of this program in September 2003, this is the first request staff
has received to pay annexation fees and CFCC through installments. Following is a
summary of the ten parcels requesting approval of installment payments along with the
total fees:
Total Annexation Fee
Parcel No. and CFCC
502-353-05 $5,249.15
502-352-06 $5,418.55
502-353-01 $6,900.25
502-361-04 $7,056.75
502-362-06 $5,884.40
502-362-05 $6,476.75
502-362-07 $6,815.55
502-362-09 $6,222.30
502-362-08 $6,561.45
502-362-11 $7,620.20
Total $64,206.36
PRIOR COMMITTEE/BOARD ACTIONS
In September 2003, the Board adopted a policy allowing property owners currently on
septic tanks to make annual payments for the Capital Facilities Capacity Charge and
Annexation Fee over a period not to exceed five years, at zero percent interest, to be
collected on the property tax bill and to provide that property owners must connect to
the local sewer system within three years from the time the sewer line is installed to
quality for the zero percent interest, five-year payment program for said fees.
PROJECT/CONTRACT COST SUMMARY
N/A
Form No.M-102 Age ca ReWn-BmW
D�pt R. , &2=2
Page 2
/ BUDGETIMPACT
❑ This item has been budgeted. (Line item: )
❑ This Rem has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
® Not applicable (information item)
ADDITIONAL INFORMATION
N/A
ALTERNATIVES
N/A
CEQA FINDINGS
N/A
ATTACHMENTS
N/A
MW
Form No.WF103 Agen"Rwd-Board
Not 20 ReviW: Brz�1300B
Page 3
BOARD OF DIRECTORS Meeting Date To Ba.or Dlr.
06/28/O6
AGENDA REPORT Item Number ItemNumbe
zz
Orange County Sanitation District
Collections
Facilies
FROM: David Ludwin, Director of Engineering
Originator: Hardat Khublall, CIP Project Manager
SUBJECT: SANTAANA RIVER INTERCEPTOR REALIGNMENT AND
PROTECTION, CONTRACT NO. 241
GENERAL MANAGER'S RECOMMENDATION
Approve an agreement with the Irvine Community Development Company to retain and
pay engineering and environmental consultants for an amount not to exceed $200,000
to provide engineering services relating to the SARI line shallow profile alternative study
and Mountain Park Sewer Line Connection, in a form approved by General Counsel.
SUMMARY
The Irvine Community Development Company (ICDC) is planning a 2,500 unit
development project in the Anaheim Hills area. The ICDC would like to connect a
15-inch sewer line from the eastern portion of the Mountain Park development to the
existing SARI line. In exchange for consideration of this connection, ICDC is willing to
retain engineering and environmental consultants, at a cost of up to $200,000, to study
the Shallow Profile Alternative. The engineering consultants would consider the
feasibility and potential costs of the Shallow Profile Alternative and develop information
regarding required easements and permits. The environmental consultants will prepare
analysis for the EIR/SEIS relating to potential environmental impacts of the Shallow
Profile alternative.
The SARI line relocation project may not be complete by the time that ICDC is ready to
connect to the line. Therefore, in the event that ICDC seeks to connect to the SARI line
before the relocation is complete, the draft agreement provides for a temporary
connection by the City of Anaheim to the existing SARI line, subject to permit terms and
conditions required by the District. Once the SARI line relocation is complete, the
Mountain Park line would be permanently connected to the new SARI line by the City of
Anaheim.
PRIOR COMMITTEE/BOARD ACTIONS
On May 4, 2006, the Planning, Design & Construction Committee (PDC) recommended
to the Board of Directors to authorize the execution of an agreement with the Irvine
Community Development Company re relocation of SARI Line and Mountain Park
Sewer Line, and to include determination and resolution of maintenance and liability
issues, in a form approved by General Counsel.
aonn.aaoroe(0) Page 1
PROJECT/CONTRACT COST SUMMARY -
N/A
BUDGETIMPACT
❑ This item has been budgeted. (Line item: )
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
® Not applicable (information item)
If additional study is determined necessary by the District beyond the $200,000
committed to by ICDC, the District will be responsible to either pay for the additional
work or to find another party (i.e. County of Orange, SAWPA) to pay the additional
costs.
ADDITIONAL INFORMATION
The Army Corps of Engineers is currently preparing an Environmental Impact
Report/Supplemental Environmental Impact Statement (EIR/SEIS) for the SARI line
relocation project. Part of the project involves relocating the SARI line between the
Green River Golf Course and the SAVI Ranch Control Gate. The EIR/SEIS contains
several alternative alignments. The preferred alignment in the EIR/SEIS is known as
the "Relocate to the South" alternative, and commonly referred to as the "South Bank
Alternative." Under the South Bank Alternative, the pipeline would be placed at a depth
of as much as 60 feet.
OCSD would like to consider a variation of the South Bank Alternative, proposed by
ICDC, where the pipeline would be constructed at a much shallower level. This
proposed variation, called the Shallow Profile Alternative, might be less costly than the
South Bank Alternative. To date, the Shallow Profile Alternative has not been studied in
any detail by the various agencies involved in the SARI relocation project planning
ALTERNATIVES
Do not agree to the terms dictated by ICDC and continue with the County of Orange
maintaining responsible to fully develop any alternatives deemed reasonable for
consideration. The ICDC would be required to connect to the SARI line at SAVI Ranch,
beyond the segment of the SARI line in jeopardy.
CEOA FINDINGS
N/A
ATTACHMENTS
Proposed Letter Agreement with ICDC
HK:eh
H:trtlglobalWgenda Draft RepcTtWoint Boards%ARI Line AR 062806.dm
a..a.e. ovm«pm Page 2
ORANGE COUNTY SANITATION DISTRICT
June 28,2006
PMne:
rim ssz-zan Bryan Austin
fee; Vice President
f7141 962-0356 Irvine Community Development Company LLC
�'0bd.ca1° 550 Newport Center Drive
..m.s address: Newport Beach,CA 92658-8904
PO Boxa127
u.,oi Valley.CA
DP728-8127 Re: Mountain Park: Letter Agreement Regarding Relocation of SARI Sewer
street address:
I644 Ems Ascnuc Dear Mr. Austin:
iuneam Valley,CA
92708-7018
This letter memorializes the understandings and agreement of the Orange County Sanitation
Mnntar District ("OCSD") and Irvine Community Development Company LLC (`YCDC') regarding
A9enciaa the connection of a sewer line of no greater than 15-inches (the "Mountain Park Sewer
• Line") from the East Village portion of ICDC's 2500 unit Mountain Park project (the
Citiei "Development') into the Santa Ana River Interceptor ("SARI") Sewer. As we have
discussed, the Los Angeles District of the U.S. Army Corps of Engineers (USACE) is
areBre.hose, currently preparing an Environmental Impact Re orUS lememal Environmental Impact
area Y P P 8 mP P uPP P
'Boone Park Statement("EIRISEIS') in connection with its Santa Ana River Mamstem Project, including
41"'ei. the proposed protection in place or relocation of a portion of the existing SARI Sewer located
-Fourocm valley
Follerton between the Orange County line at the Green River Golf Course area and the SARI Control
Gardan Grose Gate in the SAVI Ranch development in Yorba Linda as depicted by the dashed white line
;nangr°n Beach shown on Exhibit A to this letter (the "Affected Segment'). Under the USACE's preferred
each
La Habra relocation plan, the Affected Segment would be moved from its present location within the
LO Joahha
Pp6ne Santa Ana River to a location that parallels the SR-91 Riverside Freeway that is depicted in
Los al P Y P
Nowccrt Beach red on Exhibit A (the "South Bank Alternative"). OCSD is willing to allow the City of
Orange Anaheim as the local sewering agency to establish, operate, and maintain a sewer and its
Placentia
Sarre Ana connection of the Mountain Park Sewer Line into the SARI Sewer at OCSD SARI Manhole
seal Beach ID No. SAR0610-0000 (Contract 2-14-5, Station 1117+02) located on the East side of the
B7ent°n ruedn Gypsum Canyon Road Bridge so as to serve the proposed Development subject to the terms
Ville Park of this letter agreement("Agreement'). The parties to this Agreement agree as follows:
n,rbe Linda
my of Or..gc 1. Mountain Park Sewer Line Connection Into SARI Sewer. In consideration for
1CDC's performance of the obligations described in Section 2 below, OCSD agrees that the
Itary Districts City of Anaheim may establish and maintain a connection of the Mountain Park Sewer Line
- Ccsra Mesa into the SARI Sewer subject to obtaining OCSD Trunk Sewer Connection Permit(s), upon
midway Ce, such terms and conditions as OCSD may reasonably require, which Connection Permit(s)will
[our Districts not be unreasonably withheld. The location of the connection shall depend on the timing of
completion of construction of the realigned portion of the Affected Segment and the needs of
-. Irma Ranch the Development:
a. SARI Sewer Relocation to South Bank Alternative Completed First. If the
Affected Segment of the SARI Sewer has been relocated to the South Bank prior to the time
that the City of Anaheim or its agents desire to connect the Mountain Park Sewer Line to the
SARI Sewer, then the OCSD shall issue a permanent OCSD Trunk Sewer Connection Permit
30160-0171/3574834 3/30,,6
512977.3
-in[»in wnrlrlcl»»»bwdarxh,n in w»at»wn!r hod w»h——n rl ca mnhh—lnt
upon such terms and conditions as OCSD may reasonably require, including but not limited
to conditions upon the construction,operation and maintenance of the Mountain Park Sewer
Line,and the Mountain Park Sewer Line shall be connected into the relocated SARI Sewer at
Connection Point I as shown on Exhibit B to this Agreement,.
b. Mountain Park Sewer Line Connection Prior to SARI Sewer Relocation. If
the Affected Segment of the SARI Sewer has not been relocated to the South Bank
Alternative or to any other location at the time that the City desires to connect the Mountain
Park Sewer Line to the SARI Sewer, then the OCSD shall issue a temporary OCSD Trunk
Sewer Connection Permit upon such terms and conditions as OCSD may reasonably require,
including but not limited to conditions upon the construction, operation, and maintenance of
the Mountain Park Server Line,and City or its agents shall be allowed to connect to the SARI
Sewer at Connection Point 2 as shown on Exhibit B to this Agreement. OCSD may also
require as a condition of the City's temporary Trunk Sewer Connection Permit that City
relocate or modify the Mountain Park Sewer Line at no cost to OCSD in the event the
relocation or protection in place of the Affected Segment requires modifications or relocation
of the Mountain Park Sewer Line or its connection point with the SARI sewer line. After the
relocation of the Affected Segment of the SARI Sewer to the South Bank Alternative or other
location is completed,OCSD shall issue a permanent OCSD Trunk Sewer Connection Permit
upon such terns and conditions as OCSD may reasonably require, including but not limited
to conditions upon the construction,operation,and maintenance of the Mountain Park Sewer
Line,and the Mountain Park Sewer Line connection will thereafter be at Connection Point 1,
or if the Affected Segment is relocated to another location,then to such other point as OCSD
and the City agree is most feasible. In the event the relocation or protection in place of the
Affected Segment requires modifications or relocation of the Mountain Park Sewer Line or of
the connection point of the Mountain Park Sewer Line,such modifications or relocation shall
be completed pursuant to plans approved and permits issued by OCSD and the City of
Anaheim prior to commencement of construction.
The connection of the Mountain Park Sewer Line under either of the above alternatives shall
be completed at no expense to OCSD and shall be made pursuant to plans approved and
permits issued by OCSD and the City of Anaheim prior to commencement of construction.
No plan check fee shall be charged by OCSD for its review of the proposed oormection of the
City of Anaheim-owned Mountain Park Sewer Line under either of the alternatives described
above. OCSD may charge all other ordinary fees arising out of connection of such line.
2. ICDC Obligations. In consideration for OCSD's agreement to allow the connection
of the Mountain Park Sewer Line to the existing or South Bank Alternative SARI Sewer,
ICDC agrees to perform the following:
a. Administration of Preliminary Engineering and Environmental Analysis. ICDC shall
retain and manage engineering and environmental services consultants (collectively, the
"Consulmnts") approved by OCSD to prepare (i) the preliminary engineering feasibility
report for the relocation of the Affected Segment of the SARI Sewer to the South Bank
Alternative (the "Engineering Work'), and (ii) the portion of the EIR/SEIS describing the
biological resource impacts that will result from the relocation of the Affected Segment of the
SARI Sewer to the South Bank Alternative(the"Environnrenrul Work). The purpose of the
Engineering Work will be to provide sufficient information to demonstrate the feasibility of
30160-0171p67493.A 3/30106
Snan l
Y
building a shallow-profile South Bank Alternative, and to provide sufficient information to
obtain approvals for permits and easements that will be needed for the new SARI Sewer
alignment from all landowners within the South Bank Alternative alignment. The purpose of
the Environmental Work will be to analyze and quantify the impacts of building the shallow-
profile South Bank Alternative and determine mitigation measures that may be appropriate.
All work performed by the Consultants shall be reviewed by and be subject to the approval of
the OCSD, and OCSD shall not charge any plan check fees in connection with its review of
the Engineering Work and the Environmental Work Any and all resulting work product
shall be made available for use by the OCSD as OCSD, in its sole discretion, detemtines is
appropriate, including submittal of copies of the work product to local, State, and Federal
agencies and interested parties.
b. ICDC Financial Obligation. ICDC shall pay the Consultants for their services in
performing the Engineering Work and the Environmental Work; provided, however, that in
no event shall ICDC be responsible for the payment of any amounts for the cost of such
consulting services (for both the Engineering Work and the Environmental Work) in excess
of Two Hundred Thousand Dollars($200,000.00). Subject to the foregoing limitation, ICDC
shall pay the Consultants in a timely manner for their services,and shall provide copies of all
contracts,invoices and payments to OCSD.
3. Term of Consultant Contracts. The parties agree that the contracts entered for the
perforntar2ce of the Engineering Work and the Environmental Work shall each require that
the services up to the$200,000 initial amount be completed on or before October 31,2006.
4. Project Coordination. With respect to review of consulting services, plans for
connection of the city's Mountain Park Sewer Line, and any other matters requiring
coordination of efforts or the implementation of this Agreement, OCSD designates Hardat
Khublall, telephone (714) 593-7377 (fax 714-964-4775) to act as its project representative,
and ICDC designates Terry Hartman, telephone (949) 720-2707(fax 949-720-2692)to act as
its project representative. Either party may change its designated representative by providing
written notice of same to the other party within 10 days.
5. Authorization. OCSD and ICDC represent and wamant that this Agreement has been
duly authorized and executed and constitutes the legally binding obligation of their respective
organization or entity,enforceable in accordance with its terms.
6. Entire Agreement. This letter, together with the attachments hereto, constitutes the
entire agreement of the parties with respect to the subject matter contained herein, and
supersedes all prior agreements and understandings,whether oral or written.
If the above provisions accurately reflect our mutual understandings regarding the parties'
respective obligations regarding the[natters described above,please sign the enclosed copy of
this letter and retum it to me. Thank you for your cooperation.
Sincerely,
ORANGE COUNTY SANITATION DISTRICT
301600171/357493A 3/30M6
5129".3
I /
By:
Steve Anderson
Chair,OCSD Board of Directors
ATTEST:
By:
Penny Kyle
Board Secretary
APPROVED AS TO FORM:
BRADLEY R. HOGIN,DISTRICT COUNSEL
By:
David Kendig
ICDC Concurrence
The terms of this Agreement are accepted and agreed to by the undersigned.
IRVINE COMMUNITY DEVELOPMENT COMPANY LLC
By:
Bryan Austin
Vice President,Community Development
By:
Mary K.Westbrook
Assistant Secretary
30160-017W57483.4 MOM
51r8T1.3
t +
IVA
��. a r.+' t� y$�� A 1 �'�-. "� �,a� �1�� 't4e'`��ik' � t � Q �'"Y.z•�.-��0� '.
w M„
VN
�x �� fa.�','r • ■ `���� 1 .+ r ` J .. "omiIq.
irA! _ -
h i
IZ
Nk
gt
yyyy .,..i . "t > a .�+:n� ♦' i �� �'A a.>\ a 1 1, Jr a^ k+c•c { IL 2 i'K'1..� � ti.0 �Y � t �Y8 u p W" "tgr{''r�
H
�� 4A i'" � � kfi4. e S V ✓ ti '� s` �. � ti � ���n xx t ..F
t_�� r ��� u/t��y'�.� t��'iq �t ' � •F,, s i ,� ,:« w-3+,, r Y 1t "'' „/' .k(_
NZ..
h
"gyp I
r BOARD OF DIRECTORS MeeOng Date To ad.of Dlr.
06-2M6
AGENDA REPORT Iem Number Item Number
23
Orange County Sanitation District
FROM: James Ruth, Interim General Manager
Lorenzo Tyner, Director of Finance
SUBJECT: SALE OF ADDITIONAL CAPACITY TO THE SANTA ANA WATERSHED
PROJECT AUTHORITY (SAWPA)
GENERAL MANAGER'S RECOMMENDATION
Authorize the General Manager to enter the District into an agreement with the Santa
Ana Watershed Project Authority (SAWPA) for the sale of 4 million gallons per day
(MGD) of capacity for approximately $17.1 million.
SUMMARY
Pursuant to the Wastewater Treatment and Disposal Agreement dated July 24, 1996,
between OCSD and SAWPA, SAWPA possesses an ultimate Treatment and Disposal
Right of 30 MGD. Additionally, SAWPA has exercised its purchase rights and acquired
and presently owns 13 MGD of capacity defined as a Treatment and Disposal Right.
SAWPA has expressed a desire to purchase an increment of wastewater Treatment
and Disposal Right capacity of 4.0 MGD for desalting brine from groundwater
reclamation projects within SAWPA's SARI Service Area.
OCSD has expressed a desire to promote, and participate in, groundwater reclamation
in SAWPA's Santa Ana River Interceptor ("SARI") Service Area. In furtherance of that
desire, OCSD has previously established a modified Treatment and Disposal Right
Charge for wastewater treatment and disposal capacity for desalter brine, as an
incentive to the implementation of desalting projects.
PROJECT/CONTRACT COST SUMMARY
The sale of this capacity would result in revenue to the District of approximately
$17.1 million. This revenue has been assumed and included in the 2006-07 and
2007-08 Proposed Budget.
BUDGETIMPACT
® This item has been budgeted. (Line item: )
❑ This item has been budgeted, but there are insufficient funds.
❑ This item has not been budgeted.
❑ Not applicable (information item). Applies to future budget periods
a
ADDITIONAL INFORMATION
Purchase Price of Brine Capacity.
OCSD and SAWPA would agree that SAWPA will purchase Treatment and Disposal
Right capacity for the disposal of brine generated by groundwater reclamation projects
within SAWPA's SARI Service Area, at a price established pursuant to OCSD's current
Capital Facilities Capacity Charge, by the following formula for 1 MGD:
Assumptions Unit of Measure Rate Brine Capacty
Flow= 1,000,000 Per gallons/day $3.64/gpd $3,642,963
BOO = 20 mg/L Per pound/day $2,477.83/lbs/day $ 413,302
SS = 18 mg/L Per pound/day $1,517.22/lbs/day $ 227,765
$4,284,030
Application of the formula generates the purchase price of $4,284,030 per each million
gallons of capacity as of the date of this agreement.
The purchase price for any future purchases of Treatment and Disposal Right capacity
shall be determined in accordance with OCSD's then-existing Capital Facilities Capacity
Charge and then established loading assumptions as of the date of the future purchase.
Purchase and Sale of Increment of Capacity
Subject to all of the terms and conditions of the Wastewater Treatment and Disposal
Agreement dated July 24, 1996 (except as provided for in Section 1) OCSD sells to
SAWPA 4.0 MGD Treatment and Disposal Right, to be utilized for the disposal of brine
generated from groundwater reclamation projects within SAWPA's SARI Service Area.
Purchase Price
The purchase price of the Treatment and Disposal Right shall be $17,136,120 based on
the previously listed formula. This agreement shall be void if SAWPA fails to pay the
purchase price within sixty (60) days of the date first written above.
Failure to Pay Purchase Price
If SAWPA fails to comply with full purchase terms as stated above, SAWPA shall pay a
surcharge on the flow exceeding SAWPA's current Treatment and Disposal Right in
addition to the payment of Disposal Costs. The surcharge shall be calculated applying
the same rate which the District is currently applying to District's Class I users for
capacity purchases.
The surcharge shall not apply if this agreement is not signed at the time SAWPA
exceeds the current 13 MGD Treatment and Disposal Right and is due to delays
initiated by the District.
X NeplWpMe dNpMe ReprAs�MFi BcsU Appged ApeMe Rep.i' If`OfiLfiNwn 2]M4 AreCeatllwB—
Page 2
Applicability of 1996 Agreement
OCSD and SAWPA agree that solely because of the nature of the brine discharge, its
costs of treatment, and the indirect benefits to OCSD, and the residents of Orange
County, a special purchase price is appropriate for the Treatment and Disposal Rights
which are the subject of this purchase agreement.
Establishment of Baseline
The District has by virtue of this agreement, agreed to sell 4 MGD of Treatment and
Disposal Right Capacity using BOD and SS values lower than what is specified in the
July 24, 1996 Agreement. To ensure that the 4 MGD flow capacity sold to SAWPA
does not add additional BOD and SS Ibs/day than what was agreed upon by this
agreement, a maximum loading baseline using Fiscal Year 2004-05 data is hereby
established which defines the maximum loading SAWPA must maintain. If SAWPA
exceeds the maximum loading, the District may open this Agreement for negotiations to
determine the proper purchase price.
Data Used to Determine Baseline
Base Fiscal Year BOD Ibs/dav SS Ibs/day
2004-05 11,084 24,132
2006 Purchase 667 600
Max Loading Baseline 11,751 24,732
ALTERNATIVES
CEQA FINDINGS
N/A
ATTACHMENTS
1. OCSD — SAWPA Purchase Agreement
LT:Ic
H NapNpmdeBmd M�RapalS�Boyd Mahe 6 Nper6+Re SRl tem3 S4 A,e Cese[n Bme.Mc
Page 3
02/27/06
1
AGREEMENT TO ESTABLISH THE PURCHASE PRICE FOR,
AND THE PURCHASE OF,A 4.0 MGD WASTEWATER TREATMENT AND
DISPOSAL CAPACITY RIGHT FOR DESALTER BRINE
THIS AGREEMENT is made and entered into, and is to be effective this 28th day of
June,2006, by and between:
ORANGE COUNTY SANITATION DISTRICT, a public
agency,hereinafter referred to as"OCSD";
AND
SANTA ANA WATERSHED PROJECT AUTHORITY, a
joint powers public agency, hereinafter referred to as
"SAWPA".
OCSD and SAWPA are sometimes collectively referred to herein as the"Parties".
RECITALS
A. Pursuant to that certain Wastewater Treatment and Disposal Agreement dated
July 24, 1996, between the Parties (the "Agreement"), SAWPA possesses an ultimate Treatment
and Disposal Right of 30 MGD(as those terms are defined in the Agreement); and
B. Pursuant to the Agreement, SAWPA has exercised its purchase rights and
acquired and presently owns 13 MGD of capacity defined as a Treatment and Disposal Right;
and
C. OCSD has expressed a desire to promote, and participate in, groundwater
reclamation in SAWPA's Santa Ana River Interceptor("SARI") Service Area. In furtherance of
that desire, OCSD has previously established a modified Treatment and Disposal Right Charge
for wastewater treatment and disposal capacity for desalter brine, as an incentive to the
implementation of desalting projects; and
D. SAWPA has expressed a desire to purchase an increment of wastewater
Treatment and Disposal Right capacity of 4.0 MGD for desalting brine from groundwater
reclamation projects within SAWPA's SARI Service Area.
E. OCSD has adopted a Capital Facilities Capacity Charge ("CFCC") payable by all
dischargers into OCSD's system, which charge is subject to modification from time-to-time by
action of the Board of Directors.
t
NOW,THEREFORE,the Parties hereto hereby agree as follows:
Section 1: Purchase Price of Brine Capacity. OCSD and SAWPA hereby acknowledge
and agree that SAWPA will, by this agreement,purchase Treatment and Disposal Right capacity
for the disposal of brine generated by groundwater reclamation projects within SAWPA's SARI
Service Area, at a price established pursuant to OCSD's current Capital Facilities Capacity
Charge,by the following formula:
For 1 MGD
Assumptions Unit of Measure Rate Brine Capacity
Flow= 1,000,000 Pergallons/day $ 3.64/gpd $3,642,963.00
BOD=20 mg/L Per pound/day $2,477.83/lbs/day $ 413,302.00
SS = 18 mg/L Per pound/day $1,517.22/lbs/day $ 227,765.00
$4,284,030.00
Application of the foregoing formula generates the purchase price of$4,284,030.00 per
each million gallons of capacity as of the date of this agreement.
The purchase price for any future purchases of Treatment and Disposal Right capacity
shall be determined in accordance with OCSD's then-existing Capital Facilities Capacity Charge
and then established loading assumptions as of the date of the future purchase.
Section 2: Purchase and Sate of Increment of Capacity. Subject to all of the terms and
conditions of the Wastewater Treatment and Disposal Agreement dated July 24, 1996, except as
otherwise expressly provided for in Section 1 herein, OCSD hereby sells, and SAWPA hereby
purchases, 4.0 MGD Treatment and Disposal Right, to be utilized for the disposal of brine
generated from groundwater reclamation projects within SAWPA's SARI Service Area.
Section 3: Purchase Price. The purchase price of the Treatment and Disposal Right
conveyed hereunder shall be $17,136,120.00 based upon the formula set forth in Section 1
above. This agreement shall be void if SAWPA fails to pay the purchase price within sixty (60)
days of the date first written above.
Section 4: Failure to Pay Purchase Price. If SAWPA fails to comply with full purchase
terms as stated above, SAWPA shall pay a surcharge on the flow exceeding SAWPA's current
Treatment and Disposal Right in addition to the payment of Disposal Costs. The surcharge shall
be calculated applying the same rate which the District is currently applying to District's Class I
users for capacity purchases.
The surcharge shall not apply if this agreement is not signed at the time SAWPA exceeds the
current 13 MGD Treatment and Disposal Right and is due to delays initiated by the District.
Section 5: Applicability of 1996 Agreement OCSD and SAWPA acknowledge and
agree that solely because of the nature of the brine discharge, its costs of treatment, and the
indirect benefits to OCSD, and the residents of Orange County, a special purchase price is
appropriate for the Treatment and Disposal Rights which are the subject of this purchase
agreement. It is the intent of the Parties that all other terms and conditions of the Agreement
shall be applicable to the Parties and to the brine discharge from SAWPA to the OCSD system.
2
I
Section 6 Establishment of Baseline The District has by virtue of this agreement, agreed
to sell 4 MGD of Treatment and Disposal Right Capacity using BOD and SS values lower than
what is specified in the July 24, 1996 Agreement. To ensure that the 4 MGD flow capacity sold
to SAWPA does not add additional BOD and SS Ibs/day than what was agreed upon by this
agreement, a maximum loading baseline using Fiscal Year 2004-05 data is hereby established
which defines the maximum loading SAWPA must maintain. If SAWPA exceeds the maximum
loading, the District may open this Agreement for negotiations to determine the proper purchase
price.
Data Used to Determine Baseline
Base Fiscal Year BOD Ibs/day SS Ibs/day
2004-05 11,084 24,132
2006 Purchase 667 600
Max Loading Baseline 11,751 24,732
IN WITNESS WHEREOF, the Parties have executed this agreement as of the day and
year first above written.
ORANGE COUNTY SANITATION DISTRICT
By
Chair, Board of Directors
By
Secretary, Board of Directors
SANTA ANA WATERSHED PROJECT
AUTHORITY
By
Chairman of the Commission
3
FILED
IN THE OFFICE OF THE SECRETARY
ORANGE CM"... MSTRIC,
ADDENDUM NO. 1 TO THE
JUN 28 2006
ORANGE COUNTY SANITATION DISTRIC� �.
SUBSEQUENT ENVIRONMENTAL IMPACT REPORT THE
SECONDARY TREATMENT AND PLANT IMPROVEMENT PROJECT
STATE CLEARINGHOUSE NO.: 2004031076
LEAD AGENCY: Orange County Sanitation District
PREPARED BY: Integrated Program Management Consultants
DATE May 2006
PURPOSE OF ADDENDUM:
On May 25, 2005,the Orange County Sanitation District(Sanitation District) Board of
Directors certified the Final Subsequent Environmental Impact Report(SEIR) for the
Secondary Treatment and Plant Improvement Project(Project) (SCH No. 2004031076).
The SEIR analyzed the environmental impacts of numerous improvements at
Reclamation Plant No. 1 (Plant No. 1) and Treatment Plant No. 2 (Plant No. 2) required
to achieve secondary treatment standards. Where appropriate, the SEIR incorporated
by reference relevant environmental analysis from the Sanitation District's 1999
Strategic Plan Program Environmental Impact Report. This addendum, prepared in
accordance with the California Environmental Quality Act (CEQA) (Public Resources
Code Section 21000 at seq.)and its implementing Guidelines (California Code of
Regulations Title 14, Chapter 3, Section 15000 at seq.), addresses modifications to the
proposed 66kV(kilovolt)substation facility described in the SEIR. The Sanitation District
Board of Directors and the California Public Utilities Commission (CPUC)will consider
this addendum in conjunction with CPUC permitting of the 66kV substation facility.
PROJECT DESCRIPTION:
Southern California Edison (SCE) proposes to construct a new outdoor 66/12kV
substation to provide electrical service for the secondary treatment upgrades planned for
the Sanitation District Plant No. 1. The new substation would be located at 10844 Ellis
Avenue, Fountain Valley, California at the site of the existing Plant No. 1. See Figure 1.
The Project would construct a new electrical substation to provide power from SCE at
66 W. The substation would be constructed in a rectangular area approximately 200-
feet by 75-feet, which would be enclosed with a fence up to 8-feet high. Along the
Garfield Avenue facing side of the site, a block wall up to 10-feet high would be placed to
provide visual screening. The substation would include two 25-toot-high by 12-foot-
wide, open steel structures(switch racks)to support 66kV switches and breakers.
A new segment of 66kV line required to serve the new substation,would be constructed
underground and would originate from SCE property on the south side of Garfield
Avenue in the City of Huntington Beach and extend to the north side of Garfield Avenue
in the City of Fountain Valley. This new 66kV line construction would require the
OCSMPW PAGE I OF 6 my=
-T/nr0. rc Pi-y?
Y v
installation of approximately five wood and/or steel poles on SCE property, and up to
four spans of 954 stranded aluminum conductor(sac) overhead conductor. Two
separated underground substructure systems of 3,000 thousand circular mils(kcmil)
underground cable would be installed. Three new pole switches would be required to
tap the existing Ellis-Gisler 66kV line and the new 66kV underground line from Ellis
Substation to the new proposed substation at Plant No. 1. Up to six existing SCE 12kV
poles along Garfield Avenue would be removed and circuits installed underground to
facilitate substation construction. Following construction, landscaping would be provided
along Garfield Avenue for the length of the substation site.
ENVIRONMENTAL IMPACT ANALYSIS:
A new 66kV substation facility at Plant No. 1 is described in Section 2.2.3 of the SEIR.
Environmental impacts associated with a new 66kV substation facility are evaluated in
Chapter 3 of the SEIR. The SEIR does not include several components related to the
proposed substation, as at the time of certification of the SEIR, detailed engineering had
not been accomplished. This addendum describes and evaluates the environmental
impacts of modifications to the 66 kV substation facility described in the SEIR. These
modifications include the related components listed below,which comprise minor
technical changes and additions necessary to implement the proposed 66kV substation
facility.
• The substation would be constructed in a rectangular area approximately 200-feet by
75-feet,whereas the SEIR stated a footprint of approximately 150-feet by 100-feel.
• The substation would be enclosed with a fence up to 8-feet high.
• The substation would be equipped with two 25-foot-high by 12-foot-wide switch
racks.
• Up to six existing SCE 12kV poles along Garfield Avenue would be removed and
circuits installed underground to facilitate substation construction.
• An underground segment of 66kV line would be constructed from SCE properly on
the south side of Garfield Avenue in the City of Huntington Beach to the north side of
Garfield Avenue in the City of Fountain Valley. Two separated underground
substructure systems of 3,000 kcmil underground cable would be installed and three
new pole switches would be required.
• Approximately five wood and/or steel poles would be placed on SCE property,and
up to four spans of 954 sac overhead conductor.
• A block wall up to 10-feet high would be placed along Garfield Avenue to provide
visual screening.
• Landscaping would be provided along Garfield Avenue for the length of the
substation site.
The related components, including the 661kV line and poles,would be placed within a
developed area and would not substantially degrade the existing character or quality of
the environment at the site or its surroundings. Additionally, all related components,with
the exception of the subsurface line,would be placed either within the footprint of Plant
OCSDAPMC PAGE20F6 WYM
y a
No. 1 or the Ellis Substation and would be consistent with the existing land uses at these
facilities. These minor technical changes and additions would not result in new
significant environmental effects or a substantial increase in the severity of significant
effects from those determined by the SEIR certified by the Sanitation District Board of
Directors on May 25. 2005 for the Project.
Provided below is a review of the conclusions included in the SEIR and an evaluation of
the environmental impacts of changes to the 66 kV substation facility described herein.
Aesthetics:
The SEIR concluded that although several new structures would be visible from adjacent
residential neighborhoods,the Project would not substantially alter or degrade the
existing visual character of the site and surroundings. The minor technical changes and
additions to the 66 kV substation, including the 66kV line and poles,would be placed
within a developed area and would not substantially degrade the existing character or
quality of the environment at the site or surroundings. Additionally, all related
components,with the exception of the subsurface line,would be placed either within the
footprint of Plant No. 1 or the Ellis Substation and would be consistent with the existing
land uses at these facilities. These minor technical changes and additions would not
result in new significant environmental effects or a substantial increase in the severity of
significant effects related to aesthetic from those determined in the SEIR.
Air Quality:
The SEIR concluded that construction and operation of the Project would exceed
significance thresholds set by the South Coast Air Quality Management District
(SCAQMD)for nitrogen oxides(NOx)emissions. The SEIR also concluded that neither
construction nor operation of the Project would result in objectionable odors affecting a
substantial number of people. The minor technical changes and additions to the 66 kV
substation would not result in an increase in emissions described in the SEIR.
Additionally, the minor technical changes and additions would not result in objectionable
odors affecting a substantial number of people. These minor technical changes and
additions would not result in new significant environmental effects or a substantial
increase in the severity of significant effects related to air quality from those determined
in the SEIR.
Geology and Soils:
The SEIR concluded that the Project could expose people or structures to potential
adverse effects due to geologic and seismic hazards. The SEIR also concluded that
dewatering could create unstable soil conditions,creating potential risk of property
damage to proposed and nearby existing structures. The minor technical changes and
additions to the 66 kV substation would not result in new or substantially more severe
exposure of people or structures to potential adverse effects due to geologic and seismic
hazards. Additionally, the minor technical changes and additions would not increase the
possibility of unstable soil conditions associated with dewatering.These minor technical
changes and additions would not result in new significant environmental effects or a
substantial increase in the severity of significant effects related to geology and soils from
those determined in the SEIR.
ocsoAPMc PAGE3oF6 WAY 2006
G o
Hazards and Hazardous Materials:
The SEIR concluded that the Project would Increase quantities of the existing hazardous
materials used in the treatment process. The SEIR also concluded that abandoned oil
wells could be encountered during excavation at Plant No. 2 and represent both a safety
hazard for workers as well as a potential conduit for surface contamination to reach
groundwater if wells are not properly abandoned. Lastly, the SEIR concluded that soils
contaminated from previous activities In the area could be encountered during
excavation activities and create a significant hazard to the public or environment if not
properly contained and disposed of. The minor technical changes and additions to the
66 kV substation would not result In an increase in the quantities of hazardous materials
described in the SEIR. The minor technical changes and additions described herein
would occur at Plant No. 1 and would have no impact related to hazards at Plant No.2.
Additionally,these minor technical changes and additions would not result In a new or
substantially more severe Impact associated with encountering contaminated soils.
These minor technical changes and additions would not result in new significant
environmental effects or a substantial increase In the severity of significant effects
related to hazards and hazardous materials from those determined in the SEIR.
Hydrology and Water Quality:
The SEIR concluded that construction of the Project could result in erosion and receiving
water quality impacts. The SEIR also concluded that the Project area would be
susceptible to potential flooding impacts that could damage facilities. The minor
technical changes and additions to the 66 kV substation would not result In an increase
in erosion and receiving water quality impacts, or an increase In potential flooding
impacts that could damage facilities,from those described in the SEIR. These minor
technical changes and additions would not result In new significant environmental effects
or a substantial increase in the severity of significant effects related to hydrology and
water quality from those determined In the SEIR.
Marine Environment:
The SEIR concluded that the secondary effluent produced as a result of the Project
would improve effluent quality. The minor technical changes and additions to the 66 kV
substation would have no effect on the secondary effluent quality described In the SEIR.
These minor technical changes and additions would not result in new significant
environmental effects or a substantial Increase in the severity of significant effects
related to the marine environment from those determined in the SEIR.
Noise:
The SEIR concluded that operation of the Project treatment facilities would generate
noise but,with mitigation, noise levels would not exceed established standards or result
In a substantial permanent Increase above ambient conditions. The SEIR also
concluded that Project construction would generate noise that could result in substantial
temporary increases In ambient noise levels in the vicinity, and that Project construction
could generate groundbome vibration that could temporarily expose persons to vibration
above ambient conditions. The minor technical changes and additions to the 66 kV
substation would not Increase construction or operation noise levels, or result in a new
source of groundbome vibration,from those described in the SEIR. These minor
OCSOIIPMC PAGE 4 OF 0 MAY 2006
technical changes and additions would not result in new significant environmental effects
or a substantial Increase in the severity of significant effects related to noise from those
determined in the SEIR.
Transoortationlfraffic:
The SEIR concluded that periods of peak Project construction would add traffic along
local access streets(including freeway access) causing temporary but substantial
increases in traffic over existing conditions. The SEIR also concluded that Project
operation would increase vehicle trips on local access roads only slightly and would not
substantially Increase traffic levels over existing conditions or road capacity. The minor
technical changes and additions to the 66 kV substation would not result in an Increase
in construction or operation related transportation and traffic impacts from those
described in the SEIR. These minor technical changes and additions would not result in
new significant environmental effects or a substantial Increase in the severity of
significant effects related to transportation and traffic from those determined in the SEIR.
FINDINGS OF APPROVAL FOR ADDENDUM NO. 1 TO THE SUBSEQUENT
ENVIRONMENTAL IMPACT REPORT FOR THE SECONDARY TREATMENT AND
PLANT IMPROVEMENT PROJECT:
1. Environmental Impacts of the proposed 66kV substation facility were evaluated in the
SEIR certified by the Sanitation District Board of Directors on May 25, 2005,for the
Project.
2. Minor technical changes and additions to the SEIR are required to address
modifications to the proposed 66kV substation facility.
3. The project modifications would not result in new significant environmental effects or
a substantial increase in the severity of significant effects from those determined by
the SEIR certified by the Sanitation District Board of Directors on May 25, 2005 for
the Project. In addition, no new information of substantial importance,which was not
known and could not have been known with the exercise of reasonable diligence at
the time the SEIR was certified, has surfaced that shows (1) any new or
substantially more severe impacts; (2) any mitigation measures that were considered
Infeasible in the SEIR are now feasible;or(3)mitigation measures or alternatives
that are considerably different from those identified in the SEIR would substantially
reduce one or more significant effects.
OCSIMPMO PAGESOF6 MAY 2006
^' - .{ OCSD RECLAMATION PLANT NO. 1
Ward Avenue,
:.111 1ii
• r k � � -s • e 's '� C:1 i 1 1 1 1•: r
Proposed Underground SCE 66KV Line Proposed 200'x 75'66KV SCE Substation
Sx �
Garfield Street -
"*' ' Proposed Underground SCE 66KV Line
y,- o 00o �" Proposed(4(,N New SCE Wood Poles �s'+
Ezistin SCE Steel Tower Proposed New SCE Steel Pole +
Pro osed New SCE Manholes -
- SCE-FACILITY
3, t ,
Figure 1
P1-97 66KV Substation and Associated Improvements
OCSDIIPMC 6 of 6 May 2006
S0017507.e6=C Fe1.® Sefi